LAM Concept FULL 09-14-2010 Web

82
Concept Design Report • 09.14.2010

Transcript of LAM Concept FULL 09-14-2010 Web

Page 1: LAM Concept FULL 09-14-2010 Web

Concept Design Report • 09.14.2010

Page 2: LAM Concept FULL 09-14-2010 Web

This page intentionally left blank.

Page 3: LAM Concept FULL 09-14-2010 Web

Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Acknowledgments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Project Framework. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

Project Timeline. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

Functional Integration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9.

Space Needs Update. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11.

Design Narratives. Architectural.Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15. Concept.Diagrams. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18. Concept.Floor.Plans .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. . 20. Site.and.Landscape.Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25. Site.Plan. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27. Civil.Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29. Structural.Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33. Mechanical.Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37. Electrical.Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43. Code.Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51. Systems.Diagrams. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54

Exhibits (under separate cover). Exhibit.A:..Cost.Estimate. Exhibit.B:..Full.Space.List. Exhibit.C:..Conditions.Survey. Exhibit.D:..Topographic.Survey. Exhibit.E:..Geotechnical.Overview. Exhibit.F:..Haz-Mat.Report. Exhibit.G:..Phase.1.Environmental.Report

TABLE.OF.CONTENTS

Page 4: LAM Concept FULL 09-14-2010 Web

Alaska’s Memory Keeper

Page 5: LAM Concept FULL 09-14-2010 Web

1Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Owner/Client

State of Alaska, Department of Transportation and Public Facilities for

State of Alaska, Department of Education and Early Development

Division of Alaska State Libraries, Archives and Museums

Linda.Thibodeau,.DirectorP .O ..Box.110571Juneau,.AK.99811-0571

Core Design Team

ECI / Hyer Architecture & Interiors101.W ..Benson.Boulevard,.Suite.306Anchorage,.Alaska.99503Brian.Meissner,.Principal-in-Charge907 .561 .5543

THA Architecture733.SW.Oak.Street,.Suite.100Portland,.Oregon.97205Thomas.Hacker,.Lead.Designer503 .227 .1254

Walker Macy • Landscape Architecture111.SW.Oak.Street,.Suite.200Portland,.OR.97204Doug.Macy,.Landscape.Planner503 .228 .3122

Laura Millar • Archive Planner1202-1245.Quayside.DriveNew.Westminster,.BC..V3M.6J6604 .515 .4676

ACKNOWLEDGMENTS

Page 6: LAM Concept FULL 09-14-2010 Web

2 ECI/HYER :: THA ARCHITECTURE

Page 7: LAM Concept FULL 09-14-2010 Web

�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

EXECUTIVE.SUMMARY

Over. the. past. few. years. a. paradigm. shift. has.been. occurring. at. the. Alaska. State. Libraries,.Archives.and.Museums ..A.dream.for.a.new.facil-ity.that.would.integrate.the.three.units.is.becom-ing. a. reality .. Simultaneously,. the. workings. of.the. Division. are. becoming. more. integrated. on.a.daily.basis ..These.changes.have.Alaska.on.tar-get.to.become.an.international.leader.in.service.delivery. for. libraries,. archives. and. museums ..This.report.summarizes.the.process.that. led.to.where.we.are,.presents.the.concepts.that.arose.from.the.process,.and.sets.a.course.that.will.lead.to.a.new.Library,.Archives.and.Museum.Facility .

At. heart,. this. project. is. about. protecting. Alas-ka’s. treasures .. The. existing. collections. of. the.Alaska.Libraries,.Archives.and.Museums.are.full.of.those.treasures ..Many,. if.damaged,.are. irre-placeable,.yet.they.are.housed.in.buildings.that.can. no. longer. adequately. protect. them .. The.storage.facilities.are.beyond.their.useful.life.and.beyond.capacity ..There.are.additional.treasures.within.the.State.and.beyond.that.will.eventually.find their way into the collections. This project promises.to.produce.a.facility.capable.of.receiv-ing. and. protecting. valuable. artifacts .. Alaska.deserves. to. see. the. existing. and. future. collec-tions.preserved.for.generations.to.come ..

The.project.has.three.key.goals:

•. Construct.a.new.building.that.will.protect.Alaska’s.collections.while.integrating.the.library,.archives.and.museum .

•. Improve.service.delivery.and.program.of-ferings.through.integration.of.the.three.groups .

•. Create.an.integrated.digital.portal.for.access.to.information .

Building Space RequirementsAfter extensive user interviews with staff mem-bers.and.stakeholders,. the.space.requirements.have. been. updated. and. described. in. detail .. In.summary,.the.new.facility.will.include.the.follow-ing.components .

•.. 124,000.sf.new.construction

•.. 80.basement.level.parking.stalls

•.. 40.surface.parking.stalls

•.. site.development.and.landscaping

OutreachInitial outreach efforts included stakeholder interviews. with. representatives. of. 35. groups.statewide. and. an. email. poll. of. other. state.libraries,.archives.and.museums.regarding.their.expansion.projects ..A.project.fact.sheet.outlined.the. project. need. and. approach .. A. project. bro-chure.was.distributed.with.presentations.to.the.annual.meeting.of.the.Alaska.Historical.Societies.and.Museums.Alaska .

More.recently,.a.series.of.public.workshops.and.discussions with staff has led to development of.an.updated.list.of.space.requirements.and.a.concept.design.for.the.new.facility .

Over. the. next. several. months. continued. state-wide.outreach.will.be.employed.to.educate.citi-zens.about.the.project.and.to.generate.feedback.on.the.design.concepts .

Page 8: LAM Concept FULL 09-14-2010 Web

4 ECI/HYER :: THA ARCHITECTURE

Alaska Division of Libraries, Archives and MuseumsThe.U .S ..Congress.established.the.Alaska.Histori-cal Library and Museum in 1900. The first cura-tor, Andrew Kashevaroff, was appointed in 1920 and. shortly. thereafter. the. Territory. assumed.responsibility.for. its.operations ..When.the.new.federal building (now the State Capitol) was fin-ished.in.1931,.the.Library.and.Museum.moved.to.that.building ..

A. new. museum,. built. by. the. community. of.Juneau,.was.turned.over.to.the.State.of.Alaska.in.1968.to.honor.the.centennial.of.Alaska’s.pur-chase ..At.that.time,.the.Alaska.Historical.Library.was. separated. from. the. Alaska. State. Museum.and.became.a.part.of. the.Alaska.State.Library,.which. had. been. established. in. 1955 .. When. the.Alaska.State.Archives.was.created.in.1970,.public.state.records.were.transferred.to.it.from.the.His-torical.Library,.which.retained.all.manuscript.and.photograph.records.and.papers.produced.by.the.private. sector .. The. State. Archives. entered. the.current.building.in.1975 ..The.State.purchased.the.Sheldon. Jackson. Museum. in. 1988 .. In. 1991,. the.Commissioner.of.Education.created.the.Division.of.Libraries,.Archives.and.Museums ..

STATEWIDE OUTREACH – EDUCATION LOOP

Page 9: LAM Concept FULL 09-14-2010 Web

�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

PROJECTFRAMEWORK

MissionThe.mission.of.the.Alaska.Division.of.Libraries,.Archives.and.Museums.is.to.preserve.Alaska’s.cultural.heritage.and.to.facilitate.access.to.information.and.resources.for.research.and.lifelong.learning ..

In.keeping.with.this.mission.to.better.protect.and.share.our.collections.and.to.improve.our.programs.and.services,.the.division.is.working.towards.consoli-dating.and.integrating.the.work.of.its.three.sections:.the.State.Library,.the.State.Archives.and.the.State.Museums ..A.new.building.should.help.us.to.work.more efficiently and effectively for Alaskans.

Alaska State LibraryThe. Department. of. Library. Service. was. estab-lished.in.1955.to.provide.library.service.in.the.Ter-ritory. of. Alaska,. to. serve. as. a. reference. library.for Territorial offices and libraries, to coordinate and.assist.library.activities.throughout.the.terri-tory,. and. to. administer. the. annual. grant-in-aid.to.incorporated.library.associations ...In.1959.the.Department.was.placed.within.the.Department.of. Education. for. administrative. purposes;. it.assumed.the.title.Alaska.State.Library ...The.His-torical.Library.separated.from.the.State.Museum.and.joined.the.State.Library.in.1968 ...This.section.of. the. library. is. now. known. as. the. Historical.Collections .

Alaska State ArchivesThe.Alaska.State.Archives.was.established.in.1970.and.opened.its.doors.to.the.public. in.1972 ..The.State. Archives. is. the. repository. that. preserves.the.government.records.of.Alaska’s.history.and.makes.these.records.accessible.to.its.patrons.in.a.safe,.professional.and.responsible.manner ..

Government. records. with. permanent. histori-cal. value. include. legislative. bills. and. histories,.audio. recordings,. meeting. minutes,. annual.reports,.birth.and.death.records,.naturalization.records,. incorporation. records,. court. and. pro-bate.records,.correspondence,.publications.and.other.agency-related.material ..The.Alaska.State.Archives. does. not. collect. personal. manuscript.records,. but. holds. records. dated. from. 1874. -..present,.with.the.majority.of.records.created.in.the.20th.century ..Areas.of.strength.include.ter-ritorial. and. state. governor. records,. territorial.court. records,. community-based. state. govern-ment.records,.and.state.era.legislative.records ..

Alaska State MuseumsThe. purpose. of. the. Museum,. created. in. 1900,.was.to.collect,.preserve.and.exhibit.the.territo-ry’s. objects .. Initially. the. collection. was. stored.wherever. space. could. be. found. with. no. provi-sion.made.for.public.access ..In.1920,.the.collec-tion.was.made.available.to.the.public.in.Juneau’s.Arctic. Brotherhood. Building. and. in. 1923,. the.Territory.assumed.responsibility.for.operations ..By. the. mid-1940s,. the. collection.had. outgrown.its.space.and.the.Museum.could.no.longer.ade-quately.store.and.display.its.materials ..In.1968,.in.honor.of.the.centennial.purchase.of.Alaska.from.Russia,.Juneau.citizens.implemented.a.sales.tax.to.help.fund.a.new.facility—the.existing.museum.facility—subsequently. turning. over. ownership.and. governance. to. the. State. of. Alaska .. Since.that.time,.the.Museum’s.collections.have.grown.from.5,500.to.27,000.objects ..The.Alaska.State.Museum.was.accredited.by.the.American.Associ-ation.of.Museums.in.1975.and.was.re-accredited.in.1987,.and.again.in.2001 ..

Page 10: LAM Concept FULL 09-14-2010 Web

� ECI/HYER :: THA ARCHITECTURE

Page 11: LAM Concept FULL 09-14-2010 Web

�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Libraries Archives Museum Project Timeline to Date

•.......Initial.design.proposal.unveiled.in.Juneau.in.June.2010;......the.project.was.christened.the.Library.Archives.Museum.Project

• Staff and public meetings conducted in Juneau in April & May 2010

•.......Design.contract.awarded.in.spring.2010

•.......Released.design.request.for.proposals.in.November.of.2009

•.......Pre-design.program.planning.conducted.in.spring.2009

•.......Additional.design.funding.provided.by.Legislature.in.2008

•.......Needs.Assessment.completed.November.2006

•.......Partial.design.funding.secured.2005

•.......1 .8.acres.acquired.2003,.added.to.site.of.existing.Museum

Next Steps

•.......Fall.-.Winter.2010.-.2011

Schematic.design

Statewide.outreach.campaign

Contractor.selection

•.......Spring.-.Summer.2011

Design.development

Finalize.construction.timeline

Secure.project.funding.for.construction

•.......Fall.-.Winter.2011.-.2012

Final.construction.documents

Initiate.construction.contract.for.long-lead.items,.utilities.and.advanced.site.work

•......Spring.2012.-.Summer.2014

Construction

•......Fall.2014

Grand Opening

PROJECTTIMELINE

Page 12: LAM Concept FULL 09-14-2010 Web

� ECI/HYER :: THA ARCHITECTURE

Page 13: LAM Concept FULL 09-14-2010 Web

9Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

FUNCTIONALINTEGRATION

As.web-based.communications.and.digital.tech-nologies.become.increasingly.common,.a.grow-ing. national. and. international. trend. is. to. inte-grate. library,. archives. and. museum. processes,.bringing together the work of different institu-tions.into.one.or.two.integrated.agencies,.often.under.the.umbrella.term.‘memory. institutions .’.Functional. integration. emphasizes. the. simi-larities. between. library,. archives. and. museum.services. while. respecting. the. distinct. qualities.of. the. materials. being. managed:. publications,.archival.records.and.artifacts ..Not.only.does.the.integration.of.operations.provide.greater.access.to. a. wide. range. of. information. resources,. but.the. coordination. of. activities. also. allows. insti-tutions to offer extensive public services while maximizing.resources ..

While.each.type.of.material.–.publications,.his-torical. records,. or. three-dimensional. objects. –..presents. its. own. challenge. for. preservation,.description. and. access,. many. procedures. can.be coordinated effectively. For example, rather than.maintaining.separate.procedures.for.adding.new.items.to.library,.archives.or.museum.collec-tions,.an.integrated.approach.can.centralize.the.documentation. of. all. new. acquisitions .. Donor.information,. descriptions. of. new. accessions,.conservation. notes. can. all. be. consolidated;. as.

a.result,.everyone.in.the.institution.can.see.the.full. scope. of. new. holdings. and. establish. com-mon.priorities. for.action ..Similarly,. the.content.and. structure. of. library,. archives. and. museum.catalogs, finding aids, and other descriptive tools. can. be. coordinated. so. that. users. can.easily find a wide-range of relevant materials on. their. research. topic,. whether. the. items. are.publications,. historical. documents,. or. original.artifacts ..As.an.example,.the.description.of.a.pair.of beaded moccasins will be different from the description.of.a.booklet.on.Athabascan.clothing.or.of.a.historical.photograph.of.an.Athabascan.woman.in.traditional.clothing ..By.putting.those.descriptions. together. in. an. integrated. catalog,.the.user.can.access.core.information.about.each.item,.making. it.easier.to. locate.a.wide.body.of.information. and. resources. related. to. Athabas-can.traditions .

The. Library. Archives. Museum. Project. is. mov-ing.toward.functional.integration.in.many.of.its.library/archives/museum. operations .. In. particu-lar,.the.division.is.actively.investigating.new.and.coordinated.processes.for:

•. acquiring,. collecting. and. documenting. the.receipt. of. new. materials. to. support. a. com-prehensive.approach.to.acquisitions

•. identifying.and.liaising.with.potential.donors.to. coordinate. communications. and. support.positive.relationships.with.the.community

•. documenting.the.preservation.requirements.for. all. materials. in. all. media. to. prioritize.materials. at. risk. while. making. best. use. of.resources

•. providing. online. access. to. descriptions. and.catalogs to ensure users are able to find rel-evant.materials.from.throughout.the.institu-tion.regardless.of.format.or.type

•. digitizing.historical.materials,.from.historical.publications.to.archival.records.to.images.of.three-dimensional. artifacts,. to. provide. the.widest. possible. access. to. the. institution’s.holdings .

Staff members across the division are work-ing. closely. on. integration. initiatives,. bringing.together.their.unique.expertise.and.knowledge.and. looking. beyond. the. traditional. “silos”. of.libraries.versus.archives.versus.museums ..

The. goal. is. to. identify. new. and. creative.approaches. to. collecting,. documenting,. pre-serving.and.sharing.the.wealth.of.resources.that.illustrate.Alaska’s.past.and.present .

Page 14: LAM Concept FULL 09-14-2010 Web

10 ECI/HYER :: THA ARCHITECTURE

functional adjacency diagrams

Page 15: LAM Concept FULL 09-14-2010 Web

11Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

SPACE.NEEDSUPDATE

Through. numerous. stimulating. discussions.with the Executive Committee, staff and the Design.Team,.a.collaborative.method.of.working.emerged .. This. will. be. facilitated. by. an. integra-tion.of.spaces. in. the.new.facility ..Together.the.Library,. Archives,. Museum,. Administration. and.Technical.and.Imaging.Services.explained.to.the.Design.Team.what.services.they.provide.to.the.State.and.how.work.is.accomplished.within.their.current.space ..From.these.meetings.surfaced.an.understanding.of.what.each.section.shares.and.where potentially conflicting differences exist in the.program.requirements .. It. is. important.that.the.design.and.program.create.space.that.allows.collaboration in new and yet unidentified ways.

Each.section.collects,.preserves,.explains,.inter-prets,. shares. and. communicates .. Within. each.of. these. areas. are. both. nuanced. and. notice-able. procedural. distinctions .. The. Design. Team.worked. with. the. user. group. to. understand. all.the.possible.areas.of.integration.that.should.be.considered.during.the.programming.process.and.to find ways of addressing technical variations.

Collecting.is.done.both.through.outreach.result-ing.in.donations.and.through.systematic.collect-ing.and.purchasing ..New.materials.are.evaluated.for.issues.that.must.be.addressed.prior.to.being.entered. into. the. collection .. The. Museum. and.

Historical. Collection. (Library). have. the. most.issues. with. potential. contamination .. An. isola-tion. room. will. be. used. by. these. two. sections.and. by. Archives. when. necessary .. The. Museum.needs.a.direct.access.from.the.loading.dock.into.the.Exhibit.area.for. touring.shows ..Library.and.Archives. also. need. a. convenient. way. to. bring.materials. into. the. processing. area. from. receiv-ing ..The. loading/receiving.area.begins.the.back.of.house.integration.of.the.sections .

Material.preservation.involves.the.treatment.of.objects.for.contaminants,.repair.and.storage ..All.sections.have.some.level.of.paper.conservation,.so. an. area. to. serve. this. need. has. been. added.to the program. Storage has different security and.environmental.requirements.for.the.various.collections ..The.Museum.collection.requires.the.highest.level.of.security ..The.Museum,.Archives.and Historical Collections all require specific and. similar. environmental. controls .. Informa-tion. Service’s. (Library). Collection. is. browsable.and.has.the. lowest.security.and.environmental.demands ..The.various.collections.also.grow.or,.potentially, contract at different rates. A large secure. storage. area. shared. between. Archives.and.the.Historical.Collection.gives.potential.for.the.line.between.these.sections.to.move.as.stor-age.needs.change ..

The. preservation of these collections benefits all.Alaskans,.a.small.child.may.develop.a.lifelong.interest. in. history. by. visiting. the. Museum;. an.intern. for. a. State. Senator. may. look. for. prec-edent.in.the.State.Archives ..

Each.section.currently.“explains”.its.collections.through a different catalog system. The end goal.of.any.cataloging.system.is.clear.collection.access ..

When.visiting.the.new.building.looking.for.infor-mation.on.a.subject,.the.public.should.be.able.to.see.what. is.available.from.each.of.the.sections.without having to run to different locations and be.confused.by.numerous.cataloging.methods ..As. the. sections. develop. an. understanding. of.what.resources.each.has,.they.will.better.assist.patrons in their search for information. The staff is.also.looking.at.ways.to.make.cataloging.more.transparent .. These. issues. impact. the. building.program.in.a.number.of.ways ..

Upon.coming.into.the.new.facility.it.will.be.evi-dent. where. to. enter. the. Museum. Exhibit. area.and.how.to.access.the.other.collections ..There.will.be.one.entrance.to.a.reading/research.room.to. serve. Information. Services,. the. Historical.Collection. and. Archives .. A. service. desk. will. be.attended by staff who can direct patrons to items in all the collections or to another staff

Page 16: LAM Concept FULL 09-14-2010 Web

12 ECI/HYER :: THA ARCHITECTURE

member.who.will.help.with.the.search ..This.is.a.collection.for.all.Alaskans;.remote.access.should.be.as.comprehensive.as.possible ..

For the staff, collaboration will mean the poten-tial.of.cross-disciplinary.projects.with.the.goal.of.enriching.the.understanding.of.these.important.State resources. All staff from the Library and Archives and some staff from the Museum will occupy a mostly open office space and share a large.processing.area ..Special.project.rooms.will.be.located.around.the.building.to.facilitate.these.cross-disciplinary.endeavors ..

Each. of. the. sections. interprets and commu-nicates. its. collections. for. the. public,. though.method.and.level.of.interpretation.vary ..This.adds.to.the.discussion.of.overlapping.endeavors ..

Sharing. the. body. of. knowledge. stored. in. the.building and staff with greater Alaska is a primary goal. of. the. Library. Archives. Museum. Project ..Outreach. will. be. facilitated. through. the. use. of.distance.learning.technology.in.meeting.rooms ..

Spaces will be provided for visiting State staff and. Library. Archives. Museum. personnel. will.continue. to. share. their. resources. through. the.internet. and. through. actual. transport. of. items.throughout. the. State .. The. Museum. shares. its.objects.in.a.number.of.ways ..The.most.apparent.is. the. exhibit. hall. that. provides. large. numbers.of. visitors. a. broad. look. into. Alaskan. history ..Archives. and. Historical. have. very. similar. meth-ods.of.sharing.collections ..The.documents.need.to.be.monitored.at.all.times.and.do.not.circulate.outside.of. the.research.room .. Information.Ser-vices.has.both.a.circulating.and.non-circulating.collection ..

Understanding. how. each. section. shares. its.collection. was. essential. to. developing. the. pro-gram.for.each.viewing.area ..By.placing.a.secure.research.room.within.the.shared.reading.room,.Archives,. Historical. and. Information. Services.can work side-by-side, sharing material and staff resources ..There.are.also.ways.to.integrate.the.Museum.into.other.areas.of.the.building ..Exhib-

its. will. be. interspersed. throughout. the. facility,.possibly. suspending. items. from. the. ceiling. in.public.areas,.such.as.the.lobby,.and.sometimes.displaying.them.in.secure.cases ..Within.the.read-ing.room,.the.Museum.book.collections.will.be.accessible.to.the.public ..

Meeting.rooms,.classrooms,.and.an.auditorium.that.seats.120.people.will.be.used.for.numerous.educational functions. A store will offer items appropriate.to.each.of.the.collections.and.a.café.will.serve.the.public ..

The.centerpiece.of.the.building.is.the.main.lobby ..It. will. serve. not. just. as. a. passageway. to. other.rooms. and. a. large. social. gathering. area. but,.most. importantly,.a.place.where.the.extraordi-nary. nature. of. this. program. will. unfold. to. the.visitor ..This.building.aspires.to.support.a.new.era.of. collaboration. between. the. Library,. Archives.and.Museum,.enriching.the.lives.of.all.Alaskans.with.its.rich.resources .

Page 17: LAM Concept FULL 09-14-2010 Web

1�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

8/23/2010

SPACE LIST SUMMARY SHEET Net SF Total Gross SF

Public Area 13,770 17,213

Lobbies 5,260

Meeting Rooms/Auditorium/Classrooms 4,650

Retail 1,700

Misc. 2,160

Administration 4,527 5,885

Offices 827

Meeting Rooms 800

Workrooms 1,600

Misc. 1,300

Unassigned Space 16,150 17,765

Office/Workroom 450

Mechanical Spaces 10,700

Electrical/Data Spaces 2,520

Janitorial Spaces 180

Loading 1,420

Misc. 880

LAM Reference Area 25,166 32,716

Offices 2,964

Reading/Research Rooms 9,322

Workrooms 2,400

Secure Storage 10,000

Misc. 480

Digital and Imaging Services 4,769 6,200

Offices 1,069

Workrooms 1,100

Storage Area 400

Lab Area 2,100

Misc. 100

Museum 34,253 44,529

Offices 1,453

Gallery Space 16,000

Workrooms 4,300

Secure Storage 10,000

Storage Area 1,300

Misc. 1,200

TOTAL 98,635 124,307

Page 18: LAM Concept FULL 09-14-2010 Web

14 ECI/HYER :: THA ARCHITECTURE

the design concepts are inspired by waterside development patterns in juneau and statewide

Page 19: LAM Concept FULL 09-14-2010 Web

1�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Concept

The.new.facility.will.occupy.a.site.near.the.State.Capitol,.serving.the.needs.of.state.agencies.locally.and.a.broader.network.of.constituent.agencies.throughout.the.state ..It.will.act.as.the.central.repository.for.the.exceptional.historical.collections.of.the.State..Library.and.Archives,.as.well.as.the.State.Museum’s.diverse.collection.of.cultural.artifacts.–.a.major.public.attraction.during.the.summer.tourist.season ..

The.initial.design.ideas.for.the.new.Alaska.State.Library.Archives.and.Museum.Project.were.developed.through a series of staff and commu-nity.workshops.beginning.in.April.of.2010 ..During.the.workshops.a.series..of.themes.emerged ..These.themes..are.used.to.guide.the.design.process:

Our Goals. The.Building.must:

•. Fit.into.Juneau’s.historic.urban.fabric,.while.creating.a.vibrant.Library.Archives.Museum.that.celebrates.the.State.of.Alaska’s.past,.present.and.future .

•. Integrate.and.streamline.Library,.Archives.and Museum operations for greater efficien-cy.and.responsiveness.to.the.public .

•. Increase.virtual.access.to.the.collections.and.resources.for.the.State’s.residents.and.beyond ..

• Be lasting, energy-efficient and sustainable.

The. preliminary. design. of. the. facility. is. rooted.in. the. State’s. cultural. history .. The. site. layout.reflects the fan of the docks that historically occupied. the. site. and. the. roof. form. is. reminis-cent of the wing and feathers of a bird in flight. The.building.and.site.is.viewed.from.many.high.vantage. points. from. around. the. city;. including.the. Governor’s. Mansion. on. Calhoun. Avenue.and from State Office Building. An inspired and expressive.roof.form.will.be.a.beacon.to.the.city,.embracing.and.welcoming.visitors.from.around.the.world .

Building PlanningBuilding Siting and Entry: The. building. is. sited.facing.east.toward.downtown.Juneau ..The.main.entry. connects. to. the. large. public. plaza. which.is. bounded. to. the. east. by. Whittier. Street .. The.extension. of. the. northeastern. café. into. the.plaza.helps.protect.the.covered.entry.from.the.strong.northeasterly.Taku.winds.that.occur.peri-odically.during.the.winter.season ..The.decision.to.place.the.entry.at.this.location.was.driven.by.two.primary.concerns:.1).The.new.building.and.entry.plaza.provide.a.civic.focal.point.and.strong.terminus. to. the. future. plaza. extending. across.Whittier Street to the State Office Building; 2) By placing. the. entry. and. circulation. core. towards.the.northeast.of.the.site,.tremendous.views.to.the. north,. south,. and. east. could. be. preserved.for enjoyment by library users and staff alike.

General Building Order:. The. design. includes. a.generous light-filled, double height entry lobby with.a.café,.auditorium.and.shared.public.meet-ing rooms on the main floor. The café, auditorium and. meeting. rooms. are. immediately. accessible.for.evening.use.without. impacting.the.security.for. library. or. museum .. Washrooms. are. located.conveniently.near.the.entry,.servicing.the.after.

ARCHITECTURAL.NARRATIVE

Page 20: LAM Concept FULL 09-14-2010 Web

1� ECI/HYER :: THA ARCHITECTURE

hour. use. of. these. functions .. The. museum. is.located on the main floor to accommodate the large.groups.of.visitors.during.the.active.summer.months.and.to.protect.artifacts.from.direct.light ..The reading room is located on the second floor made.accessible.by.a.large.public.stair.allowing.patrons.to.enjoy.the.dramatic,.unfolding.views.to the north, south and east. A staff entry, build-ing.loading.and.service.components.are.located.on. the. northwest. corner .. Space. planning. has.been greatly influenced by the desire to have

maximum.visual.control.by.a.minimal.number.of.staff members.

Ground Floor Planning: Entry. to. the. interpre-tive.portions.of. the.museum. is.adjacent. to. the.museum.store ..This.allows.a.single.point.of.con-trol that can be managed by 1-2 staff persons, and encourages.patrons.to.purchase.items.from.the.store.or.visit.the.café ..The.interpretive.space.is.immediately. accessible. from. the. back-of-house.functions,. including. exhibit. prep. and. museum.

storage,.which.in.turn.is.immediately.accessible.from. the. northwest. loading. and. service. entry ..During.the.next.phase.of.design,.the.interpretive.vision. will. be. established. and. the. body. of. the.interpretive.space.will.be.fully.understood .

Upper Floor Planning: The.main.Reading.Room.is.conceived.as.a.high.ceilinged.‘great.room’.with.stacks. in. the. center. and. reading. opportunities.along. the. perimeter .. Controllable. daylight. will.enter. the. room. from. high. clerestory. windows.located.around.the.room’s.perimeter ..The.room.is easily reconfigurable in order to adapt to the changing.nature.of.libraries ..Patrons.may.enjoy.views. of. Mount. Juneau. and. Mount. Roberts. to.the.north.and.east.as.well.as.distant.views.down.Gastineau.Channel.to.the.south ..The.south.por-tion.of.the.great.room.is.entirely.glazed.to.give.the.feeling.of.hovering.above.the.amazing.view ..Access.to.the.library.will.be.from.the.large.land-ing.located.at.the.top.of.the.public.stair ..Patrons.will.have.clear.and.easy.access.to.the.circulation.desk. and. have. controlled. access. into. the. adja-cent.research.room ..

Basement: The. design. includes. a. basement. in.order. to. better. accommodate. the. parking. and.mechanical. needs. of. the. Library,. Archives. and.Museum .. Eighty. parking. spaces. are. planned.with. vehicular. access. from. Whittier. Street. into.the.northeast.corner.of. the.site ..A. large.public.elevator.and.stair.will.provide.access.to.the.pub-lic.lobby.for.the.Museum.and.Library.above ..

view opportunities from site

Page 21: LAM Concept FULL 09-14-2010 Web

1�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Sustainable DesignEnergy. conservation. is. a. primary. concern. for.the.State.Library,.Archives.and.Museum.Project ..Maximizing the benefits of natural lighting and minimizing. energy. loss. are. achievable. goals ..At the outset of the project, staff and patrons expressed. a. strong. desire. to. provide. daylit.spaces. and. to. minimize. long-term. operating.costs .. Space. planning. and. the. design. of. the.building. “skin”. will. be. carefully. coordinated. to.take.advantage.of.daylight ..The.goal.moving.for-ward.will.be.to.integrate.time-tested.“passive”.and. “low-tech”. strategies. with. the. economical.and.complementary.use.of.new.technologies.in.an effort to save energy while at the same time providing. for. the. well-being. of. patrons .. Deci-sions.will.be.guided.by.real.data.based.on.energy.modeling.of.the.building .

The energy-efficiency strategy will primarily focus on.the.building.“skin .”.Roof.and.walls.will.have.continuous. insulation. without. thermal. bridges.and.will.be.a.vast.improvement.over.traditional.construction.assemblies ..Other.assemblies,. like.windows,. will. be. thermally. “broken”. and. will.be. triple-glazed. where. appropriate .. Since. cool-ing.loads.in.southeast.Alaska.are.relatively.light,.

cooling.will.be.handled.primarily.through.natural.ventilation. and. economizer. cooling .. The. more.highly. controlled. spaces. in. the. museum. and..storage.spaces.will.likely.require.some.means.of.mechanical.cooling ..

To ensure the success of these strategies, staff and. operations. personnel. will. be. comfortable.with.the.design.direction.and.should.be.part.of.the. start-up. and. testing. phases. of. the. project ..Emphasis.will.be.given.to.building.systems.that.can.be.easily.maintained.and.operated.by. local.personnel .

Materials and MethodsIn. all. areas. of. construction,. emphasis. will. be.placed.on.materials.and.assemblies.that.provide.low-tech. and. economical. construction .. This.means.of.careful.planning.is.based.on.standard.material. units. that. facilitate. little. construction.waste .. Durable. materials. and. assemblies. will.be.favored.over.those.that.are.complicated.and.have high maintenance. Wherever practical, fin-ish.materials.will.be.avoided,.allowing.structural.materials.to.be.expressed.thus.minimizing.over-all.material.consumption .

historic Juneau dock forms

site plan sketch

inspiration sketch

Page 22: LAM Concept FULL 09-14-2010 Web

1� ECI/HYER :: THA ARCHITECTURE

CONCEPTDIAGRAMS

Ground.Floor.Planning Upper.Floor.Planning

Page 23: LAM Concept FULL 09-14-2010 Web

19Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

... The site layout reflects the fan of the docks that

historically occupied the site, and the roof form is

reminiscent of the wing and feathers of a bird in flight ...

Page 24: LAM Concept FULL 09-14-2010 Web

20 ECI/HYER :: THA ARCHITECTUREFirst Floor Plan

M W

Ex.Stor. C

ol. D

isp.

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

Wood Work Shop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

UP

Ground.Floor.Plan

CONCEPTFLOOR.PLANS

Page 25: LAM Concept FULL 09-14-2010 Web

21Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Elev.

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

Video Conf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical and Service Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMOffices

Open

Second Floor Plan

DN

Roof

Upper.Floor.Plan

0 20 40 80’

KEY

Public Activity Space

Museum Exhibit Space

Staff | Staff Support

Storage

Building Support

Library Space0 20 40 80’

KEY

Public Activity Space

Museum Exhibit Space

Staff | Staff Support

Storage

Building Support

Library Space

Page 26: LAM Concept FULL 09-14-2010 Web

22 ECI/HYER :: THA ARCHITECTURE

Lower.Level.Parking.Plan

Elev.

HCHC

HC

HC

Mechanical

Parking

Lower Level Parking Plan

0 20 40 80’

KEY

Public Activity Space

Museum Exhibit Space

Staff | Staff Support

Storage

Building Support

Library Space

Page 27: LAM Concept FULL 09-14-2010 Web

2�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

project location

Page 28: LAM Concept FULL 09-14-2010 Web

24 ECI/HYER :: THA ARCHITECTURE

landscaping will be informed by local textures and native plantings

Page 29: LAM Concept FULL 09-14-2010 Web

2�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Site Context and LocationSituated at the confluence of important natural borders. and. urban. corridors,. the. site. presents.opportunities.to.create.connections,.to.link.the.waterfront. to. the. site,. to. further. develop. the.arboretum,. and. to. create. a. public. plaza. as. an.important.outdoor.space ..

Located. between. the. Gastineau. Channel. and.Mount. Juneau,. the. site. occupies. an. area. that.was. once. a. tidal. beach .. A. spillway. or. tailrace.from.an.historic.hydroelectric.plant.and.a.shop-ping. center. form. the. western. boundary. to. the.site .. Egan. Drive,. an. important. highway,. along.with.a.restaurant,.hotel.and.radio.station.forms.the.southern.boundary,.with.the.waterfront.one.block. further. south .. The. eastern. site. boundary.is.Whittier.Street,.which.separates.the.museum.site. from. a. collection. of. surface. parking. lots,.Willoughby Street, the State Office Building and downtown. Juneau .. Immediately. north. of. the.site.is.a.motel,.restaurant.and.Willoughby.Street.where.the.outline.of.the.beach.is.still.somewhat.visible ...Two.well.used.pedestrian.corridors.serve.the site: between the State Office Building and the. shopping. center. (east-west). and. from. the.waterfront.to.the.museum.(south.to.north) ..

Site ConditionsThe site is built on rock fill that dates from the city’s hard-rock mining period. The fill is porous and. is. subject. to. inundation. by. tidal. waters ..Generous.precipitation.and.maritime.conditions.make.this.area.conducive.to.growing.plants.from.most.parts.of.Alaska ..Prevailing.winds.enter.the.site.from.the.southeast.with.the.occasional.Taku.winds.coming.from.the.northeast .

The area to the east of the site is typified by a lack.of.clear.connectivity.and.scattered.parking.lots,. in. spite. of. being. a. major. pedestrian. pas-sageway .. The. tailrace. on. the. west. side. of. the.site. is. partially. exposed. with. the. power. com-pany.planning.on.completing. the. piping.within.the.next.four.years ..Currently,.tour.buses.enter.the.site.and.pull.directly.to.the.building.entry ..A.collection.of.trees.and.shrubs.with.interpretive.signs.forms.an.arboretum.on-site .

Vehicular Access and CirculationThis plan proposes to relocate the bus drop-off zone.to.the.Whittier.Street.edge ..This.move.will.allow.the.site.to.reclaim.its.frontage.as.a.plaza.and. event. space,. keeping. buses. close. to. the.street for easy arrival and departure. The staff

surface. parking. and. loading. facilities. are. relo-cated.to.the.north.side.of.the.building.and.will.accommodate.up.to.two.tractor.trailers.and.two.smaller.delivery.vehicles ..Public.parking.is.under.the.building .

Pedestrian Circulation and Entrance PlazaPedestrian. access. to. the. site. will. come. primar-ily.from.the.east.with.clear.views.into.the.entry.plaza ..This.east.access.from.downtown.and.the.State Office Building will be further strengthened by.the.plaza’s.future.extension.into.the.eastern.parcel.across.Whittier.Street ..

The. other. important. pedestrian. access. to. the.site. is. from. the. south .. Pedestrian. access. over.Egan. Drive. is. addressed. with. a. path. that. can.connect. to. a. proposed. pedestrian. bridge. that.will.link.the.existing.waterfront.path.to.a.north-south.pedestrian.path ..This.passage.will.provide.an.opportunity.for.tourists.to.cross.the.highway.to.the.site ..The.path.will.continue.north.through.a. naturalized. corridor. along. the. western. site.boundary.connecting.to.Willoughby.Street ...

SITE & LANDSCAPE.NARRATIVE

Page 30: LAM Concept FULL 09-14-2010 Web

2� ECI/HYER :: THA ARCHITECTURE

LandscapeThe. entry. plaza. is. designed. to. be. low. mainte-nance, safe and flexible enough to accommo-date.a.variety.of.event.programs.and.uses,.and.to.be.an.elegant.and.enjoyable.public.space ..This.entry plaza is seen as a first step towards creat-ing.a.public.open.space.and.arboretum.that.later.expands. towards. the. east. to. create. additional.public.space.and.to.continue.uniting.the.district ..

The.plaza.landscape.will.represent.a.balance.of.plantings and hardscape, reflecting local materi-als and textures. Due to the rock fill at the site, trees.will.be.placed.in.a.raised.planting.area.sup-ported.by.stone.and.good.topsoil ..Sightlines.are.maintained.throughout.the.planted.areas.by.the.use. of. low. growing. herbaceous. plants .. Raised.plantings will define paths within the plaza space and. provide. ample. topsoil. depth. for. trees. and.other.plants ..

The. arboretum. will. be. a. lightly. forested. zone.on.the.south.side.of.the.museum,.providing.an.entry.to.the.north-south.trail ..On.the.north.side.of the building, tree plantings will buffer the staff entry.and.parking.area ..Plaza.paving.and.planter.designs will reflect the glacial activity typical of. the. region:. exposed. rock. faces;. scored. and.grooved.paving.surfaces.will.provide.a.sense.of.detail. and.directionality ..Seating.and.other. fur-nishings will further reflect the rock outcrops found.in.the.nearby.mountains.and.the.forms.of.dugout.canoes ..

Mall.Concept.--.Interim.Build-out

Mall.Concept.--.Full.Build-out

New.LAM.building1

State Office Building2

proposed.pedestrian.mall3

1

2

3

1

2

3

Page 31: LAM Concept FULL 09-14-2010 Web

2�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

CONCEPTSITE.PLAN

18

8

4

2

36

5

7

5

5

Egan...Avenue

Willoughby...Avenue

Whittier...Street

9

building.footprint1

entry.plaza2

underground.parking.entry3

bus drop-off4

pedestrian.trails5

service/maintenance.area6

staff parking7

art/sculpture8

outdoor.café.seating9

Page 32: LAM Concept FULL 09-14-2010 Web

This page intentionally left blank.

Page 33: LAM Concept FULL 09-14-2010 Web

29Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

IntroductionThe.proposed.Library.Archives.Museum.project.site.is.on.property.owned.by.the.State.of.Alaska ..ECI/Hyer provided R&M the LAM Concept Design Full. Report. on. September. 2,. 2010. to. assist. in.preparing.the.civil.concept.narrative ..Site.topo-graphic. survey. has. been. previously. been. per-formed by our firm and included as an Exhibit to the.concept.narrative.report ..

The.proposed.LAM.Building. is. located.adjacent.to. Willoughby. Avenue. to. the. north. and. to. the.east.by.Whittier.Avenue,.both.which.is.City.and.Borough.of.Juneau.(CBJ).maintained.and.owned.paved. roadways .. To. the. northwest. is. located.private. developed. property. including. the. Drift-wood.Lodge.and.Salvation.Army.Church ..To.the.south. lie. the. Prospector. Hotel. and. the. KTOO.Radio.building ..To.the.west.lie.the.Alaska.Electric.Light and Power (AEL&P) Gold Creek Tailrace Flume.and.Foodland.Shopping.Center ..The.legal.description.of.the.LAM.property.is.Lots.4,.5,.6,.9.and.12.Front.(FR),.Block.Sixty.Six.(66),.Tidelands.Addition.to.the.CBJ ..

The.LAM.Building.proposal.consists.of.a.ground.floor, upper floor and lower level below grade parking.structure ..The.facility.will.include.spaces.for. museum,. archives,. auditorium,. meeting.rooms, offices, restrooms, mechanical room,

elevator,.parking.garage.and.other.uses ..Domes-tic/fire water supply and sanitary sewer system will.be.supplied.through.the.CBJ.public.utilities ..

The. topographic. survey. prepared. for. the. site.reveals. that. Lots. 4,. 5,. and. 6. are. developed. as.the. existing. State. of. Alaska. Museum .. With. the.exception.of.the.museum.building.and.the.tem-porary annex, Lots 4, 5 and 6 are relatively flat and. are. covered. by. lawn. areas,. landscaping,.sidewalks,. an. asphalt. paved. access. road. and.parking. areas. accessing. Whittier. Street .. Lots. 9.and.12.FR.are.predominantly.developed.as.fairly.level. gravel. surfaced. parking. areas. accessing.onto.Willoughby.Avenue ..

The. following. is. our. conceptual. civil. design.based.on.our.understanding.of.the.Project ..Site.civil issues will be further refined to determine the. most. economical. and. intelligent. solutions.for.the.Project.during.the.Schematic.and.Design.Development.design.phases ..

Site Geology and SoilsPreliminary.research.of.general.site.geology.and.soils. on. adjacent. properties. indicates. that. the.site.was.originally.an.alluvial.soils.formed.by.Gold.Creek. The alluvial soils were filled with mine tail-ings.waste.rock.from.the.Alaska.Juneau.(AJ).Mine.from.the.1910.through.1940’s ..The.depth.of.this.material.varies ..The.granular.deposits.below.the.

AJ rock fill are often referred to as outwash and glacio-marine. deposits .. These. soils. commonly.consist.of.gray.to.brownish.light.gray.sand.with.gravel with pockets of fine sand/silt deposits some of which offer low bearing values.

Ground WaterGround. water. at. this. site. will. be. dependent.upon. the. tide. level. of. Gastineau. Channel. and.most likely fluctuate within the tide range on any. given. day .. Structural. foundation. members.and.site.construction.activities.below.elevation.+20’ mean lower low water would be influenced by. the. tide .. Dewatering. the. project. site. during.construction. is. important .. Mitigation. methods.for.controlling.construction.surface.and.ground-water.include.but.are.not.limited.to:

1 .. All.below-grade.portions.of.the.building.are.properly.water.and.moisture-proofed.by.waterproofing the below grade foundation walls.and.placement.of.a.plastic.vapor.bar-rier below the floor slabs.

2. Surface water is effectively isolated from entering.all.soils.below.foundation.footings.and floor slabs.

3 .. Surface.grading.is.accomplished.in.a.man-ner.that.will.positively.divert.surface.water.runoff away from the structure.

CIVILNARRATIVE

Page 34: LAM Concept FULL 09-14-2010 Web

�0 ECI/HYER :: THA ARCHITECTURE

4. Concentrated runoff is controlled by install-ing.perimeter.foundation.and.roof.drain.systems.to.route.surface.and.subsurface.drainage.away.from.the.building .

Driving and Parking SurfacesProposed.access.road.to.the.below.grade.park-ing.garage.is.assumed.to.be.a.two.lane.asphalt.paved.surface.with.concrete.curb.and.gutters.on.both.sides.and.sidewalk.on.one.side.of.the.road ..Asphalt surfaced staff parking areas, bus drop off zone, and the access road to the lower level parking.garage.are.anticipated.to.have.3”.asphalt.pavement.with.9”.depth.of.base.course,.grading.D-1.pending.outcome.of.geotechnical.exploration.recommendations ..Concrete.curbs.with.sidewalk.will be installed at the bus drop off. Architectural concrete.4”.thick.with.6”.depth.of.D-1.beneath.having. varying. widths. are. planned. in. the. plaza.area ..Parking.stalls.should.be.delineated.with.4”.wide.yellow.parking.stripes.and.accessible.park-ing.stalls.delineated.with.accessible.blue.painted.stripes. and. appropriate. accessible. signage ..Traffic control signs (Stop, No Parking, Loading Zone,.Accessible.etc .).will.meet.current.Manual.of.Uniform.Control.Devices ..D-1.gravel.paths.are.also.planned.around.the.site ..Path.width.will.be.approximately.5’.with.4”.depth.of.D-1 ..

Site UtilitiesWater. and. sewer. utilities. will. be. connected.to. the. CBJ. public. systems. located. within. Wil-

loughby.Avenue.and.Whittier.Street ..No.onsite.disposal.of.wastewater.or.private.well.water. is.anticipated. No unusual difficulties are foreseen provided.standard.design.and.construction.tech-niques.are.employed,.such.as,.proper.bedding.of.buried pipes, compacting trench backfill to 95% of modified proctor and sufficient pipe embed-ment.to.prevent.freezing.(5’.to.top.of.waterline) ..Sewer.and.water.lines.should.be.constructed.in.accordance.with.applicable.codes.and.standards.of. the. State. of. Alaska. Department. of. Trans-portation/Public. Facilities. and. CBJ. Engineering.Department ..

Water ServiceAn.existing.16”.ductile.iron.water.main.with.6”.ductile. iron. water. service. stub. out. with. gate.valve.is.located.near.the.northeast.corner.of.Lot.9 ..A.6-inch.water.main.is.assumed.to.be.installed.to meet domestic and fire protection (sprin-klered.system).needs.for.the.building.per.AMC.Engineers .. Connection. to. this. existing. water.service.will.be.made.and.the.new.6”.water.line.installed. to. the. building. mechanical. room .. It. is.assumed that there will be adequate water flow and.pressure.with.a.6”.water.line.but.this.will.be.confirmed during the schematic design phase of the.project ..An.alternative.option.for.water.ser-vice. to. the. building. involves. connecting. to. the.existing. 8”. ductile. iron. water. main. in. Whittier.Street .. This. would. involve. cutting. across. Whit-tier. Street. to. connect. the. new. 6”. ductile. iron.

line.to.the.existing.8”. line.and. installing.a.new.6”. gate. valve .. The. existing. museum. building. is.connected.to.the.water.line.in.Whittier.Street ..

Sanitary Water ServiceTwo. options. exist. for. routing. wastewater.generated. from. the. building. via. gravity. sewer.methods. to. the. CBJ. public. sewer. system .. The.first involves connecting to the existing 10” PVC sanitary.sewer.main.line.located.west.of.the.site.on. Lot. 13A .. The. sewer. main. is. reported. to. be.installed over 9’ in depth below the existing fin-ished.surfaces ..The.new.sewer.line.in.this.option.would. have. to. be. routed. below. the. existing.AEL&P 60” CMP which carries water from the upstream. power. plant .. Permission. would. need.to be granted from AEL&P, the owner of Lot 13A and. CBJ. to. make. this. connection .. The. second.option. involves. connecting. to. the. existing. 10”.AC.sanitary.sewer.line.located.in.Whittier.Street ..This. line. is. also. fairly. deep. below. the. existing.ground.surface ..

Collection.and.discharge.of.wastewater.from.the.new.LAM.building. is.assumed.to.be. via. gravity.methods.through.8”.PVC.piping ..Final.sizing.of.the wastewater line will be confirmed with the mechanical. design. engineers. in. the. schematic.design. phase .. Sanitary. sewer. cleanouts. will. be.installed. 5’. from. the. building. wall. and. sanitary.sewer.manholes.installed.as.necessary ..Asphalt.pavement. removal. and. replacement. will. be.

Page 35: LAM Concept FULL 09-14-2010 Web

�1Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

required.for.the.installation.in.either.option ..All.wastewater. generated. from. this. site. would. be.treated.at.the.CBJ.wastewater.treatment.plant ..

Storm Water SystemStorm. drain. systems. exist. within. Willoughby.Avenue. and. Whittier. Street .. It. is. assumed. for.this. concept. narrative. that. site. storm. drainage.will.be.designed.to.be.routed.to.each.of. these.areas .. An. 18”. CPP. storm. drain. line. with. curb.inlets.exists.on.Willoughby.Avenue.which.would.be. connected. to. new. storm. drain. pipe. from.this. project .. This. system. is. not. deep. (5’. below.finish street grade) but we assume there will be.enough.elevation.drop.to.allow.storm.water.from the proposed staff parking area and service area. to. be. collected. in. storm. drain. structures.and. piped. underground. in. 12”. CPP. pipe. to. the.Willoughby. Avenue. system .. Foundation. and.roof.drains.would.also.be.routed.to.this.side.of.the.site.where.feasible ..Loading.dock.walls.are.assumed.to.be.elevated.above.grade,.therefore.no.separate.system.is.required.for.drainage ..

Storm.drainage.collected.on.the.eastern.half.of.the.site.where.the.underground.parking.access.road, entry plaza, bus drop-off zone and art/sculpture areas have been identified, will drain into.the.existing.storm.drain.system.on.Whittier.Street ..An.existing.18”.CPP.storm.drain.pipe.with.storm.drain.structures.is.located.on.the.east.side.of. Whittier. Street .. The. existing. museum. storm.drain. is. currently. connected. to. this. system ..

Strategically.placed.storm.drain.structures.with.12”. CPP. gravity. storm. piping. between. them.will drain the drop-off zone, hard-scape areas, access.roads.and.sidewalks ..Roof.drains.would.be. routed. to. the. ground. surface. and. routed.away.from.the.building.foundation.walls ..Foun-dation. drains. would. be. routed. to. storm. drain.catch. basins/manholes. if. elevations. are. found.to.be.adequate ..The.lower.level.parking.garage.will.require.a.storm.drain.collection.system.and.an.electronic.submersible.pumping.system.with.high. level.alarms.to.discharge.any.storm.water.accumulated.in.the.parking.garage.to.the.gravity.storm.system ..

Required Development PermitsThe.following.is.a.list.of.potential.development.permits.that.may.be.required.for.this.project:

•. CBJ.Conditional.Use.Permit

•. CBJ.Grading.and.Drainage.Permit

•. CBJ.Building.Permit

•. CBJ.Utility.Connection.Permit

•. Utility.service.coordination.for.telephone,.electric.and.Cable.TV ..

It is assumed the site is classified as “uplands” and.that. it.would.not.fall.under.the.jurisdiction.of.the.U .S ..Army.Corps.of.Engineers.(COE) ..

Page 36: LAM Concept FULL 09-14-2010 Web

This page intentionally left blank.

Page 37: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

GeneralThe.structural.design.will.be.developed.accord-ing.to.the.applicable.building.codes.and.design.standards .. These. codes. and. standards. include,.but.are.not.limited.to.the.following:

•. 2009.International.Building.Code.(IBC)

•. ASCE.7-08.Minimum.Design.Loads.for.Build-ings.and.Other.Structures

•. AISC.341.Seismic.Provisions.for.Steel.Build-ings

The. building. will. be. designed. as. an. Occupancy.Category.II.structure.(standard.occupancy),.per.ASCE.7.Table.1-1 ..As.a.result,.importance.factors.for.snow,.wind.and.seismic.loads.are.all.1 .0 ..This.level.of.design. is. intended.to.ensure. life.safety.during.a.design-level.event .

Structural Systems SelectionIn. general,. many. factors. will. be. considered.when. selecting. the. materials. and. systems. for.the.building’s.structure ..Some.of.the.questions.that.will.be.answered.during.design.include.the.following:

•. Life.safety:.How.well.will.the.structural.systems.perform.during.catastrophic.wind,.seismic.and.snow.events?

•. Functional.performance:.How.well.will.the.structural.systems.perform.during.normal.use?.(For.example,.is.there.perceptible.vibra-tion of the floor plate underfoot?)

•. Functional.compatibility:.Are.the.structural.systems.compatible.with.the.other.design.disciplines’ functional needs (e.g. fire rat-ings,.routing.of.mechanical.systems)?

•. Constructability:.Do.the.structural.systems.work.with.the.construction.sequencing?.Are.they.consistent.with.locally.available.labor?

• Cost effectiveness: Are we achieving “bang for.the.buck”.and.staying.within.the.project.budget?

•. Cleanliness:.In.areas.where.the.building.con-tents.are.sensitive.to.contamination,.can.the.structural.systems.be.selected.to.minimize.potential.contamination?.(For.example,.in.the.storage/vault.areas,.are.there.structural.systems.that.do.not.need.spray-applied.fireproofing that may degrade over time?)

•. Aesthetics:.In.areas.where.structure.will.be.exposed.to.view,.are.the.materials.compat-ible.with.the.architectural.form?.In.areas.where.the.structure.is.NOT.exposed.to.view,.are.the.structural.members.(e .g ..seismic.braces).able.to.be.concealed?

It. is. anticipated. that. more. than. one. material.will.eventually.be.selected.for.a.given.structural.system. (e .g .. multiple. framing. systems. for. the.building floor plates), based on the answers to the.above.questions .

Foundations and Garage Floor SlabThe.foundation.design.will.be.developed.accord-ing.to.the.recommendations.of.the.geotechnical.engineer, based on the site-specific soils condi-tions ..It.is.known.that.the.general.soil.make-up.consists of man-made granular fill over native tidal beach soils. The granular fill is subject to regular.tidal.saltwater.inundation .

The. foundations. are. anticipated. to. consist.of. driven. steel. piles,. most. likely. H. sections ..Depending.on.the.structural.loads,.piles.may.be.placed.in.groups.or.standalone ..For.example,.at.heavily.loaded.interior.columns,.pile.groups.may.be.required.to.support.the.loads,.whereas.along.a. uniformly. loaded. basement. wall,. single. piles.may.be.spaced.at.regular.intervals .

Piles.will.be.capped.with.cast-in-place.concrete.pile. caps. at. concentrated. load. locations,. and.cast-in-place. concrete. grade. beams. at. uniform.load.locations .

The parking garage floor slab is anticipated to be a. cast-in-place,. mildly. reinforced. (i .e .. non-post-

STRUCTURAL.NARRATIVE

Page 38: LAM Concept FULL 09-14-2010 Web

�4 ECI/HYER :: THA ARCHITECTURE

tensioned).structural.concrete.slab ..The.slab.will.probably.be.designed.for.2-way.action,.spanning.both.directions.to.supporting.grade.beams.and.slab.beam.strips ..For.pricing.purposes,.the.slab.is.assumed.to.be.8.inches.thick,.with.double.mats.of.steel.reinforcing .

Basement WallsAt.least.two.systems.will.be.considered.for.the.basement.wall.construction:

1 .. Cast-in-place.concrete.walls:.With.a.con-crete.wall.system,.the.site.would.be.fully.excavated.before.the.basement.walls.are.constructed ..The.walls.would.be.built.on.top.of.perimeter.grade.beams,.after.the.founda-tion piling, pile caps and garage floor slab are installed. The walls would be backfilled after the main floor plate is constructed. The concrete.walls.are.assumed.to.be.12.inches.thick,.with.double.mats.of.steel.reinforcing .

2 .. Steel.sheet.piling:.With.a.sheet.pile.system,.the.sheets.would.be.driven.before.the.foundation.is.excavated ..After.the.sheets.are.driven,.the.foundation.would.be.exca-vated and the interior foundations and floor slab.would.be.constructed ..The.sheet.piling.would.take.the.place.of.the.H.piling.and.concrete.grade.beams.around.the.perimeter.walls,.and.would.be.designed.to.resist.both.gravity.and.lateral.(soil.retaining).loads ..

Factors. that. will. determine. the. basement. wall.system.selection. include.construction.sequenc-ing, cost, waterproofing design and geotechni-cal.considerations .

Elevated Floor FramingSeveral different floor framing systems are anticipated,.depending.on.the.functional.needs.of the spaces above and below the floor plates. These.systems.are.as.follows:

1. First floor framing over the parking garage: The first floor plate is anticipated to be a concrete.topping.slab.on.composite.steel.floor deck (6-1/2” typical total slab thickness, 8”.minimum.thickness.at.vibration-sensitive.floor areas) on wide-flange structural steel beam.and.girder.framing ..Beams.and.girder.would.be.supported.on.interior.columns.and.perimeter.basement.walls .

2. Second floor framing over “clean” areas: Where.potential.contamination.of.the.building.contents.in.the.space.below.is.a.consideration, the second floor plate will consist.of.a.cast-in-pace.concrete.topping.slab.(4”.minimum.thickness).over.one-way.precast.concrete.slabs.(hollow.core.planks).supported.on.precast.concrete.girders ..Gird-ers.will.be.supported.by.interior.columns.and.perimeter.concrete.bearing.walls ..This.system.eliminates.the.need.for.spray-applied.

fireproofing or gypsum board column wraps, which.could.deteriorate.over.time.and.con-taminate.the.spaces.below .

3. Second floor framing over conventional ar-eas:.Where.contamination.is.not.a.concern,.the second floor plate will be a concrete topping slab on composite steel floor deck (6-1/2” total slab thickness) on wide-flange structural.steel.beam.and.girder.framing ..Beams.and.girder.would.be.supported.on.steel.columns .

Roof FramingThe.roof.framing.systems.will.vary.depending.on.the.architectural.form,.as.follows:

1 .. Architecturally.exposed.library/lobby.roof:.Where.the.roof.structure.is.exposed.and.integrated.into.the.architectural.form,.the.framing.is.anticipated.to.consist.of.plywood.sheathing.on.timber.decking.on.curved.glu-lam.timber.and/or.HSS.beam.framing ..The.beams.will.connect.to.architecturally.exposed.precast.concrete.columns.with.cus-tom.fabricated.steel.connection.hardware .

2 .. Conventional.low.slope.roof.areas:.Where.architectural.expression.is.not.required,.roofs.will.be.framed.with.steel.roof.deck.on.wide-flange structural steel beam and girder framing,.supported.on.steel.columns .

Page 39: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Column FramingThe. column. construction. will. vary. depending.on. the. functional. needs. of. the. surrounding.spaces,.and.the.architectural.aesthetic.needs,.as.follows:

1 .. Lower.level.parking/mechanical.areas:.In.these.areas,.columns.are.anticipated.to.be.structural steel (W shapes). Where fire rating is.required,.columns.may.be.wrapped.and/or.fireproofed. Where vehicle impact resistance is.a.concern,.columns.may.be.protected.by.a.waist-high.concrete.encasement .

2. First and second floor “clean” areas: In the Secure.Storage.and.any.other.sensitive.areas,.columns.will.be.concrete.(precast.or.cast-in-place) ..This.will.eliminate.the.need.for fireproofing and/or column wraps, which could.break.down.over.time.and.contami-nate.the.room.contents .

3. First floor, second floor, and roof areas with exposed.structure:.Where.the.columns.are.exposed.to.view,.they.will.be.precast.con-crete ..Columns.may.be.cast.into.expressive.forms.according.to.the.architectural.design ..Embedded.steel.hardware.will.accept.the.connections of the surrounding floor and roof.framing.members .

4. First and second floor perimeter columns and.columns.at.braced.frame.bays:.In.these.areas,.columns.will.be.structural.steel.(HSS.or.W.shapes) .

Lateral Force Resisting SystemThe. building. will. be. subjected. to. lateral. forces.due.to.wind.and.seismic.events,.and.the.struc-ture.will.be.designed.to.resist.these.forces.and.resolve.them.into.the.ground .

Lateral.wind.forces.are.the.result.of.pressure.and.suction.on.the.building’s.vertical.surfaces ..Wind.loads.are.transferred.to.the.horizontal.roof.and.floor diaphragms by the building’s exterior wall assemblies .

Seismic. forces. are. inertial. forces,. generated.when. the. ground. accelerates. beneath. the.building .. Inertial. forces. will. concentrate. at. the.roof and second floor levels, where the seismic mass is greatest. Foundations and ground floor slabs.are. in.phase.with.the.ground,.and.do.not.contribute. seismic. forces. to. the. above-ground.structure .

The roof or floor deck at each level acts as a hori-zontal.diaphragm.to.transfer.lateral.loads.to.the.vertical.resisting.elements.(steel.braced.frames.and.concrete.shear. walls) ..The. diaphragms.are.connected. to. collector. beams. (drag. struts),.which. accumulate. and. deliver. the. lateral. loads.to.the.vertical.resisting.elements ..Collector.ele-ments. are. designed. for. special. load. combina-tions.and.detailing.provisions.as.required.by.the.building.codes ..In.general,.the.collectors.consist.of.steel.beams,.with.slip-critical.bolted.or.welded.end.connections .

The. vertical. resisting. elements. (braced. frames.and.shear.walls).will.vary.according.to.the.loca-tion.in.the.building,.as.follows:

1 .. Library/lobby.roof:.The.architecturally.exposed.roof.structure.will.be.braced.on.all.sides.by.diagonal.steel.rod.tension.bracing,.deployed in X configurations. Braces may be constructed.with.clevises.and.turnbuckles,.or.other.similar.mechanisms.for.making.the.connections .

2 .. Conventional.low-slope.roofs:.Roof.dia-phragms.will.be.connected.to.buckling-restrained.braced.frames.(BRBF’s),.which.consist of wide-flange beams and columns and.manufactured.diagonal.BRB.bracing.members.(Star.Seismic.“Powercat”.braces.or.equivalent.www .starseismic .net) ..Braces.are.generally.oriented.in.single-diagonal.or.chevron (inverted V) configurations. Diago-nal bracing members will be configured to avoid conflicts with the floor plan and window/door.openings ..BRB.members.and.their.end.connections.(gusset.plates.and.welds).are.engineered.by.the.brace.manu-facturer,.using.the.geometry.and.loading.criteria.supplied.by.the.Engineer.of.Record ..Bracing connections are field welded to gus-set.plates.(approximately.120”.total.of.5/16”.fillet weld is assumed for each connection).

3. Garage, basement mechanical room and first level.Secure.Storage.walls:.Where.concrete.

Page 40: LAM Concept FULL 09-14-2010 Web

�� ECI/HYER :: THA ARCHITECTURE

walls.are.necessitated.by.other.aspects.of.the.building.design,.the.walls.may.be.incorporated.into.the.lateral.force.resisting.system ..Where.this.occurs,.the.walls.will.be.designed.as.special.reinforced.concrete.shear.walls.(12”.thickness.assumed) ..Note.that.if.the.garage.perimeter.walls.are.con-structed.with.sheet.piling,.the.sheet.piles.will.be.designed.to.act.as.shear.walls .

The. seismic. design. will. account. for. the. overall.redundancy. of. the. seismic. load. resisting. sys-tems,. as. prescribed. by. ASCE. 7. section. 12 .3 .4 .2 ..For.each.direction.of.seismic.loading,.the.build-ing. is. assigned. a. value. of. rho,. which. acts. as. a.multiplier. on. the. calculated. nominal. seismic.loads .. A. rho. value. of. 1 .3. is. used. for. loading. in.both.directions .

Page 41: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

GeneralThe. design. of. the. mechanical. systems. to. sup-port. the. new. State. of. Alaska. Library. Archives.Museum.will.focus.on.providing.the.appropriate.indoor. environment(s). for. the. preservation. of.its.historical.collections ..This.“appropriate”.envi-ronment.will.fall.somewhere.between.the.ideal.and.the.practical.as.the.ultimate.function.of.the.facility.will.be.to.allow.both.public.and.scholarly.access.to.these.collections .

General. design. factors. to. be. considered. will.include.light,.relative.humidity,.temperature,.air.pollution,.pest.infestation.(i .e .:.mold,.fungus.and.bacteria),.shock.and.vibration,.natural.emergen-cies.and.security .

During. follow-on. design. phases,. the. types. of.collections.to.be.housed.within.this.faculty.will.be further defined and indoor environmental performance targets defined. General safety and.health,.comfort,.economy.of.operation.and.collection. requirements. (preservation. indexes.for. organic. materials). will. be. considered. and.acceptable.levels.of.risk.established .

Centralized. heating,. ventilating. and. air. condi-tioning systems, plumbing, fire protection and building. automation. systems. will. be. designed.to. achieve. the. client. approved. indoor. environ-mental. performance. targets .. The. design. will.

be. based. on. standard. commercial/institutional.grade. components. and. packaged. systems. for.ease. of. maintenance. and. vender. support .. Sys-tems. will. be. designed. to. be. safe,. reliable. and.efficient using proven techniques and current technology .. Special. consideration. will. be. given.to. incorporating. energy. saving. systems. when.feasible .. Mechanical. system. designs. will. focus.on.logical.equipment.placement,.ease.of.opera-tion.and.accessibility.for.both.preventative.and.corrective.maintenance .

Our. design. team. will. work. closely. with. the.client’s. administrators,. collections. managers,.curators,.conservators.and.security.personnel.to.solicit.further.design.input.to.allow.us.to.provide.the. appropriate. mechanical. systems. and. their.proper. level. of. environmental. control. for. this.facility .

The. following. is. our. conceptual. mechanical.design. based. on. our. current. understanding. of.the.Project ..Indoor.environmental.performance.targets will be finalized and approved, mechani-cal.equipment.and.systems.selected,.sized.and.located. by. the. end. of. Design. Development.phase ..

Applicable Codes and StandardsApplicable.Codes.include,.but.are.not.limited.to,.the.following:

•. International.Building.Code.(IBC)

•. International.Mechanical.Code.(IMC)

•. Uniform.Plumbing.Code.(UPC)

•. International.Fire.Code.(IFC)

•. National.Electric.Code.(NEC)

Applicable.Standards.include,.but.are.not.limited.to,.the.following:

•. American.National.Standards.Institute,.ANSI

•. American.Society.for.Testing.and.Materials,.ASTM

•. Underwriters.Laboratory,.UL

•. National.Fire.Codes.and.Standards,.NFPA

•. American.Society.of.Heating,.Refrigerating.and.Air.Conditioning.Engineers,.ASHRAE

•. Duct.Construction.Standards,.SMACNA

Heating System

Load Estimate

Our. conceptual. heating. load. estimate. for. this.facility. located. in. Juneau,. Alaska. is. 3,850,000 BTU/HR. for.design.day.heating.conditions ..This.estimate.includes.outside.air.ventilation.require-ments. in. accordance. with. general. ASHRAE.guidelines .

MECHANICAL.NARRATIVE

Page 42: LAM Concept FULL 09-14-2010 Web

�� ECI/HYER :: THA ARCHITECTURE

Central Hydronic Plant

The. baseline. central. hydronic. heating. system.will.utilize. three. (3). identical. forced.draft,.high.efficiency fuel oil fired boilers with modulating burner controls. Each boiler will be sized for 40% of the gross heating load providing a 20% design safety.factor ..Should.one.(1).boiler.be.shut-down.for.maintenance,.the.two.remaining.boilers.will.provide.the.buildings.heating.load.requirement ..Basis.of.design.boilers.will.be.Weil.McLain,.Model.788.(1,700,000.BTU/HR.gross.outputs.each) .

As the project progresses and our HVAC design becomes further developed, we will explore some possible alternative heating sources (i.e. ground source heat pumps).

Heating System Arrangement

The.central.boilers.will.be.connected.in.a.primary/secondary. loop. arrangement. with. each. boiler.having. its. own. primary. loop. circulator. pump.sized for a 30° F differential temperature drop across. the. boiler. at. rated. output .. The. primary.boiler. loop.will.be.connected.to.the.secondary.building.heating.loop.using.a.primary/secondary.cross-over.bridge.piping.arrangement ..

Secondary.loop.variable.speed.circulator.pumps.will. transfer. hydronic. heat. to. the. building’s. air.handling unit heating coils, the first floor radiant floor heating system and the facilities terminal hydronic.heating.units .

The.secondary.building.heating.loop.supply.tem-perature.will.vary.following.an.adjustable.reset.schedule.based.on.outside.air.temperature ..

The.HVAC.system.will.be.designed.to.eliminate.the. need. for. secondary. glycol. heating. loops.which.are.often.used.to.provide.freeze.protec-tion.to.AHU.coils .

Larger. diameter. hydronic. heating. piping. (4".and.6").will.be.schedule.40.welded.black.steel ..Smaller. diameter. hydronic. piping. (3”. and.smaller).will.be.Type.L.copper.with.95-5.tin-anti-mony.or.430.silver.solder ..Piping.will.be.routed.away.from.areas.subject.to.water.damage ..Any.piping in locations that may be difficult to access after.installation.will.be.brazed ..

Terminal Heating Units

Remote. duct. mounted. reheat. coils,. located.above. the. ceilings. (return. air. plenums). will. be.limited.to.zones.not.susceptible.to.water.dam-age .. In. general,. reheat. coils. will. be. located. in.their.associated.air.handling.unit.cabinet.(multi-zone.units).or.fan.room.serving.the.area.when-ever.possible ..

Hydronic radiant floor heating will be provided for the first floor of the facility. The underside of the first floor slab will be insulated to a minimum of.R-13.to.direct.heat.up.into.the.heated.zones .

Second floor perimeter offices will receive perim-eter.baseboard.auxiliary.heating ..Toilet.rooms.if.

located.along.an.exterior.wall.will. receive. radi-ant.ceiling.panels .

The. main. entry. vestibule. will. be. heated. with.forced air/radiant floor heat. The remaining ves-tibules/entries will receive wall or floor mounted cabinet.unit.heaters ..The.mechanical.and.electri-cal.rooms,.utility.and.other.storage.areas.will.be.heated.with.hydronic.unit.heaters .

DX Cooling Systems

Central Cooling System

Each.central.air.handling.system.will.be.equipped.with. a. direct. expansion. cooling. coil. and. dedi-cated.condensing.unit ..Each.condensing.unit.will.be.identical.(except.for.size).and.equipped.with.digital.scroll.compressors.to.provide.modulating.supply.air.temperature.control ..Each.condensing.unit.will.be.located.close.to.its.associated.air.han-dling. unit. to. limit. refrigerant. piping. runs .. Type.R-410A refrigerant will be specified. Preliminary load.estimates. indicate.a.maximum.mechanical.cooling.capacity.of.between 250 - 300 tons.will.be.required ..

Computer/Server Rooms

Computer/Server. rooms. will. have. the. capabil-ity. of. being. cooled. independently. from. the.building’s. central. ventilation. systems. utilizing.dedicated. packaged. data. room. air-condition-ing. units .. Critical. rooms. may. have. redundant.

Page 43: LAM Concept FULL 09-14-2010 Web

�9Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

cooling. units .. Packaged. air-conditioning. units.will include a wall or floor mounted evaporator section.and.a.separate. remote.condenser.unit ..Cooling. equipment. suspended. from. the. ceiling.will. be. avoided. to. prevent. interference. with.cable routing. An indirect floor drain will be pro-vided.for.condensate.drainage .

Ventilation SystemsThe. primary. building. ventilation. systems. will.include.six.(6).separate.and.independent.central.air.handling.units.(AHU’s) ..Each.unit.may.include.some.or.all.of.the.following.sections:.mixing.box,.pre-filter (MERV 7), final filter (MERV 14), desic-cant dehumidifier, gas phase filtration, supply fan, DX cooling coil, heating coil, humidification steam. dispersion. panel,. silencer. and. discharge.plenum ..Service.plenums.(18”.to.24”.wide).will.be provided between specific AHU sections to. allow. for. proper. maintenance. and. cleaning.access .. Supply. fans. will. be. equipped. with. vari-able.speed.drive.(VSD).controllers.to.allow.pre-cise. supply. air. volume. control .. Basis. of. design.for AHUs will be Scott Springfield, Haakon or a pre-approved.equal ..

AHU-1 System

AHU-1. (38,000. CFM). will. serve. the. main. entry.and first and second floor lobbies, café, audito-rium, administration, staff and technical service and.general.use.areas ..This.system.will.be.a.con-ventional.variable.air.volume.(VAV).system.and.

will have the ability to be shut-off during when the.building.is.unoccupied.to.save.energy .

AHU-2 System

AHU-2. (42,000. CFM). will. serve. the. museum.lobby. and. exhibit. areas .. This. system. will. be. a.constant.volume.multi-zone.system.with.variable.speed.fan.control.to.allow.the.adjustment.of.air.changeover. rates. within. the. zone .. This. system.will. be. capable. of. high. precision. humidity. and.temperature.control ..At.this.point.the.museum/exhibit. area. is. a. single. large. open. volume .. The.system. will. have. the. capability. to. control. this.area as a single zone and the flexibility to con-trol. it.as.several. independent.zones.depending.on.how.the.space.is.being.utilized ..

AHU-3 System

AHU-3 (27,000 CFM) will serve the central first and second floor staff collections and processing areas ..This.system.will.be.setup.with.VAV.supply.terminal. units. and. corresponding. exhaust. air.valves. (EAVs) .. The. system. will. provide. precise.pressure control using an “air flow tracking” control.strategy.similar.to.a.laboratory .

Wet. lab. areas. will. include. general. use. fume.hoods. with. dedicated. roof. mounted. exhaust.fans ..

AHU-4 and 6 Systems

AHU-4 (26,500 CFM) will serve the first floor secure. storage. (archive. area) .. This. system. will.

be. a. constant. volume. system. with. variable.speed fan motor to allow the fine adjustment of. air. change. rates. per. hour. within. zone .. This.system.will.incorporate.precise.humidity.control.(primary).and.temperature.control.(secondary) ..Outside. air. intake. will. be. kept. to. the. absolute.minimum. level. necessary. to. provide. positive.zone. pressurization. and. gas. dilution. (if. neces-sary .. The. need. for. redundant. supply. fans. and.“ready.for.use”.spare.parts.will.be.determined.as.part.of.the.project.risk.assessment .

Special.indoor.environments.required.for.media.storage. will. be. provided. using. air. tight. vaults.“cocooned”. with. the. archive. area .. These. spe-cialty. vaults. will. incorporate. dedicated. cooling.and dehumidification systems.

AHU-6 will serve the second floor secure storage (archive.area).and.will.be.identical.to.AHU-4 .

AHU-5 System

AHU-5 (24,000 CFM) will serve the second floor reading/research rooms, LAMP offices and cen-tral.processing.areas ..This.system.will.be.setup.with.VAV.supply.terminal.units.and.correspond-ing. exhaust. air. valves. (EAVs). similar. to. AHU-3 ..It.will.provide.precise.pressure.control.using.an.“air flow tracking” control strategy similar to a laboratory .

General Exhaust Air

Toilet.rooms.and.janitor.closest.will.have.exhaust.systems. sized. to. provide. between. 8. and. 12. air.

Page 44: LAM Concept FULL 09-14-2010 Web

40 ECI/HYER :: THA ARCHITECTURE

changes. per. hour .. Exhaust. fans. will. operate.continuously. when. the. associated. ventilation.systems.are.operating .

Shop Ventilation

The. wood. shop. will. ventilated. from. the. AHU-3.system.whenever.the.room.is.occupied.and.not.recirculated .. A. small. commercial. hard. ducted.saw.dust.collection.system.with.remote.exhaust.fan.will.be.provided ..

Parking Garage Ventilation

Four.(4).propeller.type.exhaust.fans.(16,000.CFM.each).equipped.with.motor.operated.relief.lou-vers.will.ventilate.the.unheated.parking.garage ..The.fans.will.be.interlocked.with.corresponding.outside.air. intake.louvers.equipped.with.motor.operated. dampers. which. will. provide. make-up.air. to. the. parking. garage .. The. fans. will. oper-ate. intermittently. using. air. sensors. to. control.parking.garage.exhaust.fume.concentrations.to.within.safe.levels .

Humidification SystemEach. building. zone. will. include. humidity. con-trol ..Relative.humidity.levels.and.tolerances.will.determined. as. the. design. progresses. for. each.ventilation. system .. A. separate. electric. humidi-fier with dedicated air handler mounted steam dispersion.panel.will.be.provided. for.each.cen-tral air handling system. The maximum humidifi-cation.load.is.estimated.to.be.800 LBS/HR .

To provide full humidity control, dehumidifica-tion will also be required. Baseline dehumidifica-tion. control. will. be. accomplished. using. the. DX.cooling. coil .. A. desiccant. system. will. be. added.in series to provide precise dehumidification control .

Acoustical ControlMechanical.systems.will.be.designed.and.speci-fied in accordance with current ASHRAE guide-lines.(Room.Criteria.(RC)).to.provide.a.comfort-able. indoor. acoustical. environment .. Special.sound. attenuation. will. be. provided. at. central.AHUs,. ventilation. return. air. transfer. openings.and. at. the. auditorium. to. control. sound. power.levels .. Rotating. equipment. will. incorporate.vibration.isolation.and/or.thickened.housekeep-ing.pads.as.required.to.reduce.the.transmission.of.equipment.vibration.to.adjacent.areas ..Initial.room.background.sound.goals.are.as.follows:.

. Lobby:. RC.(N).35-45

Office Areas: RC (N) < 35

. Auditorium:. RC.(N).25

. Library/Museum:. RC.(N).30-40

. Processing:. RC.(N).40-50.(w/.fume.hoods)

. Storage:. RC.(N).40-50

Plumbing Systems

Domestic Water

Domestic. water. will. be. provided. from. the.municipal.water.system ..It.is.assumed.that.water.pressure.is.adequate ..If.water.supply.water.pres-sure.is.found.to.be.in.excess.of.80.psig,.pressure.regulators.will.be.used.to.reduce.domestic.water.pressure.to.below.80.psig .. If.water.pressure. is.below.40.psig,.a.variable.speed.domestic.water.booster.pump.system.will.be.provided .

Domestic. hot. water. will. be. provided. using. an.indirect.water. heater. utilizing. the.central.heat-ing.system.as.a.heat.source .

Process Water

Local. domestic. water. will. be. tested. and. evalu-ated for use with the HVAC humidification system .. The. use. of. straight. tap. or. deionized.(DI). water. and. the. associated. maintenance.requirements.associated.with.each.water.purity.level.will.be.considered ..The.mechanical.system.necessary.to.provide.the.appropriate.quality.of.humidification system make-up water will be provided ..

Non-Potable Water (Processing Areas)

Where. processing. chemicals. are. used. and/or.where.the.possibility.of.cross-contamination.may.be of concern, additional backflow protection of the. domestic. water. system. will. be. provided. at.the zone and/or fixture level.

Page 45: LAM Concept FULL 09-14-2010 Web

41Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Tempered Water System

A. dedicated. tempered. water. system. (85.Degrees.F.supply.temperature.(adjustable)).will.be. provided. to. serve. the. facilities. combination.emergency. shower/eyewashes. (EWS) .. Water.temperature.will.be.controlled.using.a.dedicated.hydronically.heated.indirect.water.heater.and.a.single.tempering.valve.designed.for.multi-emer-gency.shower.usage ..Tempered.water.recircula-tion.will.be.provided.utilizing.an.inline.circulator.pump.to.continuously.provide.tempered.water.to. each. combination. emergency. shower/eye-wash.location ..Our.design.will.assume.that.only.one.EWS.will.be.operational.at.any.given.time .

Compressed Air

A. compressed. air. system. will. be. provided. to.serve. the. wood. shop .. Remote. compressed. air.outlets.will.be.provided.at.other.locations.identi-fied by the Client (i.e. fume hoods) as the design progresses .. Compressed. air. will. typically. be.piped.at.80.to.90.psig,.with. local. regulators.at.each.point.of.use ..All.point.of.use.regulators.will.be furnished with filters.

Plumbing Piping

•. Domestic.water.piping.will.be.type.L.copper ..Solder.will.be.95-5.tin-antimony.or.430.silver.solder ..Lead-tin.(50-50).solder.will.not.be.accepted .

•. Vent.piping.above.ground.will.be.DWV.(drain,.waste,.and.vent).copper.or.cast.iron .

•. Sanitary.and.storm.drain.piping.will.be.cast.iron,.except.drains.from.processing.areas.will.be.chemical.resistant.up.to.a.point.of.dilution,.typically.downstream.of.major.rest-rooms ..Below.ground.piping.will.use.no-hub.fittings. No-hub fittings are also acceptable for.above.ground.piping .

• Plumbing fixture groups will be provided with.isolation.valves.to.facilitate.mainte-nance ..Valves.two.inches.and.smaller.will.be.quarter-turn.ball.valves .

General Plumbing Fixtures

•. Plumbing.Fixtures.will.be.vitreous.china.and.stainless.steel.as.applicable .

•. Wall.hung.toilets,.urinals.and.lavatories.will.be specified based on American Standard or as.approved .

•. Public.toilets.and.urinals.will.have.120VAC.automatic infrared flush valves. Staff toilets and urinals shall have manual flush valves.

•. .Drinking.fountains.with.push-bar.type.faucet operators will be specified for handi-capped.operation .

•. Floor.drains.will.be.provided.for.all.rest-rooms.and.mechanical.rooms,.as.well.as.janitor.closets.equipped.with.mop.sinks .

•. Exterior.hose.bibbs.will.be.non-freeze,.auto-matic.draining.will.be.provided.at.a.mini-mum.of.100.FT.intervals ..Each.hose.bibb.will.

include an indoor seasonal shut-off ball valve above.the.ceiling .

Processing/Wet Lab Area Plumbing Fixtures

•. Sinks.and.counters.will.be.integral.units.specified by the Architect.

•. Associated.faucets.will.be.institutional.grade .

•. Drain,.waste.and.vent.piping.will.be.stan-dard.DWV.piping .

•. Acid.resistant.DWV.system.will.be.provided.if.required .

•. Emergency.shower.and.eyewash.station.designs.will.be.based.on.HAWS.or.Guard-ian.and.supported.by.local.tempered.water.systems .

Elevator Pits

An.automatic.elevator.sump.pump.with.oil.sens-ing shut-off will be provided for each elevator pit sump ..Pumps.will. indirect.drain. to. the.building.exterior .

Fire ProtectionThe.facility.will.receive.its.water.from.the.munici-pal water system. Backflow protection will be provided at the fire protection system connec-tion. point. to. the. service. water. riser .. If. water.pressure is inadequate, a fire pump/jockey pump system.will.be.provided .

Page 46: LAM Concept FULL 09-14-2010 Web

42 ECI/HYER :: THA ARCHITECTURE

The.facility.will.be.protected.by.a.full.coverage,.wet type, fire sprinkler protection system with fast.reaction.sprinkler.heads.in.accordance.with.the.latest.requirements.of.NFPA.13 ..

A pre-action sprinkler is currently designated for the Museum/Exhibit and Secure Storage (Archive) areas. Recent studies show that wet systems are the most reliable type of fire protection system available and are currently being used at the Library of Congress, the Smithsonian Institute and other prominent museums. The need for a pre-action sprinkler system will be reevaluated during follow-on design phases. In addition, the need for a stand-alone “clean agent” fire suppression sys-tem for the main telecommunications room will also be evaluated.

Dry. pipe. sprinkler. systems. will. be. provided. for.areas.subject.to.freezing.(i .e ..basement.parking.garage.and.loading.dock) .

A.dedicated.sprinkler.riser.room.will.be.provided.with fully accessible zone shut-off valves. Wet sprinkler. mains. will. be. strategically. routed. to.minimize.potential.water.damage.to.collections .

Fire.hose.standpipes.will.be.provided.as.required.by.NFPA.13 .

The fire department connection (FDC) location and. connection. type. will. be. fully. coordinated.with the local fire department.

Mechanical and Electrical Rooms

Central Mechanical Room

The. required. mechanical. (boiler). room. size. is.currently. estimated. at. 950. SF .. The. mechanical.room. will. be. located. with. direct. access. to. at.least.one.building.exterior.wall. for.combustion.and.ventilation.air. intake ..Double.doors.will.be.provided.for.equipment.replacement.and.main-tenance.access ..Rated.chases.to.accommodate.boiler.exhaust.stacks.will.be.provided ..The.room.should be located to minimize potential fire/explosion.damage.to.the.collections .

A. boiler. room. will. include. a. cabinet. fan. with.mixing box and filter sections to maintain the mechanical. room. temperature. below. 80°F.(adjustable) ..Excess.air.will. relieve.through.the.combustion.air. opening(s) ..Supplemental.heat-ing. in. the. boiler. room. will. be. provided. with.hydronic.unit.heaters .

An. engineered. boiler. room. combustion. air.opening.will.be.designed.and.sized.to.meet.the.combustion requirements of the fuel fired equip-ment.in.the.space .

Fan Rooms

Fan.rooms.will.be.located.to.minimize.potential.

water.damage.to.collections,.reduce.sound.and.vibration.transmission.to.adjacent.sound.sensi-tive. areas. simplify/shorten. duct. runs. and. mini-mize.system.pressure.drops ..Total.required.fan.room.area.is.estimated.at.9,200.SF ..

Fan. rooms. will. include. a. cabinet. fans. and. unit.heaters.similar.to.the.mechanical.room .

Electrical Room

A. cooling. exhaust. fan. will. be. provided. to. cool.the.electrical.room ..Supplemental.heating.in.the.electrical. room. will. be. provided. with. hydronic.unit.heaters.if.necessary .

Building Automation SystemThe. buildings. mechanical. system. is. designed.to. operate. using. a. direct. digital. control. (DDC).building. automation. system. (BAS) .. The. design.will.be.based.on.Siemens.Building.Technology.or.a.pre-approved.equal .

Engineering Design ParametersLocation:. Juneau,. Alaska:. 58 .36. N. Latitude,.134 .58.W.Longitudes

Elevation:.25.FT

Design.ParametersOutside.Temperatures: Winter (99.6% Design) 3 .8oF

Summer.(1% DB/MWB Design) 69 .9/58 .2oF

Inside.Design.Temperatures: Winter 68oF.±.2oFSpring/Fall 68oF.±.2oF

Page 47: LAM Concept FULL 09-14-2010 Web

4�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

GeneralThe. design. of. the. electrical. systems. to. sup-port. the. new. Statewide. Library,. Archives. and.Museum. will. focus. on. providing. the. appropri-ate.indoor.environment(s).for.the.preservation,.viewing.and.security.of.its.historical.collections ..

The. project. design. will. utilize. information. pro-vided.by.the.Alaska.Department.of.Transporta-tion.and.Public.Facilities.State.Libraries,.Archives.and.Museums.Needs.Assessment.dated.Septem-ber.2009 ..Our.design.team.will.work.closely.with.the. client’s. administrators,. collections. manag-ers,.curators,.conservators.and.security.person-nel.to.solicit.further.design.input.to.allow.us.to.provide. the. appropriate. electrical. systems. and.their.proper.level.of.control.for.this.facility .

While.the.Library,.Archives.and.Museum.project.is not pursuing LEED certification, the principles for energy efficiency and environmentally sen-sitive.design.will.play.a.key.role. in.the.decision.making. process. regarding. electrical. systems ..In. addition,. emphasis. will. be. given. to. build-ing. systems. that. can. be. easily. maintained. and.operated .

Electrical. systems. will. include. lighting,. normal/emergency/standby. power. distribution. and.special systems. Special systems will include fire alarm,. telecommunications. distribution,. audio/

video. for. auditorium,. access. control,. CCTV. and.burglary/intrusion. detection .. The. following. is.our. conceptual. electrical. design. based. on. our.current.understanding.of.the.Project ..

Applicable Codes and StandardsApplicable.Codes.include,.but.are.not.limited.to,.the.following:

•. International.Building.Code.(IBC)

•. International.Mechanical.Code.(IMC)

•. International.Fire.Code.(IFC)

•. National.Electric.Code.(NEC)

Applicable.Standards.include,.but.are.not.limited.to,.the.following:

•. Illuminating.Engineering.Society.of.North.America,.IESNA

•. National.Electrical.Contractors.Association.-.NECA

•. National.Electrical.Manufacturers'.Associa-tion.-.NEMA

•. National.Fire.Protection.Association.-.NFPA

•. EIA/TIA.Telecommunications.Standards

•. BiCSi.Telecommunications.Distribution.Meth-ods.Manual

•. Underwriters.Laboratory,.UL

Service and Distribution

Incoming Service

A.new.electrical.service.will.be.provided.to.sup-port.the.Library.Archives.Museum.Building ..The.new. electrical. service. will. be. fed. from. existing.Alaska Electric Light and Power (AEL&P) facili-ties.located.near.the.site ..A.pad.mounted.trans-former.will.be.provided.near.the.building.service.entrance.adjacent.to.the.building.wing.with.the.main.electrical.room .

Main Distribution

Preliminary. load. calculations. estimate. the. size.of. the. Main. Distribution. Switchboard. to. be.approximately. 2,500. Amps. at. 480Y/277. Volts ..The. switchboard. will. be. located. in. a. dedicated.main.electrical.room ..The.main.switchboard.will.distribute. power. to. satellite. electrical. rooms.located. on. each. level .. The. satellite. electrical.rooms. will. be. placed. strategically. throughout.the. facility. to.minimize.branch.circuit.homerun.lengths ..

The. Library. Archive. Museum. will. be. served. at.480Y/277.volts,.3.phase,.4.wires ..Dry. type.step.down. transformers. will. be. provided. to. derive.208Y/120V.power.for.required.loads ..

ELECTRICAL.NARRATIVE

Page 48: LAM Concept FULL 09-14-2010 Web

44 ECI/HYER :: THA ARCHITECTURE

480Y/277V.power.will.typically.be.utilized.for:

•. 3.phase.motors/compressors

•. Equipment.requiring.480V.or.277V.power

•. Elevators

•. Lighting.(277V)

208Y/120V.power.will.typically.be.utilized.for:

•. Receptacles

•. Equipment.requiring.208V.or.120V.power

•. Utilization.equipment

Electrical Distribution and Branch Circuit Panels

Branch. circuit. distribution. panels. will. be. pro-vided. throughout. the. building. as. required. by.the. load. density .. These. panels. will. typically. be.located. in.dedicated.electric. rooms.and.will.be.surface. mounted. on. the. walls. of. the. electric.rooms ..Panels.that.are.not.located.in.dedicated.rooms will be flush mounted in walls.

In. addition,. emergency. and. standby. power.panels. will. be. provided. as. required. to. serve.emergency. and. standby. power. loads .. These.power. panels. will. be. located. in. the. vicinity. of.equipment. requiring. emergency. and. standby.power .. See. below. for. additional. information.regarding.equipment.that.will.be.supported.by.the.generator .

Emergency/Standby Power

An.onsite.diesel.powered.generation.system.will.be.provided.to.support.building.emergency.and.standby loads. The generator will be classified as.a.Level.1,.Class.X,.Type.10.in.accordance.with.NFPA. 110 .. The. generator. will. provide. power. to.NEC.Article.700.Emergency.loads.and.NEC.Arti-cle.702.Optional.Standby.loads.via.two.separate.transfer.switches .

On.site.fuel.storage.will.be.provided.and.will.be.sized.to.operate.the.generator.for.a.minimum.of.96. hours. in. accordance. with. NFPA. 110. require-ments.for.Level.1.systems.installed.in.areas.des-ignated.as.Seismic.Design.Category.D .

The. following. loads. will. be. supported. by. the.Emergency.generation.system:

•. Emergency.egress.lighting.and.exit.signage

•. Fire.alarm.system.(battery.backup.will.also.be provided; fire alarm system requires two sources.of.power.per.Code)

The. following. loads. will. be. supported. by. the.Standby.generation.system:

•. Standby.Lighting

•. Heating.system.(freeze.protection,.e .g .,.boil-ers.and.pumps)

•. Telecom.equipment

•. ACS/Security.equipment.(battery.backup.will.also.be.provided.for.this.equipment)

•. Air.Handling.Units.and.Exhaust.Fans.in.the.collections.areas

•. Freezers

•. Refrigerators

•. Other.equipment.as.determined.during.design

The.generator. location.will.be.determined.dur-ing.the.next.design.phase ..The.location.may.be.within. the. building. or. located. adjacent. to. the.building.in.a.heated.weatherproof.enclosure ..If.installed. in. the. building,. the. generator. will. be.required.to.be.located.in.a.separate.room.with.a minimum 2-hour fire rating. The room will be designed.and.located.to.minimize.damage.from.flooding.

Surge Protective Devices (SPDs)

A.surge.protective.device.(SPD).is.a.device.that.attenuates. (reduces. in. magnitude). random,.high. energy,. short. duration. electrical. power.anomalies.caused.by.utilities,.atmospheric.phe-nomena.or.inductive.loads.such.as.motors ..Such.anomalies.occur.in.the.form.of.voltage.and.cur-rent. spikes. with. durations. of. less. than. half. an.AC. cycle .. These. high. energy. power. spikes. can.damage. sensitive. electronic. equipment,. such.as. computers,. instrumentation. and. process.controllers .

SPDs.will.be.provided.on.the.Main.Distribution.Switchboard.and.on.all.208Y/120V.branch.circuit.

Page 49: LAM Concept FULL 09-14-2010 Web

4�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

panelboards. serving. specialty. electronic. equip-ment,. telecommunications.equipment. or. other.sensitive.loads .

Lighting Systems

General

Lighting. will. typically. be. furnished. in. accor-dance.with.the.IES.Lighting.Handbook,.9th.Edi-tion .. Design. lighting. levels. will. be. coordinated.with. the. recommendations. of. the. IES. and. the.requirements. for. preservation. of. the. collec-tions .. The. architectural. design. will. provide. a.generous. amount. of. daylight. in. those. spaces.where. it. is. desirable .. The. lighting. design. will.take. advantage. of. this. natural. light. while. pro-viding. a. smooth. transition. from. daytime. to.nighttime.operations .

Lighting ConceptsLighting. concepts. will. be. developed. with. the.architect. and. interior. designer. during. the. next.design.phase ..Lighting.will.be.conducive.to.the.building. architecture. and. will. enhance. the. visi-tor’s.experience.and.interest ..Fixture.types.and.geometric.layout.patterns.will.compliment.room.shapes,.functions.and.operational.goals .

The. most. prevalent. light. source. will. be. high.efficiency fluorescent lighting which will be employed. throughout. the. interior. spaces .. A.variety of fixture types will be used to distribute light in a controlled way that will be efficient,

flexible and will compliment the architecture in their. respective. spaces .. Fluorescent. lamps. will.be. T5. or. T5HO,. RE841. type. with. a. high. color-rendering.index.and.a.4100.degree.K.color.tem-perature .. Higher. color. rendering. index. sources.will.be.investigated.during.the.design.for.use.in.critical. work. areas .. Lamps. will. be. low. mercury.type and will meet the requirements for classifi-cation.as.non-hazardous.waste.when.subjected.to. the. Toxic. Characteristic. Leaching. Procedure.(TCLP).prescribed.by.the.Environmental.Protec-tion.Agency ..

A. combination. of. other. lamp. sources. will. be.utilized. where. the. function,. maintenance,. or.control. scheme. require. their. use .. These. lamp.sources.will.include.high.intensity.discharge.(HID).metal.halide,.solid.state.(LED).and.incandescent ..Efforts will be made to consolidate lamp types and.reduce.future.maintenance.costs .

Lighting Control

Lighting. control. schemes. will. vary. from. areas.with. highly. specialized. control. to. areas. with.basic. lighting. control .. Refer. to. the. system. dia-grams.for.a.representation.of.these.areas.at.this.stage.of.design .

General. lighting. control. in. public. areas. will. be.accomplished. with. manual. and. automatic. con-trol ..Automatic.control.will.be.actuated.by.Build-ing. Automation. System. (BAS). output. signals.and.will.control.the. lighting.circuits.via. lighting.contactors. located. in. electrical. rooms .. Manual.

control. will. be. via. switches. located. within. the.spaces. to. be. controlled .. Switches. for. public.spaces.will.be.key.switches.or.will.be.located.in.areas occupied by facility staff.

In.individual.work.areas.occupant.control.will.be.specified to support optimum productivity and comfort. conditions .. Occupancy. sensors. will. be.provided.to.maximize.energy.savings .

Daylight.activated.control.will.be.considered.for.areas.with.daylight.contributions .

Selected fixtures will be connected to generator/standby.power.to.allow.limited.operation.during.power. outage. conditions .. Refer. to. the. system.diagrams.for.a.representation.of.these.areas.at.this.stage.of.design ..These.areas.will.be.further.defined during the next design phase.

Emergency.egress.lighting.and.exit.signs.will.be.connected. to. generator/emergency. power. to.provide. Code. required. egress. lighting .. Under.normal circumstances the fixtures will be switched along with the other room fixtures, but during a power failure the emergency fixtures will.fail.“ON” .

Exterior Lighting

With. the. recent. improvements. in. the. develop-ment.of.solid.state.light.sources,.it.is.anticipated.that. the. exterior. lighting. will. utilize. LED. (Light.Emitting. Diodes). as. the. light. source .. This. light.source.minimizes.energy.consumption.will.pro-viding. excellent. control. and. long. life .. Source.

Page 50: LAM Concept FULL 09-14-2010 Web

4� ECI/HYER :: THA ARCHITECTURE

color.temperature.is.anticipated.to.be.4100K.(a.“white”.light.source) .

Exterior.open.parking.spaces.will.be.illuminated.by pole mounted area lighting fixtures. The entry plaza. will. be. illuminated. by. a. combination. of.specialty pedestrian scale pole mounted fixtures and.low.level.light.bollards ..The.lower.level.park-ing garage will be illuminated with fixtures that minimize.glare.in.the.direct.viewing.zone.while.projecting.light.into.the.parking.spaces .

Exterior fixtures, supports and pole assemblies will be specified to be capable of withstanding 100 mph.winds.with.130.mph.gusts.with.no.damage.and.will.be.suitable.for.the.marine.environment .

Exposure Effects of Lighting

Light. is. radiant.energy.and.therefore.exposure.to. light. gradually. causes. damage. to. artifacts ..The. annual. extent. of. exposure. is. governed. by.the.intensity.of.the.light.over.time.and.the.spec-tral.power.distribution.of.the.light ..These.factors.will.be.considered.in.all.areas.where.artifacts.are.stored,. analyzed,. processed. or. viewed .. Where.it. is. determined. that. an. object. will. be. at. risk.for.damage.due.to.light.exposure,.lighting.con-trols and lighting filters (both infrared (IR) and ultraviolet.(UV).will.be.applied.as.appropriate.to.reduce.the.exposure.to.acceptable.levels .

Telecommunications Distribution System

Incoming Service

A.new.telephone.service.will.be.provided.to.sup-port.the.Library.Archives.Museum ..The.new.tele-phone. service. will. be. fed. from. existing. Alaska.Communications.Systems.facilities.located.adja-cent. to. the. Library. Archive. Museum. property ..Four.4.inch.conduits.only.(PVC.with.GRC.elbows).will. be. stubbed. out. from. the. building’s. Main.Telecom.Room.to.the.property.line ..One.4.inch.conduit. will. be. for. use. of. the. local. phone. util-ity.for.phone.service,.one.4.inch.conduit.will.be.for.use.by.the.local.cable.TV.company.for.cable.TV. service,. the. third. 4. inch. conduit. will. be. for.potential.use.by.ETS.for.providing.data.service.to.the. Library. Archives. Museum. from. other. State.facilities ..The.fourth.4.inch.conduit.will.be.spare.for. future. use .. The. telephone. service. conduit.may.be.run.in.the.same.trench.as.the.building’s.power. service. feeder. subject. to. coordination.with AEL&P.

Standards

A. Structured. Cabling. System. will. be. provided.for. telecommunications. distribution. within. the.building ..The.building.will.be.prewired.to.EIA/TIA.Category.6. level.of.network.performance.using.unshielded,. twisted. pair. products .. The. system.will. be. in. accordance. with. the. latest. currently.

adopted. EIA/TIA. standards. for. telecommunica-tions .. Conduit. from. the. data. outlets. in. rooms/offices will be stubbed up into the accessible ceil-ing.space.to.the.nearest.cable.tray ..The.cable.tray.will.run.in.the.accessible.ceiling.space.to.the.near-est.telecommunications.room ..Pathway.(conduit.and/or.cable.tray).will.also.be.provided.between.the. Main. Telecom. Room. (MTR). and. each. satel-lite.Telecom.Rooms.(TRs).needed.to.support.the.configuration of the building. High bandwidth backbone fiber optic cabling will be provided to connect.the.MTR.to.each.satellite.TR .

Overview

The. system. will. include. outlets,. conduit,. cable.trays,.cables,.terminations,.specifying.test.docu-mentation. and. other. “passive”. components ..A.partial.system.description.includes:

a). Telecommunication.outlets.in.the.labs/class-rooms/offices/miscellaneous areas

b). Horizontal.cabling.from.the.outlets.to.the.modular.patch.panels.in.the.MTR.or.TR

c). Patch.cables.in.the.MTR.and.TRs

d) Backbone cabling (copper and fiber) be-tween.the.MTR.and.the.TRs

e). Phone.Switch/Service.and.associated.cabling.(owner.provided)

Telecommunication.cabling.will.be.run.in.conduit.or.cable.tray ..All.cabling.will.be.plenum.rated .

Page 51: LAM Concept FULL 09-14-2010 Web

4�Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Main Telecom Room: The.MTR.will.serve.as.the.main. hub. for. the. communications. systems. for.the.facility.and.will.contain.the.following:

a). Telephone.service.entrance

b). Modular.patch.panels.for.termination.of.lo-cal.horizontal.telecom.cabling

c). Fiber.Optic.distribution.panels.for.connect-ing.the.MTR.to.each.satellite.TR.for.the.purposes.of.providing.data.connectivity.and.for.voice.communications.if.a.Voice.Over.IP.telephone.system.(VoIP).(owner.provided)

d). Voice.riser.terminations.for.connecting.the.MTR.to.each.satellite.TR.if.a.VoIP.telephone.system.(owner.provided).is.not.intended.for.use.in.the.facility

e). Data.Network.switches.(owner.provided)

f). Data.Network.equipment.(owner.provided)

g). VoIP.network.switches.(owner.provided)

h). VoIP.server.(owner.provided)

To. accommodate. head. end. equipment. for. the.access. control. system. (see. below),. the. Closed.Circuit. Television. System. (CCTV),. and. other.special.systems,.we.recommend.the.Main.Tele-com.Room.(MTR).be.at.least.20.feet.long.by.18.feet. wide. with. at. least. 10. foot. ceilings .. Should.the.need.or.desire.arise.to.co-locate.any.of.the.intended. digital. archival. storage. into. the. MTR,.an.increase.in.size.of.the.MTR.will.be.required .

Satellite.telecom.rooms.or.TRs.should.be.at.least.14.feet.long.by.18.feet.wide.with.at.least.10.foot.ceilings ..Exact.location.and.quantities.of.TRs.will.be.determined.during.design,.but.a.minimum.of.two.satellite.TRs.in.addition.to.the.MTR.are.envi-sioned.to.adequately.serve.the.building.square.footage.and.required.special.systems.head.end.equipment .

Cable Tray: A.cable.tray.system.will.be.provided.for. telecommunications. cabling .. Cable. tray. will.be. provided. to. serve. the. various. areas. of. the.facility. and. provide. pathway. back. to. the. MTR.and.TRs ..Cabling.will.be.plenum.rate.for.use. in.the.cable.tray.in.accordance.with.Code .

Conduit.will.be.provided.from.the.devices.(tele-communication.outlets,.television.outlets,.etc .).to. the. accessible. ceiling. space. and. then. to. the.nearest.cable.tray .

Where.devices.are.not.capable.of.being.served.by. the. cable. tray. system,. conduit. will. be. pro-vided.from.the.devices,.direct.to.the.nearest.TR.or.the.MTR .

Access Control SystemAn. access. control. system. will. be. provided. to.control.access.to.the.following.areas:

•. Building.entrances.including.overhead.doors.(basic.or.Level.1.access.control) .

•. Access.portals.between.public.spaces.and.secure.spaces.(secure.or.Level.2.access.control) .

•. Access.portals.between.public.and.secure.spaces.and.semi-ultra.spaces.(semi-ultra.secure.or.Level.3.access.control) .

•. Access.portals.between.public,.secure.and.semi-ultra.secure.spaces.and.ultra.secure.spaces.(ultra.secure.or.Level.4.access.con-trol) .

The system will be capable of providing differ-ent.levels.of.access ..The.system.will.use.proxim-ity.or.contactless.card.readers ..The.exact.place-ment.and.types.will.be.coordinated.during.the.design.process .

A. badging. system. will. be. provided. to. allow.production. of. access. control. cards. on. site .. A.badging.system.typically.consists.of.a.worksta-tion. with. access. to. the. access. control. system.server,.a.camera.for.taking.of.badge.photos.and.a.badge.printer.for.printing.of.badges ..The.loca-tion.of.the.badging.system.will.be.coordinated.during.the.design.process ..

Remote.control.operation.of.a.lobby.entry.door.or.a.loading.dock/delivery.door.can.be.provided.should the need be identified during design. Such. remote. control. operation. could. rely. on.CCTV.cameras.and.a.small.local.intercom.system.to.verify.the.validity.of.a.request.to.enter .

The. access. control. system. will. be. capable. of.being.accessed.and.will.be.monitored.from.the.Security Office.

Page 52: LAM Concept FULL 09-14-2010 Web

4� ECI/HYER :: THA ARCHITECTURE

The. access. control. system. will. be. designed.around.Lenel.and.will.be.an.IP.based.system .

Video Surveillance (CCTV)Video.surveillance.or.closed.circuit.TV.(CCTV).will.be. provided. that. includes. video. recording. and.archival.storage ..The.system.will.consist.of. the.following.features:

• All cameras will be "fixed" only (no pan/tilt/zoom.capabilities) ..The.cameras.will.be.IP.network.based .

•. The.following.areas.will.be.monitored:

o.Exterior.of.the.building:.Outdoor.CCTV.camera.locations.will.be.coordinated.dur-ing.the.design.process.and.will.be.housed.in.heated.weatherproof.enclosures .

o.High.density.surveillance.of.the.museum.exhibit.space,.the.museum.lobby,.and.the.2D.and.3D.conservation.rooms .

o.Low.density.surveillance.of.the.public.spaces.and.the.secure.corridor .

o.Building.entry.portals .

•. A.SAN.(Storage.Area.Network).and.a.CCTV.System.server.will.be.provided.to.record.the.camera.images.at.frame.rates,.storage.capacity.and.retention.time.as.coordinated.during.the.design .

•. An.“alarm”.output.from.the.security.system.to.the.CCTV.system.to.command.the.system.

to.increase.the.frame-recording.rate.dur-ing.alarms.(during.times.when.the.security.system.is.armed) .

CCTV monitoring will only be provided as specifi-cally directed by Library Archives Museum staff, but.at.a.minimum.we.recommend.monitoring.of.the CCTV system in the Security Office.

The. desired. level. of. video. surveillance. to. be.implemented for this project will be confirmed by.Library.Archives.Museum.before.proceeding.with.design.development .

Intrusion Detection Security SystemA.remote.reporting.security.system.will.be.pro-vided ..The.system.will.be.monitored.by.the.local.monitoring.service.contracted.by.the.Owner .

Detection:.Door.contacts.will.be.provided.on.all.exterior.doors ..Glass.break.detectors.will.be.pro-vided.at.grade.level.accessible.glazing.locations .

The.Security.system.will.be. intertied.with.light-ing. via. the. BAS. to. turn. on. building. common.area. lights.and.site. lighting.whenever.an.alarm.is.received .

The. system. will. be. zoned. based. on. input. from.State Library and Museum staff during design development .

Fire Alarm SystemAn. electrically. operated,. electrically. supervised.analog addressable fire alarm system will be

provided,.including.control.unit,.power.supplies,.alarm. initiating.and. indicating.devices,.conduit,.wire, fittings and all accessories required to pro-vide.a.complete.operating.system .

The.system.will.comply.with.the.applicable.pro-visions.of.the.current.NFPA.Standard.72.National.Fire.Alarm.Code,.local.building.codes,.and.meet.the.requirements.by.Underwriters.Laboratories.Inc .. and/or. the. Factory. Mutual. System .. All. wir-ing. will. be. in. accordance. with. Article. 760. of.the.National.Electrical.Code.and. local.electrical.codes.and.will.be.in.raceways .

The. system. will. operate. as. a. low. voltage,. non-coded general evacuation fire alarm system. Initiating.circuits.will.be.wired.as.two-wire,.Class.B .

In.addition.to.Code.required.actions,.alarms.will.signal.the.intrusion.detection.system ..Common.area. lights. and. site. lighting. will. be. energized.(unless.prohibited.by.photocell).upon.alarm .

Alarms will be annunciated at the fire alarm annunciator.panel.located.in.the.main.entry.and.in the security office. A complete building floor plan. showing. all. alarm. zones. oriented. to. the.physical.location.of.the.panel.including.“You.Are.Here”.notation.will.be.provided.at.each.annun-ciator.location .

Both.audible.and.visual.alarms.will.be.provided.throughout. the. building. to. meet. the. require-ments.of.the.International.Fire.Code.and.Author-ity. Having. Jurisdiction. (AHJ). requirements ..

Page 53: LAM Concept FULL 09-14-2010 Web

49Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Audio-visual.horn/strobe.units.with.combination.horn and flashing alarm strobe will be used.

Comprehensive. smoke. and. heat. detection. will.be. provided. throughout. the. building .. Smoke.detectors. will. utilize. multiple. detection. meth-odologies.and.time.based.algorithms.to.provide.increased.detection.sensitivity.while.minimizing.false.alarms ..In.addition.smoke.detection.will.be.provided.as.noted.below:.

a). Smoke.detectors.will.be.installed.in.me-chanical.return.air.systems.in.accordance.with.International.Mechanical.Code.(IMC).requirements .

b). For.control.of.smoke.control.doors .

c) For control of fire/smoke dampers.

Sprinkler Switches: Sprinkler flow and tamper switches will be monitored to indicate flow in any.part.of.the.system.or.a.partial.or.complete.shutdown.of.the.system.at.the.gate.valves .

Sprinkler. Pre-Action. Systems,. Clean. Agent.Systems. and. Fire. Suppression. Systems. will. be.monitored. by. the. Fire. Alarm. System .. Smoke.detection.required.for.initiation.of.these.systems.(e .g .,.cross.zoned.smoke.detectors).will.be.pro-vided.and.monitored.by.the.Fire.Alarm.System ..Appropriate.relay.outputs.will.be.provided.from.the.Fire.Alarm.System.to.activate.these.systems.upon a verified alarm.

Auditorium Audio/Video System A.complete.audio/video.distribution.system.will.be.provided.in.the.Auditorium.to.allow.distribu-tion of multiple sources and allow flexible use of the. space. for. presentations,. teaching,. movies,.etc .. The. system. will. include. high. quality. sound.system,.microphones.(including.wireless),.over-head.projector(s),.powered.projection.screen(s),.A/V. control. system. and. sophisticated. lighting.and.controls .

Teleconference/video. conference. capabilities.will. also. be. provided. as. determined. during.design ..

Page 54: LAM Concept FULL 09-14-2010 Web

This page intentionally left blank.

Page 55: LAM Concept FULL 09-14-2010 Web

�1Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

CODESUMMARY

Assumptions

Two-story. building. with. a. total. building. area.of. approximately. 114,000. sf. plus. 10,600. sf. of.mechanical.space.and.82.stalls.of.parking.below.grade ..Building.will.be.constructed.according.to.the.2009. International.Building.Code. (IBC). and.all.applicable.local.and.state.code.amendments ..The.following.study.is.based.on.the.2006.IBC.as.the.2009.version.has.yet.to.be.adopted .

Occupancy

•.. A-3.–.Assembly.(Library,.museum,.audito-rium.and.meeting.rooms)

• B – Business (Offices); most likely an acces-sory.occupancy.to.A-3

•.. S-1.–.Moderate-hazard.storage:.Archives.(books, files and artifacts)

•.. S-2.–.Low-hazard.storage:.Parking.garage.

Occupancy. Separation:. Non-separated. use. per.section.508 .3 .2 ..Use.the.most.restrictive,.A-3,.for.construction.purposes .

Construction Type

II-A.

Allowable Area and Height

•.. Based.on.A-3.occupancy,.type.II-A.construc-tion.and.fully.sprinklered .

•.. Basic.Allowable.area.–.3-stories.and.15,500.sf.per.story .

• Allowable Increase – based on 200% allow-able area increase per floor (IBC 506.3) plus a 75% allowable area increase for frontage per.section.506 .2.=.58,125.sf.allowable.per.floor.

•.. Height.increase:.automatic.sprinkler.increase.to.4-stories.and.shall.not.exceed.85’.per.IBC.504 .2

•.. Area.separation.between.the.A-3.and.S-1.oc-cupancies .

Fire Resistance Rated Construction

Incidental.Use.Areas

•.. Boiler.Room.–.An.automatic.sprinkler.system.is.provided,.therefore.a.separation.capable.of.resisting.the.passage.of.smoke.is.required.per.section.508 .2 .2 .1 .

•.. Storage.Rooms.over.100.sf.–.An.automatic.sprinkler.system.is.provided,.therefore.a.separation.capable.of.resisting.the.passage.of.smoke.is.required.per.section.508 .2 .2 .1 .

•.. Furnace.Rooms.w/.any.piece.of.equipment.is.over.400,000.Btu/hour.input.-.An.automatic.sprinkler.system.is.provided,.therefore.a.separation.capable.of.resisting.the.passage.of.smoke.is.required.per.section.508 .2 .2 .1 .

• Book Drop – 2 Hr fire resistant rated con-struction .

Structural Frame: type II-A buildings

• 1 Hr fire protection as required per table 601 and.602 ..

Exterior Walls: type II-A buildings

• No fire protection is required for type II-A buildings.which.are.equal.to.or.greater.than.30.feet.from.a.property.line.per.table.601.and.602 ..

• 1 Hr fire protection is required for type II-A buildings.which.are.less.than.30.feet.from.a.property.line.per.table.601.and.602 ..

Interior Non bearing Walls: type II-A buildings

• No fire protection required per table 601 and 602 ..

Floor Construction type II-A buildings

• 1 Hr fire protection as required per table 601 and.602 ..

Roof Construction type II-A buildings

• 1 Hr fire protection as required per table 601 and.602 ..

•.. Fire.retardant-treated.wood.members.shall.be allowed at 20’ or more above finished floor (table 601, exception C).

Page 56: LAM Concept FULL 09-14-2010 Web

�2 ECI/HYER :: THA ARCHITECTURE

Corridors

•.. Corridors.in.sprinklered.‘A’.occupancy.build-ings are not required to be fire rated per section.1017 .1.and.table.1017 .1 .

Roof Coverings

•.. Per.table.1505 .1,.a.class.‘B’.roof.covering.is.required .

Fire Protection System & Requirements

•.. Sprinklering.–.Section.506 .3.requires.an.au-tomatic.sprinkler.system.to.help.achieve.the.desired floor area and construction type. An automatic.sprinkler.system.is.also.required.per Section 903.2.1.3 for fire areas exceed-ing 12,000 sf and when the fire area has an occupant.load.of.300.or.more ..The.sprinkler.system.shall.be.designed.to.the.require-ments.of.NFPA.13 .

• Fire Extinguishers – one type 2A, 10BC fire extinguisher.is.required.for.each.3,000.sf.of floor area with no more than 75 feet of travel.distance.to.an.extinguisher.per.sec-tion.906.of.the.International.Fire.Code.(IFC) .

•.. Fire.Alarms.–.An.alarm.system.with.manual.pull.stations.is.required.per.section.907 .2 .1.where.the.occupant.load.is.greater.than.300 ..The.exception.to.this.section.allows.for.the.pull.stations.to.be.eliminated.when.there.is.an automatic fire extinguishing system.

•.. Fire.Safety.and.Evacuation.Plan.–.An.ap-proved fire safety and evacuation plan is

required.per.IFC.404 .2 .1 ..Employee.training.in.response.procedures.is.required.per.Sec-tion 406. Quarterly fire drills for employees are.required.per.Table.405 .2 ..A.detailed.seat-ing.plan,.occupant.load.and.occupant.load.limit.shall.be.provided.as.part.of.the.plan.per.408 .2 .1 .

•.. Fire.Apparatus.Access.Roads.–.At.the.discre-tion of the Fire Chief, fire apparatus road-ways.are.required.to.extend.within.150.feet.of.all.portions.of.the.facility.or.any.portion.of.the.exterior.wall.as.measured.along.an.approved.access.route.per.an.Alaska.State.amendment to IFC 503.1.1. The code official is.authorized.to.increase.the.dimension.of.150.feet.where.the.building.is.sprinkled,.or.the.roads.cannot.be.installed.due.to.topog-raphy .

Exiting

•.. Occupant.load.–.per.table.1004 .1 .1,.the.occupant.load.is.calculated.at.300.sf.gross.for.accessory.storage.areas.and.mechani-cal.equipment.rooms,.7.sf.net.for.assembly.areas with concentrated and non-fixed chair seating,.5.net.sf.for.assembly.areas.with.standing.space,.15.net.sf.for.unconcentrated.tables.and.chairs,.100.gross.sf.for.business.areas,.200.gross.sf.for.kitchens,.50.net.sf.for.reading.rooms.and.100.gross.sf.for.book.stack.areas ..

•.. Occupancy.signage.–.per.section.1004 .3,.

every.room.or.space.that.is.an.assembly.occupancy.shall.have.the.occupant.load.of.the.room.or.space.posted.in.a.conspicuous.place,.near.the.main.exit.or.exit.access.door-way.from.the.room.or.space ..Posted.signs.shall.be.of.an.approved.legible.permanent.design.and.shall.be.maintained.by.the.owner.or.authorized.agent .

•.. Exit.Separation.–.Where.two.exits.are.required,.the.distance.between.exit.doors.must.be.a.distance.apart.that.is.a.minimum.of.one-third.the.diagonal.of.the.area.served-per.section.1015 .2 .1,.exception.2.for.auto-matic.sprinkler.systems .

•.. Number.of.exits.–.Two.exits.or.exit.access.doorways.are.required.from.any.space.with.an.occupant.load.greater.than.49.per.sec-tion.1015 .1 .

•.. Maximum.Travel.Distance.–.250.feet.per.table.1016 .1 .

•.. Maximum.Dead.End.–.not.to.exceed.20.feet.per.section.1017 .3 ..However,.per.exception.3,.a.dead-end.corridor.shall.not.be.limited.in.length.where.the.length.of.the.dead-end.corridor.is.less.than.2 .5.times.the.least.width.of.the.dead-end.corridor .

•.. Maximum.Common.Path.of.Egress.Travel.–..not.to.exceed.75.feet.per.section.1014 .3 .

• Panic Hardware – Panic and fire exit hard-ware.is.required.at.each.means.of.egress.

Page 57: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

serving.an.occupant.load.of.50.or.more.per.section.1008 .1 .9 .

•.. Corridor.Width.–.Corridors.may.be.no.less.than.44.inches.in.width.per.section.1017 .2 .

• Emergency Lights & Exit Signs – The entire building.is.required.to.have.emergency.lighting.and.exit.signs.per.section.1006 .1.and.1011 .1 ..Exceptions:.Approved.exit.sign.illumination.means.that.provide.continuous.illumination.independent.of.external.power.sources.for.duration.of.not.less.than.90.min-utes,.in.case.of.primary.power.loss,.are.not.required.to.be.connected.to.an.emergency.electrical.system.per.section.1011 .5 .3 .

•.. Address.Numbers.–.The.Fire.Chief.may.require.address.numbers.plainly.visible.and.legible.from.the.street .

•.. Key.Boxes.–.The.Fire.Chief.may.require.an.approved.key.box .

Zoning Requirements

Per. Zoning. requirements. for. the. City. and. Bor-ough.of.Juneau:

•.. Setbacks.–.5’.all.sides

•.. Height.Limitations.–.35.feet.max ..(Possible.height.increase.to.45.feet.with.CBJ.credits,.or.with.a.variance.or.planned.rezoning.of.the.area) .

•.. Landscaping.–.Will.meet.planning.and.zon-ing.requirements .

•.. Parking.–.per.City.of.Juneau.Planning.Department.with.anticipated.extension.of.Cultural District Overlay (60% reduction).

•.. Loading.zones.–.4.required

Page 58: LAM Concept FULL 09-14-2010 Web

�4 ECI/HYER :: THA ARCHITECTURE

KEY

Collections Areas

Collections

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 59: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

KEY

Collections Areas

Collections

Media 1Media 1

Media 2Media 2

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 60: LAM Concept FULL 09-14-2010 Web

�� ECI/HYER :: THA ARCHITECTURE

Floor Structure

0 20 40 80’

Note: Wall and column thicknessare exaggerated for graphic clarity

Elev.

HCHC

HC

HC

KEY

Cast in PlaceConcrete Slab onConcrete Grade Beamsover Steel Piles

Precast ConcreteColumns OverSteel Piles

Cast In Place ConcreteWall with PilastersOver Steel Piles

Steel Columns OverSteel Piles

0 20 40 80’

Elev.

HCHC

HC

HC

Parking Level

Mechanical

Parking

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM September 14, 2010

SySTEMS DIAGRAMS

Page 61: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

KEY

Concrete Slab onComposite Steel Deck

Concrete Topping Slab onConcrete Pre-cast Planks

Pre-Cast Concrete Column

Steel Columns

Cast In Place Concrete Wall

Buckling-RestrainedBraced Frame (BRBF)

Floor Structure

Note: Wall and column thicknessare exaggerated for graphic clarity

Cast in Place Concrete Slabon Concrete Grade Beamsover Steel Piles

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 62: LAM Concept FULL 09-14-2010 Web

�� ECI/HYER :: THA ARCHITECTURE

Floor Structure

KEY

Concrete Slab onComposite Steel Deck

Concrete Topping Slab onConcrete Pre-cast Planks

Pre-Cast Concrete

Steel Columns

Cast In Place Concrete Wall

Buckling-RestrainedBraced Frame (BRBF)

Note: Wall and column thicknessare exaggerated for graphic clarity

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 63: LAM Concept FULL 09-14-2010 Web

�9Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

ConventionalLow Slope Roof

Architecturally Exposed,Curved Timber Frame Roof

Note:Wall and column and bracingthickness are exaggerated for graphic

KEY

Pre-Cast Concrete

Steel Columns

Cast In Place Concrete Wall

Tension Rod Cross Bracingfrom High Roof to Low Roof

Roof Structure

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

M

SpecialProjects

LAMPOffices

Elev.

Open

Roof Structure Diagram

DN

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 64: LAM Concept FULL 09-14-2010 Web

�0 ECI/HYER :: THA ARCHITECTURE

Air Handler Zones

Air Handler -2, CV

KEY

Air Handler -1, VAV

Air Handler -3, VAV

Air Handler -4, CV

Air Handler -5, VAV

Air Handler -6, CV

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 65: LAM Concept FULL 09-14-2010 Web

�1Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

KEY

Air Handler Zones

Air Handler -2, CV

Air Handler -1, VAV

Air Handler -3, VAV

Air Handler -4, CV

Air Handler -5, VAV

Air Handler -6, CV

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 66: LAM Concept FULL 09-14-2010 Web

�2 ECI/HYER :: THA ARCHITECTURE

Building Environment

( 0 ) ( 0 ) ( 0 ) ( 0 )

( 0 )

( 0 )

( 0 )

( ++ )

(++

)

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( + )

( ++ )

( + )( 0 )

( 0 )

( - )

( - )

( 0 )

( 0 )

( 0 )

( 0 )

( + )

Semi-Clean

KEY

Ultra Clean

Semi-Dirty

Ultra Dirty

Pressure FlowNeutral Pressure

( + )

( ++ )

PressureLevel

EnvironmentalAir Quality

( 0 )

( - )

Note: Outside ReferenceAir Pressure Level = ( 0 )First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 67: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Building Environment

( 0 )

( 0 )

( ++ )

( ++ )

( + )

( + )( + )

( + )

( + )

( + )

( + )

( + )

( + ) ( + ) ( + ) ( + )

( + )

( + ) ( + )

( + )

( + )

( + )

( 0 )

( 0 )

( 0 )

Note: Outside ReferenceAir Pressure Level = ( 0 )

Semi-Clean

KEY

Ultra Clean

Semi-Dirty

Ultra Dirty

Pressure FlowNeutral Pressure

( + )

( ++ )

PressureLevel

EnvironmentalAir Quality

( 0 )

( - )

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 68: LAM Concept FULL 09-14-2010 Web

�4 ECI/HYER :: THA ARCHITECTURE

Fire Protection

0 20 40 80’

KEY

Wet Sprinklers

Dry Pipe Sprinklers

0 20 40 80’

Elev.

HCHC

HC

HC

Parking Level

Mechanical

Parking

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM September 14, 2010

SySTEMS DIAGRAMS

Page 69: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Pre-action Sprinklers

KEY

Wet Sprinklers

Dry Pipe Sprinklers

Fire Protection

VaultVault

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 70: LAM Concept FULL 09-14-2010 Web

�� ECI/HYER :: THA ARCHITECTURE

Pre-action Sprinklers

KEY

Wet Sprinklers

Fire Protection

Media 1Media 1

Media 2Media 2

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 71: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Emergency Power

0 20 40 80’

KEY

Basic Freeze Protection andEmergency Egress Lighting(All Areas)

Limited EmergencyPower Operation( HVAC, Reduced Lighting,and Limited Power )

Fully Operational( HVAC, Lighting, and Power )

0 20 40 80’

Elev.

HCHC

HC

HC

Parking Level

Mechanical

Parking

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM September 14, 2010

SySTEMS DIAGRAMS

Page 72: LAM Concept FULL 09-14-2010 Web

�� ECI/HYER :: THA ARCHITECTURE

Emergency Power

KEY

Basic Freeze Protection andEmergency Egress Lighting(All Areas)

Limited EmergencyPower Operation( HVAC, Reduced Lighting,and Limited Power )

Fully Operational( HVAC, Lighting, and Power )

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 73: LAM Concept FULL 09-14-2010 Web

�9Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Emergency Power

Media 1Media 1

Media 2Media 2

KEY

Basic Freeze Protection andEmergency Egress Lighting(All Areas)

Limited EmergencyPower Operation( HVAC, Reduced Lighting,and Limited Power )

Fully Operational( HVAC, Lighting, and Power )

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 74: LAM Concept FULL 09-14-2010 Web

�0 ECI/HYER :: THA ARCHITECTURE

Light Control

0 20 40 80’

KEY

BASIC LIGHTING

0 20 40 80’

Elev.

HCHC

HC

HC

Parking Level

Mechanical

Parking

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM September 14, 2010

SySTEMS DIAGRAMS

Page 75: LAM Concept FULL 09-14-2010 Web

�1Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

KEY

Light Control

SPECIALIZED

HIGHLY SPECIALIZED

FULL CONTROL

MODERATE CONTROL

BASIC LIGHTING

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 76: LAM Concept FULL 09-14-2010 Web

�2 ECI/HYER :: THA ARCHITECTURE

KEY

Lighting Control

Media 1Media 1

Media 2Media 2

Media 1Media 1

Media 2Media 2

SPECIALIZED

HIGHLY SPECIALIZED

FULL CONTROL

MODERATE CONTROL

BASIC LIGHTING

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 77: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Public Surveillance

KEY

Public

Secure

Semi-Ultra Secure

Ultra Secure

Access Control

Secure Public

PublicSurveillance

PublicHigh ValueObjectsHigh ValueObjects

VaultVault

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 78: LAM Concept FULL 09-14-2010 Web

�4 ECI/HYER :: THA ARCHITECTURE

Public Surveillance

KEY

Public

Secure

Ultra Secure

Access Control

Secure Public

Media 1Media 1

Media 2Media 2

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 79: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Closed Circuit Surveillance

0 20 40 80’

Low Density Surveillance

KEY

No CC TV Surveillance

Exterior Surveillance

0 20 40 80’

Elev.

HCHC

HC

HC

Parking Level

Mechanical

Parking

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM September 14, 2010

SySTEMS DIAGRAMS

Page 80: LAM Concept FULL 09-14-2010 Web

�� ECI/HYER :: THA ARCHITECTURE

Low Density Surveillance

KEY

High Density Surveillance

No CC TV Surveillance

Exterior Surveillance

Closed Circuit Surveillance

VaultVault

First Floor Plan

M W

Ex.Stor. C

olle

ctio

n

M

W

Lobby

CafeM

W

Auditorium

Classroom

Store

SecureStorage

Loading

MuseumExhibit

Wet Lab

Coll.Sup.

Vest.

WoodWorkShop

CrateStorage

2DCon.

Lock.

CleanShop

Photo

Pro-cessing

VolunteerMuseumStaff

SecurityOff.

Wet Lab

3DCon.

Elev.

Ed.Coll.Sup.

Wd.Stor.

Storage

Conf. Conf.

Elev.

MuseumLobby

Cons.Supply

Iso.

0 20 40 80’

UP

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 81: LAM Concept FULL 09-14-2010 Web

��Concept Design Report • 09.14.2010LIBRARY ARCHIVES MUSEUM PROJECT

Low Density Surveillance

KEY

Closed Circuit Surveillance

Media 1Media 1

Media 2Media 2

No CC TV Surveillance

0 20 40 80’

W

SecureStorage

SpecialProjects

Micrographics

Workspace

Supply

M

WElev.

Storage

VideoConf.

RoofTerrace

ReadingRoom

MicroformReaders

ResearchRoom

Processing

Technical andService Administration Outreach Staff Class-

room

Staff

Roof

M

ServiceDeskSpecial

Projects

LAMPOffices

Elev.

Open

Second Floor Plan

DN

Roof

September 14, 2010

S TAT E O F A L A S K A

LIBRARY ARCHIVES MUSEUM

SySTEMS DIAGRAMS

Page 82: LAM Concept FULL 09-14-2010 Web

ECI / Hyer Architecture & Interiors101 W. Benson Boulevard, Suite 306Anchorage, Alaska 99503907.561.5543

THA Architecture733 SW Oak Street, Suite 100Portland, Oregon 97205503.227.1254