Kölbl N Certification Ankara Nov 2015
Transcript of Kölbl N Certification Ankara Nov 2015
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 1
08-13
Hoş Geldiniz!
ASME N-Certificates How to become N-type
certified by ASME
TÜV Thüringen ASME Certificate
TÜV Thüringen Group
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 2
Experts in ASME Code
CIS GmbH Consulting Inspection Services
Consulting
Training
Design
Audits
3rd Party Inspection
CIS GmbH
ASME Certificate Holders BPV & N‐Type & QSC
0
500
1000
1500
2000
2500
3000
3500
4000
4500
1974 1979 1984 1989 1994 1999 2004 2009 2014
USA
International
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 3
ASME Certificate Holders BPV & N‐Type & QSC
TURKEY(118)50
01-15
ASME certified companies
4544
4812
5137
5500
5748
5956 6038
6290
6683 6841
173180
196
221
270
331
374
395
380
340
150
200
250
300
350
400
3000
3500
4000
4500
5000
5500
6000
6500
7000
7500
8000
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
ASME Certificate Holders
BPV N Type & QSC
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 4
Dangerous Machines!
Gif:www.nrc.gov
Power Plant
Boiling Water ReactorBWR
Pressurized Water ReactorPWR
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 5
component: a vessel, concrete containment, pump,pressure relief valve, line valve, storage tank, piping system,or core support structure that is designed, constructed, andstamped in accordance with the rules of this Section.
part: an item that is attached to or becomes a portion of acomponent or support before completion and stamping ofthe component or support. Parts have work performed onthem requiring verification by an Inspector.
item: a product constructed under a Certificate ofAuthorization or NS Certificate of Authorization (supports)(NCA‐3120), or material (NCA‐1220).
material: for Section III, Division 1, metallic materialsmanufactured to an SA, SB, SFA, or any other materialspecification permitted in Section III and that aremanufactured, identified, and certified in accordance withthe requirements of Section III.
NCA-9000 Glossary
Components /Parts / Material
ComponentN‐Certificate Holder
Design SpecificationDesign Report
PartNPT‐Certificate Holder
Becomes Part of ComponentNo Design Report
MaterialMaterial OrganisationCMTR or COC
N
NPT
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 6
ASME Nuclear Application
ASME Nuclear Application
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 7
ASME Certification
Piping Systems
Valves & Pumps
Material(Plate, Pipe, Forgings, WFM, etc.)
Services(Design, NDE, testing, machining, PWHT, etc.)
Manufacturers of:
NO ASME Certification(Except: Section I => BEP)
ASME Certificationrequired!
NO ASME Certification(Except: Pressure Relief Valves)
ASME Certificationrequired!
ASME Certification orQualification required!
Qualification required!
NO ASME Certification
NO ASME Certification
Boiler & PV NUCLEAR
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 8
Contract with an AIA (Inspection Service Agreement)
Establish the Scope and Locations
‐ Application to ASME, https://caconnect.asme.org/
‐ Purchase Code Books
‐ Develop QA Manual and Procedures
‐ Implement the QA Program entirely
‐ Qualify Personnel & procedures (Welding, NDE, LA, ITP)
‐ Run a Demo Order (design, purchasing, fabrication, etc)
‐ Demonstration of Material Supply, USM, drop shiment
‐ ANI shall perform inspections
Pre Survey with AIA
Final preparation
Survey with ASME and AIA (3 Teams, 3‐5 days )
ASME Nuclear Certification
1 Organization2 Quality Assurance Program3 Design Control4 Procurement Document Control5 Instructions, Procedures, and Drawings6 Document Control7 Control of Purchased Items and Services8 Identification and Control of Items9 Control of Processes10 Inspection11 Test Control12 Control of Measuring and Test Equipment13 Handling, Storage, and Shipping14 Inspection, Test, and Operating Status15 Control of Nonconforming Items16 Corrective Action17 Quality Assurance Records18 Audits
NQA-1 Part 1 Requirements
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 9
Contract with an AIA (Inspection Service Agreement)
Establish the Scope and Locations
‐ Application to ASME, https://caconnect.asme.org/
‐ Purchase Code Books
‐ Develop QA Manual and Procedures
‐ Implement the QA Program entirely & audit
‐ Qualify Personnel & procedures (Welding, NDE, LA, ITP)
‐ Run a Demo Order (design, purchasing, fabrication, etc)
‐ Demonstration of Material Supply, USM, drop shiment, QMO
‐ ANI shall perform inspections
Pre Survey with AIA
Final preparation
Survey with ASME and AIA (3 Teams, 3‐5 days )
ASME Nuclear Certification
8 – 12mo
12 – 18mo
1 – 1,5mo
3 – 6mo
12 – 18mo
12 – 18mo
3 – 6mo
3 – 6mo
8 – 12mo
timeline
80d
1d
20d
20d++
60d
0‐50d
20d+
Labour estd.
20d
40d
250‐350 days
1 year
ASME Typical Nuclear Survey
ASME: 1 TL & 2‐3 TM, AIA: ANIS & ANIMonday: QA Manual reading
Team 1 QA 2 Software 3 Hardware
TL & ANIS TM 1 TM 2 & ANI
Tuesday Opening, Shop TourQAM
Opening, Shop Tour,Design
Opening, Shop Tour,Welding demo andrecords
Wednesday QAM Procurement, Vendorqualification, NCR, CAR, I&T Personnel, Audit Personnel,
NDE, PWHT, Traveler, procedures, Material Receiving andmarking, CMTR, Material Supply
Thursday ApplicationScope
Training, Audits, Records
Calibration, Testing, USM
Friday Team meetingExit Meeting
Team meetingExit Meeting
Team meetingExit Meeting
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 10
A Successful Survey Team
• Manufacturer Certification• Quality System• Material, testing and certification• Design• Fabrication• Examination• Inspection• Testing• Certification• Assembly and Erection• Records• Pressure Relief
Not adressed:
In-Service Inspection, Repairs, Alterations.
Construction Codes ?
N
(c) CIS Gmbh ‐ Ankara Conference November 2015 Page 11
Nuclear ASME Certificates
ASME Code Section III
N Nuclear ComponentsPressure Vessels, Containment, Piping Systems, Tanks, Valves, Pumps.
N3 Storage and Transport Containments
NPT Nuclear PartsWelded Parts / Appurtenances
NV Nuclear Safety Valves
NA Nuclear InstallerShop and Field Assembly
NS Nuclear Supports, No STAMP!
QSC Quality System CertificateMaterial Organisations
ASME Product Certification Mark
+ Designator: NA, …
Any Questions?
We Have Answers!
Dr. Dirk Kölbl, CIS GmbH Consulting Inspection ServicesKarolingerstr. 9645141 Essen, Germany
Tel.: +49 201 747275‐0Fax: +49 201 747275‐29
www.cis‐inspector.com