Kearney Precast Concrete Deck Panel Bridge Project

47
KEARNEY PRECAST CONCRETE DECK PANEL BRIDGE PROJECT Presented By T. Farber, G. Marcous, J. Ridder 37 th Annual Concrete Paving Workshop January 19-20, 2016

Transcript of Kearney Precast Concrete Deck Panel Bridge Project

KEARNEY PRECAST CONCRETE DECK PANEL BRIDGE PROJECT

Presented By

T. Farber, G. Marcous, J. Ridder

37th Annual Concrete Paving Workshop

January 19-20, 2016

Acknowledgements

• Nebraska Department of Roads

• University of Nebraska-Lincoln (UNL)

• Hawkins Construction Company

• CoreSlab Structures Inc.

• Federal Highway Administration

• Werner Construction, Inc.

3

4

NU Deck Panel Bridge

Phase 1(completed)

Phase 2

5

6

Project Specifics

Prime Contractor: Werner Construction, Inc.

Contract Amount: $26.5 million

Calendar Days to complete project: 776 days

Construction Started: July 2014

Construction Costs for the Bridges

Group 6 ( NU Deck Panel ): $2.6 million

Group 6A ( Cast-in-Place ): $1.6 million

Table of Contents• Background

• Project Description

• Construction Sequence

1. Girder Production

2. Panel Production

3. Girder Placement

4. Panel Placement

5. Transverse Joints Grouting

6. Deck Post-tensioning

7. Haunch & Pockets Grouting

8. Deck Grinding

Background• Why precast concrete deck systems are not commonly

used?– Too many pieces to handle

– Too many joints to grout

– Open channels or pockets need an overlay

– Not fully pre-stressed in both directions

8

Background

• The newly developed precast concrete deck system (2nd

Generation NUDECK) has the following features:1. Full-depth, full-width, 12-ft long panels to minimize CIP transverse joints

2. Covered pockets to eliminate deck overlay

3. 4 ft. spacing between shear connectors to simplify fabrication

4. Prestressed in both directions to enhance durability

9

Project Description

10

NU Deck Panel Bridge

BB-EB CL: 332 ft

Span:

166 ft

166 ft

Precast:

166.17 ft

166.17 ft

1.33 f t

39 f t

1.33 f t

41.67 f t

7.5

in

3.83 f t

8.5 f t

8.5 f t

8.5 f t

8.5 f t

3.83 f t

1

2

3

4

5

11

NU Deck Panel Description

5 ea. NU1800Girders

13,850 sq.ft.Bridge Deck

NU Deck Panel Description

12

26 Typical Panels + 2 End Panels

Construction Sequence1. Girder Production

2. Panel Production

3. Girder Placement

4. Panel Placement

5. Transverse Joints Grouting

6. Deck Post-tensioning

7. Haunch & Pockets Grouting

8. Deck Grinding

13

1- Girder Production

14

1- Girder Production

15

1- Girder Production

16

2- Panel Production

17

2- Panel Production

2- Panel Production

2- Panel Production

20

2- Panel Production

21

3- Girder Placement

22

3- Galvanized Shelf Angles

23

3- Post-tensioning Cable Strands

24

3- Post-tensioning Cable Strands

25

3- Pier Diaphragm Steel

26

4- Deck Panel Placement

4- Panel Placement

4- Panel Placement

4- Panel Placement

4- Panel Placement

4- Panel Placement Progress• Wednesday 07/08 afternoon only 3 panels

• Thursday 07/09 morning only 2 panels

• Monday 07/13 6 panels

• Tuesday 07/14 6 panels

• Wednesday 07/15 6 panels

• Thursday 07/16 5 panels

TOTAL 28 panels

5- Transverse Joints Grouting

5- Transverse Joint Grouting

5- Transverse Joint Grouting

5- Transverse Joint GroutingConcrete

TruckStart Time End Time Quantity No. of Joints Temperature

Deg. FRelative

Humidity %

#1 6:30 am 7:30 am 3 cy 13.5 63 83

#2 8:00 am 8:30 am 2 cy 7.5 65 80

#3 8:45 am 9:15 am 2 cy 6 66 78

Transverse joint concrete mixture had 6 in. initial slump and was vibrated

6- Deck Post-tensioning

6- Deck Post-tensioning

6- Deck Post-tensioning

Jacking End Movement = 5/16 in. Dead End Movement = ¼ in.

Predicted deck elastic shortening = ½ in.

7- Haunch & End Pocket SCC Grouting

40

20 batches of about 6 cu.yd. each for a total of 6 hours

7- Haunch & End Pocket SCC Grouting

41

Average SCC slump flow = 29 in.

7- Haunch & End Pocket SCC Grouting

42

7- Haunch & End Pocket SCC Grouting

43

H-3 H-3A G-2 J-4 K-5 F-1

4 8,120 7,240 7,480 6,790 7,380 7,860 7,402

7 8,360 7,250 7,690 7,170 7,510 7,870 7,596

28 9,200 9,050 9,170 8,430 8,420 9,030 8,854

Air Content (%) 2.6 3 4.2 4.6 4.6 4.6 3.8

Girder Batch IDAge (day) Average

8- Deck Grinding

NU Deck Panel

Cast in Place

8- NU Deck Grinding & Texturing

Transverse Joint Grouting Holes

46

Completed Structure

Outside

Setting next to CIP Bridge