Sr.No. Punch Description Area/System Action By
1 Earthing for all cable tray shall be provided. Cable tray SPETCO/HOT
2 Cable tray covers at many places are missing. Cable Tray SPETCO/HOT
3 All cable step ups shall be appropriately sealed. Field SPETCO/HOT
4 As built drawings shall be kept inside the JBs. Drawings are not available in JBs Junction Boxes SPETCO/HOT
5 Cable route markers not installed Field SPETCO/HOT
6 Edge guard shall be provided in the cable tray. Field SPETCO/HOT
7 Field tag plates for all instruments including SDVs and control valves shall be provided Field SPETCO/HOT
8 The label provided for Partial stroke shall be replaced with ‘Emergency Close PB” for the SDV SDV-3009 SPETCO/HOT
9 Cable tag for PSL-3005 is missing SDV-3005 SPETCO/HOT
10 LT-3006 is not showing the level properly. To be rectified/replaced LT-3006 SPETCO/HOT
11 Primary Cable tag for JBS(D)-3001 is not installed. Bolts shall be tightened properly. JBS(D)-3001 SPETCO/HOT
12FT-3001, FT-3017, TE-3035, LT-3060, LI-3011, LI-3061, PI-3065, PI-3066 are not installed. Missing instruments
SPETCO/HOT
13 ZSO/ZSC cables not terminated. To be terminated and tested MOV-2050 SPETCO/HOT
14 Cable tag for PY-3020 missing. Earthing for PCV instruments is missing PCV-3020 SPETCO/HOT
15 Cable tags for TE-3020/3024 missing TE-3020/3024 SPETCO/HOT
16 PT-3020 is not reading properly. To be rectified/replaced. PT-3020 SPETCO/HOT
17 Tray cover clamp is missing for JBPA-3003 JBPA-3003 SPETCO/HOT
18 Cable Tag for GD-3006 is not legible and need to be replaced. Earthing cable from the instrument stand shall be laid underground. GD-3006 SPETCO/HOT
19 TE-3039 Cable to be routed and secured properly TE-3039 SPETCO/HOT
20 Cable tray for FT-3050 is not fixed properly FT-3050 SPETCO/HOT
21 Spare cable entry shall be plugged LT-3050 SPETCO/HOT
22 All the bolts shall be tightened properly. JBP(D)-3001 SPETCO/HOT
23 Earthing cable shall be connected properly and to be laid underground GDT-3001 SPETCO/HOT
24IRP cabinet inside need to be cleaned. Cable entry shall be sealed properly. Cable ferrules are missing at terminals 4 & 5 of TB: IRP-01-04 IRP-01 Cabinet
SPETCO/HOT
25Safety Earth cable kept loose. Cable entry shall be sealed properly. Instrument earth bars are not connected each other. DCS cabinet DCS-SC/ MR01(F/R)
SPETCO/HOT
26 The terminals of the following signals are kept open: UL-3012A/B, UL-3015A/B, UA-3006A/B, UA-3020. Functional checks of these signals shall be carried out. DCS cabinet DCS-SC/ MR01(R) SPETCO/HOT
27
IRP-01-03 Terminals 1/2/3/4 and MOV-2050 terminals are kept open(UA-3001AA, UL-3001 AC) Signals need to be tested. DCS cabinet DCS-SC/ MR01(R)
SPETCO/HOT
28
Gland plates shall be sealed properly. Main safety earth cables to the plant safety earth bar are connected together in the same terminal inside the cabinet. ESD/FGS Cabinet ESD/FGS-01(F)
SPETCO/HOT
29FO internal cables are not connected. Gland plates shall be sealed properly. ESD/FGS Cabinet ESD/FGS-01(R)
SPETCO/Emerson
30 Terminals are kept open for LT-3060 & BF-3001(without fuse) ESD/FGS Cabinet ESD/FGS-01(R) SPETCO/HOT
31 Cable duct cover is not secured properly ESD/FGS Cabinet ESD/FGS-01(R) SPETCO/HOT
TV Compressor area - Punch list
Instrument Punch items
32
UPS fail signal from Enerflex UPS is not terminated. Signal need to be tested. ESD/FGS Cabinet ESD/FGS-01(R)
SPETCO/HOT
33 Panel keys are missing. DCS/ESD panels SPETCO/HOT
34Emerson could not establish Serial communication for GEG/ Synchronizing panel and I/A Compressor panel Delta V DCS
SPETCO/Emerson
35 Printer not configured. Delta V DCS SPETCO/Emerson
36 DCS Report not configured. Error messages are displayed while accessing graphics. Delta V DCS SPETCO/Emerson
37 ALL the FQ points shall be configured with auto reset. Delta V DCS SPETCO/Emerson
38Proper power supply sockets shall be fixed for operator workstations. Cable duct behind the workstation shall be covered. DCS furniture supplied are not approved. Delta V DCS
SPETCO
39 Modbus list for the Enerflex PLC, GEG and synchronizing panel shall be submitted to KOC PLCs SPETCO
40 Enerflex PLC program back up and program printout shall be handed over to KOC Enerflex PLC SPETCO
41
Field/ cabinet wiring was modified for the following: XZ-3003/3013/3006A/3006B/3005A/ 3005B/3005C, HT-3001(H/F/T), HT-3002(H/F/T), Compressor trip signal to
MCC XZ-3023, UPS fail signal from Enerflex UPS, FD-3001/3002/3003/3004/3005/3006. As built documents like Cable schedule, JB wiring diagram and Loop wiring
diagram shall be submitted to KOC for approval
Site changes
SPETCO
42 GDT-3004 and GDH-3001 could not calibrate as their buttons are defective. To be replaced F&G SPETCO
43 Smoke detector and Heat detector wiring is faulty at Substation F&G SPETCO/HOT
44 chiller by-pass line instruments to be provided (TG and PG) Field SPETCO/HOT
45
Battery room lighting work is pending Control Room
SPETCO/HOT
46 Battery room exhaust fan installation is not done Control Room SPETCO/HOT
47 Toilet exhaust fan installation and lighting work not done Control Room SPETCO/HOT
48 Safety mats for UPS panels needs to be provided. Control Room SPETCO/HOT
49 Safety mats needs to be provided in substation substation SPETCO/HOT
50 Substation civil works needs to be completed such as floor finishing, battery room works etc. substation SPETCO/HOT
51 Cable entry holes needs to be sealed. substation SPETCO/HOT
52 Panel bottom holes, gaps needs to sealed. Switchboard cable entries needs to sealed. substation SPETCO/HOT
53 Battery room exhaust fan and window works needs to be completed. substation SPETCO/HOT
54 Substation and Control room illumination level is very low. Additional light fixtures needs to be installed. substation/Control room SPETCO/HOT
55 Substation cutouts needs to be closed with chequred plates. substation SPETCO/HOT
56GEG shed needs to be provided. All the electrical works such as lighting, earthing, LDB installation for the GEG shed needs to be completed. Outside area and General works
SPETCO
57 Plant power sockets ( 3 phase and single phase) needs to be installed as per drawings with associated cabling works. Outside area and General works SPETCO
58 Fence gates lighting pole installation work needs to be completed along with associated cabling work etc. Outside area and General works SPETCO
59 Canopy cover for GEG cooling fans distribution board, shall be provided. Outside area and General works SPETCO
60 DG set battery isolator to be replaced. Outside area and General works SPETCO
61 Fire Wall work between the transformers needs to be carried out as per drawing. Outside area and General works SPETCO
62 Lighting in GEG area, air-cooler area is not adequate Outside area and General works SPETCO
63 GEG temporary battery and battery chargers (hired by SPETCO) are installed, permanent battery & battery charger to be ordered and installed. substation SPETCO/HOT
Electrical Punch items
Civil Punch items
64 Entry gates are still pending. TV area Fence SPETCO
65 Control room toilet / bath room works and soak-pit for sewage disposal is pending Control Room and outside SPETCO
66Platform grating to be completed near TV compressor area. TC Compressor skid
SPETCO
67 Platform and ladder to be provided for PA receiver and N2 receiver. Platform grating to be completed for IA receiver. Air and nitrogen receiver area SPETCO
68 Egg barrel sump : Ladder and grating or railing is pending Egg barrel sump SPETCO
69 Platform ladders : Foot rests to be provided. Outside area and General works SPETCO
70 Access road need to be properly leveled and marked Outside area and General works SPETCO
71 Support at the base for all stairs and crossovers are not completed Outside area and General works SPETCO
72 foundation for seal pot is missing Outside area and General works SPETCO
73piping trench cover is missing in GEG area Outside area and General works
SPETCO
74 Pits for corrosion coupon and probes are not provided Outside area and General works SPETCO
75Water offloading pumps piping works needs to be completed. Water offloading pump with motor testing and commissioning works needs to be completed. Outside area and General works
SPETCO
76 Proper pipe supports for small bore lines at several locations. Outside area and piping works SPETCO
77 PSV header between TV compressor and air coolers in sagging position. To be properly supported. Outside area and piping works SPETCO
78fire hydrants isolation valves are missing Outside area and piping works
SPETCO
79 Transformer area shed and gate is pending Outside area and piping works SPETCO
80 IA/PA receiver drain line support is missing Outside area and piping works SPETCO
81 Stud bolts are not as per the standard. Some places long bolts are used. Some places short bolts. Need to be replaces with proper bolts Outside area and piping works SPETCO
82 XV-3001 bypass line is missing Outside area and piping works SPETCO
83 piping joints touchup painting is pending Outside area and piping works SPETCO
84 Chiller bypass line piping work is pending Outside area and piping works SPETCO
85 Lube oil line need proper support Outside area and piping works SPETCO
86 Insulation work for TV compressor discharge lines Outside area and piping works SPETCO
87 Utility water system (for wash room use etc.): Tank, pumps (2 Nos.) to be installed and piping work to be started. Utility water system SPETCO
88 Installation of corrosion coupons Outside area and piping works SPETCO
89 Line markers for identification Outside area and piping works SPETCO
90 Identification, removal and Internal coating of carbon steel spools (~ 20 Nos.) for Q-class drain lines – shut down job. Outside area and piping works SPETCO
91
Drain lines (required for TV compressor) yet to be erected: 3”-PC-3036-Q15B and 4”-PC-3012-Q15B. At least one is required, at present condensate is routed to GO burn
pit and GO is not willing for continued operation of their burn pit.Outside area and piping works
SPETCO
92 Fuel gas purge - flow transmitters (2 Nos.) are yet to be installed. FG area SPETCO
93 GEG serial communication with DCS - yet not established. DCS SPETCO
94 Sampling system in feed line should be provided as per contract clause # 5.7.1.11 General SPETCO
95 Chemical injection Skid for TV Compressor package is not available General SPETCO
96Documentation submission ( Design drawings, Manufacturer Record books, Construction records, As built drawings, Operation & Maintenance manual of equipment etc.) General
SPETCO
97 Color coding of piping is pending Outside area and piping works SPETCO
Process Punch items
Mechanical Punch items
98 list of spare parts of all the equipment for 3 years General SPETCO
99 list of all special tools, jigs, templates General SPETCO
100 Purge connection with valve on tie-in points are not provided Outside area and piping works SPETCO
101 Emergency access doors are missing General SPETCO
102 sign boards are missing General SPETCO
103 Air chiller package is missing IA system SPETCO
104 All tie-in valves need to be replaced with proper class and rating as per the drawings General SPETCO
SPETCO comments (TA) on Jan 4 2014
Done
Done
Done
Done
Done
Done
SPETCO to complete asap
SPETCO to complete asap
Done
Done
Done
These instruments are relating to equipment not yet installed and will be completed when
the equipment is installed (see mech points)
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
This is part of Emerson Punchlist. Commercial issues with Emerson are preventing the
completion of this. To be done once AO-5 is completed and funds paid to Emerson
Done
Will be completed during GCP Commissioning
repeat from point #12 above
done
TV Compressor area - Punch list
Instrument Punch items
This is part of Emerson Punchlist. Commercial issues with Emerson are preventing the
completion of this. To be done once AO-5 is completed and funds paid to Emerson
done
SPETCO requires Emerson, Waukesha, and Ingersoll Rand vendors to complete this. To
be done ASAP
done
Emerson Punch list (see explanation above)
Emerson Punch list (see explanation above)
SPETCO to complete first two points. For the third one, have requested KOC to clarify the
point on approved furniture, awaiting reply
SPETCO to complete asap
SPETCO to complete asap
SPETCO is reviewing this point and will respond shortly
done
done
SPETCO is reviewing this point and will respond shortly
Awaiting completion of the building by civil subcontractor. The current subcontractor is
not responding to our requests. SPETCO is searching for another subcontractor to
complete the works, after which the electrical points will be closed
same
same
SPETCO to complete asap
SPETCO to complete asap
same as point 45 above
done
will utilize the fabrication shop to do this, shall be completed asap
same as point 45 above
as per our design, lighting is completed
will utilize the fabrication shop to do this, shall be completed asap
will utilize the fabrication shop to do this, shall be completed asap
SPETCO to complete asap
to be completed once the gates are completed
will utilize the fabrication shop to do this, shall be completed asap
Awaiting reply from our DG vendor for this as it should be under warranty
SPETCO to complete asap
lighting completed as per design
awaiting approval for offer submitted to KOC for approval
Electrical Punch items
will utilize the fabrication shop to do this, shall be completed asap
to be completed with new building subcontractor.
This was not part of our design but will be completed by our fabrication shop
will utilize the fabrication shop to do this, shall be completed asap
will utilize the fabrication shop to do this, shall be completed asap
SPETCO to complete asap
SPETCO will do this shortly using gatch
repeat point from 69 above
done
will utilize the fabrication shop to do this, shall be completed using chequered plate asap
1 pit is available, will be completed asap
SPETCO to complete asap
SPETCO to complete asap
under review by SPETCO and to be advised shortly
awaiting valves from UK, to be delivered after funds from Ao-5 are received
SPETCO to complete asap
under review by SPETCO and to be advised shortly
under review by SPETCO and to be advised shortly
under review by SPETCO and to be advised shortly
done and painting reports signed off by KOC
bypass is done
under review by SPETCO and to be advised shortly
will be completed with remaining insulation works
repeat from civil and mechanical points
under review by SPETCO and to be advised shortly
SPETCO to complete asap
to be done in a planned shutdown shortly
pipeline scope, not TV
under review by SPETCO and to be advised shortly
repeat from instrumentation point above
under review by SPETCO and to be advised shortly
to be delivered after Ao-5 is completed and funds received
under preparation by SPETCO, awaiting completion of pending construction items
SPETCO to complete asap
Process Punch items
Mechanical Punch items
SPETCO to complete asap
SPETCO to complete asap
under review by SPETCO and to be advised shortly
under review by SPETCO and to be advised shortly
done
chiller came damaged from the manufacturer, to be sent back for repair
under review by SPETCO and to be advised shortly
Civil Punch items Area
64
Entry gates are still pending. TV area Fence
65
Control room toilet / bath room works and soak-
pit for sewage disposal is pendingControl Room and outside
66
Platform grating to be completed near TV
compressor area.TC Compressor skid
67
Platform and ladder to be provided for PA
receiver and N2 receiver. Platform grating to be
completed for IA receiver.
Air and nitrogen receiver area
68
Egg barrel sump : Ladder and grating or railing is
pendingEgg barrel sump
69
Platform ladders : Foot rests to be provided.Outside area and General
works
70
Access road need to be properly leveled and
marked
Outside area and General
works
71
Support at the base for all stairs and crossovers
are not completed
Outside area and General
works
72
foundation for seal pot is missingOutside area and General
works
73
piping trench cover is missing in GEG areaOutside area and General
works
74
Pits for corrosion coupon and probes are not
provided
Outside area and General
works
Action by Material
SPETCO
will utilize the fabrication shop to do this,
shall be completed asap
Gate Material should
provided by
fabrication shop /
before civil take over
the foundation
SPETCO
to be completed with new building
subcontractor. _
SPETCO
This was not part of our design but will be
completed by our fabrication shop_
SPETCO
will utilize the fabrication shop to do this,
shall be completed asap_
SPETCO
will utilize the fabrication shop to do this,
shall be completed asap_
SPETCO
SPETCO to complete asap
Concrete 4 meter
cubic, Plywood,
woods, nails, Rebars
SPETCO
SPETCO will do this shortly using gatchGrader, Gatch, Roller
Compactor
SPETCO
repeat point from 69 above _
SPETCO
done _
SPETCO
will utilize the fabrication shop to do this,
shall be completed using chequered plate
asap
_
SPETCO
1 pit is available, will be completed asap _
Quantities Manpower Duration Remarks
3 Main gate and 2
pedestrian
gate/Concrete k-350
apprx. 4 m3
Carpenter 1 , mason 1,
labour 2.1 week
_ _ _
see attach excel
sheet/ check with new
subcontructor
_ _ _To be provided by
mechanical / fabshop
_ _ _To be provided by
mechanical / fabshop
_ _ _To be provided by
mechanical / fabshop
4 meter cubicMason 1 , Carpenter 1, Steel
Fixer5 days
lumpsum for gatch Heavy Duty driver, labours 2 4 days
_ _ _repeat point from 69
above
_ _ _ Done
_ _ _To be provided by
mechanical / fabshop
_ _ _
Drawing for corrosion
coupon is not
available