KINGDOM OF SAUDI ARABIAArriyadh Development AuthorityRIYAD
السعودية العربية المملكةالعلي ـئـــيـاله ا ــة
الري رـلتطوي اضـمدينة
ASSOCIATED CONSULTING ENGINEERS
Project Description
The Upgrade of King Abdullah Road Project will provide a continuous 5.3 km Urban Freeway in Riyadh from Prince Turkey Road to King Abdulaziz Road.
The 5.3 km segment will complete one of the remaining gaps of grade separated intersections in one of the most congested corridors in the Kingdom’s capital. Existing traffic in the project area is mostly stop and go throughout the day.
Project Purpose and Need
The primary purpose of the proposed project is to:
Reduce existing and forecast traffic congestion on king Abdullah Road between Prince Turkey Road and King Abdulaziz Road. The project is expected to enhance traffic operations by adding freeway level capacity in an area that currently experiences heavy congestion, and is expected to see increased congestion in the future.
Improve both existing and future mobility and enhance safety throughout the corridor, while minimizing environmental and economic impacts. The project will:
ease congestion, improve mobility by moving almost twice as many cars, decrease commute times for all drivers, enhance traffic safety, and reduce air pollution.
Prince Turkey Underpas s
Takhas s us s i Underpas s
King Fahd Tunnel Olaya Tunnel
Prince Ahmad Inters ection
King Abdul Aziz Underpas s
Project Phases
Detour of Classical Construction
Top-Down Construction Methodology
The “Top-Down” construction approach was primarily devised for existing structures short of space (parking, offices, utilities etc..) such as the existing building may remain in place and its activities uninterrupted while the additional construction works and expansion is happening beneath it. Later it was adopted to other construction industries such as highways, bridges, and even new buildings where significant benefits may be achieved by adding the ability to proceed with construction in both directions at the same time, starting at the ground surface.
In existing buildings or structures, where appreciable loads are present on the existing foundations, micropiles will be required to retain the sides of the excavation and to transfer the vertical loads onto a new bearing stratum taking into consideration differential settlement and its effects on the structure. Normally such works are very sensitive and require high technicity and expertise.
Design principle
Step One:
Drill the 60 cm piles, 150 cm on centers, install the piles reinforcement cage, and cast concrete up to the bottom level of the (60x146) pile cap.
Step Two:
Install the reinforcement cage of the (60x146) pile cap.
Design principle
Step Three:
Cast 20 cm of the 146 cm depth of the pile cap to provide seating for the pre-cast pre-stressed beams.
Design principle
Step Four:
Place the (60x100) pre-cast pre-stressed beams, seated 3 cm on the 20 cm cast portion of the pile cap. One beam is placed every 150 cm, i.e. one per pile.
Design principle
Step Five:
Lay the 6 cm pré-dalle seated 3 cm on the top of the pre-cast pre-stressed beams.
Design principle
Step Six:
Place the reinforcement of the 20 cm topping slab, anchored in the pile cap reinforcement cage.
Design principle
Step Seven:
Cast the topping slab along with the pile cap.
Design principle
Top-Down Construction Stages
A view of thearea just underneath the building showing the light on theother side
Top-Down Construction Applied to Existing Buildings
Top-Down Construction Applied to Existing Buildings
View of thebuilding’sfaçade
Utility Detour
Proposed Detours
Duration: 18 days (100 piles and 2 drilling machines)
Lanes lost: 1 lane of the service road for each direction
Proposed Detours
Duration: 18 days (100 piles and 2 drilling machines)
Lanes lost: 1 lane of the service road for each direction
Proposed Detours
Duration: 18 days (100 piles and 2 drilling machines)
Lanes lost: Zero (Compensated by the median between service road & freeway)
Proposed Detours
Duration: 18 days (100 piles and 2 drilling machines)
Lanes lost: Zero (Compensated by the median between service road & freeway)
Proposed Detours
Duration: 15 days drilling (80 piles) & 20 days slab works
Lanes lost: zero
PILES DRILLING STAGE 5
SLAB WORKS STAGE 1
Proposed Detours
Duration: 20 days excavation
Lanes lost: Zero
SLAB WORKS STAGE 2
Proposed Detours
STAGE 3
FREEWAAY WORKS AFTER INTERSECTION IS REINSTATED
Proposed Typical Sections
CL
TYPICAL SECTION
CL
TYPICAL SECTION
AT AMIR TORKEY TUNNEL
R.O
.W.
R.O
.W.
Typical section
At underpass
Proposed Typical Sections
CL
Proposed Typical Sections
CL
TYPICAL SECTION BEFORE KING FAHED AND AFTER OLAYA INTERSECTIONS
WHERE CLEARANCE BELOW 5.6m
Proposed Typical Sections
Typical Sections
CL
TYPICAL SECTION BEFORE KING FAHED AND AFTER OLAYA INTERSECTIONS
WHERE CLEARANCE EXCEEDS OR EQUALS 5.6m
Proposed Typical Sections
CL
R.O
.W.
R.O
.W.
Typical section
At tunnel
Proposed Typical Sections
Analytical Preparation Works
Topographic survey for existing roads and buildings- Geometric- Levels
Underground utilities survey Verification of Dornier's design Research and proposing of an alternative construction system Introducing two support system instead of one system to provide future construction flexibility
- LRT stations- fly Overs
Testing traffic model Coordination with relevant authorities
Design Criteria
Design Criteria
Design Criteria
Design Criteria
Design Criteria
Raising LRT at Prince Ahmad Intersection Finalizing the LRT access opening size and location Providing LRT rails and stations loading on King Fahd/Olaya Tunnel
OUTSTANDING ISSUES
Methodology for Traffic Assessment
In the macro-simulation- Check the traffic volumes - Determine the impact of detours (speeds and capacities)- Identify the diversion points and routes (by pass)
Tests of the options of detours in a micro-modeling tool - Determine the Level Of Service (LOS)- The design of the new intersections- Traffic optimization- Reduce as possible the impact of the works
Detailed detour plans and the required signage
Sample Run
As per Highway Capacity Manual (HCM), the adopted Level of Service (LOS) are:
- A speed >=41 kph - B speed >=32 & speed <41 kph
- C speed >=23 & speed <32 kph
- D speed >=18 & speed <23 kph
- E speed >=14 & speed <18 kph- F speed <14 kph
Microscopic Simulation
Microscopic Simulation
Microscopic Simulation
Microscopic Simulation
Microscopic Simulation
Microscopic Simulation
PM: 1 LaneMicroscopic Simulation