Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas...

35
Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1

Transcript of Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas...

Page 1: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Q4 FY10 ExoplanetPresentation

Philip Hinz - PI

Thomas McMahon - PM

LBTI

1

Page 2: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Project Overview

OctSepAug

Technical Schedule Resources ProgrammaticOctSepAug SepAugJul OctSepAug

Page 3: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

LBTI Summary

Outstanding LBTI on-sky results during 1st three nights on the sky

• Obtained instrument First Light!• Obtained instrument first Fringes!• Telescope is well behaved, i.e. stable enough

to easily interfere the beams.

Next LBTI Observing Block November 4-6• Concentrate on Adaptive Optics Imaging at 2-10µm• Attempt initial interferometry science.

FY11 Project Schedule• Resources now available to support 10+ commissioning nights

during FY11.• NIC Imager scheduled to start commissioning in March 2011• A fraction of the nights will focus on science observations of key

science targets.3

Page 4: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

4

FIRST Light and Fringes!Beta Peg: Combined 10µm image from the LBTI imager. Image is “seeing limited” under poor weather conditions (seeing ~1.2 arc sec). It does demonstrate the LBTI instrument and LBTO telescope’s 23 meter resolution capabilities and stability “right out of the box”.

Page 5: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

5

The Next Observing RunNovember 4-6, 2010

LBTI November observing will be used to attempt two separate goals: 1.AO imaging, and 2.Interferometry Science.

We will intersperse tasks from each area during the run, to maximize use of on-sky time.

Page 6: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

6

Targets for the Next Observing Run

Page 7: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10-11 Commissioning Accomplishments

• Instrument Shipped to LBTO on September 31, on schedule.

• Installed on Telescope September 2, two days ahead of schedule.

7

Sept 31: Instrument Arrives at noon Prepping the platform. We noticed some new obstacles to overcome

Reassembling the instrument

Day One

Page 8: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10-11 Commissioning Accomplishments

8

Installing the Wave Front Sensor fixtures.The wave front sensor sit inside the rotators (circular apertures) and have to be stowed out of the way while the beam combiner is installed

Day Two, 15:00 Oct 1

Lifting the Wave Front Sensors onto the holding fixtures

Working both sides of the primary.Oli Durvey finishes the Wave Front Sensor installation

We were not able to gain access to the telescope until the MODS Facility instrument team finished with their day

Page 9: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10-11 Commissioning Accomplishments

9

Lifting the beam combiner to the telescope

Day Two, 19:00 Oct 1

Lifting over the telescope. A very nervous 45 minutes

90 minutes later we are on the telescope!

We were not able to gain access to the telescope until the MODS Facility instrument team finished with their day

Page 10: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10-11 Commissioning Accomplishments

10

Completing the electrical system

Day Three to Nine, Oct 2 - 8

Activity on the telescope

Aligning the imager pupil to the system

Adjusting the DX wave front sensor

Page 11: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10-11 Commissioning Accomplishments

11

Day Ten, Oct 14… First Night of Observing

Here the telescope is horizon pointing giving the best vantage point of the instrument mounted on the telescope

Page 12: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10-11 Commissioning Accomplishments

12

Day Ten, Oct 14… First Night of Observing

Defocused 10µm image of the primaries showing secondary spider arms. This is the first image of both primaries on a single focal plane.

Not the best night sky conditions… But then it cleared…

Page 13: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10-11 Commissioning Accomplishments

13

Day Ten, Oct 14… First Night of Observing

First Light. A very comatic and out of focus stellar image at 10µm. All the time in the lab paid off…

The beams were cleaned up and the wave front sensors were utilized. The image on the left in the pyramid pupil image from the right beam.

And first Fringes… Combined image of Beta Peg in seeing-limited mode

Page 14: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY11 Commissioning

14

DXSX

Adaptive Secondary Mirror (ASM) Unit #1

Fixed Secondary

Telescope Present Configuration and Capabilities

November ’10 - June ’11•One Adaptive Secondary System (right side).•One Fixed Secondary System (left side).•Binocular pointing mode commissioning.

September ’11 - January ’12•2 AO Secondaries

• One being commissioned• One operational

•Binocular pointing mode commissioned

Telescope Configuration in 2010-11

Page 15: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

15

Near Term Commissioning Timeline

The graph below indicates the top level commissioning schedule and telescope schedule we anticipate to maintain over the next 12+ months.

Page 16: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 2011 Goals

• Utilize the remaining nights to continue characterization of the telescope and interferometer.

• Perform preliminary science on select targets.

• Diffraction limited imaging from 3.5µm to 13µm

• Seeing limited speckle interferometry with 23 m baseline

• Prepare the system for diffraction limited interferometry.

16

Page 17: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Telescope Milestones

Item Milestone Date (Planned) Date (Completed)

Status

  AO Unit #2 Hardware Acceptance 10-Nov-09 10-Nov-09 Complete1 AO Unit # 1 Acceptance 20-Dec-09 20-Dec-09 Complete2 AO Unit # 1 Arrival in AZ 15-Feb-10 Feb-15  Complete 3 AO Unit # 1 Installation 15-Mar-10 Mar-6  Complete4 True Binocular Ops 1-Dec-10   On Schedule 5 Daytime AO Commissioning 11-Jun-10 Mar-20  Complete 6 AO Unit # 1 on-sky

commissioning30-Jan-11   In progress 

7 AO Unit # 2 Arrival in AZ Q1 FY11   Now May ‘118 AO Unit #2 Commissioning Q3 FY11   Now Sep ‘11 

17

True Binocular Ops Definition:Activities in preparing the telescope for coordinated binocular (simultaneous) observations. Activities include Instrument ports commissioning, software, mirror mount upgrades, mirror covers, two secondary/tertiary mirrors operational.

Daytime AO Commissioning Definition:Secondary mounted with artificial source at center of curvature (See image on next slide) and wave front sensor. Testing conducted during the daytime hours with dome closed. Repeat of test suite performed in Italy that will verify proper, and expected on-telescope performance.

On-sky Commissioning Definition:Open dome, closed loop testing using natural guide star. Italians have asked for 50+ nights with seeing “good seeing”. This is the driver for the 4-5 month on-sky commissioning period. LBTI expect near normal AO operations to be achieved by late-Fall ‘10

Page 18: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Instrument Milestones

Item Milestone Date (Planned)

Actual Status

1 Telescope re-installation 7/27/10 9/2/10 Completed

2 First Light (seeing limited, fringes) 9/1/10 10/14/10 Completed

3 2 Aperture Speckle imaging tests 9/1/10 10/14/10 Completed

4 NIC on-sky testing with MMT Telescope

9/30/10 Going directly to LBT in late Q2 FY11

5 LBTI AO Commissioning Q4 FY10 11/4/10 Initial 3 night this week (Nov 4-6)

6 Single Aperture AO Imaging (3-12µm) Q2 FY11 Late Q1/early Q2 FY11

7 AO Interferometry Commissioning Q4 FY11 Start in Oct ’10, continued in FY12due to FY11 funding profile

18

Telescope re-installation:Includes mechanical installation of the Beam Combiner, Wave Front Sensors, electronics.Internal alignment and integration included the instrument alignment with the optical axis of the telescope. Alignment will be accomplished with an infrared test camera, and prototype nulling interferometer (BLINC/MIRAC)

LBTI AO Commissioning:Commissioning tasks associated with the operations of the first dedicated wave front sensor (Unit #1). Unit # 2 commissioning will take place after the AO Secondary Mirror unit #2 is commissioned in calendar 2011.

AO Interferometry Commissioning:Commences after AO Secondary Mirror #2 is installed and commissioned and when funding profile supports the activity.

Page 19: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Other Project Activities

The Project has also pushed a head with the testing of the NIC imager:

• Limited progress due to limited resources… i.e. everyone was concentrating on support the installation and first observing run.

• Testing in continuing in the lab with performance characterization.

• LMIRCam testing finishing up in Virginia. Expect delivery in late November.

19

Inside of of the NIC cryostat just prior to installation of detector systems in August

Page 20: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Other Project Activities

First light article in the Arizona Daily Star:http://azstarnet.com/news/local/education/college/article_d0bcb666-9378-5330-abfc-09f58b536310.html

Instrument Wiki and Blog page:http://zero.as.arizona.edu/groups/lbti/

NASA Feature Article due out November 9

20

Page 21: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY10/11 Project Schedule

21

See following slide for annotations

Page 22: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Annotated FY10/11 Project Schedule

22

Final testing carried out after AO Unit #2 delivered.

Today

Will work on lab testing of imager until allowed to integrate with telescopePre-ship review of Imager in late January/early February (to be scheduled)

Canceled. Determined effort too great for limited resources and scheduling issues with MMT

First opportunity to integrate and test imager on telescope

Anticipated commissioning of AO Unit #2. Limited schedule information available

Page 23: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Annotated FY11 Project Schedule

23

• Observing Block 1 is complete• We have 3 more scheduled nights.• We have requested 6 additional nights in 2011A telescope period.• AO Unit #2 is expected to be delivered in May prior to telescope summer shutdown (~2 month slip)• Anticipate 3 month AO Unit #2 commissioning period between September and December 2011• LBTI AO Interferometry commissioning can take place concurrently with AO Unit #2 commissioning• Anticipate transitioning to science operations in early calendar 2012

Page 24: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Open Items

24

Planned Completed Status/Description

Page 25: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Problems & Concerns

25

Page 26: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Problems & Concerns

Description

Item #1: LBT Schedule dependency -Telescope construction schedule is on the critical path.

Current StatusCompletion of the interferometric capable telescope now scheduled for late Fall 2011. Expected Resolution/ImpactLBTI expects to move forward with commissioning tasks to the limit of the telescope capabilities. AO Unit #2 remains on the critical path to Science Operations. Expect Unit #2 to be delivered in May 2011.

26

C

Page 27: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Problems & Concerns

Description

Item #2: LBT Performance -Telescope performance has impacts on instrument productivity.

Current StatusTelescope commissioning continues. Presently no known issues of telescope performance are show stoppers. LBTO is actively addressing all issues. First light performance showed no issues that cannot be addressed and overcome before the observatory commissions interferometric capabilities. AO performance meets LBTI requirements. Expected Resolution/ImpactLBTI project continues to monitor the evolution of the telescope system.

27

C

Page 28: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Problems & Concerns

Description

Item #3: Instrument Integration Schedule -Instrument commissioning schedule is ambitious for 20 nights.

Current StatusLBTI struggles with sufficient funds for full commissioning schedule and with the log jam of telescope facility commissioning tasks that take priority.

We have been able to jump the line and start limited commissioning. Project plan and finances support 10 nights of on-sky commissioning in FY11. Expected Resolution/Impact

28

C

Page 29: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Problems & Concerns

Description

Item #5: FY 11 funding impacts upon commissioning.

Current StatusRetired/Resolved.

Expected Resolution/Impact

LBTI now has promise of sufficient funds to maintain staff level to support 10 nights of on-sky commissioning and possibility of ramping up/re-organizing staff to support start of science ops in FY12.

29

C

Page 30: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Action Items

30

ACTIONITEMNO.

DESCRIPTIONSTATUS:

I/C*CLOSURE REFERENCE/

DOCUMENT ID

*I = In Work/C = Complete

Page 31: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Labor Summary

31

Page 32: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY 10 Project Finances

32

Page 33: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

FY11 Project Finances

33

Page 34: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Risk

34

Approach

M - Mitigate

W - Watch

A - Accept

R - Research

Med

High

Low

CriticalityL x C Trend

Decreasing (Improving)

Increasing (Worsening)

Unchanged

New Since Last Period

No change from last reporting period.

Page 35: Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas McMahon - PM LBTI 1.

Larg

e Bi

nocu

lar T

eles

cope

In

terf

erom

eter

(UA)

Risk Focus

35