Lady Zia Wernher School Luton New Build Extension

Transcript of Lady zia wernher school case study lts

Lady Zia Wernher School

Luton

New Build Extension

The Lady Zia Wernher School has children aged from 2 to 11 years who have a range of medical needs,

physical disabilities and learning difficulties. Due to an increase in demand , additional classroom space with

extra facilities was needed. A 2 storey extension was built which provided an extra 600m2 of space for the

school.

The Design Team were commissioned to provide;

2 nr. Flexible classrooms

Treatment room with office and store

Training Rooms to provide specialist training for other teachers supporting children with similar difficulties

Staffroom

Adapted WC’s

Contract Value: £1,040,000