Lancaster County Metropolitan Transportation Plan Update
Transcript of Lancaster County Metropolitan Transportation Plan Update
Lancaster Metropolitan Transportation Plan 2
Today’s Road Map
• Stakeholder Engagement Update
• Review of Existing Transportation Conditions
• Review of Draft Revenue Forecast
• Summary and Review of Next Steps
Lancaster Metropolitan Transportation Plan 4
Stakeholder Engagement Update
Focus Group Meetings
Confirmed Focus Group Meetings
• Active Transportation
• Amish Safety
• Emergency Response
• Municipal Officials
• Shippers & Business
• Transit and Human Services
• Transportation Program
• Underserved Populations
6Lancaster Metropolitan Transportation Plan
SocioeconomicsPopulation Change
450,000
460,000
470,000
480,000
490,000
500,000
510,000
520,000
530,000
540,000
550,000
2010 2011 2012 2013 2014 2015 2016 2017
Year
8Lancaster Metropolitan Transportation Plan
Road Network
Linear Miles by Ownership DVMT by Ownership
9Lancaster Metropolitan Transportation Plan
Road Network
DVMT Trend from 2013 to 2017
10.0
10.5
11.0
11.5
12.0
12.5
13.0
2013 2014 2015 2016 2017
DV
MT (
Millio
ns)
Year
10Lancaster Metropolitan Transportation Plan
Roadway NetworkFunctional Classification
Facility TypeLinear
Miles%
FHWA
Recommended
Urban System (%)
Interstate 30.6 0.8 1 – 3
Other
Freeway/Expres
sway
20.0 0.5 0 – 2
Other Principal
Arterial99.7 2.6 4 – 5
Minor Arterial 291.2 7.5 7 – 12
Major Collector 456.7 11.8 7 – 15
Minor Collector 234.3 6.1 7 – 15
Local Road 2,730.3 70.1 63 - 75
12
Roadway ConditionsOverall Pavement Conditions - % Poor
0%
1%
2%
3%
4%
5%
6%
7%
8%
9%
10%
NHS, Non-Interstate Non-NHS, >2000 ADT Non-NHS, <2000 ADT
Lancaster State
13
Roadway Safety
Total Vehicle Crashes by 5-Year Average
5,256 5,263
5,372
5,475
5,590
5,000
5,100
5,200
5,300
5,400
5,500
5,600
14
Roadway Safety
Total Fatalities by 5-Year Average
46.4
49.0
46.8
45.845.6
40
41
42
43
44
45
46
47
48
49
50
15Lancaster Metropolitan Transportation Plan
Bridges - State
Percent Poor Bridges (Lancaster and PA)
0
5
10
15
20
25
2015 2016 2017 2018 2019
Pe
rce
nt
Po
or
Year
Lancaster Penna
16Lancaster Metropolitan Transportation Plan
Bridges - State
State Bridges Built by Decade
0
20
40
60
80
100
120
< 1920s 1920s 1930s 1940s 1950s 1960s 1970s 1980s 1990s 2000s 2010s
Nu
mb
er
Decade Built
17
Bridges - Local
Local Bridges Closed and Posted, 2015-19
62 61 6057 58
9 108
6 6
0
10
20
30
40
50
60
70
2015 2016 2017 2018 2019
# o
f B
rid
ge
sYear
Posted Closed
282 Local Bridges
266 Local Bridges
59 Poor Condition
15 County
Poor
22Lancaster Metropolitan Transportation Plan
Active TransportationBikeway and Pedestrian Safety
0
20
40
60
80
100
120
140
160
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
# o
f C
rash
es
Year
Pedestrian Crashes Bicycle Crashes
Bicyclist and Pedestrian Crashes
23Lancaster Metropolitan Transportation Plan
Active TransportationBikeway and Pedestrian Safety
0
2
4
6
8
10
12
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
# o
f F
ata
liti
es
Year
Pedestrian Fatalities Bicycle Fatalities
Bicyclist and Pedestrian Fatalities
25Lancaster Metropolitan Transportation Plan
Revenue Forecast Overview
• MPOs must provide an estimate of funding received over the 25-year period of the MTP
• Revenue forecast is used to develop the fiscally-constrained Investment Plan
26Lancaster Metropolitan Transportation Plan
Revenue Forecast: Assumptions
• PennDOT Financial Guidance documentation for the 2021 Program was used as base funding allocations
• The draft revenue forecast assumes:
• No increases in Federal revenue after the FAST Act expires in September 2020
• Funding levels in FFY 2032 are expected to carry forward through the plan horizon year of 2045
• No major funding increases from state actions (e.g., Act 44 of 2007 and Act 89 of 2013)
• No funding from discretionary “Spike” funding or competitive grant programs (e.g., MTF, GLG, etc.)
• A 3% rate of inflation
27Lancaster Metropolitan Transportation Plan
Revenue Forecast
• Using these assumptions, Lancaster County has a long-range forecast of $1.33 billion in today’s dollars through the 2045 plan period. Adjusting for inflation, this amount comes to $925 million.
PeriodNominal Dollars
($000s)
Real Dollars
($000s)
TIP (2021-2024) $209,134 $189,464
TYP (2021-2032) $641,646 $523,287
MTP (2021-2045) $1,332,934 $925,788