Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas...
-
Upload
marcus-cook -
Category
Documents
-
view
215 -
download
0
Transcript of Large Binocular Telescope Interferometer (UA) Q4 FY10 Exoplanet Presentation Philip Hinz - PI Thomas...
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Q4 FY10 ExoplanetPresentation
Philip Hinz - PI
Thomas McMahon - PM
LBTI
1
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Project Overview
OctSepAug
Technical Schedule Resources ProgrammaticOctSepAug SepAugJul OctSepAug
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
LBTI Summary
Outstanding LBTI on-sky results during 1st three nights on the sky
• Obtained instrument First Light!• Obtained instrument first Fringes!• Telescope is well behaved, i.e. stable enough
to easily interfere the beams.
Next LBTI Observing Block November 4-6• Concentrate on Adaptive Optics Imaging at 2-10µm• Attempt initial interferometry science.
FY11 Project Schedule• Resources now available to support 10+ commissioning nights
during FY11.• NIC Imager scheduled to start commissioning in March 2011• A fraction of the nights will focus on science observations of key
science targets.3
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
4
FIRST Light and Fringes!Beta Peg: Combined 10µm image from the LBTI imager. Image is “seeing limited” under poor weather conditions (seeing ~1.2 arc sec). It does demonstrate the LBTI instrument and LBTO telescope’s 23 meter resolution capabilities and stability “right out of the box”.
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
5
The Next Observing RunNovember 4-6, 2010
LBTI November observing will be used to attempt two separate goals: 1.AO imaging, and 2.Interferometry Science.
We will intersperse tasks from each area during the run, to maximize use of on-sky time.
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
6
Targets for the Next Observing Run
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10-11 Commissioning Accomplishments
• Instrument Shipped to LBTO on September 31, on schedule.
• Installed on Telescope September 2, two days ahead of schedule.
7
Sept 31: Instrument Arrives at noon Prepping the platform. We noticed some new obstacles to overcome
Reassembling the instrument
Day One
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10-11 Commissioning Accomplishments
8
Installing the Wave Front Sensor fixtures.The wave front sensor sit inside the rotators (circular apertures) and have to be stowed out of the way while the beam combiner is installed
Day Two, 15:00 Oct 1
Lifting the Wave Front Sensors onto the holding fixtures
Working both sides of the primary.Oli Durvey finishes the Wave Front Sensor installation
We were not able to gain access to the telescope until the MODS Facility instrument team finished with their day
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10-11 Commissioning Accomplishments
9
Lifting the beam combiner to the telescope
Day Two, 19:00 Oct 1
Lifting over the telescope. A very nervous 45 minutes
90 minutes later we are on the telescope!
We were not able to gain access to the telescope until the MODS Facility instrument team finished with their day
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10-11 Commissioning Accomplishments
10
Completing the electrical system
Day Three to Nine, Oct 2 - 8
Activity on the telescope
Aligning the imager pupil to the system
Adjusting the DX wave front sensor
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10-11 Commissioning Accomplishments
11
Day Ten, Oct 14… First Night of Observing
Here the telescope is horizon pointing giving the best vantage point of the instrument mounted on the telescope
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10-11 Commissioning Accomplishments
12
Day Ten, Oct 14… First Night of Observing
Defocused 10µm image of the primaries showing secondary spider arms. This is the first image of both primaries on a single focal plane.
Not the best night sky conditions… But then it cleared…
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10-11 Commissioning Accomplishments
13
Day Ten, Oct 14… First Night of Observing
First Light. A very comatic and out of focus stellar image at 10µm. All the time in the lab paid off…
The beams were cleaned up and the wave front sensors were utilized. The image on the left in the pyramid pupil image from the right beam.
And first Fringes… Combined image of Beta Peg in seeing-limited mode
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY11 Commissioning
14
DXSX
Adaptive Secondary Mirror (ASM) Unit #1
Fixed Secondary
Telescope Present Configuration and Capabilities
November ’10 - June ’11•One Adaptive Secondary System (right side).•One Fixed Secondary System (left side).•Binocular pointing mode commissioning.
September ’11 - January ’12•2 AO Secondaries
• One being commissioned• One operational
•Binocular pointing mode commissioned
Telescope Configuration in 2010-11
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
15
Near Term Commissioning Timeline
The graph below indicates the top level commissioning schedule and telescope schedule we anticipate to maintain over the next 12+ months.
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 2011 Goals
• Utilize the remaining nights to continue characterization of the telescope and interferometer.
• Perform preliminary science on select targets.
• Diffraction limited imaging from 3.5µm to 13µm
• Seeing limited speckle interferometry with 23 m baseline
• Prepare the system for diffraction limited interferometry.
16
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Telescope Milestones
Item Milestone Date (Planned) Date (Completed)
Status
AO Unit #2 Hardware Acceptance 10-Nov-09 10-Nov-09 Complete1 AO Unit # 1 Acceptance 20-Dec-09 20-Dec-09 Complete2 AO Unit # 1 Arrival in AZ 15-Feb-10 Feb-15 Complete 3 AO Unit # 1 Installation 15-Mar-10 Mar-6 Complete4 True Binocular Ops 1-Dec-10 On Schedule 5 Daytime AO Commissioning 11-Jun-10 Mar-20 Complete 6 AO Unit # 1 on-sky
commissioning30-Jan-11 In progress
7 AO Unit # 2 Arrival in AZ Q1 FY11 Now May ‘118 AO Unit #2 Commissioning Q3 FY11 Now Sep ‘11
17
True Binocular Ops Definition:Activities in preparing the telescope for coordinated binocular (simultaneous) observations. Activities include Instrument ports commissioning, software, mirror mount upgrades, mirror covers, two secondary/tertiary mirrors operational.
Daytime AO Commissioning Definition:Secondary mounted with artificial source at center of curvature (See image on next slide) and wave front sensor. Testing conducted during the daytime hours with dome closed. Repeat of test suite performed in Italy that will verify proper, and expected on-telescope performance.
On-sky Commissioning Definition:Open dome, closed loop testing using natural guide star. Italians have asked for 50+ nights with seeing “good seeing”. This is the driver for the 4-5 month on-sky commissioning period. LBTI expect near normal AO operations to be achieved by late-Fall ‘10
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Instrument Milestones
Item Milestone Date (Planned)
Actual Status
1 Telescope re-installation 7/27/10 9/2/10 Completed
2 First Light (seeing limited, fringes) 9/1/10 10/14/10 Completed
3 2 Aperture Speckle imaging tests 9/1/10 10/14/10 Completed
4 NIC on-sky testing with MMT Telescope
9/30/10 Going directly to LBT in late Q2 FY11
5 LBTI AO Commissioning Q4 FY10 11/4/10 Initial 3 night this week (Nov 4-6)
6 Single Aperture AO Imaging (3-12µm) Q2 FY11 Late Q1/early Q2 FY11
7 AO Interferometry Commissioning Q4 FY11 Start in Oct ’10, continued in FY12due to FY11 funding profile
18
Telescope re-installation:Includes mechanical installation of the Beam Combiner, Wave Front Sensors, electronics.Internal alignment and integration included the instrument alignment with the optical axis of the telescope. Alignment will be accomplished with an infrared test camera, and prototype nulling interferometer (BLINC/MIRAC)
LBTI AO Commissioning:Commissioning tasks associated with the operations of the first dedicated wave front sensor (Unit #1). Unit # 2 commissioning will take place after the AO Secondary Mirror unit #2 is commissioned in calendar 2011.
AO Interferometry Commissioning:Commences after AO Secondary Mirror #2 is installed and commissioned and when funding profile supports the activity.
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Other Project Activities
The Project has also pushed a head with the testing of the NIC imager:
• Limited progress due to limited resources… i.e. everyone was concentrating on support the installation and first observing run.
• Testing in continuing in the lab with performance characterization.
• LMIRCam testing finishing up in Virginia. Expect delivery in late November.
19
Inside of of the NIC cryostat just prior to installation of detector systems in August
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Other Project Activities
First light article in the Arizona Daily Star:http://azstarnet.com/news/local/education/college/article_d0bcb666-9378-5330-abfc-09f58b536310.html
Instrument Wiki and Blog page:http://zero.as.arizona.edu/groups/lbti/
NASA Feature Article due out November 9
20
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY10/11 Project Schedule
21
See following slide for annotations
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Annotated FY10/11 Project Schedule
22
Final testing carried out after AO Unit #2 delivered.
Today
Will work on lab testing of imager until allowed to integrate with telescopePre-ship review of Imager in late January/early February (to be scheduled)
Canceled. Determined effort too great for limited resources and scheduling issues with MMT
First opportunity to integrate and test imager on telescope
Anticipated commissioning of AO Unit #2. Limited schedule information available
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Annotated FY11 Project Schedule
23
• Observing Block 1 is complete• We have 3 more scheduled nights.• We have requested 6 additional nights in 2011A telescope period.• AO Unit #2 is expected to be delivered in May prior to telescope summer shutdown (~2 month slip)• Anticipate 3 month AO Unit #2 commissioning period between September and December 2011• LBTI AO Interferometry commissioning can take place concurrently with AO Unit #2 commissioning• Anticipate transitioning to science operations in early calendar 2012
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Open Items
24
Planned Completed Status/Description
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Problems & Concerns
25
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Problems & Concerns
Description
Item #1: LBT Schedule dependency -Telescope construction schedule is on the critical path.
Current StatusCompletion of the interferometric capable telescope now scheduled for late Fall 2011. Expected Resolution/ImpactLBTI expects to move forward with commissioning tasks to the limit of the telescope capabilities. AO Unit #2 remains on the critical path to Science Operations. Expect Unit #2 to be delivered in May 2011.
26
C
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Problems & Concerns
Description
Item #2: LBT Performance -Telescope performance has impacts on instrument productivity.
Current StatusTelescope commissioning continues. Presently no known issues of telescope performance are show stoppers. LBTO is actively addressing all issues. First light performance showed no issues that cannot be addressed and overcome before the observatory commissions interferometric capabilities. AO performance meets LBTI requirements. Expected Resolution/ImpactLBTI project continues to monitor the evolution of the telescope system.
27
C
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Problems & Concerns
Description
Item #3: Instrument Integration Schedule -Instrument commissioning schedule is ambitious for 20 nights.
Current StatusLBTI struggles with sufficient funds for full commissioning schedule and with the log jam of telescope facility commissioning tasks that take priority.
We have been able to jump the line and start limited commissioning. Project plan and finances support 10 nights of on-sky commissioning in FY11. Expected Resolution/Impact
28
C
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Problems & Concerns
Description
Item #5: FY 11 funding impacts upon commissioning.
Current StatusRetired/Resolved.
Expected Resolution/Impact
LBTI now has promise of sufficient funds to maintain staff level to support 10 nights of on-sky commissioning and possibility of ramping up/re-organizing staff to support start of science ops in FY12.
29
C
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Action Items
30
ACTIONITEMNO.
DESCRIPTIONSTATUS:
I/C*CLOSURE REFERENCE/
DOCUMENT ID
*I = In Work/C = Complete
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Labor Summary
31
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY 10 Project Finances
32
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
FY11 Project Finances
33
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Risk
34
Approach
M - Mitigate
W - Watch
A - Accept
R - Research
Med
High
Low
CriticalityL x C Trend
Decreasing (Improving)
Increasing (Worsening)
Unchanged
New Since Last Period
No change from last reporting period.
Larg
e Bi
nocu
lar T
eles
cope
In
terf
erom
eter
(UA)
Risk Focus
35