Kiribati Aggregate Mining 71b

download Kiribati Aggregate Mining 71b

of 19

Transcript of Kiribati Aggregate Mining 71b

  • 8/9/2019 Kiribati Aggregate Mining 71b

    1/19

    EU EDF 8 SOPAC Project Report 71bReducing Vulnerability of Pacific ACP States

    KIRIBATI TECHNICAL SUMMARYREPORT OF ECONOMIC ANALYSIS OF AGGREGATE

    MINING ON TARAWA

    March 2007

  • 8/9/2019 Kiribati Aggregate Mining 71b

    2/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 2

    Prepared and submitted by:

    Greer Consulting ServicesMarch 2007

    PACIFIC ISLANDS APPLIED GEOSCIENCE COMMISSION

    SOPAC SecretariatPrivate Mail Bag, GPO, Suva

    FIJI ISLANDShttp://www.sopac.org

    Phone: +679 338 1377Fax: +679 337 0040

    [email protected]

    IMPORTANT NOTICE

    This report has been produced with the financial assistance of the European Community; however, theviews expressed herein do not reflect the official opinion of the European Community.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

    http://www.sopac.org/mailto:[email protected]:[email protected]://www.sopac.org/
  • 8/9/2019 Kiribati Aggregate Mining 71b

    3/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 3

    TABLE OF CONTENTSPage

    INTRODUCTION AND OVERVIEW .....................................................................................................5

    CURRENT AGGREGATE ACTIVITIES ON TARAWA.......................................................................5Demand for aggregate on Tarawa...............................................................................................6Supply of aggregate for Tarawa...................................................................................................6Future supply and demand for aggregate ...................................................................................7

    DATA ............................................................................................................................................8Comparative aggregate costs......................................................................................................8Impacts of coastal mining on Tarawa..........................................................................................9

    Losses to Infrastructure and Property................................................................................ 9 Public utilities ................................................................................................................... 10 Protective works .............................................................................................................. 10 Impact on agriculture....................................................................................................... 10 Impact on public health ................................................................................................... 10

    FINANCIAL AND ECONOMIC ANALYSIS....................................................................................... 11Financial analysis...................................................................................................................... 11

    Introduction and assumptions ......................................................................................... 11 Annual dredge costs........................................................................................................ 12 Annual dredge revenue................................................................................................... 12 Commercial profitability of the KAC ................................................................................ 13 Viability of the dredge...................................................................................................... 13

    Economic analysis..................................................................................................................... 14Results of the economic analysis.................................................................................... 14 Not quantified benefits and social costs.......................................................................... 14

    RECOMMENDATIONS AND POLICY IMPLICATIONS................................................................... 15Public interest concerns ............................................................................................................ 15

    Environmental monitoring................................................................................................ 15 Cost sharing/Subsidisation.............................................................................................. 15 Governance issues.......................................................................................................... 16 Education and public awareness .................................................................................... 16

    Dredge operational aspects ...................................................................................................... 16Recommendations for further action......................................................................................... 17

    CITED WORKS AND REFERENCES............................................................................................... 18

    List of Tables

    Table 1: Estimated current demand for aggregate per year................................................................... 7Table 2: Estimated future demand for aggregate per year..................................................................... 8Table 3: Comparative costs of aggregate ............................................................................................... 8Table 4: Summary of social and environmental impacts..................................................................... 11Table 5: Dredge Aggregate Extraction and Processing Costs............................................................. 13

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    4/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 4

    ABBREVIATIONS

    BCA Benefit Cost AnalysisEDF European Development FundEIA Environmental Impact AssessmentESA Environmentally Safe Aggregates ProjectEU European UnionFSP Foundation for Peoples of the South PacificKAC Kiribati Aggregate CompanySOPAC Pacific Islands Applied Geoscience CommissionTSKL Telecom Services Kiribati Limited

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    5/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 5

    INTRODUCTION AND OVERVIEW

    Kiribati, a small and developing country in the central Pacific is currently experiencing a constructionboom on its main atoll of Tarawa. This is a result of increasing population as people from the outer

    islands move to Tarawa for work and opportunities, but also reflects increased development, supportedsubstantially by the international community, through numerous development and infrastructureprojects. Recent and planned development and infrastructure projects include a new sports stadium atBetio, upgrading Betio port, upgrading roads on South Tarawa and building health infrastructure.

    Construction uses gravel and rocks (aggregates). The government, businesses, families and donor-funded projects require aggregates to build homes, renovate buildings, construct seawalls and reclaimland. The majority of the aggregates needed to supply these needs are excavated, either by hand orusing machinery, from the beaches and coastal flats around Tarawa.

    Although this coastal mining is a cheap and effective way to supply aggregates on Tarawa, there aresome problems. First, the supply of locally sourced aggregates is often insufficient to meet local

    demand. The gap in aggregate demand is currently met using imports, which are expensive. Secondand critically, the Government of Kiribati is concerned that continued extraction of aggregates from thecoastal area, particularly South Tarawa where extraction is most concentrated, will subject Tarawa toan increased risk of flooding and erosion and damage to infrastructure.

    The Government already regulates coastal mining by limiting aggregate extraction to designated areasand by operating a permit system. However, it is also keen to further reduce the risks of coastal mining.It is therefore considering: removing the current designated area management system and banning aggregate extraction

    across South Tarawa; and establishing a commercial government body to dredge aggregate from the lagoon to meet local

    demands that way instead.

    This report summarises the findings of an economic analysis of the feasibility of this package ofmeasures. For details, see (Greer, 2007). This report discusses:

    aggregate activities on Tarawa; the competitiveness of using coastal sources of aggregate on Tarawa compared to lagoon or

    imported supplies; and policy implications.

    CURRENT AGGREGATE ACTIVITIES ON TARAWA

    Aggregates are used on Tarawa by the government and businesses for construction, road building,making cement building blocks, seawall protection and reclamation. In addition families use sand,gravel and shells for home construction, reclamation and seawall construction, landscaping, coveringgraves, covering the floors of pig pens, fencing boundaries and for sale (Pelesikoti, in prep.). Somedevelopment agencies also use locally sourced aggregates in their development or infrastructureprojects, such as the airport runway extension project on South Tarawa and the recent maneaba construction project. These large and occasional projects require significant amounts of aggregate fromtime to time.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    6/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 6

    Demand for aggregate on Tarawa

    At present, the total amount of aggregate needed to meet government, commercial, family and donorneeds on Tarawa is not known. There is only sporadic information of use by different user groups. Forinstance, the Ministry of Public Works is estimated to use a minimum of 5-10 cubic metres of gravelaggregate per day for regular road maintenance and small work projects ( pers. comm. Metai, Ministry

    of Works). This is equivalent to 25-50 cubic metres per week or 1,300-2,600 cubic metres per year.Bigger projects require much more aggregate material. For instance, the Public Works Departmentused around 125,000 cubic metres of aggregates for the airport runway extension project during 1993-1995 (Biribo & Smith 1994). However, the Public Works do not generally keep records of the amount ofaggregate used for their larger projects. Consequently, total demand for aggregates by theGovernment of Kiribati is not known. Likewise, the total amount of aggregate used by internationalagencies for their development projects is not known with certainty, although it is known how muchaggregate has been used on some individual projects. For instance, the upgrading of Betio port by theJapanese required 600 containers of aggregate imported from Fiji.

    Finally, there is no collection of data by the government on the demand for aggregates by families onTarawa.

    Supply of aggregate for Tarawa

    Most of the aggregate needs for Tarawa are sourced locally from the beaches and sand flats. Theseare mainly obtained from around South Tarawa where the population and demand for aggregates ishighest. Other aggregates are obtained from imports.

    On Tarawa, locally sourced aggregate is obtained by two means:

    Government and businesses who extract from the beaches and sand flats using machinery; and Households who extract aggregate from the beaches by hand.

    The total amount of aggregate actually supplied locally is not known, as records of mining by thegovernment and businesses are incomplete and unreliable, while no records of extraction by familiesexist.

    At the government level, what is known is that Public Works sources its 1,300-2,600 cubic metres ofaggregate for regular road maintenance and small work projects per year by excavating on the inter-tidal lagoon flats and in borrow pits. However, as there are no records of the amount of aggregate ituses for bigger activities the total supply per year by the government is not known.

    The amount of aggregate extracted by commercial businesses is also uncertain, but in a normal year isexpected to be at least 2,500 cubic metres, and much more when there are large construction andreclamation projects.

    There are no official records of the amount of aggregates supplied locally to donor-funded projects.

    Until 2006, there were no records of the amount of aggregate extraction by households on Tarawa.However, in early 2006, the Pacific Islands Applied Geoscience Commission (SOPAC), in collaborationwith the Government of Kiribati, conducted a household survey of aggregate extraction in SouthTarawa of aggregate extraction. This study was funded under SOPACs EDF Project on ReducingVulnerabilities of Pacific ACP States, which has already conducted surveys on Tarawa of the damageto coastlines caused by the removal of aggregates.

    According to the survey (Pelesikoti, in prep.), 73 percent of households across South Tarawa minedaggregate (sand, gravel, rock and shell) and of the households that were mining a third mined more

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    7/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 7

    than once a week. Data analysis indicates that as much as 70,000 cubic metres of aggregate iscurrently being mined by families each year in South Tarawa alone. The amount of coastal miningconducted by households around North Tarawa is unknown but is considered to be limited.

    Some aggregates for use on Tarawa are sourced from overseas. This is because:

    the quantity of aggregates from local sources is not always sufficient to meet the demand fromoccasional donor-funded construction projects;

    donor organisations sometimes require access to aggregate of a superior quality to that locallyavailable; and

    some donors are required to use imports for environmental reasons.

    Consequently, there is a history of importing aggregate for donor-funded and private constructionprojects. For example, over the last two years the Japanese have imported 600 containers ofaggregate from Fiji for the Betio port upgrade project, and previously they imported aggregate for thepower station and water supply project.

    A summary of current demand for aggregate is shown in the following table. This total amount of locallyand internationally sourced does not include any aggregate removed by households around NorthTarawa. More importantly, it does not include the use of aggregate for occasional large-scale infrastructure or development projects. This estimate of supply from Tarawa is therefore highlyconservative.

    Table 1: Estimated current demand for aggregate per year.

    Source of aggregate Current demand (m3

    ) Data source/commentHousehold sector 70,000 Pelesikoti 2006 (does not include North Tarawa)

    Ministry of Public Works and Utilitiesmaintenance/small projects

    5,000 Consultant estimate, allowing for maintenance and smallprojects

    Imports 5,000 Consultant estimate, based on recent imports

    Commercial sector 2,500 Consultant estimate, based on maintenance needs,excluding large projects

    Total 82,500 Minimum total not allowing for occasional largeinfrastructure projects.

    Future supply and demand for aggregate

    The total demand for aggregate on Tarawa is likely to increase in the future: as the population increases (especially from inward migration from the outer islands) demanding

    more housing; and when several planned large infrastructure projects which need for large quantities of aggregate are

    executed (such as the Japanese-funded road upgrade project estimated to require around 20,000cubic metres of material).

    At the same time, demand for aggregate from businesses and families is likely to increase slowly asthe population on Tarawa increases and housing is upgraded. The importation of aggregate is

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    8/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 8

    expected to increase at a higher rate than the other sectors because of the stricter enforcement ofmining controls and growing awareness of the negative environmental effects of mining, especially bythe donor community.

    A summary of the estimated future demand for aggregate is shown in the following table. Again, thistotal amount of locally and internationally sourced does not include the use of aggregate for occasional

    large-scale infrastructure or development projects that may arise in the future . This estimate istherefore a conservative estimate.

    Table 2: Estimated future demand for aggregate per year.

    Source of aggregate Current demand (m3) Future increase per year

    Household sector 70,000 +5% per year MPWU maintenance/projects 5,000 +5%

    Imports 5,000 +7% Commercial sector 2,500 +5% Total(not allowing for occasional large infrastructureprojects)

    82,500

    DATA

    Comparative aggregate costsThe comparative costs of accessing aggregate from four sources hand mining by households,mechanical mining by businesses and the government, the proposed dredging operations by thegovernment and from importing were analysed based on information obtained during fieldwork inKiribati and other reports and information. Details are available in the full technical report. Informationon the cost of imported aggregate material was taken from imports of aggregate from Fiji.

    A summary of financial costs is given in Table 3.

    Table 3: Comparative costs of aggregate.

    Source of aggregate Cost per m 3 CommentManual mining by household sector A$50 Inferior and variable qualityMechanical excavation & screening A$60 From inter-tidal zoneImports A$104 Superior materialDredge material plus screening A$58-60 Similar or better quality to mechanical mining

    Source: Consultants estimates

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    9/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 9

    Impacts of coastal mining on Tarawa

    Numerous studies in Kiribati and elsewhere have highlighted the causal link between coastal mining ofaggregate and increased threat of coastal communities to erosion and flooding (Webb 2005; Forbes &Hosoi, 1995; Howorth 1982, 1983). The removal of aggregate material from the foreshore reduces the

    buffering effect and exposes the coastline to increased wave energy.

    Coastal mining can therefore increase the risk on Tarawa of flooding and land erosion. This can have anumber of negative consequences such as losses to:

    infrastructure and property; public utilities (water and sewerage, electricity and phone lines); protective works; agriculture; and public health.

    To estimate any losses associated with these sectors, it would be necessary to:

    determine the physical losses of land and amenities arising from flooding and erosion on Tarawagenerally;

    determine the proportion of those losses that are directly attributable to coastal mining; and convert those amounts into monetary values.

    Unfortunately, it is not possible to do this for most of the sectors. The main problems in determiningimpacts are that (i) coastal processes are natural and dynamic and it is difficult to distinguish betweenthose events that would occur naturally and those that occur because excessive aggregate removalhas tipped the balance; and (ii) coastal processes not only result in erosion of land in some areas butalso accrete land in others. This makes determining the overall impact of coastal mining difficult toassess. Certainly, those areas of Tarawa that are clearly experiencing erosion are frequently the mostdensely populated, or close to important infrastructure such as the Tungaru Hospital. Add the impact ofglobal warming and increased coastal pressures from rising sea levels on Tarawa and it is clear thatthe threats to Tarawa from coastal mining are significant but it is not known by how much and when.Nevertheless, because of the difficulties in assessing the actual losses attributable to coastal miningspecifically, it is only possible to describe many of these losses and evaluate losses in money terms foronly one or two.

    Losses to Infrastructure and Property

    Losses of land are definitely occurring on Tarawa and much of this has been attributed to coastalmining (Webb 2005). Significantly, some locations that are losing sand are those that are the mostvaluable because they are most densely populated, or close to important infrastructure such as theTungaru Hospital.

    On the other hand, coastal accretion, erosion and longshore transport of sand is a dynamic processaffected by both natural weather patterns and man-induced processes through reclamation andbuilding causeways, so that over time a beach may in turn build up or wash away (Howorth 1983).

    Consequently, it is not possible to determine with certainty the total area of land that has been lost tocoastal erosion in recent years, let alone the proportion that is due to coastal aggregate mining alone. Itis also not possible to predict what the likely land losses will be in the future. While the area is not large,its proportionate loss in comparison to total land area may yet be significant.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    10/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 10

    Public Utilities

    Coastal erosion and flooding is a serious threat to public utilities because most of the electrical andtelephone cables are buried underground, as are water supply and sewerage works. Buried cables,particularly those flanking the causeways are very susceptible to erosion and the state telecomcompany Telecom Services Kiribati Limited had allowed for the replacement of the cables that were

    threatened by coastal erosion along the Bairiki Causeway, before the Ministry of Works built a newsandbag seawall to protect the causeway. Electricity cables face a similar risk and therefore similarcosts. The piped water supply system is also buried underground and erosion and seawatercontamination is a threat to that infrastructure. However no accurate estimate of the future cost of thisthreat is available.

    Protective works

    The Ministry of Works is responsible for the maintenance and protection of government buildings,including the Betio Hospital and the main Tungaru Hospital, roads, government housing and thegabion protection at the ocean end of the airport. An asset register compiled in 1999 lists 22 sea wallsand coastal protection structures on South Tarawa with a total length of 2.7 kilometres, although thislist does not include the more recent causeway and protective walls that had been built. Taking intoaccount protective works belonging to the private sector and non-government organisations, theamount of coastal protection is likely to be considerably more. The cost of a sandbag seawall isbetween A$100-A$200 per metre while concrete sea walls such as that along the Betio Causeway cancost A$5,000 per metre. The capital cost of the protective works that have been built is likely to be inthe order of several million dollars, which implies an annual maintenance and replacement cost of overA$100,000 per year. In the future the impact of coastal mining of sand and gravel coupled with globalwarming is expected to increase the threat of coastal erosion requiring an increased investment inmaintenance and additional protective works, possibly requiring investment of tens of millions ofdollars.

    Impact on agriculture

    An increase in severity and incidence of coastal erosion and flooding could be expected to adverselyaffect agricultural production in the future. However data on the quantity and value of agricultural andlivestock production on South Tarawa is not available, and there is no information on the collectiveimpact of coastal erosion flooding and salt water intrusion apart from anecdotal evidence and isolatedexamples. Most households have access to breadfruit and coconuts and also raise pigs. In terms ofthe impact of coastal erosion the current annual cost is likely to be relatively minor.

    Impact on public health

    Water supply and sanitation and their associated illnesses are a major issue for the densely populatedcommunities on South Tarawa. Increased flooding potentially could have serious impact. Although themain urban centres have a piped water supply other communities and settlements rely on well waterfrom the fragile freshwater lens. The main cause of mortality and sickness amongst the under-five agegroup is diarrhoea and pneumonia; the former is closely connected with poor water supply andsanitation. An increase in flooding and saltwater intrusion arising from aggregate-related erosion couldcontaminate the groundwater and impact sanitation to result in a lower quality of life through

    inconvenience and an increase in disease. Although the Ministry of Health are not able to pinpoint anyexamples where seawater flooding has been associated with an outbreak of diarrhoea or disease,there are pockets of waterborne disease outbreaks that had been clearly associated with a broken

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    11/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 11

    water main or a lack of chlorination in the water supply, so it is likely that it would have an effect.However it is not possible to realistically estimate the future impact of this risk.

    Table 4: Summary of social and environmental impacts.

    Sector Economic impact from coastal mining

    Infrastructure and property Loss, not determined

    Public utilitiesWater and sewerageElectricityPhone lines

    Not determinedNot determinedNot determined

    Protective works Maintenance cost A$100,000 per year

    Agriculture Losses to breadfruit and coconut production, not determined

    Public health Degradation of freshwater supplies (saltwater intrusion into groundwater) andimpact of poor sanitation to sickness, not quantified

    FINANCIAL AND ECONOMIC ANALYSIS

    The proposed government dredging operations are planned to be done by a commercially sustainableenterprise called the Kiribati Aggregate Mining Company (KAC).

    The specifications for the KAC were originally expressed in its first feasibility assessment (Cruickshanket al. 1998) and are being used as the basis for the proposal for EU funding for its implementation.Accordingly these specifics are used as the basis for the financial and economic feasibilityassessments that follow. Details are available in the technical report (Greer, 2007).

    Financial analysis

    Introduction and assumptions

    The purpose of the financial analysis in this study is to determine the commercial feasibility andsustainability of the proposed KAC.

    For the financial analysis it is assumed that:

    KAC will receive a grant up to 2.2 million to fund the purchase of the dredge and equipment andTechnical Assistance costs for an initial three-year period.

    The dredge will be based at Betio port and operate for 230 days per year (46 weeks on a five-dayweek basis) allowing for six weeks downtime per year because of maintenance needs, delays inobtaining essential spare parts from overseas, rough weather and public holidays.

    The suction dredge is able to load and unload aggregate at the rate of 70 cubic metres per hourand the barge has a capacity of 200 cubic metres. Total annual production is assumed to be46,000 cubic metres.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    12/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 12

    The Betio aggregate screening and crushing plant can handle 1000 cubic metres of aggregate aweek.

    Two Technical Assistance Advisors funded by the EU would be attached to KAC (a ProjectManager and a Dredge Master) for an initial period of three years.

    KAC would be required to meet its variable operating costs from its revenue which include costs ofI-Kiribati staff, fuel, oil and essential repairs and maintenance. Depreciation charges and intereston capital are not included as the capital costs would be met from the EU grant.

    There are no major infrastructure projects underway in a normal year.

    Details on the assumptions used for the analysis are given in the technical report (Greer, 2006).Critically, assumptions about work rates and the capacity of the crushing plant are approximate andcould have a wide margin of error.

    Annual dredge costs

    Total operating costs for the dredge and for transport and processing aggregate material based on anannual excavated volume of 46,000 cubic metres are estimated to be in the region of A$2.6 million peryear (Table 5).

    Table 5: Dredge Aggregate Extraction and Processing Costs.

    Operation Cost per m3 Total annual cost Percent of

    totalDredge variable operating costs A$9.64 A$443,440 17%

    Excavation from the stockpile (borrow pit) and transport toMPWU depot

    A$3.14 A$144,440 6%

    Processing and screening at MPWU depot A$44.24 A$2,035,040 77%

    Total A$57.00 A$2,622,920Source: Consultants estimates

    The majority (77 percent) of the costs are estimated to be incurred as a result of processing and

    screening material at the depot.

    Annual dredge revenue

    For the construction sector there is more demand for gravel than for sand, most likely by a factor of atleast two or three of gravel to one of sand. 1

    The Vinstra Shoal deposit, where the dredge would work, has been assessed as being able to provide35-50 percent gravel. Taking the mid point of this range of 42.5 percent gravel means that dredging46,000 cubic metres per year would produce 19,550 cubic metres of gravel and 26,450 cubic metres of

    sand.

    1 The SOPAC report of 1995 (Biribo & Smith, 1995) assessed that there is a greater demand for gravel than sand by a ratio of almost 7:1. While by comparison the SOPAC 2006household mining survey assessed that the volume of gravel sold was greater than sand by a ratio of 2.6:1.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    13/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 13

    Gravel commands a higher price than sand because it has to be processed and screened, andparticularly where local gravel can substitute for more expensive imported material. Sand is cheaper toproduce, and may have to compete with beach sand mined by families for a share of the market whendemand is low. To maximise its revenue it is likely that KAC would have to sell its gravel at a higherprice than the actual cost of production and sell sand at a discounted price because of competitionfrom householders. The gravel price would need to be less than the cost of imported aggregate to

    compete, and the sand price would need to be competitive compared to the price of coastal sandmined by households. If for example the company sold gravel for A$90 per cubic metres and sand forA$35, annual revenue would be:

    Gravel income 19,550 m 3 @ A$90 = A$1,759,500Sand income 26,450 m 3 @ A$35 = A$925,750Total 46,000 m3 A$58.38 A$2,685,250

    Commercial profitability of the KAC

    This would theoretically be sufficient to meet the annual operating costs and return a small profit asshown in the following summary.

    Production 46,000 m3 per year A$Total revenue 2,685,250Total costs 2,622,920Total profits 62,330

    However the profitability of the dredges operation is sensitive to changes in the level of costs andincome. A 10 percent increase in costs would eliminate any profit and produce a loss of A$200,000 peryear, while a 10% decrease in costs would increase the profit to A$325,000 per year. Similarly a 10percent reduction in the price of sand and gravel would result in a loss of over A$200,000 per year,while if only 75 percent of the production of sand was able to be sold there would be an annual loss ofA$169,000 per year.

    Viability of the dredge

    There are several issues that affect the ability of the company to make this potential profit (operationalviability):

    1. The actual dredge operating costs are only part of the total cost of producing screened sand andgravel of a uniform quality. In fact, the on-shore cost for processing and screening aggregate costsare estimated to be more than the cost of operating the dredge.

    2. The demand for aggregate material for infrastructure or development projects funded by thegovernment or donors is lumpy and not the same from year to year. In some years, there may bemore major projects, which increase the demand for aggregate, and therefore increase theprofitability of the KAC. In other years when there are no large-scale projects, the commercialdemand for KACs aggregate may be less than its production. In this case, a large part of thedredges production may have to be sold to the domestic private market at a lower price. However,families that sell hand-mined aggregate are likely to be able to undercut the dredge aggregate(although the quality may not be as high) creating competition and lowering prices. In this case

    selling excess dredge material to households will depend on the government being able to enforceits proposed island-wide ban on coastal mining

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    14/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 14

    3. The dredge operation would receive full time support of EU-funded advisors for the first three tofive years of its operation while being supported by the EU grant, so it could be expected that theoperation would work. However the long-term viability of the dredge will depend on local expertiseand capacity to maintain the operation. It will be important to respond to breakdowns quickly toensure that the dredge is not out of action for too long a period so that customers do not loseconfidence in the operation and resort to alternative sources and importation. The long-term

    operational viability after the end of EU support is therefore a critical issue which the governmentand the EU (funding the exercise) would need to address to ensure continuity.

    4. The life of the dredge equipment is expected to be 10 years at the end of which new equipment isneeded. (The barge and hull is expected to last 20 years). Therefore a plan for capitalreplacement needs to be incorporated into company operations. Failure to do so would mean thecessation of dredge activities and a return to coastal mining. In fact, a detailed business plan forKAC should be developed well in advance of the commencement of operations.

    Economic analysis

    The purpose of the economic analysis is to assess the viability of the project from a nationalperspective taking into account economic, social and environmental factors. The methodology used isthe application of Benefit Cost Analysis (BCA). In this approach the costs and benefits of KAC overtime are compared to calculate the Economic Internal Rate of Return (EIRR). This is equivalent to afinancial rate of return on an investment but represents the wider impact on society and nationalinterests. Details of the assumptions and methodology used for the economic analysis are given in thetechnical report (Greer, 2006).

    The key assumptions for the economic analysis are: It allows for a period of 50 years to reflect the long-term and inter-generational nature of coastal

    mining impact. Comparative economic mining costs are expressed in constant 2006 prices adjusted for a shadow

    value of labour and long run un-taxed fuel costs. The opportunity cost of capital (discount rate) is assumed to be 10 percent. The costs of the 2.2 million EU grant for the capital cost of the dredge and equipment and

    Technical Assistance are included. The future demand for aggregate is assumed to increase at 5 percent per year for a period of 10

    years then to stabilise. Imported aggregate is assumed to increase at a rate of 7 percent per year for 10 years and then to

    stabilise. In future with situation there is a residual production of 1,500 cubic metres per year of

    mechanical excavation allowing for rocks and large aggregate material that could not be suppliedby the suction dredge.

    There are no major infrastructure or development projects at work in a normal year.

    Results of the economic analysis

    The EIRR is 16 percent, which is an attractive return for this type of project. (This is the equivalent tothe return on a financial investment). The majority of the economic benefits come from cost savings asa result of replacing imports of aggregate with locally sourced dredge aggregate.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    15/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 15

    However, the results are very sensitive to the relative cost of the aggregate from different sources andthe underlying assumptions about the cost of operating the dredge and processing the dredgedmaterial. A 3 percent increase in the average cost per cubic metre of the dredge material reduces theEIRR to 10 percent; which means that the project would only break even from an economicperspective. The economic return is also sensitive to the cost of the manually mined materials, and thegrowth in future demand for aggregate. The estimate is based on the assumption that the there are no

    major infrastructure projects under way. However, if there were, the EIRR the payoff from the KACand the ban would be expected to be still higher.

    Not quantified benefits and social costs

    The EIRR underestimates the economic value of the KAC and the ban because it does not include allthe benefits to Kiribati of environmental changes brought about by reduced coastal mining ofaggregate. Although very difficult to predict, these values may be highly significant. For instance, thebenefits of preventing further loss of land, infrastructure and utilities may be extremely high.

    On the other hand, the social impact on the people of South Tarawa of relocating mining to the offshorelagoon area and banning coastal mining cannot be overlooked. The recent SOPAC study onhousehold mining of coastal aggregates estimated that around 1200 households around South Tarawaalone get extra income from mining activities and that approximately 150 households, mostly in thevillages of South Tarawa Temaiku and Bonriki, the main gravel mining areas, rely entirely on sellingaggregates for their livelihood. The introduction of the dredge will reduce the scope for suchhouseholds to supply aggregate legally and will therefore reduce income to the families. It will beimportant to provide assistance to help these families develop alternative income generating andlivelihoods, such as providing assistance related to agriculture and fishing. This is also critical to thesuccess of the KAC, which relies on the mining ban to ensure a market for its aggregate.

    RECOMMENDATIONS & POLICY IMPLICATIONS

    Public interest concerns

    Environmental monitoring

    There will be a need to closely monitor the environmental impact of the operation of the dredge withrespect to any disturbance of the marine environment at the Vinstra shoal where the sand and gravelwould be extracted, and also for the area where the material is offloaded into the old borrow pit on theinter-tidal flat at Betio.

    As there is likely to be lively public concern and interest in the effect that the dredge may have on themarine environment and fishing resources, close monitoring and transparent disclosure about theimpact will be necessary to avoid negative and possibly un-informed public opinion.

    Closer monitoring and recording of the household mining sector is also required to build up a timeseries of data on mining, usage and public attitudes to management and control of coastal mining bygovernment.

    Cost sharing/Subsidisation

    As an incentive to reduce the dependence on coastal mining by households for domestic use ofaggregate, the feasibility of selling them with dredge material at a basic cost, or at a subsidised price

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    16/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 16

    should be looked into. The supply of dredge material to donor-funded construction projects as asubstitute for imports should allow for a reasonable profit margin, which could then allow the cost ofaggregate that is distributed for household use to be subsidised. Dredge material could be transportedfree of charge to other parts of Tarawa to reduce transport costs for consumers and supplied to smallretailers or on-sellers at minimum cost.

    Compliance with the ban on beach mining will be crucial for KACs viability and long-term survival toensure a sufficient cash flow after the end of EU assistance.

    Governance issues

    The operation of the proposed State-owned KAC aggregate mining company that has a monopolisticposition will require careful control and good management to ensure that it operates efficiently andgenerates sufficient return to meet its overheads and operating costs. The performance of somepublicly owned enterprises in Kiribati that are supposed to be self-supporting have not been sosuccessful, and the dredges operation will require good governance to ensure that it operatesprofitably and achieves long-term viability.

    Education and public awareness

    The control of coastal mining cannot be achieved without the full co-operation and involvement of localcommunities. Further education and public awareness is required to change people's attitudes to theuse of what is regarded as a common resource, and to reduce the mining of coastal aggregate,particularly for non-economic landscaping use. Without the backing of the local communityenforcement of the regulations will be very difficult, if not virtually impossible.

    Dredge operational aspects

    Some aspects of the proposed dredges operation required clarification and more investigation. Thefollowing comments are put forward to highlight issues that need more investigation:

    1. The dredge should be registered in Kiribati, rather than an overseas country, to avoid thenecessity to travel to Fiji (or elsewhere) for the annual survey and renewal of registration.

    2. The practicality of the proposal to discharge the material into the borrow pit needs to be confirmed.Coordinating activities around the tides will be crucial to the efficient operation as the dredge willonly be able to discharge into the borrow pit at high water needing three to four hours, and thematerial can, in turn, only be transported to land at low tide during a three to four hour window. Adredge with bottom-opening doors would be able to discharge more quickly than by using a sandpump. This option should be considered to allow more flexibility to the operation. Thedisadvantage of this discharge method is that sufficient draught of water under the dredge isneeded for the material to disperse which may reduce the operating window at high tide fordischarge. Another alternative is to have a permanent pump and discharge pipe at the dischargelocation and transport material directly from the dredge to the stockpile at the Ministry of Worksdepot reducing the time and cost of discharge at transport to dry land. An anchoring pole shouldalso be installed at the discharge site to facilitate the positioning and mooring of the dredge for

    unloading the material.3. The capacity of the borrow pits to hold the material is not known and there may be some loss of

    material as it is discharged into the pit if there is strong tidal flow. The original dredge proposal in

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    17/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 17

    1995 considered that the dredge would discharge to the Public Works quay site at Bonriki.Discharging at the main Betio wharf is another possibility, but the port is already overcrowded andtrucking the material from the port to the aggregate depot would add to road congestion and causemore wear and tear on the roads. Nevertheless using stockpiling dumps and processing sites atmore than one location may make sense and other alternatives should also be investigated morefully.

    4. Public Works aggregate storage and processing depot at Betio may have to be expanded to copewith the increased amount of material and more machinery will be required to cope withtransporting material off the beach and screening it through the gravel crusher and screen. (It isnot confirmed whether the current equipment is capable of dealing with the anticipated 1,000 cubicmetres of material a week produced by the dredge).

    5. The suction dredge will produce a mixture of sand and gravel material with a greater proportion ofsand. It is not known what will be the proportion in the dredge material between sand and graveland whether the production of gravel from the dredge will be sufficient to meet the future needs forgravel aggregate from government and donor-funded projects.

    6. As the dredge will not be able to produce large-sized aggregate and cobbles because of the sizeof the suction pipe the need for large aggregate and rocks will still have to be obtained fromcoastal mining.

    7. A business plan for the operation of KAC should be prepared at the start of the project.

    Recommendations for further action

    Information on the supply and demand of aggregate in Tarawa is incomplete, and it is not possible tocompile a comprehensive record of the volume extracted over time, prices, nor the use of aggregate.The 2006 SOPAC mining survey has provided very useful information on the extent of mining activitiesby the household sector and the use of aggregate material. It has highlighted how widespread miningis and how important mining is to the domestic economy. There is a need for further monitoring of themining sector to gain more information and to help with ensuring compliance with the regulationsconcerning mining.

    The price of the aggregate that is mined by the dredge will be important to developing a market formaterial as an alternative to coastal mining.

    More research must be conducted by those designing and implementing the Kiribati Governmentsprogramme on the use, demand, cost of supply of aggregate and markets and prices. This informationshould also be monitored regularly.

    The following recommendations are put forward for further consideration:

    1. The Ministry of Public Works should be legally required to no longer conduct coastal mining fromthe inter-tidal flats and as far as in practical to obtain all its supply of aggregate from the dredgematerial.

    2. A comprehensive monitoring system should be established to monitor coastal mining and toestablish a database of key suppliers and consumers.

    3. The current system of relying on voluntary reporting of the quantities mined by permit holders forthe purpose of estimating the royalty that is payable to the landowners should be changed to amore exacting recording system through regular monitoring of activities.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    18/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 18

    4. Coastal erosion hotspots and areas prone to flooding should be well documented and a zerotolerance approach used against illegal miners. The local community should be encouraged totake a more active role in policing illegal mining by public relations and community awarenessprogrammes and through providing appropriate recognition to those villages and communities thatrespect the mining regulations.

    5. The Governments intention to impose an absolute ban on coastal mining (initially for SouthTarawa and, possibly, eventually elsewhere) is likely to be impractical and un-enforceable. It wouldundermine attempts to develop community cooperation for reducing the negative effects of coastalmining and could encourage disrespect for law and order. As a compromise, in recognition of thecommon practice in obtaining domestic supplies of aggregate, a certain amount of mining forhousehold use from less high-risk areas should be tolerated with enforcement concentrated onstopping mining for sale from non-mining designated areas and all mining in crucial erosion-proneareas. Viability rests with public support, which needs to be supported and promoted by strategicpublicity.

    6. A public awareness campaign should be conducted when the dredge starts to generate supportfor the programme and to educate the public. An organisation such as the Foundation for thePeoples of the South Pacific (FSP) could be used to mobilise public support and raise awareness.They think that the radio and visual means such as drama shows are the most effective mediumfor this purpose.

    CITED WORKS & REFERENCES

    Cited Works

    Biribo, Naomi and Smith, Robert. Sand and Gravel Usage South Tarawa, Kiribati 1989-1993. Ministryof Environment & Natural Resources, Kiribati SOPAC Secretariat, Preliminary Report 75,December 1994.

    Cruickshank, Michael J. & Morgan, Charles L. Economic Feasibility and Environmental Impact Assessment for Extraction of Sand Offshore Tarawa. Report prepared for Ministry of NaturalResources Development, Kiribati by M.J. Cruickshank & C.L. Morgan Consultants, October 1998.

    Darrock, Neil. Kiribati Land Ownership and Land Valuation. Darrock Valuations, Auckland, 1996.

    Government of Kiribati, 2005. Adapting to Climate Change KAP II: Kiribati Adaptation Program,Phase 2: Building Participation and Capacity, Project Implementation Plan. Office of Te Beretitenti,Bairiki, Tarawa, Republic of Kiribati, December 2005.

    Greer Consulting Services, 2007. Kiribati Technical Report Economic analysis of aggregate mining on Tarawa. EU-SOPAC Project Report 71. 110 p. SOPAC Secretariat, Suva.

    Hajkowicz, Stefan & Okotai, Petero. An Economic Valuation of Watershed Pollution in Rarotonga, the Cook Islands. CSIRO Sustainable Ecosystems. Brisbane, Australia. April 2005.

    Howorth, Russell. Report on Coastal Erosion in Kiribati; Visit to South Tarawa 23 August 8September 1983. SOPAC Technical Report 31. Suva, Fiji. November 1983.

    Pelesikoti, Netatua (in prep.) Kiribati Technical Report Extent of Household Aggregates Mining in Kiribati and Proposed Integrated Monitoring Framework for Tarawa Lagoon. EU-SOPAC ProjectReport 72 (in prep.). Fiji, June 2006.

    [EU-SOPAC Project Report 71b Greer Consulting Service]

  • 8/9/2019 Kiribati Aggregate Mining 71b

    19/19

    EU EDF-SOPAC Reducing Vulnerability of Pacific ACP States Kiribati Summary Aggregate Mining Economic Report 19

    Toyo Pumps, Canada and Blue Water Craft, Fiji. Suction Dredge Specifications and Costs . SOPAC,Suva, December 2005.

    WBGU. The Future Oceans Warming Up, Rising High, Turning Sour- Summary for Policy Makers .German Advisory Council on Global Change (WBGU). Berlin, 2006.

    Webb, Arthur. An assessment of coastal processes, impacts, erosion mitigation options and beach mining South Tarawa. EU-SOPAC Project Report 46. Fiji. 2005.

    Personal Communications

    Biribo-Atauea, Naomi. Senior Minerals Development Officer, Ministry of Fisheries and marineResources, South Tarawa, Kiribati. Personal Communication September 2006.

    Kabaua, Tiaon. Civil Engineer, Ministry of Public Works and Utilities. Personal Communication. Kiribatimission July 2006.

    Kinaai, Kairo, Ms. Director of Agriculture. Ministry of Environment, Lands & Agricultural Development.Personal Communication. Kiribati mission July 2006.

    Lin, Kuo-Tai. Project Manager, Overseas Engineering & Construction Ltd. Personal Communication.Kiribati mission July 2006.

    Metai, Eita. Engineer, Ministry of Public Works and Utilities. Personal Communication. Kiribati missionJuly 2006.

    Nonogaki, Masahiro. Manager, Dai Nippon Construction. Personal Communication. Kiribati missionJuly 2006.

    Taaeta, Maman, Permanent Secretary, Ministry of Finance. Personal Communication. Kiribati missionJuly 2006.

    Takeke, Rikiana, Deputy Secretary, Ministry of Environment. Personal Communication , Kiribati missionJuly 2006.

    Tiiban, Dr Kabwea. Director, Ministry of Health. Personal Communication. Kiribati mission July 2006.

    General References

    ADB. Kiribati Country Strategy and Program Update 2006-2007 . Asian Development Bank, Manila.January 2006.

    Lonely Planet. South Pacific: Polynesia, Melanesia & Micronesia. 1st Edition. Lonely PlanetPublications. Melbourne. 2000.

    UNDP. Human Development Report 2005 , UNDP, New York 2005.

    World Bank. Cities, Seas and Storms (regional economic report on the Pacific Islands).Washington, DC. 2000.