King Abdullah Road 4 12 07 Presentation

47
KINGDOM OF SAUDI ARABIA Arriyadh Development Authority RIYAD ة السعوديةكة العربيممل ال اله ـ ي ـــ ئ ـعلي ة ال ــ ا لتطوي ـ ر مدينة الري ـ اضASSOCIATED CONSULTING ENGINEERS

Transcript of King Abdullah Road 4 12 07 Presentation

Page 1: King Abdullah Road 4 12 07 Presentation

KINGDOM OF SAUDI ARABIAArriyadh Development AuthorityRIYAD

السعودية العربية المملكةالعلي ـئـــيـاله ا ــة

الري رـلتطوي اضـمدينة

ASSOCIATED CONSULTING ENGINEERS

Page 2: King Abdullah Road 4 12 07 Presentation

Project Description

The Upgrade of King Abdullah Road Project will provide a continuous 5.3 km Urban Freeway in Riyadh from Prince Turkey Road to King Abdulaziz Road.

The 5.3 km segment will complete one of the remaining gaps of grade separated intersections in one of the most congested corridors in the Kingdom’s capital. Existing traffic in the project area is mostly stop and go throughout the day.

Page 3: King Abdullah Road 4 12 07 Presentation

Project Purpose and Need

The primary purpose of the proposed project is to:

Reduce existing and forecast traffic congestion on king Abdullah Road between Prince Turkey Road and King Abdulaziz Road. The project is expected to enhance traffic operations by adding freeway level capacity in an area that currently experiences heavy congestion, and is expected to see increased congestion in the future.

Improve both existing and future mobility and enhance safety throughout the corridor, while minimizing environmental and economic impacts. The project will:

ease congestion, improve mobility by moving almost twice as many cars, decrease commute times for all drivers, enhance traffic safety, and reduce air pollution.

Page 4: King Abdullah Road 4 12 07 Presentation

Prince Turkey Underpas s

Takhas s us s i Underpas s

King Fahd Tunnel Olaya Tunnel

Prince Ahmad Inters ection

King Abdul Aziz Underpas s

Page 5: King Abdullah Road 4 12 07 Presentation

Project Phases

Page 6: King Abdullah Road 4 12 07 Presentation

Detour of Classical Construction

Page 7: King Abdullah Road 4 12 07 Presentation

Top-Down Construction Methodology

The “Top-Down” construction approach was primarily devised for existing structures short of space (parking, offices, utilities etc..) such as the existing building may remain in place and its activities uninterrupted while the additional construction works and expansion is happening beneath it. Later it was adopted to other construction industries such as highways, bridges, and even new buildings where significant benefits may be achieved by adding the ability to proceed with construction in both directions at the same time, starting at the ground surface.

In existing buildings or structures, where appreciable loads are present on the existing foundations, micropiles will be required to retain the sides of the excavation and to transfer the vertical loads onto a new bearing stratum taking into consideration differential settlement and its effects on the structure. Normally such works are very sensitive and require high technicity and expertise.

Page 8: King Abdullah Road 4 12 07 Presentation

Design principle

Step One:

Drill the 60 cm piles, 150 cm on centers, install the piles reinforcement cage, and cast concrete up to the bottom level of the (60x146) pile cap.

Page 9: King Abdullah Road 4 12 07 Presentation

Step Two:

Install the reinforcement cage of the (60x146) pile cap.

Design principle

Page 10: King Abdullah Road 4 12 07 Presentation

Step Three:

Cast 20 cm of the 146 cm depth of the pile cap to provide seating for the pre-cast pre-stressed beams.

Design principle

Page 11: King Abdullah Road 4 12 07 Presentation

Step Four:

Place the (60x100) pre-cast pre-stressed beams, seated 3 cm on the 20 cm cast portion of the pile cap. One beam is placed every 150 cm, i.e. one per pile.

Design principle

Page 12: King Abdullah Road 4 12 07 Presentation

Step Five:

Lay the 6 cm pré-dalle seated 3 cm on the top of the pre-cast pre-stressed beams.

Design principle

Page 13: King Abdullah Road 4 12 07 Presentation

Step Six:

Place the reinforcement of the 20 cm topping slab, anchored in the pile cap reinforcement cage.

Design principle

Page 14: King Abdullah Road 4 12 07 Presentation

Step Seven:

Cast the topping slab along with the pile cap.

Design principle

Page 15: King Abdullah Road 4 12 07 Presentation

Top-Down Construction Stages

Page 16: King Abdullah Road 4 12 07 Presentation

A view of thearea just underneath the building showing the light on theother side

Top-Down Construction Applied to Existing Buildings

Page 17: King Abdullah Road 4 12 07 Presentation

Top-Down Construction Applied to Existing Buildings

View of thebuilding’sfaçade

Page 18: King Abdullah Road 4 12 07 Presentation

Utility Detour

Page 19: King Abdullah Road 4 12 07 Presentation

Proposed Detours

Duration: 18 days (100 piles and 2 drilling machines)

Lanes lost: 1 lane of the service road for each direction

Page 20: King Abdullah Road 4 12 07 Presentation

Proposed Detours

Duration: 18 days (100 piles and 2 drilling machines)

Lanes lost: 1 lane of the service road for each direction

Page 21: King Abdullah Road 4 12 07 Presentation

Proposed Detours

Duration: 18 days (100 piles and 2 drilling machines)

Lanes lost: Zero (Compensated by the median between service road & freeway)

Page 22: King Abdullah Road 4 12 07 Presentation

Proposed Detours

Duration: 18 days (100 piles and 2 drilling machines)

Lanes lost: Zero (Compensated by the median between service road & freeway)

Page 23: King Abdullah Road 4 12 07 Presentation

Proposed Detours

Duration: 15 days drilling (80 piles) & 20 days slab works

Lanes lost: zero

PILES DRILLING STAGE 5

SLAB WORKS STAGE 1

Page 24: King Abdullah Road 4 12 07 Presentation

Proposed Detours

Duration: 20 days excavation

Lanes lost: Zero

SLAB WORKS STAGE 2

Page 25: King Abdullah Road 4 12 07 Presentation

Proposed Detours

STAGE 3

FREEWAAY WORKS AFTER INTERSECTION IS REINSTATED

Page 26: King Abdullah Road 4 12 07 Presentation

Proposed Typical Sections

CL

TYPICAL SECTION

Page 27: King Abdullah Road 4 12 07 Presentation

CL

TYPICAL SECTION

AT AMIR TORKEY TUNNEL

R.O

.W.

R.O

.W.

Typical section

At underpass

Proposed Typical Sections

Page 28: King Abdullah Road 4 12 07 Presentation

CL

Proposed Typical Sections

Page 29: King Abdullah Road 4 12 07 Presentation

CL

TYPICAL SECTION BEFORE KING FAHED AND AFTER OLAYA INTERSECTIONS

WHERE CLEARANCE BELOW 5.6m

Proposed Typical Sections

Page 30: King Abdullah Road 4 12 07 Presentation

Typical Sections

CL

TYPICAL SECTION BEFORE KING FAHED AND AFTER OLAYA INTERSECTIONS

WHERE CLEARANCE EXCEEDS OR EQUALS 5.6m

Proposed Typical Sections

Page 31: King Abdullah Road 4 12 07 Presentation

CL

R.O

.W.

R.O

.W.

Typical section

At tunnel

Proposed Typical Sections

Page 32: King Abdullah Road 4 12 07 Presentation

Analytical Preparation Works

Topographic survey for existing roads and buildings- Geometric- Levels

Underground utilities survey Verification of Dornier's design Research and proposing of an alternative construction system Introducing two support system instead of one system to provide future construction flexibility

- LRT stations- fly Overs

Testing traffic model Coordination with relevant authorities

Page 33: King Abdullah Road 4 12 07 Presentation

Design Criteria

Page 34: King Abdullah Road 4 12 07 Presentation

Design Criteria

Page 35: King Abdullah Road 4 12 07 Presentation

Design Criteria

Page 36: King Abdullah Road 4 12 07 Presentation

Design Criteria

Page 37: King Abdullah Road 4 12 07 Presentation

Design Criteria

Page 38: King Abdullah Road 4 12 07 Presentation

Raising LRT at Prince Ahmad Intersection Finalizing the LRT access opening size and location Providing LRT rails and stations loading on King Fahd/Olaya Tunnel

OUTSTANDING ISSUES

Page 39: King Abdullah Road 4 12 07 Presentation

Methodology for Traffic Assessment

In the macro-simulation- Check the traffic volumes - Determine the impact of detours (speeds and capacities)- Identify the diversion points and routes (by pass)

Tests of the options of detours in a micro-modeling tool - Determine the Level Of Service (LOS)- The design of the new intersections- Traffic optimization- Reduce as possible the impact of the works

Detailed detour plans and the required signage

Page 40: King Abdullah Road 4 12 07 Presentation

Sample Run

As per Highway Capacity Manual (HCM), the adopted Level of Service (LOS) are:

- A speed >=41 kph - B speed >=32 & speed <41 kph

- C speed >=23 & speed <32 kph

- D speed >=18 & speed <23 kph

- E speed >=14 & speed <18 kph- F speed <14 kph

Page 41: King Abdullah Road 4 12 07 Presentation

Microscopic Simulation

Page 42: King Abdullah Road 4 12 07 Presentation

Microscopic Simulation

Page 43: King Abdullah Road 4 12 07 Presentation

Microscopic Simulation

Page 44: King Abdullah Road 4 12 07 Presentation

Microscopic Simulation

Page 45: King Abdullah Road 4 12 07 Presentation

Microscopic Simulation

Page 46: King Abdullah Road 4 12 07 Presentation

Microscopic Simulation

Page 47: King Abdullah Road 4 12 07 Presentation

PM: 1 LaneMicroscopic Simulation