    U.S. Army Corps of Engineerspresentation to

    SAME

    John A. Keever P.E.

    Chief Construction DivisionLos Angeles DistrictUS Army Corps of Engineers

    29 April 2010

  • 7/30/2019 Keever Presentation

    2/44

    BUILDING STRONG

    You may not know usYou may not know us.. but you are familiar with our workbut you are familiar with our work

    Nellis AFB Dormitory

    Border Fence

    LA River Port of Los Angeles

    Rio Salado

    Prado Dam

  • 7/30/2019 Keever Presentation

    3/44

    BUILDING STRONG

    Construction Division Where the Work isSouthern California

    Area Off iceArizona / Nevada

    Area Off ice

    SoCal

    Area Office Resident Office:Edwards AFBFt Irwin AFB

    Vandenberg AFBSan Diego Resident OfficeSan Andreas Resident OfficeSanta Ana Dams Resident Office

    AZ/NV Area Office Resident Office:Las Vegas Resident OfficeRoad Runner Resident OfficeTucson Resident Office

  • 7/30/2019 Keever Presentation

    4/44

    BUILDING STRONG

    Field Offices

    Contractor Performance Evaluations

    Office Outstanding AboveAverage

    Satisfactory Marginal Unsat

    SoCal

    AreaOffice

    42 58 23 0 1

    AZ/NV AreaOffice

    31 22 22 1 2

    36%

    98%

  • 7/30/2019 Keever Presentation

    5/44

    BUILDING STRONG

    Field Office Safety Records As of 23 April 10

  • 7/30/2019 Keever Presentation

    6/44

    BUILDING STRONG

    Where the Work is

    US Army Cor psof Engineer s

    Construction Placement Summary - FY 2010 thru FY 2012Los Angeles District in cludin g Sub-Offices

    22 Apr 2010

    Los Angeles District

    A 37.3%

    B 62.0%

    Other

    A 44.0%

    B 56.0%

    Other

    A 63.6%

    B 36.4%

    FY 2010

    OCT33.7

    NOV26.6

    DEC45.4

    JAN35.1

    FEB38.3

    MAR47.3

    APR83.7

    MAY71.0

    JUN64.4

    JUL59.6

    AUG55.6

    SEP48.9

    $105.7 M $120.7 M $219.1 M 164.1 M

    $609.6 M

    FY 2011

    OCT49.5

    NOV50.3

    DEC48.7

    JAN52.1

    FEB53.3

    MAR54.6

    APR53.7

    MAY56.9

    JUN59.9

    JUL62.0

    AUG61.9

    SEP61.8

    $148.5 M $160.1 M $170.6 M 185.7 M

    $665.0 M

    FY 2012

    OCT58.8

    NOV56.2

    DEC54.5

    JAN52.0

    FEB48.5

    MAR47.2

    APR47.0

    MAY43.1

    JUN41.8

    JUL38.0

    AUG33.3

    SEP30.9

    $169.5 M $147.7 M $131.9 M 102.2 M

    $551.3 M

    Office FY 2010Placement

    A. Ar izona/Nevada Area Off ice $227.5 M

    B. Southern Calif ornia Area Of fice $378.0 M

    C. Tech/Env Support Br $2.1 MD. Service Contracts $2.0 M

    FY 2011Placement

    Change fromPrevious YR

    PercentChange

    $292.6 M $65.1 M 28.6 %

    $372.3 M -$5.7 M -1.5 %

    $0.0 M -$2.1 M -100.0 %$0.0 M -$1.9 M -97.8 %

    FY 2012Placement

    Change fromPrevious YR

    PercentChange

    $ 350.8 M $ 58.2 M 19.9 %

    $ 200.5 M -$ 171.7 M -46.1 %

    $ 0.0 M $ 0.0 M 0.0 %$ 0.0 M $ 0.0 M -100.0 %

    Actu al Earni ng s Pro ject ed Earning s

    $80-100 Mil in VA work$38 Mil Army Reserve work

    Not shown

    $42 Mil Army Reserve workNot shown

    $15 Mil Army Reserve work$11 Mil CBP Tactical Infrastructure

    Not Shown

  • 7/30/2019 Keever Presentation

    7/44

    BUILDING STRONG

    Civil Works Program

    Ecosystem

    Restoration:Tres Rios

    Navigation, Ports & Harbors:

    Port of L.A.

    Flood Risk

    Management:

    Prado Dam

  • 7/30/2019 Keever Presentation

    8/44

    BUILDING STRONG

    Civil Works OpportunitiesSanta Paula Creek Phase 2 Q4/FY10 $1M - $5M

    Rio de Flag Ph 2A, Open Channel Q2/FY10 $1M - $5M

    Tucson Drainage Upper Reach Q3/FY10 $1M - $10M

    Tres Rios - Phase 3A Water Marsh (D/B?) Q4/FY10 $1M - $10M

    Nogales Bridge Design Q3/FY10 $1M - $2M

    Santa Ana River Floodwall Q3/FY10 $5M - $10M

    Santa Ana River Auxi liary Dike Q4/FY10 $10M - $20M

    Santa Ana River Reach 9 , Phase 2B Q4/FY10 $1M - $5M

    Santa Ana River Reach 9, Phase 2A Q4/FY10 $10M - $20M

    Santa Barbara Harbor - Dredging Q3/FY10 $1M $1.5M

    San Diego Harbor - Dredging Q4/FY10 $1M $1.5M

  • 7/30/2019 Keever Presentation

    9/44

    BUILDING STRONG

    Facility Renovations

    Road Paving

    Heavy Equipment Maintenance

    Shade Structure Construction

    Fencing

    Sediment Removal

    Vegetation and Debris Removal

    Infrastructure Improvements

    ERGO Assessments

    Alternative Energy Solutions

    Dam component replacement

    Water fil tration and re-use

    Facility Lighting

    Physical Security improvements

    Removal and Installation of Trees

    Graffiti Removal

    Operations and Maintenance

    (FRM) Program Projects

  • 7/30/2019 Keever Presentation

    10/44

    BUILDING STRONG

    NEVADA

    Pine & Matthews Canyon Dams (NV): $ 321,100Inspection of Completed Works (ICW) - (NV): $ 54,500

    CALIFORNIALos Angeles County Drainage Area (LACDA): $ 4,329,800

    Santa Ana River Basin (SARB): $ 2,924,600Mojave Dam(CA): $ 271,300Scheduling Reservoir Ops (CA): $ 260,600Inspection of Completed Works (ICW) - (CA): $ 1,207,900

    ARIZONAAlamo Dam (AZ): $ 1,450,400Painted Rock Dam (AZ): $ 1,241,500Whit low Ranch Dam (AZ): $ 282,200Scheduling Reservoir Ops (AZ): $ 31,500Inspection of Completed Works (ICW) - (AZ): $ 187,200

    17 Projects54 miles of channels

    O&M (FRM) ProgramARRA: $13,011,000

    FY 2010 Budget: $ 14,914,600FY 2011 Presidents Budget: $ 19,837,000

  • 7/30/2019 Keever Presentation

    11/44

    BUILDING STRONG

    Davis-Monthan AFB

    Fort Huachuca

    Military Program

  • 7/30/2019 Keever Presentation

    12/44

    BUILDING STRONG

    Military

    FY 10 Contracting OpportunitiesFY10 Project

    ContractingMethod

    Scheduled Award PA Amount ($000)

    Davis Monthan AFB-CSAR HC-

    130J -

    Infrastructure TBD 3 QTR FY 10 $1,000 -

    $5,000

    Davis Monthan AFB-CSAR HC-

    130J-Simulator Facility

    TBD 3 QTR FY 10 $5,000-$10,000

    Davis Monthan AFB-CSAR HC-

    130J-Ops Building

    TBD 3 QTR FY 10 $5,000-$10,000

    FT Huachuca

    Battalion

    HeadquartersSB Set Aside 3 QTR FY 10 $5,000-$10,000

    Ft Huachuca

    UAS Hangar Unrestricted 3 QTR FY 10 $10,000-$20,000

  • 7/30/2019 Keever Presentation

    13/44

    BUILDING STRONG

    FY10 Project RTAScheduled

    AwardPA Amount ($000)

    Nellis AFB F-35A Maintenance Hangar/AMU 3 QTR FY 10 2 QTR FY 11 $20,000 -

    $50,000

    Nellis AFB F-35 Add/Alter Flight Instrument Fac 4 QTR FY 10 2 QTR FY 11 $

  • 7/30/2019 Keever Presentation

    14/44

    BUILDING STRONG

    FY10 Project RTA Scheduled Award PA Amount ($000)

    Davis MonthanAMARG Hangar 3 QTR FY 10 2 QTR FY 11 $20,000 -

    $50,000

    TBD F-35 Academic Training Center TBD FY 11 $50,000-$100,000

    TBD F-35 Squadron Operations FacilityTBD FY 11 $10,000-$20,000

    Military

    FY 11 Contracting Opportunities

  • 7/30/2019 Keever Presentation

    15/44

    BUILDING STRONG

    TYPES of PROJECTS

    Barracks Renovations

    Road Paving

    Install Drainage

    Construct Dog Park

    Fencing

    Upgrade / install HVAC

    Replace Auditorium Carpet, Seating,

    Lighting

    Replace Roof / Exterior Doors

    Restore Dental Clinic

    Restore Building Systems

    Restore HVAC and Alarm Systems

    Replace Standby Potable Water Pump

    Remove and Install Trees

    Military Operationsand Maintenance Program

  • 7/30/2019 Keever Presentation

    16/44

    BUILDING STRONG

    SPL FY10 O&M ProgramINSTALLATION # OF OPEN

    PROJECTSCUR FY

    TOTAL $$$for FY09

    (Obligated)

    POCA / IFBIDIQ / Other

    # FY10PROJECTS(Planned)

    EDWARDS AFB 58 $ 51,700,000 POCA/ IDIQ 30

    VANDENBERG AFB 17 $ 11,700,000 POCA 10

    MARCH ARB 3 TBD

    YUMA PROVING GROUND 3 TBD

    FORT IRWIN NTC 5 $ 13,500,000 POCA/IDIQ 10

    NELLIS AFB 3 $ 5,200,000 POCA TBD

    CREECH AFB POCA TBD

    BARRY M GOLDWATER AFV 0 TBD

    CAMP PENDLETON 42 $ 24,000,000 POCA 25

    DAVIS MONTHAN AFB 0 $ 2,200,000 POCA TBD

    NAVY SEAL BEACH 1 TBDFORT HUACHUCA 6 $ 6,800,000 POCA 0

    TOTAL 366 $ 129,000,000 - 63

  • 7/30/2019 Keever Presentation

    17/44

    BUILDING STRONG

    Government Purchase Card Program Simplified Acquisition Procedures Indefinite Delivery/Indefinite Quantity Contracts

    (IDIQ) Performance Orientated Construction Activity

    Contracts (POCA,) Design Build MATOC (D-B MATOC) A&E Contracts Service & commercial items contracts

    Contracting ToolboxContracting Toolbox

  • 7/30/2019 Keever Presentation

    18/44

    BUILDING STRONG

    ContractingContractingStrategiesStrategies

    UNDER 3,000K

    SIMPLIFIED ACQUISITIONPROCEDURES (SAP)

    Credit Card

    Accommodation VISA Check

    UNDER 3,000KUNDER 3,000K

    SIMPLIFIED ACQUISITIONPROCEDURES (SAP)

    Credit Card

    Accommodation VISA Check

    BETWEEN 3,001 100K (SAP)

    SIMPLIFIED ACQUISITION

    PROCEDURES (SAP) Purchase Order

    GSA Schedule

    Commercial Products/Services upto $5.5M

    BETWEEN 3,001BETWEEN 3,001 100K (SAP)100K (SAP)

    SIMPLIFIED ACQUISITIONPROCEDURES (SAP)

    Purchase Order

    GSA Schedule

    Commercial Products/Services upto $5.5M

    Over 100K Contract

    Single Project C

    IDIQ D (Indefinite DeliveryIndefinite Quantity)

    Over 100KOver 100K Contract

    Single Project C

    IDIQ D (Indefinite DeliveryIndefinite Quantity)

  • 7/30/2019 Keever Presentation

    19/44

    BUILDING STRONG

    IDIQ ContractsIDIQ ContractsIndefinite Delivery-Indefinite Quantity Contract

    Purpose

    Provides for an indefinite quantity of supplies or servicesduring a fixed period

    Features

    Task Order Contracts

    Single Award

    no competition for T.O.

    Multiple Award competition among several contractorsfor T.O.

  • 7/30/2019 Keever Presentation

    20/44

    BUILDING STRONG

    POCA Construction ContractorsPOCA Construction Contractors

    Performance OrientedConstruction Activit ies

    Contracts

    Performance Oriented

    Construction ActivitiesContracts

    1MD, Inc., Castro ElectricAlbright Diversified Svc

    Allied IndustriesAlpine

    Barajas AssociatesCandelaria Construction

    CJWCumbre Construction

    Custom Mechanical System CorpsDiaz Yourman Associates

    Dixon Company

    Dotzler Construction dba Northcoast Construction

    DWJ & AssociatesEPC CorpHal Hays ConstructionInnovative Tech Solutions

    J&P ConstructionMacro Z Technology CoM2M SwiftMajesty ConstructionMarcon Engineering

    Miramar ConstructionMRM Construction ServicesNicoles ConstructionOnsite ConstructionPojoaque Pueblo Service CorpsRick Garcia Construction

    RMA Land ConstructionRockwood Gen Constr.South Bay EDCSouthern Calif ContractorsTACT ConstructionUtility Construction

    Vanguard Const., Inc.Walter ThomasWebco Construction

  • 7/30/2019 Keever Presentation

    21/44

    BUILDING STRONG

    Must be registered in FedBizOpps to:

    View/download Plans and Specification Receive Amendments and Notices

    View plan holders list. (Plan holders list islocated within the Opportunity Notice only if vendorchooses to make information public)

    FedBizOpps

  • 7/30/2019 Keever Presentation

    22/44

    BUILDING STRONG

    http://www.fbo.govVIEW our solicitations at:VIEW our solicitations at:

    http://www.fbo.gov/http://www.fbo.gov/
  • 7/30/2019 Keever Presentation

    23/44

    BUILDING STRONG

    Whats New

    Other Contract Opportunities

    Los Angeles District MATOCSCenters of Standardization

    Program Account ManagerDesign Centers

  • 7/30/2019 Keever Presentation

    24/44

    BUILDING STRONG

    Los Angeles District

    FY10 IDIQ DB MATOCPA Contracting Method Solicitation Notice

    $150M Unrestricted Phase II Advertised Apr. 5

    $100M SB Set aside Phase I Advertised Apr. 5

    $100M 8A Set-Aside Phase I Advertised Apr. 16

    $88M SDVOSB Set-Aside Phase I to be Advertised Apr. 27

    $69M HUBz

    SB-Set-Aside Phase I to be Advertised May 18

  • 7/30/2019 Keever Presentation

    25/44

    BUILDING STRONG

    Design Districts Supporting Los Angeles District

    Sacramento District Military Design for all

    Army Installations and Air Force Installations inCalifornia and Nevada

    Albuquerque District Military Design for AirForce Installations in Arizona

    Los Angeles District Civil Works Design in LosAngeles District

    Each Design District will have Architectural /Engineering Contracts to support their mission.

  • 7/30/2019 Keever Presentation

    26/44

    BUILDING STRONG

    USACE Centers of Standardization (COS) Facility Types

    Centers of Standardization: Norfolk (NAO), Savannah (SAS), Mobile (SAM),

    Omaha (NWO), Louisville (LRL) Huntsville (HNC), Fort Worth (SWF)

  • 7/30/2019 Keever Presentation

    27/44

    BUILDING STRONG27

    Pending Acquisition Vehicles

    COS - SWFFacilityType

    Region BusinessStandard

    Balance/

    Capacity

    Planned

    Award

    Seed Project Status

    Admin North West Set-Aside $49M 1st Qtr/FY11 TBD w/ RIT whenAP approved

    Ant. PARCApproval May 10

    Admin South East Set-Aside $45M 1st Qtr/FY11 TBD w/ RIT whenAP approved

    Ant. PARCApproval May 10

    Admin South West Set-Aside $28M 1st Qtr/FY11 TBD w/ RIT when

    AP approved

    Ant. PARC

    Approval May 10AIT/BT/

    WIT

    South East UR $405M 1st Qtr/FY11 TBD w/ RIT whenAP approved

    Ant. PARCApproval May 10

    AIT/BT/

    WIT

    South West UR $432M 1st Qtr/FY11 TBD w/ RIT whenAP approved

    Ant. PARCApproval May 10

    AIT/BT/

    WIT

    North West UR $410M 1st Qtr/FY11 TBD w/ RIT whenAP approved

    Ant. PARCApproval May 10

    Capacity remaining is based on that awarded to date and current reservations,to include FY10 Projects.

  • 7/30/2019 Keever Presentation

    28/44

    BUILDING STRONG28

    Pending Acquisition Vehicles

    COS - SWF

    FacilityType

    Region ContractType

    Balance/

    Capacity

    Planned

    Award

    Seed Project Status

    Warehouse SouthWest

    Set-Aside $23.75M 1st Qtr/FY11 TBD w/ RIT whenAP approved

    Ant. PARCApproval May 10

    Warehouse NorthWest

    Set-Aside $48M 1st Qtr/FY11 TBD w/ RIT whenAP approved

    Ant. PARCApproval May 10

    Starship East UR $495M 1st Qtr/FY11 TBD w/ RIT whenAP approved Ant. PARCApproval May 10

  • 7/30/2019 Keever Presentation

    29/44

    BUILDING STRONG

    Centers of Standardization Fort Worth (SWF)

  • 7/30/2019 Keever Presentation

    30/44

    BUILDING STRONG30

    Pending COS Acquisition VehiclesHNC/NAO/SAS

    FacilityType

    Region BusinessStandard

    Balance/

    Capacity

    Planned

    Award

    Seed Project Status

    PFF South 8(a) $175M 2nd

    Qtr/FY 11AWD(S):31MAR 11

    65147

    Campbell

    RTA

    30 Sep 10

    DFAC Southeast HUBZone $33.5M 3rd Qtr/FY10AWD(S):17Jun10

    70180

    (Knox)

    Ph 2 ADVscheduled for

    14 Apr 10

    COF TBD TBD TBD 2nd

    Qtr/FY11 TBD w/ RITwhen AP

    approved

    Ant. PARCApproval Jun10

    HQ TBD TBD TBD 2nd

    Qtr/FY11 TBD w/ RITwhen APapproved

    Ant. PARCApproval Jun

    10

    TEMF TBD TBD TBD 2nd

    Qtr/FY11 TBD w/ RITwhen APapproved

    Ant. PARCApproval Jun

    10

  • 7/30/2019 Keever Presentation

    31/44

    BUILDING STRONG

    Centers of Standardization Huntsville (HNC)

  • 7/30/2019 Keever Presentation

    32/44

    BUILDING STRONG

    Centers of Standardization Norfolk (NAO)

  • 7/30/2019 Keever Presentation

    33/44

    BUILDING STRONG

    Centers of Standardization Savannah (SAS)

  • 7/30/2019 Keever Presentation

    34/44

    BUILDING STRONG

    Centers of Standardization Mobile (SAM)

  • 7/30/2019 Keever Presentation

    35/44

    BUILDING STRONG

    Centers of Standardization Omaha (NWO)

  • 7/30/2019 Keever Presentation

    36/44

    BUILDING STRONG

    Centers of Standardization Louisville (LRL)

  • 7/30/2019 Keever Presentation

    37/44

    BUILDING STRONG

    Account Managers /

    Center of Expertise Customs and Border Protection (CBP) and Immigration and Customs Enforcement

    (ICE)Southwestern Division (SWD) Engineering and Construction Support

    Organization (ECSO)

    Military Munitions Center of ExpertiseHuntsville Center

    Account Manager for AF Hospital workTulsa District Account Manager for AF Military Munitions

    Omaha District Account Manager for Army Reserve

    Louisville District

    There are other Account Managers and Centers of Expertise. They

    may put contracts

    out to support their mission. These contracts may have Task Orders that includework in Los Angeles Districts Area of Responsibility.

    Interagency & International SupportInteragency & International Support

  • 7/30/2019 Keever Presentation

    38/44

    BUILDING STRONG

    NEVADA

    Interagency & International SupportInteragency & International Support

    ARIZONA

    UTAH

    CALIFORNIA

    CBP Tactical InfrastructureVertical Infrastructur e ( 225 miles )

    Border Patrol / Customs andBorder Protection

    Bureau of Indian AffairsBureau of Land ManagementBureau of PrisonsDepartment of AgricultureDrug Enforcement AgencyEnvironmental Protection AgencyFederal Emergency Management

    AgencyDepartment of Homeland SecurityFood and Drug AdministrationInternational Boundary and WaterCommission Veterans Affairs

    VA Support CA -

    FY09 $47.9 M(43 projects)

    FY10 $133.4M(63 projects)

    LOS ANGELES

    LAS VEGAS

    PHOENIXYuma Wellton

    AjoTucson

    Casa Grande Florence

    Wilcox

    DouglasNacoNogales

    Brown Field

    Campo

    Chula Vista

    El Cajon

    Imperial Beach

    San Clemente

    Murrieta

    Calexico

    El Centro

    Indio

    Riverside

    Blythe

    CBP Support26 FY10 Vert icalConstruction Projectsto Award ($87.4M)

    SBI-NET Support6 FY10 Border FenceProjects to Award($36M)

    Los Angeles District

  • 7/30/2019 Keever Presentation

    39/44

    BUILDING STRONG

    SustainableSustainable GreenGreen EngineeringEngineering

    Cambria Desalinization PlantCambria, CA

    850kW Wind Power GeneratorFort Huachuca, AZ

    MOUT SiteFort Irw in, CA (NTC)

    Walls made of s tudcast Cut the budget by 30%Accelerated constr by50%

    Will provide potable watersupply; contamination currentlylimiting available sources

    Sustainable Needand Potential!

    Opportunity fornew partnerships in:

    MILCONCivil Works

    I&IS

    Wind

    Solar

    Land area

    Lack of water

    Growing population

  • 7/30/2019 Keever Presentation

    40/44

    Points of ContactPoints of Contact

  • 7/30/2019 Keever Presentation

    41/44

    BUILDING STRONG

    Points of ContactPoints of Contact

    ConstructionConstruction

    Chief Construction Division

    John Keever

    P.E.

    213/452-3349

    Deputy Chief Construction Division

    Kevin Inada P.E.213/452-3350

    S. California Area Office Harold Hartman P.E.661/265-7222Arizona/Nevada Area Office -

    Neil Erwin

    P.E.

    602/640-2018 x256

    Environmental Construction

    Thad Fukushige

    P.E.

    626-401-4048

    Points of ContactPoints of Contact

  • 7/30/2019 Keever Presentation

    42/44

    BUILDING STRONG

    Points of ContactPoints of Contact

    Project ManagementProject ManagementDDPM & Chief of PPMD

    Brian Moore

    213-452-3971

    Chief Civil Works Branch

    David Van Dorpe.

    213-452-4008

    Chief of Navigations Branch

    Charles (Steve) Dwyer

    213-452-3385

    Chief Military Branch

    Debra Ford

    213-452-3979Chief IIS Branch -

    Larry Flatau

    602/640-2018 x256

    Points of ContactPoints of Contact

  • 7/30/2019 Keever Presentation

    43/44

    BUILDING STRONG

    Points of ContactPoints of Contact

    Asset ManagementAsset Management

    Chief Asset Mgmt Division

    Terri Kaplan

    213/452-3118

    Deputy AM Division Bob Colangelo.213/452-3122Chief Ops Bch Tomas Beauchamp-Hernadez213/452-3142

    Points of ContactPoints of Contact

  • 7/30/2019 Keever Presentation

    44/44

    BUILDING STRONG

    Points of ContactPoints of Contact

    Other LA District ChiefsOther LA District Chiefs

    Chief Engineering Division

    Rick Leifield

    213-452-3629Deputy Chief Engineering Division Brian Tracy213-452-3630Chief Planning Division Josephine Axt213-452-3783Small Business Advisor Mary Spencer213-452-3938