Karnal Distt. Link Roads

65
Summary of Road Network Haryana State Agricultural Marketing Board Karnal Karnal Chronology of roads constructed by HSAMB in Karnal Division: HSAMB Constructed Roads 133 343.71 Roads Completed before 1-9-1999 roads km 145 317.03 Roads Completed between 1-9-1999 and 31-3-2005 roads km 11 23.76 Roads Sanctioned prior to 1-4-2005 and Completed after 1-4-2005 roads km 43 119.14 Roads Sanctioned between 1-4-2005 and 24-9-2009 roads km 1 3.04 Roads Sanctioned after 24-9-2009 roads km 333 806.68 Total: roads km Likely to be Transferred Transferred to PWD (938 roads) - Likely to come from PWD 27 74.46 roads km Transferred to PWD (Individual) - Proposal by PWD to transfer back 2 3.41 roads km 29 77.87 Group Total: roads km Completed Roads under Maintenance Bad Condition 1 1.70 roads km Good Condition 255 616.38 roads km Maintained by PWD 1 4.13 roads km Old SR - Unawarded 1 2.22 roads km Ordinary repairs required / ongoing 2 3.21 roads km Work Plan - Awarded 13 36.83 roads km Work Plan - Unawarded 2 6.09 roads km 275 670.56 Group Total: roads km Transferred Transferred to MC 14 18.83 roads km Transferred to PWD (938 roads) 44 120.00 roads km Transferred to PWD (Individual) 2 3.92 roads km 60 142.75 Group Total: roads km New Construction going on New Construction - Awarded 8 26.61 roads km New Construction - Unawarded 19 49.45 roads km 27 76.06 Group Total: roads km Planned - New Construction Approved by Government but AA pending 3 5.41 roads km 3 5.41 Group Total: roads km Dropped Dropped 4 6.38 roads km 4 6.38 Group Total: roads km Tuesday, April 02, 2013 Page 1 of 65

description

HSAMBoard Link roads of Karnal District

Transcript of Karnal Distt. Link Roads

Page 1: Karnal Distt. Link Roads

Summary of Road Network

Haryana State Agricultural Marketing Board

KarnalKarnal

Chronology of roads constructed by HSAMB in Karnal Division:

HSAMB Constructed Roads

133 343.71Roads Completed before 1-9-1999 roads km

145 317.03Roads Completed between 1-9-1999 and 31-3-2005 roads km

11 23.76Roads Sanctioned prior to 1-4-2005 and Completed after 1-4-2005 roads km

43 119.14Roads Sanctioned between 1-4-2005 and 24-9-2009 roads km

1 3.04Roads Sanctioned after 24-9-2009 roads km

333 806.68Total: roads km

Likely to be Transferred

Transferred to PWD (938 roads) - Likely to come from PWD 27 74.46roads km

Transferred to PWD (Individual) - Proposal by PWD to transfer back

2 3.41roads km

29 77.87Group Total: roads km

Completed Roads under Maintenance

Bad Condition 1 1.70roads km

Good Condition 255 616.38roads km

Maintained by PWD 1 4.13roads km

Old SR - Unawarded 1 2.22roads km

Ordinary repairs required / ongoing 2 3.21roads km

Work Plan - Awarded 13 36.83roads km

Work Plan - Unawarded 2 6.09roads km

275 670.56Group Total: roads km

Transferred

Transferred to MC 14 18.83roads km

Transferred to PWD (938 roads) 44 120.00roads km

Transferred to PWD (Individual) 2 3.92roads km

60 142.75Group Total: roads km

New Construction going on

New Construction - Awarded 8 26.61roads km

New Construction - Unawarded 19 49.45roads km

27 76.06Group Total: roads km

Planned - New Construction

Approved by Government but AA pending 3 5.41roads km

3 5.41Group Total: roads km

Dropped

Dropped 4 6.38roads km

4 6.38Group Total: roads km

Tuesday, April 02, 2013 Page 1 of 65

Page 2: Karnal Distt. Link Roads

Planned - New Construction

Approved by Government - Conditionally 1 2.73roads km

Approved by Government but AA pending - Land Issue 1 5.50roads km

Planned 1 2.15roads km

PR in Field Office 1 1.77roads km

PR in Head Office 1 roads km

PR Upward of Engineer-In-Chief 17 42.24roads km

PR with AM Office 1 2.11roads km

PR with CM Office 1 2.78roads km

PR with PSA Office 1 2.24roads km

Rejected by Government 22 50.38roads km

47 111.89Group Total: roads km

Planned - New Construction

Relates to other department 1 3.20roads km

1 3.20Group Total: roads km

446 1094.12Division Total: roads km

Likely to be Transferred

Transferred to PWD (938 roads) - Likely to come from PWD

H - 3952 Shergarh Tapu To Yamuna Bandh. 0.661) km.Indri

PWD has allotted works worth 10.2 lacs.43594 20-Mar-13

PWD has allotted works worth 10.2 lacs.43202 19-Mar-13

Constructed 11/1997. SR 10.12.07, Path-6karam, Crust-150 mm8593 07-Oct-11

Transferred to PWD. PWD RoadID : 88557700 03-Oct-11

H - 3982 Hansi Road To Namastey Chowk 1.702) km.Karnal

Constructed 7/2006. Path-9karam, Crust-225 mm8597 07-Oct-11

Transferred to PWD. PWD RoadID : 88437792 03-Oct-11

H - 4009 Brass To Sambhli 4.683) km.Nilokheri (SC)

PWD has allotted works worth 79.56 lacs.43604 20-Mar-13

PWD has allotted works worth 79.56 lacs.43206 19-Mar-13

Constructed 11/2008. Path-6, 7 & 8karam, Crust-225 mm. No SR done.

8601 07-Oct-11

Transferred to PWD. PWD RoadID : 88787857 03-Oct-11

H - 4051 Nilokheri To Badshahi Pul 2.024) km.Nilokheri (SC)

PWD executing / has executed work worth 8 lacs.43347 19-Mar-13

Constructed 6/1998. Path-12karam, Crust-150 mm. PC done in 11/2005.

8612 07-Oct-11

Transferred to PWD. PWD RoadID : 88897860 03-Oct-11

H - 4097 Jai Singh Pura To Khanda Kheri 1.765) km.Assandh

Tuesday, April 02, 2013 Page 2 of 65

Page 3: Karnal Distt. Link Roads

Completion- 14 june-1995, Path-6karam, Crust-150 mm. SR done in 3/2008 (Expenditure 14.49 lacs).

8618 07-Oct-11

Transferred to PWD. PWD RoadID : 89037429 03-Oct-11

H - 4109 Thari To Phapharna 6.016) km.Assandh

Constructed 1/2002. SR 10.2008, Path-6 & 18karam, Crust-150 mm, Metalled width-5.49m

8619 07-Oct-11

Transferred to PWD. PWD RoadID : 89047430 03-Oct-11

H - 4114 Kurlan To Bal Pabana 6.627) km.Assandh

Constructed 7/2002. No SR done, Path-6karam, Crust-150 mm8620 07-Oct-11

Transferred to PWD. PWD RoadID : 89057431 03-Oct-11

H - 4117 Alawla To Tharwa Majra 0.908) km.Assandh

Constructed 8/2002. No SR done, Path-6karam, Crust-150 mm8621 07-Oct-11

Transferred to PWD. PWD RoadID : 89067434 03-Oct-11

H - 4120 Ardana To Muwana 4.619) km.Assandh

Constructed 12/2002. Path-6 & 7karam, Crust-150 mm8622 07-Oct-11

Transferred to PWD. PWD RoadID : 89147427 03-Oct-11

H - 4121 Bahri To Gangtheri 2.6110) km.Assandh

Constructed 3/2003. No SR done, Path-7karam, Crust-150 mm8623 07-Oct-11

Transferred to PWD. PWD RoadID : 89077435 03-Oct-11

H - 4123 Kabulpur Khera road To Shiv Mandir, Salwan 0.4211) km.Assandh

Constructed 10/2003. No SR done, Path-6karam, Crust-150 mm8624 07-Oct-11

Transferred to PWD. PWD RoadID : 89087432 03-Oct-11

H - 4126 Padhana To Jabala 5.9212) km.Assandh

Constructed 12/2003. Path-6&7karam, Crust-225 mm8625 07-Oct-11

Transferred to PWD. PWD RoadID : 89097433 03-Oct-11

H - 4127 Assandh To Malik Pur 7.7013) km.Assandh

Constructed 6/2003. No SR done, Path-6karam, Crust-150 mm8626 07-Oct-11

Transferred to PWD. PWD RoadID : 89107436 03-Oct-11

H - 4131 Rahra To Lalain 3.4214) km.Assandh

Constructed 12/2003. No SR done, Path-6karam, Crust-150 mm8627 07-Oct-11

Transferred to PWD. PWD RoadID : 89117437 03-Oct-11

H - 4132 Rehra To P.C. Rehra 1.8615) km.Assandh

Constructed 6/2003. No SR done, Path-6karam, Crust-150 mm8628 07-Oct-11

Transferred to PWD. PWD RoadID : 89127438 03-Oct-11

H - 4134 Bilona Rehra Khizrabad Assandh Road 2.6816) km.Assandh

Tuesday, April 02, 2013 Page 3 of 65

Page 4: Karnal Distt. Link Roads

Constructed 1/2004. No SR done, Path-6karam, Crust-150 mm8629 07-Oct-11

Transferred to PWD. PWD RoadID : 89137439 03-Oct-11

H - 4162 Hassanpur Road To Padha Kurlan Road 1.0817) km.Assandh

Constructed 10/1998. Path-6karam, Crust-150 mm8633 07-Oct-11

Transferred to PWD. PWD RoadID : 89157440 03-Oct-11

H - 4168 Picholia To Jani 3.8118) km.Assandh

Constructed 6/2002. No SR done, Path-6karam, Crust-150 mm8634 07-Oct-11

Transferred to PWD. PWD RoadID : 89168251 03-Oct-11

H - 4178 Pyont To Bansa 3.9519) km.Assandh

Constructed 11/1993. SR 05.02.03, Path-6karam, Crust-150 mm8637 07-Oct-11

Transferred to PWD. PWD RoadID : 89178252 03-Oct-11

H - 4194 Phurlak To Raseen 2.6020) km.Gharaunda

Sh. Sushil Kr, JE reported that Actual length is 3.60 instead of 3.06.29516 16-Aug-12

Constructed 5/1991. SR 05.07.05, Path-6karam, Crust-150 mm8638 07-Oct-11

Transferred to PWD. PWD RoadID : 88957628 03-Oct-11

H - 4197 Alipur Khalsa To Dera Harisingh Pura 0.6221) km.Gharaunda

Constructed 6/1993. SR 20.12.06, Path-5karam, Crust-150 mm8639 07-Oct-11

Transferred to PWD. PWD RoadID : 88967630 03-Oct-11

H - 4211 Kaimla To Shamshan Ghat Kaimla 1.3522) km.Gharaunda

Constructed 10/1998. SR 06.08.05, Path-6karam, Crust-150 mm8640 07-Oct-11

Transferred to PWD. PWD RoadID : 88977631 03-Oct-11

H - 4212 Garhi Biral To Ram Rang 1.2523) km.Gharaunda

Constructed 11/1998. SR 31.03.08, Path-6karam, Crust-150 mm8641 07-Oct-11

Transferred to PWD. PWD RoadID : 88987632 03-Oct-11

H - 4214 Bassi Akbarpur To Behlolpur 2.0124) km.Gharaunda

Constructed 12/1999. SR 31.03.08, Path-6karam, Crust-150 mm8642 07-Oct-11

Transferred to PWD. PWD RoadID : __________.7633 03-Oct-11

H - 4220 Barsat To Behlolpur 2.0025) km.Gharaunda

Tender approved on 5.3.2012 (M/s S.K. Contractor).20593 06-Mar-12

Constructed 10/2001. No SR done, Path-6karam, Crust-150 mm8643 07-Oct-11

Transferred to PWD. PWD RoadID : 89007634 03-Oct-11

H - 4243 Gharaunda Aripura Road To Gharaunda Panouri Road Leading To Ngm Gharaunda

1.2626) km.Gharaunda

Constructed 4/2008. No SR done, Path-6karam, Crust-150 mm8645 07-Oct-11

Transferred to PWD. PWD RoadID : 89017635 03-Oct-11

Gharaunda

Tuesday, April 02, 2013 Page 4 of 65

Page 5: Karnal Distt. Link Roads

H - 4244 Dadlana To Begampur Upto Khond- Assandh Road 0.9627) km.Gharaunda

Constructed 6/2009. No SR done, Path-12karam, Crust-150 mm8646 07-Oct-11

Transferred to PWD. PWD RoadID : 89027627 03-Oct-11

74.46 km. Sub Total:

Transferred to PWD (Individual) - Proposal by PWD to transfer back

H - 3987 Tikari Kailash To Lado Ki Gamri 1.401) km.Karnal

Constructed 11/1999. Path-7 karam, Crust-150 mm. PC in 10/2009.8569 07-Oct-11

Transferred to PWD. PWD RoadID : 88568247 03-Oct-11

H - 4147 Chor Karsa To Jalmana Uplani Road 2.012) km.Assandh

PWD road ID 8918.19084 18-Feb-12

Constructed 8/1994. Path-6karam, Crust-150 mm. PC done in 2005.8570 07-Oct-11

Transfer under process to PWD.7101 30-Sep-11

3.41 km. Sub Total:

Completed Roads under Maintenance

Bad Condition

H - 6808 Choura to Malikpur Gadian 1.701) km.Gharaunda

R/C/E submitted to SE on 12.03.2013 for A/A.42630 15-Mar-13

RCE under preparation.40766 12-Feb-13

Constructed in 2004. Path 8 & 4 Karam. Crust 150mm.40394 06-Feb-13

1.70 km. Sub Total:

Good Condition

H - 3900 Bir Rahat Khana To Garhi Sadan 4.021) km.Indri

Work completed on 15.10.2012.36597 30-Oct-12

A/A on 15.06.2012 for Rs. 5.46 lacs.29958 20-Aug-12

Work allotted to M/S Rajesh Const. Co. on 24.07.201230062 20-Aug-12

Work Plan: 157m (Bir Rahat Khana) Paver blocks (EC 7 lacs)14900 16-Nov-11

Constructed- 1990, Path- 4&5 Karam, Crust- 150mm, SR 02/2010 with 75mm WBM + PC in 1350m and PC in entire length. AR ( 09/ 2011) done with Rs. 0.86 Lacs.

8481 04-Oct-11

AR done during 30-Aug-11 to 31-Aug-115504 20-Sep-11

H - 3901 Darar To Sanghoya 3.782) km.Indri

EE reported: Work Completed on 30.11.2012. Road is in good condition.

38909 18-Dec-12

A/A on 17.7.2012 for Rs. 10.23 lacs.29941 20-Aug-12

Work allotted on 24.07.2012 to Rajesh const. co. 30045 20-Aug-12

Work Plan:120m (Sanghoya Phirni RD0 to 120m), 80m (Darar Phirni RD 2924 to 3004m) GSB+pavers; in rest Patches (EC. 11 lacs).

9281 16-Nov-11

Tuesday, April 02, 2013 Page 5 of 65

Page 6: Karnal Distt. Link Roads

Constructed 11/1990. Crust 150mm WBM. CC in 510m(RD3004 to 3514m): in rest PC(3.070 Km) done in 12/2007.

9280 07-Oct-11

H - 3907 Dabkoli To Biana 2.563) km.Indri

Constructed 12/1994. Crust 150mm. PC (2.145 km) C/C (0 .415 km) done on 10/2009. (108.34 sqm) patches done 5/09/2011 to 7/09/2011 (22 K). No patch.

9072 07-Oct-11

H - 3908 Karwa To Badheri 2.814) km.Indri

Repair of berms to be done under MGNREGA scheme.37134 08-Nov-12

work completed.32268 04-Sep-12

Work Plan: 347m (Karwa Phirni), 270m (Santri Phirni), 60m ( (Badheri Phirni) GSB+pavers (EC 34 lacs). A/A on 15.08.2012 for Rs. 36.25 lacs.

29960 20-Aug-12

Constructed 10/06/1994. Crust 150mm. CC (0.325) +PC (2.485 km) done 12/2007. (316.62 sqm) patches done 1/09/2011 to 13/09/2011 (63 K).

9073 07-Oct-11

H - 3911 Dhona Kheri To Kalra Jagir 2.475) km.Indri

Constructed 3/1994. Path 5 Karam. Crust 150mm. SR done on 7/2006. No Patches.

14443 15-Nov-11

H - 3912 Ghari Jattan To Ghari Sadan 0.906) km.Indri

Repair of berms work is in progress under MGNREGA scheme.(Est. Cost 21128/-)

37141 08-Nov-12

Constructed 3/1996. Path 5 Karam. Crust 150mm. 75mm WBM done on 1/2010. No Patches.

14444 15-Nov-11

H - 3914 Kalsora To Japti Chhapra 4.617) km.Indri

Work completed on 08.10.2012.36600 30-Oct-12

Work allotted (Harjeet Singh) on 28.07.2012.30023 20-Aug-12

A/A on 17.07.2012 for Rs.17.47 lacs.29985 20-Aug-12

Work Plan: Patches (EC 3 lacs).9287 16-Nov-11

Constructed 05/1997. Crust 150mm. Path 5 & 8 karam. CC in 153m (Japti Chhapra Phirni)+in rest PC done in 01/2010.

9286 07-Oct-11

H - 3916 Garhi Birbal To Leading To Nandi 2.258) km.Indri

Work completed on 11/3/2013.42689 15-Mar-13

Paver block in progress. Likely to be completed upto 28/2/2013.40771 12-Feb-13

Repair of berms to be done under MGNREGA scheme.37138 08-Nov-12

A/A on 17.07.2012 for Rs. 8.51 lacs. Work allotted to Rajesh const. co. on 24.07.2012.

29984 20-Aug-12

Constructed 31/03/1998. Crust 150mm. PC (entire) done 8/2006. (170.97sqm) patches done 1/09/2011 to 5/09/2011(33 K).

9074 07-Oct-11

Work Plan:155m (Garhi Birbal Phirni RD 0 to 100m, RD 250 to 305m) GSB+pavers; (EC 8 lacs).

9289 07-Oct-11

H - 3917 Jainpur To Chhaper 1.499) km.Indri

Road is Patchless.21883 03-Apr-12

Tuesday, April 02, 2013 Page 6 of 65

Page 7: Karnal Distt. Link Roads

WBM patch done PC patch left likely date 31.032012.19098 18-Feb-12

Patches are being contracted (Estimated cost 52 K).9291 16-Nov-11

Constructed 01/1998. Crust 150mm WBM. 97m (RD0 to 97m)(Jainpur Phirni) CC+rest length (1.393km) PC done in 03/2008.

9290 07-Oct-11

H - 3918 Garhi Birbal Road To Indri Road Via Kartapur 1.0710) km.Indri

Repair of berms to be done under MGNREGA scheme.37137 08-Nov-12

Constructed 3/1998. Path 4, 7 Karam. Crust 150mm. SR done on 6/2006. Patchless

14445 15-Nov-11

H - 3919 Norta To Depot Janesaro 1.4311) km.Indri

Constructed 12/1998. Crust 150mm. 75mm WBM+PC (entire) done 1/2010. (56.24sqm) patches done 4/09/2011 to 6/09/2011 (16 K). No patch.

9075 07-Oct-11

H - 3920 Ghisar Puri To Johar Majra 1.1912) km.Indri

Repair of berms to be done under MGNREGA scheme.37131 08-Nov-12

Road is Patchless.21884 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19099 18-Feb-12

Patches to be contracted. (EC 41 K).9293 16-Nov-11

Constructed 11/1998. Crust 150mm WBM. 183m (Jainpur Phirni) CC+rest length PC done in 03/2008.

9292 07-Oct-11

H - 3921 Matak Majri To Ngm Indri 0.9713) km.Indri

Road is Patchless.21885 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19100 18-Feb-12

Patches to be contracted. (EC 44 K).9295 10-Nov-11

Constructed 11/1998; 3.66 m wide. Crust 150mm WBM. PC done in 02/2010 with 3' widening of both side Crust is 225m.

9294 07-Oct-11

H - 3923 Khanpur To Ladwa Indri Road 0.8214) km.Indri

completed.32271 04-Sep-12

A/A on 17.07.2012 for Rs. 4.32 lacs.29978 20-Aug-12

Work allotted to Jitender Kumar on 28.07.2012.30061 20-Aug-12

Constructed 03/1999. Crust 150mm. Path 4 & 5 karam. PC done in 02/2005.

9296 07-Oct-11

Work Plan:70m (RD750 to 820m Khanpur Phirni) GSB+pavers; in rest patches (EC. 5 lacs).

9297 07-Oct-11

H - 3924 Dhanokheri To Dhanora 2.7915) km.Indri

Constructed 3/1999. Crust 150mm. CC(0.148 km ) +PC (2.64 )km done 12/2007. (502.18 sqm) patches done 2/09/2011 to 6/09/2011 (95 K). No patch.

9077 07-Oct-11

H - 3925 Dabkoli Bus Stand To Cause Way Dabkoli 0.5916) km.Indri

Constructed 7/1999. Path 4, 5 Karam. Crust 150mm. CC done on 3/2008. Patchless.

14446 15-Nov-11

H - 3926 Rasulpur To Johar Majra 1.2817) km.Indri

Tuesday, April 02, 2013 Page 7 of 65

Page 8: Karnal Distt. Link Roads

Repair of berms to be done under MGNREGA scheme.37142 08-Nov-12

Cosntrucrted 3/2000. Crust 150mm. 75mm WBM + PC (entire) done 10/2009. (82.73sqm) patches done 5/09/2011 to 7/09/2011 (18 K). No patch.

9078 07-Oct-11

H - 3927 Manoharpur To Nagla Roran 1.5018) km.Indri

Constructed 5/2000. Path 5 Karam. Crust 150mm. 75mm WBM + PC done 10/2009. Patchless.

14447 15-Nov-11

H - 3928 Japti Chhapra To Nabiabad 1.2019) km.Indri

Constructed 9/2000. Path 5 Karam. Crust 150mm. CC done on 9/2009. Patchless.

14448 15-Nov-11

H - 3929 Churni To Bibipur Jattan 2.9020) km.Indri

Constructed 7/2000. Path 5 Karam. Crust 150mm. 75mm WBM + PC done 10/2009. Patchless.

14449 15-Nov-11

H - 3930 Rajepur To Umarpur Society 1.7921) km.Indri

Constructed 9/2000. Path 4, 5 Karam. Crust 150mm. CC (Rajepur phirni) + 75mm WBM + PC done 10/2009. Patchless.

14450 15-Nov-11

H - 3931 Chand Samand To Nagla Roran 3.6022) km.Indri

Constructed 10/2001. Crust 150 mm. PC (entire) done 1/2010. (439.52sqm) patches done 3/09/2011 to 4/09/2011 (90 K). No patch.

9079 07-Oct-11

H - 3933 Rampur To Sawarn Majra 3.0023) km.Indri

Constructed 12/2001. Crust 150mm. 75mm WBM (2.4 km) + PC (entire) done 1/2010. (178.48sqm) patches done 30/08/2011 to 3/09/2011 (39 K). No patch.

9080 07-Oct-11

H - 3934 Pathera To Budhanpur 2.2424) km.Indri

Work completed on 20.10.2012.36580 30-Oct-12

75 mm WBM + PC (Rs. 21.47 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 9/8/2011.

14914 16-Nov-11

Constructed 11/2002. Path 5 Karam. Crust 150mm. 14451 15-Nov-11

H - 3935 Shekupura To Manak Majra 1.0325) km.Indri

Work complete on 22.10.2012.36581 30-Oct-12

75 mm WBM + PC (Rs. 9.92 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 9/8/2011.

14915 16-Nov-11

Constructed 5/2009. Path 5 Karam. Crust 150mm.14452 15-Nov-11

H - 3936 Randoli To Dabkoli Kalan 2.1326) km.Indri

Work completed on 26.10.2012.36582 30-Oct-12

75 mm WBM + PC (Rs. 20.39 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 9/8/2011.

14916 16-Nov-11

Constructed 4/2002. Path 5 Karam. Crust 150mm.14453 15-Nov-11

H - 3937 Garhi Birbal To Ghat 2.4427) km.Indri

Tuesday, April 02, 2013 Page 8 of 65

Page 9: Karnal Distt. Link Roads

Work completed on 23.10.2012.36583 30-Oct-12

75 mm WBM + PC (Rs. 23.97 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 9/8/2011.

14917 16-Nov-11

Constructed 11/2003. Path 4, 12 Karam. Crust 150mm.14454 15-Nov-11

H - 3938 Ghari Birbal Road To Inder Garh Primary School 1.9128) km.Indri

Work completed on 18.10.2012.36584 30-Oct-12

75 mm WBM + PC (Rs. 17.97 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 9/8/2011.

14918 16-Nov-11

Constructed 2/2003. Path 4 Karam. Crust 150mm.14455 15-Nov-11

H - 3939 Main Road Ram Nagar To Dera School 0.7629) km.Indri

Work completed on 19.10.2012.36585 30-Oct-12

75 mm WBM + PC (Rs. 7.26 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 9/8/2011.

14919 16-Nov-11

Constructed 6/2003. Path 4 Karam. Crust 150mm.14456 15-Nov-11

H - 3940 Dhano Kheri To Kalri Jagir 0.4430) km.Indri

Road is Patchless.21886 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19101 18-Feb-12

Patches to be contracted. (EC 18 K).9299 16-Nov-11

Constructed 03/2004. Crust 150mm. Path 5 karam.9298 07-Oct-11

H - 3941 Garhi Jattan To Dhumsi 2.8131) km.Indri

EE reported: Work Completed on 15.11.2012. Road is in good condition.

38910 18-Dec-12

A/A Rs. 47.83 lacs. Work allotted to harjeet singh on 21.08.2012.29993 20-Aug-12

Work Plan:53m (Garhi Jattan Phirni), 385m (Dhumsi) GSB+pavers; in rest 75mm WBM+PC (EC. 46 lacs).

9301 07-Oct-11

Constructed 04/2004. Crust 150mm. Path 5 karam.9300 07-Oct-11

H - 3942 Garhpur Khalsa To Kalri Khalsa 2.5232) km.Indri

EE reported: Work Completed on 30.11.2012. Road is in good condition.

38911 18-Dec-12

Repair of berms to be done under MGNREGA scheme.37133 08-Nov-12

A/A on 17.07.2012 for Rs. 22.92 lacs. Work allotted on 24.07.2012 to Narender Kumar.

29975 20-Aug-12

Work Plan:385m (Garhpur Khalsa Phirni) GSB+pavers; in rest patches with in 44K- per Km (EC. 20 lacs).

9303 07-Oct-11

Constructed 06/2004. Crust 150mm. Path 4, 5 & 6 karam.9302 07-Oct-11

H - 3943 Rampur To Habitpur 1.8233) km.Indri

Road is Patchless.21887 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19102 18-Feb-12

Work Plan:Needs O/R within 44 K-Per Km (EC. 80 K).9305 07-Oct-11

Constructed 04/2004. Crust 150mm. Path 5 & 8 karam.9304 07-Oct-11

H - 3945 Shah Pur To Manohar Pur 1.5434) km.Indri

Tuesday, April 02, 2013 Page 9 of 65

Page 10: Karnal Distt. Link Roads

Work allotted on 28.09.2012 (SK const. Co. ) Work completed on 20/12/2012.

36660 12-Feb-13

Repair of berms to be done under MGNREGA scheme.37132 08-Nov-12

Work Plan: Patches (EC. 5 lacs).9309 16-Nov-11

Constructed 12/2006. Crust 150mm. Path 5 karam.9308 07-Oct-11

H - 3946 Rajepur To Umar Pur 1.2235) km.Indri

Repair of berms to be done under MGNREGA scheme.37136 08-Nov-12

Work completed on 15.10.2012.36604 30-Oct-12

A/A on 17.07.2012 for Rs. 1.33 lacs.29970 20-Aug-12

Work allotted on 28.07.2012 to Harjeet Singh. 30048 20-Aug-12

Patches to be contracted. (EC 1 lacs).9311 16-Nov-11

Constructed 05/2007. Crust 150mm. Path 4 & 6 karam.9310 07-Oct-11

H - 3948 Approach Road To Stadium At Kalri Jagir 0.1936) km.Indri

Constructed 3/2009. Path 4 Karam. Crust 225mm. Patchless.14457 15-Nov-11

H - 3951 Bara Goan To Sangoya 3.8437) km.Indri

Constructed 3/1995. Crust 150mm. PC (entire) done 1/2010. (436-78 sqm) patches done 3/09/2011 to 4/09/2011 (88 K). No patch.

9082 07-Oct-11

H - 3953 Kalweri-Kunjpura Road To Kalwari Basti 0.7238) km.Indri

Work allotted on 28.09.2012 (SK const. Co.). Work completed on 20/12/2012.

36661 12-Feb-13

AA on 7/9/2012 for Rs. 7.34 lacs.32417 10-Sep-12

Work Plan:75mm WBM in 370m (RD350 to 720m) in rest patches also PC in entire length (EC 7 lacs).

9313 07-Oct-11

Constructed 01/2001. Crust 150mm. Path 4 karam.9312 07-Oct-11

H - 3955 Karnal Indri Road To Dera Amrik Singh 1.3439) km.Indri

Constructed 4/1995. Path 3, 4 Karam. Crust 150mm. SR done on 12/2007. Patchless.

14458 15-Nov-11

H - 3957 Tikri To Dera Khera 0.5040) km.Indri

Road is Patchless.21888 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19103 18-Feb-12

Patches to be contracted. (EC 22 K).9317 15-Nov-11

Constructed 11/1999. Crust 150mm. Path 3 karam.9316 07-Oct-11

H - 3961 Nanhera To Badarpur 4.4741) km.Indri

Road is Patchless.21889 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19104 18-Feb-12

Patches to be contracted. (EC 1.34 lacs)9323 16-Nov-11

Constructed 12/2009. Crust 225mm. Path 5, 6 & 7 karam.9322 07-Oct-11

H - 3962 Johar Majra To Fazilpur 1.9242) km.Indri

Tuesday, April 02, 2013 Page 10 of 65

Page 11: Karnal Distt. Link Roads

Constructed 12/2009. Crust 225mm. WBM. (28.67 sqm) Patches done 3/09/2011 to 4/09/2011 ( 8 K). No patch.

9083 07-Oct-11

H - 3964 Kurak To Gobind Garh Gamri Of Nadana Uptogamri Chopri Road

1.7843) km.Indri

Constructed 12/2009. Path 3, 4 Karam. Crust 225mm. Patchless.14459 15-Nov-11

H - 3965 Karnal Indri Road To Village Churni 2.3144) km.Indri

Constructed 6/2010. Path 5 Karam. Crust 225mm. Patchless.14460 15-Nov-11

H - 3966 Baragoan To Mugal Majra 3.1045) km.Indri

Road is Patchless.21890 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19105 18-Feb-12

Patches to be contracted. (EC 62 K)9325 16-Nov-11

Constructed 05/2010. Crust 225mm. Path 5 & 8 Karam.9324 07-Oct-11

H - 3970 Kunjpura Bus-Stand To Vegetable Market/Mehmadpur Road (Old Mandi Of Kunjpura Town)

0.3246) km.Indri

Constructed 12/1997. Path 4, 5 Karam. Crust 150mm. CC done on 4/2007.

14461 15-Nov-11

H - 3972 Chamar Khera To Pwd Road 3.3647) km.Karnal

(600 sqm) pathces done 19/10/2011 to 19/12/2011 (144 K).16662 02-Jan-12

Patches allotted. (EC 1.48 Lacs).14901 16-Nov-11

Constructed- 1994, Path- 5 Karam, Crust- 150mm, 75mm WBM + PC in entire in 1/2010. Road settled in 800m.

8483 04-Oct-11

H - 3973 Kachwa To Dera Purbian 0.3748) km.Karnal

Road is Patchless.21891 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19106 18-Feb-12

Patches yet to be awarded. (EC 0.17 Lacs).14902 16-Nov-11

Constructed- 1993, Path-5 Karam, Crust- 150mm, WBM + PC in entire done in 3/2008. Work Plan- Patch work.

8484 04-Oct-11

H - 3975 Dabri To Kaithal Road 2.0849) km.Karnal

Work completed on 10/3/2013.42690 15-Mar-13

AA on 9/8/2012 for Rs. 6.85 lacs. Work allotted on 3/10/2012 (Sh. Jatinder Khera).

39324 20-Dec-12

In RD 400 to 570m (Phirni of village Dabri), water is reported to be coming on road.

20564 02-Mar-12

Constructed 4/1994. Crust 150mm. 75mm WBM+PC (entire) done on 29/1/2010 with an expenditure of 10.54 lacs. (161 sqm) patches done during 22/08/2011 to 24/08/2011 (40 K). No patch.

9084 07-Oct-11

H - 3976 Kachwa To Shahpur 3.4550) km.Karnal

(730 sqm) patches done 19/10/2011 to 19/12/2011 (180 K).16663 02-Jan-12

Patches awarded. (EC 1.52 Lacs).14903 16-Nov-11

Tuesday, April 02, 2013 Page 11 of 65

Page 12: Karnal Distt. Link Roads

Constructed- 1994, Path- 5 Karam, Crust- 150mm, 75mm WBM + PC.

8486 04-Oct-11

H - 3977 Namaste Chowk To Gopi Ka Kuan 1.7951) km.Karnal

Constructed 10/1994. SR 03.2002, Path-5karam, Crust-150 mm8653 07-Oct-11

EE Reported: Road is in good condition.2301 22-Aug-11

H - 3978 Kachwa To Sita Mai 0.6052) km.Karnal

Road is Patchless.21892 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19107 18-Feb-12

Patches to be awarded. (EC 0.26 Lacs).14904 16-Nov-11

Constructed- 2001, Path- 4 Karam, Crust- 150mm, Patch + PC done in 01/2010.

8485 04-Oct-11

H - 3979 Rattangarh To Kaithal Road 1.8453) km.Karnal

work completed.30107 20-Aug-12

SR Allotted on 1/2/2012 (M/s S.K. Construction Co.). 155m paver completed.

21922 03-Apr-12

A/A on 01/02/2012 for Rs. 11.97 lacs.17973 06-Feb-12

185m (Rattangarh) pavers, rest patches (9.65 lacs) sanctioned on 15/9/2011.

14910 16-Nov-11

Constructed- 1995, Path- 5 Karam, Crust- 150mm, 75mm WBM + PC done in 7/2005.

8487 04-Oct-11

H - 3980 Assandh Road To Taharpur 0.1554) km.Karnal

Constructed- 07/2009, Path- 4 Karam, Crust- 150mm, SR- Nil, No traffic, Good condition.

8488 04-Oct-11

H - 3981 Kachwa-Zarifabad Road To Bajida Roran 2.4755) km.Karnal

(630 sqm) patches done 19/10/2011 to 19/12/2011 (126 K).16664 02-Jan-12

Patches allotted.14905 16-Nov-11

Constructed- 07/2009, Path- 5 Karam, Crust- 225mm. Work Plan- Patch work. EC- 1.09 Lacs.

8489 04-Oct-11

H - 3983 Approach Road To Sports Stadium At Pundark 0.3156) km.Karnal

No Patch.14956 16-Nov-11

Constructed 7/2009. No SR done, Path-5karam, Crust-225 mm, Metalled width-5.49m

8654 07-Oct-11

H - 3995 Nissing To Brass 5.0457) km.Nilokheri (SC)

E.E reported road is patchless.18044 14-Feb-12

Constructed 10/1994. Crust 150mm . 225mm WBM(0.45 km) +150mm WBM (0.170 km)+PC (entire) done 2/2010. (218.99 sqm) patches done 20/08/2011 to 23/08/2011 (46 K). No patch.

9085 07-Oct-11

H - 3996 Chakda To Gudha 1.7058) km.Nilokheri (SC)

Road is Patchless.21893 03-Apr-12

Tuesday, April 02, 2013 Page 12 of 65

Page 13: Karnal Distt. Link Roads

Constructed 10/1994. Crust 150mm. Path 5 & 6 karam. PC done in 04/2005.

9342 07-Oct-11

H - 3997 Seroi To G.M. Nissing 4.6659) km.Nilokheri (SC)

Work completed on 15/1/2013.36608 12-Feb-13

Work Plan :510m (Nissing Phirni) GSB + pavers; in rest patches (EC.20 lacs). A/A on 12/10.2011 fo rRs. 19.82 lacs. Work allotted on 19.04.2012 to S.K Contractor.

31863 23-Aug-12

Constructed 07/1995. Crust 150mm. Path 5 & 6 karam. PC done in 11/2005.

9344 07-Oct-11

A small video of this road was shown to E-In-C by villagers showing road as real bad. An estimate is also said to have been sent to H.Q. SE(Karnal) was telephoned and asked to solve maintenance issue. Please put up the estimate or bottlenecks for solution with proposed solution.

1 20-Jul-11

H - 3999 Throta To Guniana 2.3160) km.Nilokheri (SC)

Work completed on 25/12/2012.37239 12-Feb-13

Work Plan:450m (Guniana Phirni) GSB + Pavers; in rest patches + PC (EC 15 lacs). A/A on 14.08.2012 for Rs. 39.32 lacs.

31880 23-Aug-12

Constructed 03/1995. Crust 150mm. Path 5 & 6 karam. PC done in 07/2006.

9346 07-Oct-11

H - 4000 Gonder To Dacher 2.7461) km.Nilokheri (SC)

Work Completed.32387 07-Sep-12

Work Plan: 200m (Gonder Phirni) GSB + pavers; in rest 75 mm WBM +PC in entire length (EC 28 lacs). A/A on 04.05.2012 for Rs. 27.38 lacs. Allotted on 6/5/2012.

31865 23-Aug-12

Constructed 07/1995. Initial crust 150mm. Path 5 & 6 karam. Patches + PC done in 05/2004. Crust now 225mm.

9348 07-Oct-11

H - 4001 Guniana To Badnara 2.8162) km.Nilokheri (SC)

E.E reported road is patchless.18045 14-Feb-12

Constructed 11/2001. Path 5, 6 Karam. Crust 150mm. 14462 15-Nov-11

H - 4003 Amupur To Shambli 7.0663) km.Nilokheri (SC)

E.E reported road is patchless.18046 14-Feb-12

Constructed 9/2002. Crust 150mm. PC(entire) done 2/2010. (350 sqm) patches done 19/08/2011 to 22/08/2011 (68 K). No patch.

9086 07-Oct-11

H - 4005 Guniana Bandrana Via Sirsal Boundary 3.2264) km.Nilokheri (SC)

E.E reported road is patchless.18047 14-Feb-12

75 mm WBM + PC (Rs.31.23 lacs) sanctioned on 15/10/2010. Awarded to Harjit contractor on 8/8/2011. Work completed on 31/12/2011. Work completed on 31/12/2011.

16682 03-Jan-12

Constructed 3/2004. Path 5, 7 Karam. Crust 150mm. 14464 15-Nov-11

H - 4006 Bastali To Brass 3.3065) km.Nilokheri (SC)

75 mm WBM + PC (Rs.36.21 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 8/8/2011. Work completed on 31/12/2011.

31832 23-Aug-12

Tuesday, April 02, 2013 Page 13 of 65

Page 14: Karnal Distt. Link Roads

E.E reported road is patchless.18048 14-Feb-12

Work completed on 31/12/2011.16683 03-Jan-12

Constructed 3/2004. Path 5, 6 Karam. Crust 150mm. 14465 15-Nov-11

H - 4008 Balu To Singra 2.8666) km.Nilokheri (SC)

Patches completed on 25/03/2012. Road is patchless.31843 23-Aug-12

Constructed 04/2007. Crust 225mm. Path 5 & 6 karam.9352 07-Oct-11

H - 4010 Dacher To Badnara 3.6067) km.Nilokheri (SC)

Patches completed on 25/03/2012. Road is patchless.31844 23-Aug-12

Constructed 11/2008. Crust 225mm. Path 5 & 7 karam.9354 07-Oct-11

H - 4011 Gonder To Gobind Garh 4.1068) km.Nilokheri (SC)

Patches completed on 25/03/2012. Road is patchless.31845 23-Aug-12

Constructed 01/2009. Crust 225mm. Path 5 & 6 karam.9356 07-Oct-11

H - 4012 App. Road To Village Bastali 0.2669) km.Nilokheri (SC)

Road is Patchless.21894 23-Aug-12

Patches done on 25.03.2012.31849 23-Apr-12

Constructed 1991. Crust 150 mm. Path 5 Karam. 50 mm BUSG & PC completed on 29-01-2010 with on expenditure of RS. 2.13 lacs.

31835 07-Oct-11

H - 4013 Gullarpur To Manchuri 2.7170) km.Nilokheri (SC)

Patches completed on 25.03.2012. Road is patchless.31840 23-Aug-12

Constructed 02/2009. Crust 225mm. Path 5 karam.9360 07-Oct-11

H - 4014 Brass To Singra Bojpura Road. 3.2871) km.Nilokheri (SC)

Patches completed on 25.03.2012. Road is patchless.31841 23-Aug-12

Constructed 05/2009. Crust 225mm. Path 5 & 6 karam.9362 07-Oct-11

H - 4016 Nidana To Purchase Centre Sagga 2.7072) km.Nilokheri (SC)

EE reported: Work Completed on 28.11.2012. Road is in good condition.

38912 18-Dec-12

Work completed on 15.11.2012.37684 23-Nov-12

AA for Rs. 33.36 lacs on 17.08.12, to S.K contractor.32290 04-Sep-12

Work Plan:75mm WBM+PC in entire length (EC 30 lacs)9365 07-Oct-11

Constructed 02/1996. Crust 150mm. Path 5 karam. PC done in 08/2006. Shellers traffic.

9364 07-Oct-11

H - 4018 I.T.I. Taraori To Nidana Road 0.3573) km.Nilokheri (SC)

E.E reported road is patchless.18049 14-Feb-12

No Patch.14958 16-Nov-11

Constructed 8/1993. Path 5 Karam. Crust 150mm. SR done on 1/2010.

14466 15-Nov-11

H - 4020 Shamgarh To Taraori 3.5074) km.Nilokheri (SC)

Tuesday, April 02, 2013 Page 14 of 65

Page 15: Karnal Distt. Link Roads

Work completed on 30/9/2012.36219 21-Oct-12

Toewall & GSB (200m) completed - likely date of completion 15.10.12.

32291 04-Sep-12

Work plan :390 m (Shamgarh phirni) GSB + pavers; in rest patches (EC 23 lacs). A/A on 15.06.2012 for RS. 25.11. work allotted on 20.06.2012.

31862 23-Aug-12

Constructed 04/1993. Crust 150mm. Path 5 karam. PC done in 07/2004.

9366 07-Oct-11

H - 4022 Sandir To Padhana 3.1575) km.Nilokheri (SC)

75 mm WBM + PC (Rs. 30.63 lacs) Sanction on 15.10.2010. Awarded to Harjit contractor on 8/8/2011. work completed by 25/3/2012.

31826 23-Aug-12

EE reported, road is patchless.20943 14-Mar-12

Constructed 12/2002. Path 5 Karam. Crust 150mm. 14467 15-Nov-11

H - 4023 Nidana To Sonkra 3.0476) km.Nilokheri (SC)

EE reported: Work Completed on 07.11.2012. Road is in good condition.

38913 18-Dec-12

Work plan : patches (EC 4 lacs). A/A on 17.07.2012for Rs. 5.00 lacs. Work allotted on 28.07.2012.

31861 23-Aug-12

Constructed 03/1994. Crust 225mm. Path 5 karam. 75mm WBM & PC done in 03/2005.

9370 07-Oct-11

H - 4024 Taraori Rly Crossing To G.T. Road 1.4377) km.Nilokheri (SC)

EE reported: Work Completed on 30.11.2012. Road is in good condition.

38914 18-Dec-12

work Plan : Patches (EC 0.850 lacs). A/A on 17.07.2012 for Rs. 1.01 lacs. Work allotted on 30.07.2012.

31860 23-Aug-12

Constructed 02/1994. Crust 225mm. Path 5 karam. 75mm WBM & PC done in 10/2009.

9372 07-Oct-11

H - 4025 Mohri Jagir To Purchase Centre Sagga 8.5478) km.Nilokheri (SC)

Work completed on 25/12/2012.36614 12-Feb-13

Work Plan: 310m (Mohri Jagir Phirni) GSB + pavers; in rest patches (EC 64 lacs). A/A for Rs. 59.63 lacs on 09.08.2012.

31867 23-Aug-12

Constructed 02/1994. Crust 225mm. Path 5 karam. 75mm WBM & PC done in 08/2007.

9374 07-Oct-11

H - 4026 Ramana To Sambhi 2.7579) km.Nilokheri (SC)

EE reported: Work Completed on 28.11.2012. Road is in good condition.

38915 18-Dec-12

Work plan: Patches (EC 3 lacs). AA on 20.074.2012 for Rs. 3.91 lacs. Work allotted on 28.07.2012.

31879 23-Aug-12

Constructed 06/1994. Crust 150mm. Path 5 karam. PC done in 12/2007.

9376 07-Oct-11

H - 4027 Sultan Pur To Khera 3.4880) km.Nilokheri (SC)

E.E reported road is patchless.18050 14-Feb-12

No Patch.14959 16-Nov-11

Tuesday, April 02, 2013 Page 15 of 65

Page 16: Karnal Distt. Link Roads

Constructed 5/1994. Crust 150mm. Path 4 Karam. 75mm WBM + PC done 10/2009.

14468 15-Nov-11

H - 4028 Sonkra To Anjanthli 3.9081) km.Nilokheri (SC)

EE reported: Work Completed on 30.11.2012. Road is in good condition.

38916 18-Dec-12

Work plan: Patches (EC 3 lacs). AA on 17.07.2012 for Rs. 3.67 lacs. Work allotted on 30.07.2012 to Harjeet singh.

31878 23-Aug-12

Constructed 07/1995. Crust 150mm. Path 5 karam. PC done in 05/2006.

9378 07-Oct-11

H - 4031 Sagga To Behlolpur 3.1782) km.Nilokheri (SC)

E.E reported road is patchless.18051 14-Feb-12

Constructed 3/1997. Crust 150mm. PC(entire) done 12/2007. (211.68 sqm) patches done 27/08/2011 to 29/08/2001 (47 K). No patch.

9087 07-Oct-11

H - 4033 Padhana To Cremation Ground Padhana 0.9183) km.Nilokheri (SC)

E.E reported road is patchless.18052 14-Feb-12

No Patch.14960 16-Nov-11

Constructed 1/1999. Crust 150mm. Path 3 Karam. Patches + PC done on 3/2008.

14469 15-Nov-11

H - 4034 Bir Naraina To Dera'S 1.1684) km.Nilokheri (SC)

Patches completed on 25.03.2012. Road is patchless.31842 23-Aug-12

Work Plan:WBM patches+PC patches (EC. 0.25 lacs).9381 07-Oct-11

Constructed 08/2001. Crust 150mm. Path 5 karam. PC done in 01/2010.

9380 07-Oct-11

H - 4035 Upto School In Shenkhanpur 0.9885) km.Nilokheri (SC)

E.E reported road is patchless.18053 14-Feb-12

No Patch.14961 16-Nov-11

Constructed 6/2002. Crust 150mm. Path 6 Karam. Patches + PC done on 2/2010.

14470 15-Nov-11

H - 4036 Solo Majra To Sambhi Road 2.1686) km.Nilokheri (SC)

75 mm WBM + PC (Rs. 10.06 lacs) sanctioned on 15/10/2012. Awarded to Harjit Contractor on 8/8/2011. completed on 15/03/2012.

31821 23-Aug-12

EE reported, road is patchless.20942 14-Mar-12

Constructed 6/2002. Crust 150mm. Path 5 Karam. 14471 15-Nov-11

H - 4037 Galib Kheri To Saddiqpur 1.0387) km.Nilokheri (SC)

75 mm WBM + PC (Rs. 10.16 lacs) sanctoned on 15/10/2010. Awarded to Harjit Contractor on 8/8/2011. EE reported , road is patchless.

31822 23-Aug-12

EE reported, road is patchless.20944 14-Mar-12

Constructed 9/2003. Crust 150mm. Path 5 Karam. 14472 15-Nov-11

H - 4040 Padhana To Ganger 2.4088) km.Nilokheri (SC)

Tuesday, April 02, 2013 Page 16 of 65

Page 17: Karnal Distt. Link Roads

Work completed on 10/12/2012.39319 20-Dec-12

Work plan :590 m (Ganger phirni), 530m (Padhana Phirni) GSB + pavers; in rest patches + PC in entire Lengh (EC 66 lacs). A/A on 30.07.2012 for RS. 71.48. work allotted on 24.07.2012.

31864 19-Aug-12

Constructed 09/2004. Crust 150mm. Path 5 karam.9382 07-Oct-11

H - 4041 Sonkra To Shambi 4.8289) km.Nilokheri (SC)

EE reported: Work Completed on 30.11.2012. Road is in good condition.

38917 18-Dec-12

Work allotted to S.K contractor on 14.08.2012.30067 20-Aug-12

Work Plan: 75m WBM + PC in entire length (EC 53 lacs). A/A for Rs. 59.63 lacs on 09.08.2012.

31868 14-Aug-12

Constructed 02/2004. Crust 150mm. Path 5 karam.9384 07-Oct-11

H - 4042 Lalaini To Bhani Minor 1.1990) km.Nilokheri (SC)

EE reported: Work Completed on 30.11.2012. Road is in good condition.

38918 18-Dec-12

Work plan: Patches (EC 2 lacs). AA on 17.07.2012 for Rs. 2.39 lacs. Work allotted on 28.07.2012.

31877 23-Aug-12

Constructed 04/2006 Crust 150mm. Path 5 karam.9386 07-Oct-11

H - 4043 Nadana (Gobind Garh Gamri) To To Sham Garh 6.0491) km.Nilokheri (SC)

Work completed on 30.10.12.36618 30-Oct-12

AA on 7/9/2012 for Rs. 8.58 lacs. Tender approved.32418 10-Sep-12

Work Plan: Patches (EC 7 lacs).9389 07-Oct-11

Constructed 03/2009. Crust 150mm. Path 6 karam.9388 07-Oct-11

H - 4044 Barthal To Amin 4.7792) km.Nilokheri (SC)

Work completed.30108 20-Aug-12

0-530 cc, 75 mm WBM & PC on rest sanctioned on 12/10/2010 for RS. 60.81 lacs. Tender allotted on 6/3/2012 (The Bath CO-OP L&C Society). R/A/A on 6.3.2012 for Rs. 67.98 lacs.

20601 07-Mar-12

Constructed 6/1990. Crust 150mm. Path 4, 5 & 6 Karam. 75mm WBM + PC done on 2/2006.

14473 15-Nov-11

H - 4045 Samana Bahu To Bairsal 3.4893) km.Nilokheri (SC)

Work completed on 10/12/2012.39320 20-Dec-12

Work awarded on 21.08.12 to bath co-op society.32301 04-Sep-12

Work plan: Bitumen factory situated 590m (Bairsal Phirni) GSB+pavers; in rest patches + PC in entire length (EC 53 lacs).A/A Rs. 37.84 lacs. Work allotted on 2.08.2012.

31869 23-Aug-12

Constructed 01/1993. Crust 150mm. Path 5 & 6 karam. PC done in 07/2006.

9392 07-Oct-11

H - 4047 Samani To Bairsal 4.1394) km.Nilokheri (SC)

Work completed on 11/3/2013.42692 15-Mar-13

Work alloted to bath co-op society on 21.08.12, supply of stone metal in 2km completed.

32302 04-Sep-12

Tuesday, April 02, 2013 Page 17 of 65

Page 18: Karnal Distt. Link Roads

Work plan: hot mix plant situated 350m (samani phirni) GSB + paver; 75mm WBM + PC in 2 km in rest, patches &PC in entire (EC 53 lacs). A/A Rs.57.54. work allotted on 21.08.2012.

31875 23-Aug-12

Constructed 03/1194. Crust 150mm. Path 4 & 5 karam. PC done in 02/2007.

9394 07-Oct-11

H - 4048 Samani Bairsal To Buktipur 0.6795) km.Nilokheri (SC)

Patches completed on 20/03/2012. Road is Patchless. 31839 23-Aug-12

Constructed 04/1994. Crust 150mm. Path 4 karam. PC done in 03/2008.

9396 07-Oct-11

H - 4049 Dabarthala To Anjanthali 3.5596) km.Nilokheri (SC)

E.E reported road is patchless.18054 14-Feb-12

Constructed 6/1994. Crust 150mm. Path 4, 5 Karam. Patches + PC done in 12/2007.

14474 15-Nov-11

H - 4052 Raipur Roran To Barthal 5.4297) km.Nilokheri (SC)

Work completed on 21/2/2013.42693 15-Mar-13

Work Plan: Patches (EC 6 lacs).9399 07-Oct-11

Constructed 05/1999. Crust 150mm. Path 4 Karam. PC done in 03/2008.

9398 07-Oct-11

H - 4053 Sherpur To Dera Bajigram 0.8998) km.Nilokheri (SC)

Work Completed on 30/9/2012.36220 21-Oct-12

Work Plan: heavy traffic diverts to avoid Toll Plaza, 340 m (Dera Bajigran Phirni), 155m (Shergarh Phirni) GSB + Pavers; in rest patches (EC.18 lacs). A/A on 15.06.2012 for Rs. 21.41 lacs. Work allotted on 20.06.2012.

31872 23-Aug-12

Constructed 02/2002. Crust 225mm. Path 4 karam. 75mm WBM & PC done in 10/2009.

9400 07-Oct-11

H - 4054 Sandhir To Kheri Man Singh 3.0399) km.Nilokheri (SC)

Patches completed. Road is patchless. 31847 23-Aug-12

Constructed 07/200. Crust 150mm. Path 5 & 6 karam. PC done in 12/2007.

9402 07-Oct-11

H - 4056 Kalsi To Sherpur 1.89100) km.Nilokheri (SC)

Work completed on 30/9/2012.36221 21-Oct-12

Work Plan: heavy traffic diverts to avoid Toll Plaza, 340 m (Kalsi Phirni) GSB + Pavers; in rest patches (EC.19 lacs). A/A on 15.06.2012 for Rs. 22.36 lacs. Work allotted on 20.06.2012.

31873 23-Aug-12

Constructed 12/2001. Crust 150mm. Path 5 karam. PC done in 02/2010.

9404 07-Oct-11

H - 4057 Barsalu To Butankheri 2.69101) km.Nilokheri (SC)

E.E reported road is patchless.18055 14-Feb-12

Constructed 5/2002. Crust 150mm. 75mm WBM +PC(entire) done 2/2010. (202.50 sqm) patches done 27/08/2011 to 29/08/2011 (43 )K. No patch.

9088 07-Oct-11

H - 4058 Seedpur To Nilokheri Road 1.92102) km.Nilokheri (SC)

Tuesday, April 02, 2013 Page 18 of 65

Page 19: Karnal Distt. Link Roads

75 mm WBM + PC (Rs. 18.74 lacs) sanctioned on 15/10/2010. Awarded to Harjit contractor on 8/8/2011. work completed. EE reported is patachless.

31823 23-Aug-12

Constructed 10/2002. Crust 150mm. Path 5 Karam. 14475 15-Nov-11

H - 4059 Raipur To Pujam 3.42103) km.Nilokheri (SC)

75 m WBM + PC (Rs. 33 lacs) sanctioned on 15/10/2010. Awarded to Harjit contractor on 8/8/2011. work completed. Ee reported, road is patchless.

31820 23-Aug-12

EE reported, road is patchless.20938 14-Mar-12

Constructed 2/2002. Crust 150mm. Path 5 Karam. 14476 15-Nov-11

H - 4061 Amar Garh To Kheri Man Singh 3.58104) km.Nilokheri (SC)

Work completed on 30/9/2012.36214 21-Oct-12

75 mm WBM + PC (Rs. 37.45 lacs) sanctioned on 15/10/2010. Awarded to Harjit Contractor on 8/8/2011.

14929 16-Nov-11

Constructed 6/2003. Crust 150mm. Path 5, 6 Karam. 14477 15-Nov-11

H - 4062 Butana To Sandhir 2.68105) km.Nilokheri (SC)

75 mm WBM + PC (Rs.26 lacs) sanctioned on 15/10/2010. Awareded to Harjit contractor on 8/8/2011. work completed. EE reported , road is patchless.

31830 23-Aug-12

Constructed 7/2003. Crust 150mm. Path 4, 5 Karam. 14478 15-Nov-11

H - 4063 Bakipur To Lathron 2.69106) km.Nilokheri (SC)

work completed. 30110 20-Aug-12

Constructed 12/2003. Crust 150mm. Path 4, 5 Karam. 14479 15-Nov-11

75 mm WBM + PC (Rs. 26 lacs) sanctioned on 15/10/2010. Awarded to Harjit contractor on 8/8/2011.

31825 23-Sep-11

H - 4064 Seedpur To Gurukul School 0.95107) km.Nilokheri (SC)

Work completed, EE reportred road is patchless.31857 23-Aug-12

75 mm WBM + PC (Rs. 9.30 lacs) sanctioned on 15/10/2010. Awarded to Harjit contractor on 8/8/2011.

31829 23-Aug-12

Constructed 5/2003. Crust 150mm. Path 4, 5 Karam. 14480 15-Nov-11

H - 4066 Barshalu To Manak Majra 2.05108) km.Nilokheri (SC)

Work completed on 30/9/2012.36215 21-Oct-12

75 mm WBM + PC (Rs. 19.79 lacs) sanctioned on 15/10/2010. Awarded to Harjit contractor on 8/8/2011.

31824 16-Nov-11

Constructed 1/2004. Crust 150mm. Path 4 Karam. 14481 15-Nov-11

H - 4067 Raipur Roran To Village Barana 1.90109) km.Nilokheri (SC)

Work completed on 30.10.12.36619 30-Oct-12

work Plan: heavy traffic diverts to avoid Toll Plaza, 390 m (Raipur Raran Phirni) GSB + Pavers; in rest patches (EC.21 lacs). A/A on 15.06.2012 for Rs. 23.64 lacs. Work allotted on 20.06.2012. 200 m toe wall completed & 200 m GSB laid.

31874 18-Aug-12

Constructed 02/2006 Crust 150mm. Path 5 karam.9406 07-Oct-11

Tuesday, April 02, 2013 Page 19 of 65

Page 20: Karnal Distt. Link Roads

H - 4068 Sambhi To Gholpura 4.22110) km.Nilokheri (SC)

E.E reported road is patchless.18056 14-Feb-12

Constructed 1/2009. Crust 225mm. (641.55 sqm) patches done 24/08/2011 to 26/08/2011 (126 K). No patch.

9089 07-Oct-11

H - 4069 Bhola Khalsa To Bir Badalwa 2.40111) km.Nilokheri (SC)

Patches done , road is patchless. 31848 23-Aug-12

Constructed 11/1994. Crust 150mm. Path 5 karam. PC done in 03/2008.

9408 07-Oct-11

H - 4070 Sonkra To Nigdhu 4.60112) km.Nilokheri (SC)

Work completed on 30/9/2012.36222 21-Oct-12

Work plan: Heavy Mandi Traffic 75 mm WBM + PC in entire length (EC.50 lacs). A/A on 23.04.2012 for RS. 51.10 lacs. Allotted on 07.05.2012

31870 23-Aug-12

Constructed 1993. Crust 150mm. Path 5 karam. PC done in 12/2006.9410 07-Oct-11

H - 4071 Pattanpuri To Hathira 4.20113) km.Nilokheri (SC)

AA on 7/9/2012 for Rs. 7.43 lacs. Work allotted on 28.09.2012 (SK const. Co.), work complated on 26.10.2012.

36664 30-Oct-12

Work Plan: Patches (EC. 6 lacs).9413 07-Oct-11

Constructed 01/1995. Crust 150mm. Path 5 & 8 karam. PC done in 11/2006.

9412 07-Oct-11

H - 4073 Jamba To Abla Jagir 2.76114) km.Nilokheri (SC)

E.E reported road is patchless.18057 14-Feb-12

Constructed 11/2001. Crust 150mm. PC (entire) done 1/2010. (206.26 sqm) patches done 27/08/2011 to 29/08/2011 (45 K). No patch.

9090 07-Oct-11

H - 4074 Budhera To Hathira 2.42115) km.Nilokheri (SC)

Patches done. Road is patchless.31852 23-Aug-12

Constructed 11/2001. Crust 150mm. Path 5 & 6 karam. PC done in 01/2010.

9414 07-Oct-11

H - 4075 Bukhapuri To Budhera 1.72116) km.Nilokheri (SC)

Patches completed on 25/03/2012. Road is patchless. 31846 23-Aug-12

Constructed 01/2002. Crust 150mm. Path 4 karam. PC done in 01/2010.

9416 07-Oct-11

H - 4076 Pastana To Hathira.-II 1.68117) km.Nilokheri (SC)

EE reported: Work Completed on 25.11.2012. Road is in good condition.

38919 18-Dec-12

Work Plan: patches (EC 1 lacs). A/A on 17.07.2012 for Rs. 1.31 lacs. Work allotted on 28.07.2012.

31876 23-Aug-12

Constructed 04/2002. Crust 150mm. Path 5 & 6 karam. PC done in 01/2010.

9418 07-Oct-11

H - 4077 Mohri Jagir To Dera Souda 1.25118) km.Nilokheri (SC)

Tuesday, April 02, 2013 Page 20 of 65

Page 21: Karnal Distt. Link Roads

E.E reported road is patchless.18058 14-Feb-12

No Patch.14963 16-Nov-11

Constructed 3/2002. Crust 150mm. Path 4 Karam. Patches + PC done in 1/2010.

14482 15-Nov-11

H - 4078 Keor To Mohri 3.40119) km.Nilokheri (SC)

E.E reported road is patchless.18059 14-Feb-12

No Patch.14964 16-Nov-11

Constructed 7/2002. Crust 150mm. Path 4 Karam. Patches + PC done in 2/2010.

14483 15-Nov-11

H - 4079 Keor To Dikhana 2.61120) km.Nilokheri (SC)

E.E reported road is patchless.18060 14-Feb-12

Constructed 7/2002. Crust 150mm. PC (entire) done 2/2010. (200 sqm) patches done 26/08/2011 to 28/08/2011 (42 K). No patch.

9091 07-Oct-11

H - 4081 Borsham To Gittalpur 0.76121) km.Nilokheri (SC)

Work completed, EE reportred road is patchless.31858 23-Aug-12

75 mm WBM + PC (Rs. 7.54 lacs) sanctioned on 15/10/2010. Awarded to Harjit contractor on 8/8/2011.

31828 23-Aug-12

Constructed 11/2003. Crust 150mm. Path 4 Karam. 14484 15-Nov-11

H - 4082 Bir Badalwa To Gholpura 4.30122) km.Nilokheri (SC)

Work completed on 30/9/2012.36216 21-Oct-12

0-250m paver blocks in village Bir badalwa, 0-3850, 75 mm WBM, Carpet 4.05 km sanctioned on 31/10/2011 for RS. 48.62 lacs.

31817 23-Aug-12

Constructed 05/2005. Crust 150mm. Path 5 Karam.9422 07-Oct-11

H - 4083 Haibatpur To Gholpura 2.20123) km.Nilokheri (SC)

Work completed on 30.10.2012.36620 30-Oct-12

work plan: 220m (Haibatpur Phirni) GSB + paver; in rest patches (EC 15 lacs), A/A on 17.07.2012 for Rs. 17.87 lacs. Work allotted on 20.07.2012.

31866 23-Aug-12

Constructed 03/2006. Crust 150mm. Path 5 karam.9424 07-Oct-11

H - 4084 Sawant To Haibatpur 2.10124) km.Nilokheri (SC)

Patches done, road is patchless. 31850 23-Aug-12

Constructed 08/2008. Crust 150mm. Path 4 karam.9426 07-Oct-11

H - 4085 App Road To Stadium, Nigdhu 0.18125) km.Nilokheri (SC)

E.E reported road is patchless.18061 14-Feb-12

No Patch.14965 16-Nov-11

Constructed 1/2008. Crust 150mm. Path 5 Karam. 14485 15-Nov-11

H - 4086 Rukanpur To Jattpura 3.72126) km.Nilokheri (SC)

Patches done, road is patchless. 31851 23-Aug-12

Tuesday, April 02, 2013 Page 21 of 65

Page 22: Karnal Distt. Link Roads

Constructed 07/1995. Crust 150mm. Path 4 & 5 karam. PC done in 12/2007.

9428 07-Oct-11

H - 4089 Bhani Khurd To Railway Station 0.36127) km.Nilokheri (SC)

EE reported: Work Completed on 28.11.2012. Road is in good condition.

38920 18-Dec-12

AA on 7/9/2012 for Rs. 4.47 lacs. Work allotted on 24.09.2012 (SK const. Co)

36665 30-Oct-12

Work Plan:75mm WBM+ PC in entire (EC.4 lacs).9431 07-Oct-11

Constructed 03/2000. Crust 150mm. Path 5 karam.9430 07-Oct-11

H - 4090 Dadupur To Kurali 2.11128) km.Nilokheri (SC)

To be repair under Annual Repair.36807 05-Nov-12

The Phirni is in 0 to 500m. It is seen that if the drains are made then road would not come under is attack of water. In any case, the drain would be required even if paver blocks are also laid. Hence, the following action be taken :-(a) patch the road even in the phirni portion.(b) make the drains first Katcha then Pucca and find out disposal of water.(C ) then review, if paver blocks are required.

36799 05-Nov-12

Road is Patchless.21902 03-Apr-12

Constructed 02/2002. Crust 225mm. Path 4 & 6 karam. 75mm WBM & PC done in 01/2010.

9432 07-Oct-11

H - 4098 Ballah To Goli 2.93129) km.Assandh

Work completed on 30/11/2011.16696 03-Jan-12

Sanctioned on 15/10/2010 for Rs. 1.64 lacs, 75mm WBM (100m), rest Patches + PC in entire length, Awarded (S.K. const.) on 8/8/2011, work completed except berms.

14936 16-Nov-11

Constructed 6/1993. Crust 150mm. Path 5 Karam.14507 15-Nov-11

H - 4099 Bir Bassi To Chogama 3.03130) km.Assandh

Work completed on 15/12/2011.16697 03-Jan-12

Sanctioned on 15/10/2010 for Rs. 30.93 lacs, CC (575m) Chogama phirni, rest Patches + PC in entire length, Awarded (S.K. const.) on 8/8/2011, PC complete, CC in progress.

14937 16-Nov-11

Constructed 1994. Crust 150mm. Path 5 Karam.14508 15-Nov-11

H - 4100 Dera Gama To Lalain 3.91131) km.Assandh

Work completed on 30/11/2011.16698 03-Jan-12

Sanctioned on 15/10/2010 for Rs. 22 lacs, Patches + PC, Awarded (S.K. const.) on 8/8/2011,Work complete except berms.

14938 16-Nov-11

Constructed 3/1994. Crust 150mm. Path 5 Karam. PC done in 3/2003.

14509 15-Nov-11

H - 4101 Rahra To Khizarabad 5.00132) km.Assandh

EE reported: Work Completed on 20.11.2012. Road is in good condition.

38921 18-Dec-12

A/A on 13.08.2012 for rs. 89.64 lacs. Work allotted to S.K contractor on 14.08.2012.

30078 20-Aug-12

Tuesday, April 02, 2013 Page 22 of 65

Page 23: Karnal Distt. Link Roads

Work Plan:150m (Rahra Phirni) ,480m (khizrabad Phirni) GSB+pavers; in rest 75mm WBM +PC (4370m) (EC. 80 lacs).

9147 07-Oct-11

Constructed 06/1997. Crust 150mm. Path 5 & 6 karam. PC done in 12/2004.

9146 07-Oct-11

H - 4102 Ballah To Dharm Garh 3.72133) km.Assandh

(334 sqm) patches done 31/10/2011 to 27/12/2011 ( 66 K).16673 02-Jan-12

Patches yet to be awarded. (EC 1.64 lacs).9149 16-Nov-11

Constructed 05/1999. Crust 150mm. Path 5 & 6 karam. PC done in 03/2008.

9148 07-Oct-11

SR completed on: 31-03-2008 with an expenditure of Rs 14.56 lacs2225 31-Mar-08

H - 4103 Assandh Salwan Road To Dupedi 0.56134) km.Assandh

Patchless.14966 16-Nov-11

Constructed 4/2000. Path-4karam, Crust-150 mm8655 07-Oct-11

H - 4104 Jai Singh Pura To Rangrurti Khera 3.02135) km.Assandh

Patchless.14967 16-Nov-11

Constructed 1/2000. Path-4karam, Crust-150 mm8656 07-Oct-11

H - 4105 Jalmana To Dacher 5.55136) km.Assandh

To be repair under Annual Repair36808 05-Nov-12

The phirni is 4745 to 4900m is not damaged as the photograph on 24 dec. show. There is water coming only in 20m at RD 5.04km. The XEN has not tried to solve the problem in ordinary repair when he had plenty of money in ordinary repairs. SE to personally a monitor the road to ensure that required works are carried out under Annual repairs within the money available under the repair. There are some 'Kurdi' on the road stretches near the village have berms higher than road. This should be set right.

36800 05-Nov-12

RD 4745 to 4900m - Phirni damaged. Paver block required.27576 17-Jul-12

Constructed 1/1994. Crust 150mm. CC (0.260 km ) + PC (5.29 km ) done 12/2006. (400.85 sqm) patches done 16/08/2011 to 19/08/2011 (85 K). No patch.

9093 07-Oct-11

H - 4106 Rattak To Pangala 3.16137) km.Assandh

Work completed on 30.09.2012.36622 30-Oct-12

A/A Rs. 35.01 lac on 17.08.12 & work awarded on 17.08.12 to harjeet Singh.

32316 04-Sep-12

Constructed 03/1994. Crust 150mm. Path 5 karam. PC done in 01/2005.

9150 07-Oct-11

Work Plan:75mm WBM(RD500 to 1500, RD 2000 to 3000)+PC in entire length(EC.35 lacs)

9151 07-Oct-11

H - 4107 Mardan Heri To Thal 5.69138) km.Assandh

Constructed 3/2001. Crust 150mm. PC (entire) done 10/2009. (412 sqm) patches done 17/08/2011 to 21/08/2011 (87 K). No patch.

9094 07-Oct-11

H - 4108 Khizrabad To Gurudwara 0.30139) km.Assandh

Patchless.14968 16-Nov-11

Tuesday, April 02, 2013 Page 23 of 65

Page 24: Karnal Distt. Link Roads

Constructed 11/2001. Path-5karam, Crust-150 mm8657 07-Oct-11

H - 4110 Shekhpura To Kurlan 4.99140) km.Assandh

Patchless.14969 16-Nov-11

Constructed 8/2002. Path-5 &6 karam, Crust-150 mm8658 07-Oct-11

H - 4111 Depudi To Padhana 3.00141) km.Assandh

Patchless.14970 16-Nov-11

Constructed 8/2002. Path-5karam, Crust-150 mm8659 07-Oct-11

H - 4112 Jai Singh Pura Karnal Road To Salwan 2.53142) km.Assandh

Repair of berms work is in progress under MGNREGA scheme.(Est. Cost 25021/-)

37130 08-Nov-12

Constructed 7/2002. Crust 150mm. PC(entire) done 2/2010. (225 sqm) patches done 9/08/2011 to 14/08/2011 (54 K). No patch.

9095 07-Oct-11

H - 4113 Assandh To Badrala 3.09143) km.Assandh

Repair of berms work is in progress under MGNREGA scheme.(Est. Cost 64367/-)

37129 08-Nov-12

Work complete on 18.09.2012.36623 30-Oct-12

A/A on 15.06.2012 for Rs. 35.32 lacs. Work allotted on 16/7/2012 (S.K. Trader).

29957 20-Aug-12

Work Plan:75mm WBM(RD0 to 2400m)+PC in entire length(EC. 33 lacs)

9153 07-Oct-11

Constructed 06/2002. Crust 150mm. Path 5, 6 & 7 karam.9152 07-Oct-11

H - 4115 Dera Gobind Garh To Dera Gurdas Chowk 1.66144) km.Assandh

Patchless.14971 16-Nov-11

Constructed 12/2002. Path-5 & 6karam, Crust-150 mm8660 07-Oct-11

H - 4116 Salwan Road To Karnal Assandh Road 1.06145) km.Assandh

(144 sqm) patches done 25/11/2011 to 27/12/2011 ( 27 K).16665 02-Jan-12

Patches yet to be awarded. (EC 0.37 lacs).9155 16-Nov-11

Constructed 07/2002. Crust 150mm. Path 5 akram. 50mm BM+PC in entire; PC done in 02/2010.

9154 07-Oct-11

H - 4118 Govt.School To Ring Bandh Ardana 0.42146) km.Assandh

Work completed on 30/11/2011.16699 03-Jan-12

75 mm WBM + PC (Rs. 4.20 lacs) sanctioned on 15/10/2010. Awarded to S.K const. on 8/8/2011. Work completed except berms.

14939 16-Nov-11

Constructed 12/2002. Crust 150mm. Path 5 Karam. PC done in 3/2003.

14510 15-Nov-11

H - 4119 Bahri To Theh Bahri 2.71147) km.Assandh

EE reported: Work Completed on 20.11.2012. Road is in good condition.

38922 18-Dec-12

A/A Rs. 27.21 lacs. Work allotted to S.K contractor on 21.08.2012.30080 20-Aug-12

Tuesday, April 02, 2013 Page 24 of 65

Page 25: Karnal Distt. Link Roads

Work Plan:80m(Bahri Phirni)GSB+pavers; 300m 75mm WBM+PC(EC. 33 lacs).

9157 07-Oct-11

Constructed 12/2003. Crust 150mm. Path 5 & 6 karam.9156 07-Oct-11

H - 4122 Rangruti Khera To Jabala 2.85148) km.Assandh

Repair of berms work is in progress under MGNREGA scheme.(Est. Cost 29987/-)

37128 08-Nov-12

Work completed on 30/11/2011.16700 03-Jan-12

75 mm WBM + PC (Rs. 28.84 lacs) sanctioned on 15/10/2010. Awarded to S.K const. on 8/8/2011. Work completed.

14940 16-Nov-11

Constructed 3/2003. Crust 150mm. Path 4 & 5 Karam.14511 15-Nov-11

H - 4124 Jaisingh Pura To Karnal Assandh Road 1.12149) km.Assandh

Work completed on 30.09.2012.36625 30-Oct-12

A/A on 16.07.2012 for Rs. 14.44 lacs. 29961 20-Aug-12

Work allotted on 16/7/2012 (Sh. Harjeet Singh).27583 17-Jul-12

Work Plan:75mm WBM+ PC in entire (EC. 10 lacs).9159 07-Oct-11

Constructed 07/2003. Crust 150mm. Path 5 karam.9158 07-Oct-11

H - 4125 Main Road Rathak To Harizan Chopal 0.40150) km.Assandh

Work completed on 15.09.2012.36626 30-Oct-12

A/A on 16.07.2012 for Rs. 65.63 lacs. 29966 20-Aug-12

Work Plan:75mm WBM+ PC in entire (EC 4.50 lacs).9161 07-Oct-11

Constructed 10/2003. Crust 150mm. Path 5 Karam.9160 07-Oct-11

H - 4128 P.W.D. Road To Vikash Bhawan Ballah 0.43151) km.Assandh

EE reported: Work Completed on 30.11.2012. Road is in good condition.

38923 18-Dec-12

A/A on 14.08.2012 for RS. 31.23 lacs. Work allotted on 14.08.2012 to Rajesh const. co.

30082 20-Aug-12

Work Plan: 430m ( Ballah) GSB+pavers (EC 22 lacs).9163 07-Oct-11

Constructed 11/2003. Crust 115mm. Path 4 karam. BOE only.9162 07-Oct-11

H - 4129 Ballah To Munak 4.59152) km.Assandh

work completed on 30.09.2012.36586 30-Oct-12

A/A on 23.05.2012 for Rs. 24.13.29987 20-Aug-12

Work allotted on 20.06.2012 to Rajesh const. co.30034 20-Aug-12

RD 0 to 300m Phirni portion 80mm thick interlocking tiles with 0.25mm thick GSB (Estimated cost: Rs. 15.00 lacs).

17812 23-Jan-12

Constructed 11/2003. Crust 150mm. 75mm WBM + PC (entire) done 12/2006.

9096 07-Oct-11

(324.51 sqm) patches done 9/08/2011 to 18/08/2011 (73 K). No patch.

17519 07-Sep-11

H - 4130 Chochra To Chor Karsa 3.68153) km.Assandh

Work completed on 15/12/2011.16701 03-Jan-12

Tuesday, April 02, 2013 Page 25 of 65

Page 26: Karnal Distt. Link Roads

75 mm WBM + PC (Rs. 37.30 lacs) sanctioned on 15/10/2010. Awarded to S.K const. on 8/8/2011. Completed upto WBM.

14941 16-Nov-11

Constructed 6/2003. Crust 150mm. Path 5 & 6 Karam.14512 15-Nov-11

H - 4133 Khizrabad To Dera Gama 1.76154) km.Assandh

Work completed on 16.09.2012.36628 30-Oct-12

A/A on 15.06.2012 for Rs. 22.65 lacs. Work allotted on 20/6/2012 (Sh. Harjeet Singh).

29952 20-Aug-12

Work Plan:75mm WBM+PC in entire (EC 20 lacs).9167 07-Oct-11

Constructed 05/2004. Crust 150mm. Path 4 karam.9166 07-Oct-11

H - 4136 Rathak To Dera Mohar Singh 1.98155) km.Assandh

Work completed on 30/11/2011.16702 03-Jan-12

75 mm WBM + PC (Rs. 20.13 lacs) sanctioned on 15/10/2010. Awarded to S.K const. on 8/8/2011. Work completed except berms.

14942 16-Nov-11

Constructed 3/2004. Crust 150mm. Path 5 Karam.14513 15-Nov-11

H - 4137 Dera Gujrai Wala To Dera Pattu Wala 1.76156) km.Assandh

Work completed on 30.09.2012.36629 30-Oct-12

A/A on 16.07.2012 for Rs. 22.84 lacs. 29963 20-Aug-12

Work allotted on 12/7/2012 (Sh. Harjeet Singh).27588 17-Jul-12

Work Plan: 75mm WBM+PC (EC 19.50 lacs).9171 07-Oct-11

Constructed 04/2004. Crust 150mm. Path 5 & 6 Karam.9170 07-Oct-11

H - 4138 Bal Rangran To Gandhi Gram 2.05157) km.Assandh

(506 sqm) patches done 31/10/2011 to 27/12/2011 ( 94 K).16666 02-Jan-12

Patches awarded. (EC 0.90 lacs).9173 16-Nov-11

Constructed 2004 execpt 100m length balnace due to dispute in phirni portion(Bal Rangran) & constructed in 11/2008. Crust 150mm. Path 5 karam.

9172 07-Oct-11

H - 4140 Mor Majra To Ballah 1.55158) km.Assandh

Constructed 2/2009. Crust 225mm. (131.13 sqm) patches done 15/08/2011 to 19/08/2011 (26 K). No patch.

9097 07-Oct-11

H - 4141 Mor Majra To Dharam Garh 3.21159) km.Assandh

Completed on 20/3/2012. Road is patchless.21310 22-Mar-12

Patches awarded. (EC 1.41 lacs).9177 16-Nov-11

Constructed 11/2009. Crust 225mm. Path 5 karam.9176 07-Oct-11

H - 4142 Approach Road To Stadium Jaisinghpura 0.23160) km.Assandh

(57 sqm) patches done 31/10/2011 to 27/12/2011 ( 12 K).16667 02-Jan-12

Patches yet to be awarded. (EC 0.11 lacs)14908 16-Nov-11

Constructed 08/2009. Crust 150mm. Path 5 Karam.9178 07-Oct-11

H - 4143 Balu To Jalala Veeran 2.86161) km.Assandh

Completed on 25/3/2012. Road is patchless.21400 26-Mar-12

Tuesday, April 02, 2013 Page 26 of 65

Page 27: Karnal Distt. Link Roads

Patches awarded. (EC 65 K)14909 16-Nov-11

Constructed 12/1993. Crust 150mm WBM. PC done in 01/2010; 710m (Balu side)75mm WBM strengthening+PC in entire length. Path 5, 6 Karam.

9180 07-Oct-11

H - 4144 Nissing Nardak Canal To Aungad 2.25162) km.Assandh

Road is Patchless.21903 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19126 18-Feb-12

Patches awarded. (EC. 50 K)9183 16-Nov-11

Constructed 01/1994. Crust 150mm WBM. PC done in 01/2010; 77m CC pavement (RD2173 to 2250m). Path 5 Karam.

9182 07-Oct-11

H - 4145 Manjura To Hathlana 1.34163) km.Assandh

Road is Patchless.21904 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19127 18-Feb-12

Patches awarded. (EC 57 K)9185 16-Nov-11

Constructed 01/1994. Crust 225mm. PC done in 12/2006. Path 5, 6 Karam.

9184 07-Oct-11

H - 4146 Balu To Budanpur 2.13164) km.Assandh

Constructed 3/1994. Crust 150mm. PC(entire) done 3/2008. (160.96 sqm) patches done 21/08/2011 to 24/08/2011 (34 K). No patch.

9098 07-Oct-11

H - 4148 Balu To Bajida Roran 3.52165) km.Assandh

EE reported: Work Completed on 20.12.2012. Road is in good condition.

38924 12-Feb-13

A/A on 24.07.2012 for Rs. 4.99 lacs. Work allotted on 28.07.2012 to Harjeet Singh.

29989 20-Aug-12

Work Plan:Heavy Patchwork (EC 4 lacs).9187 07-Oct-11

Constructed 05/1996. Crust 150mm. Path 5 karam. PC done in 104/2005.

9186 07-Oct-11

H - 4149 Dacher To Rugsana 4.35166) km.Assandh

Work completed.27577 17-Jul-12

A/A on 23.04.2012 for Rs. 31.19 lacs. Allotted on 07.05.201222970 03-Jul-12

Work Plan: Patches + PC in entire length (EC 37 lacs).9189 07-Oct-11

Constructed 1997 Crust 225mm. Path 5 & 6 Karam. PC done in 07/2004.

9188 07-Oct-11

H - 4150 Shekhupura To Gonder 2.12167) km.Assandh

Patchless.14972 16-Nov-11

Constructed 4/1997. Crust 225mm, Path-5karam. 75mm WBM + PC done in 12/2006.

8663 07-Oct-11

H - 4151 Dacher Jalmana Road To Dera Fatehgarh 1.08168) km.Assandh

Road is Patchless.21905 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19128 18-Feb-12

Patches yet to be awarded. (EC 20 K)9191 16-Nov-11

Tuesday, April 02, 2013 Page 27 of 65

Page 28: Karnal Distt. Link Roads

Constructed 12/1998. Crust 225mm. PC done in 01/2010. Path 4, 5 Karam.

9190 07-Oct-11

H - 4152 Behlolpur To Bir Majra 2.94169) km.Assandh

Road is Patchless.21906 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19129 18-Feb-12

Patches yet to be awarded. (EC 50 K)9193 16-Nov-11

Constructed 11/2001. Crust 150mm. PC done in 01/2010. Path 5 Karam.

9192 07-Oct-11

H - 4153 Sitamai Road To Dera Soda 0.59170) km.Assandh

Road is Patchless.21907 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19130 18-Feb-12

Patches yet to be awarded. (EC 12 K)9195 16-Nov-11

Constructed 11/2001. Crust 150mm. PC done in 01/2010. Path 5 Karam.

9194 07-Oct-11

H - 4154 Gonder To Machuri 5.05171) km.Assandh

Work complete on 15.10.2012.36630 30-Oct-12

A/A on 17.07.2012 for Rs. 5.49 lacs. Work allotted on 28.07.2012 to S.K contractor.

29981 20-Aug-12

Work Plan:Heavy Patchwork (EC 4 lacs).9197 07-Oct-11

Constructed 07/2002. Crust 150mm. Path 5 karam.9196 07-Oct-11

H - 4157 Prem Khera To Balu 3.44172) km.Assandh

Work completed on 16.10.201236631 30-Oct-12

A/A on 15.06.2012 for Rs. 23.16 lacs. Work allotted on 21/6/2012 (Sh. Amarpal).

29953 20-Aug-12

Work Plan:325m (Prem Khera Phirni) GSB+pavers; in rest patches (EC 19 lacs).

9199 07-Oct-11

Constructed 03/2003. Crust 150mm. Path 5 karam.9198 07-Oct-11

H - 4158 Hathlana To Jundla 4.18173) km.Assandh

Work completed on 10/12/2012.39321 20-Dec-12

A/A Rss 92.14 lacs. Work allotted to harjeet singh on 21.08.2012.30087 20-Aug-12

Work Plan:400m (Hathlana Phirni) , 600m (Jundla Phirni) GSB+pavers; in rest patches+ PC (EC 75 lacs).

9201 07-Oct-11

Constructed 07/1993. Crust 150mm. PC done in 12/2004. Path 5 & 6 karam.

9200 07-Oct-11

H - 4159 Chirao To Pingli 2.23174) km.Assandh

Work completed on 30/1/201336633 12-Feb-13

Work Plan: 390m (Chirao Phirni), 380m (Pingli Phirni) GSB+pavers; in rest 75mm WBM+PC (EC 55 lacs). D/Estimate T/sanction Rs. 55.13 lacs on 25.06.12. Tender allotted on 26.06.12(Sh. Harjit singh) 15.50% above NIT.

26723 12-Jul-12

Constructed 12/1996. Crust 150mm + extra 0.075m in both Vill phirni portions WBM. PC done in 11/2004. Path 4 & 5 karam.

9202 07-Oct-11

Assandh

Tuesday, April 02, 2013 Page 28 of 65

Page 29: Karnal Distt. Link Roads

H - 4163 Kheri Naru To Jundla (R/A/A) 4.95175) km.Assandh

Repair of berms to be done under MGNREGA scheme.37124 08-Nov-12

Constructed 7/1999. Crust 150mm. CC (0.140 km) + PC(4.81 km )done 12/2007. (353.51 sqm) patches done 8/08/2011 to 12/08/2011 (75 K). No patch.

9099 07-Oct-11

H - 4164 Dera Chasham Pal Nain To Jani Road 0.80176) km.Assandh

Patchless.14973 16-Nov-11

Constructed 6/2002. Path-3karam, Crust-150 mm8661 07-Oct-11

H - 4165 Dadupur To Chirao 1.69177) km.Assandh

Constructed 1/2001. Crust 150mm. PC(entire) done 1/2010. (141.95 sqm) patches done 8/08/2011 to 12/08/2011 (28 K). No patch.

9100 07-Oct-11

H - 4166 Barota To Neru Khari 3.44178) km.Assandh

Work completed on 12/12/2012.39322 20-Dec-12

GSB in progress, likely date of completion 31.12.12.36634 30-Oct-12

A/A Rs. 59.52 lacs on 10.8.2012. Work allotted to harjeet singh const. on 21.08.2012.

30089 20-Aug-12

Work Plan: 400m (Barota Phirni) GSB+pavers; in rest 75mm WBM+ PC (EC 54 lacs).

9205 07-Oct-11

Constructed 04/2002. Crust 150mm. Path 5 karam.9204 07-Oct-11

H - 4167 Aungad To Katlehri 2.96179) km.Assandh

Repair of berms to be done under MGNREGA scheme.37127 08-Nov-12

Patchless.14974 16-Nov-11

Constructed 6/2002. Patches + PC done in 01.2010, Path-5karam, Crust-150 mm

8662 07-Oct-11

H - 4170 Anchla To Bansa 4.66180) km.Assandh

Work completed on 15/12/2011.16703 03-Jan-12

75 mm WBM + PC (Rs. 46.11 lacs) sanctioned on 15/10/2010. Awarded to S.K const. on 8/8/2011. Completed upto WBM.

14943 16-Nov-11

Constructed 6/2002. Crust 150mm. Path 5 & 7 Karam.14514 15-Nov-11

H - 4171 Dera Chasam Pal Nain Upto Other Scarratted House 0.74181) km.Assandh

Work completed on 15/12/2011.16704 03-Jan-12

75 mm WBM + PC (Rs. 7.37 lacs) sanctioned on 15/10/2010. Awarded to S.K const. on 8/8/2011. Material supplied.

14944 16-Nov-11

Constructed 11/2003. Crust 150mm. Path 3 Karam.14515 15-Nov-11

H - 4172 Neru Kheri To Dadupur 1.47182) km.Assandh

Work completed on 30.09.2012.36635 30-Oct-12

A/A on 16.07.2012 for Rs. 17.46 lacs. Work allotted on 16/7/2012 (S.K. Traders).

29962 20-Aug-12

Work Plan: 75mm WBM+PC (EC 18 lacs).9207 07-Oct-11

Constructed 04/2004. Crust 150mm. Path 5 karam.9206 07-Oct-11

Assandh

Tuesday, April 02, 2013 Page 29 of 65

Page 30: Karnal Distt. Link Roads

H - 4173 Neru Kheri To Jani 2.78183) km.Assandh

(343 sqm) patches done 31/10/2011 to 27/12/2011 (65 K).16668 02-Jan-12

Patches awarded. (EC. 1.22 lacs).9209 16-Nov-11

Constructed 07/2008. Crust 150mm WBM. Path 4, 5 Karam.9208 07-Oct-11

H - 4174 Bansa To Jundla 4.59184) km.Assandh

(953 sqm) patches done 31/10/2011 to 27/12/2011 ( 184 K).16669 02-Jan-12

Patches awarded. (EC 2.02 lacs).9211 16-Nov-11

Constructed 01/2007. Crust 150mm. Path 5, 6 Karam.9210 07-Oct-11

H - 4175 Pucca Khera To Bansa 4.69185) km.Assandh

Repair of berms work partly complete under MGNREGA scheme.37125 08-Nov-12

Constructed 11/2008. Crust 225mm. (340 sqm) patches done 9/08/2011 to 13/08/2011 (2 K). No patch.

9101 07-Oct-11

H - 4176 Jalala Veeran To Behlolpur 3.05186) km.Assandh

Road is Patchless.21908 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19131 18-Feb-12

Patches awarded. (EC 1.30 lacs).9435 16-Nov-11

Constructed 03/2009. Crust 225mm. Path 5 Karam.9434 07-Oct-11

H - 4179 Manjura To Katlehri 4.95187) km.Assandh

Patchless.14975 16-Nov-11

Completion 28-Oct-2009. No SR done, Path-5 & 6karam, Crust-225 mm, Assandh Constituency

8667 07-Oct-11

H - 4180 Pangala To Vill. Bakal 5.45188) km.Assandh

Constructed 7/2009. Crust 225mm. (340.65 sqm) patches done 15/08/2011 to 19/08/2011 (72 K). No patch.

9102 07-Oct-11

H - 4181 Tharwa To Padha 5.20189) km.Assandh

(1165 sqm) patches done 31/10/2011 to 27/12/2011 ( 218 K).16670 02-Jan-12

Patches awarded. (EC 2.29 lacs).9213 16-Nov-11

Constructed 12/2009. Crust 225mm. Path 5, 6, 7 Karam.9212 07-Oct-11

H - 4182 Jalmana To Kabulpur Khera 2.86190) km.Assandh

(577 sqm) patches done 31/10/2011 to 27/12/2011 (121 K).16671 02-Jan-12

Patches awarded. (EC 1.26 lacs).9215 16-Nov-11

Constructed 05/2010. Crust 225mm. Path 5 Karam.9214 07-Oct-11

H - 4184 Thal To Mund 2.45191) km.Assandh

Patchless.14976 16-Nov-11

Completion 10-June-2010. No SR done, Path-5karam, Crust-225 mm.

8668 07-Oct-11

H - 4185 Birachpur To Jani 1.93192) km.Assandh

Tuesday, April 02, 2013 Page 30 of 65

Page 31: Karnal Distt. Link Roads

Constructed 3/1997. Crust 150mm. PC (entire) done 1/2010. (159.40 sqm) patches done 8/08/2011 to 11/08/2011 (32 K). No patch.

9104 07-Oct-11

H - 4186 Birachpur Budanpur 2.84193) km.Assandh

Repair of berms to be done under MGNREGA scheme.37126 08-Nov-12

Constructed 5/2001. Crust 150mm. PC(entire) done 1/2010. (234.30 sqm) patches done 8/08/2011 to 10/08/2011 (24 K). No patch.

9105 07-Oct-11

H - 4195 Kaimla To Barsat 4.65194) km.Gharaunda

Constructed 8/1992. Crust 150mm. 75mm WBM+PC (entire) done 1/2010. (210.25 sqm) patches done 27/08/2011 to 29/08/2011 (49 K). No patch.

9106 07-Oct-11

H - 4196 Dinger Majra To Kaimla 1.91195) km.Gharaunda

Road is Patchless.21909 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19132 18-Feb-12

Patches yet to be awarded. (EC 84 K)9219 16-Nov-11

Constructed 09/1993. Crust 150mm . PC done in 05/2004. Path 4 Karam.

9218 07-Oct-11

H - 4199 Kalheri To Jamalpur 1.69196) km.Gharaunda

Patchless.14977 16-Nov-11

Constructed 12/1993. Crust 150mm. Path 5 karam. PC done in 01/2010.

14441 15-Nov-11

H - 4200 Garhi Baral To Rana Majra 3.73197) km.Gharaunda

Work completed on 12/12/2012.39323 20-Dec-12

A/A on 14.08.2012 for Rs. 36.06 lacs. Work allotted to S.K const. on 21.08.2012.

30092 20-Aug-12

Work Plan: 530m (Rana Majra Phirni ) GSB+pavers; in rest patches (EC 32 lacs).

9223 07-Oct-11

Constructed 03/1999. Crust 150mm. Path 5 karam. PC done in03/2008.

9222 07-Oct-11

H - 4201 Malikpur To Gadian To Panori 2.31198) km.Gharaunda

A/A on 15.06.2012 for Rs. 18.51 lacs. work allotted on 20.06.2012 to S.K contractor.

29949 20-Aug-12

Work completed.30071 20-Aug-12

Work Plan: Patches+PC in entire length (EC 16 lacs)9225 07-Oct-11

Constructed 04/1994. Crust 225mm. Path 4 karam. 75mm WBM+PC in entire length done in 04/2005.

9224 07-Oct-11

H - 4202 Hassanpur To NGM Gharuanda 3.44199) km.Gharaunda

Road is Patchless.21910 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19133 18-Feb-12

Patches yet to be awarded. (EC. 1.51 lacs)9227 16-Nov-11

Tuesday, April 02, 2013 Page 31 of 65

Page 32: Karnal Distt. Link Roads

Constructed 03/1994. Crust 150mm . PC done in 03/2008. Path 4 Karam.

9226 07-Oct-11

H - 4203 Chora Gharuanda To N.G.M. Ghd 1.28200) km.Gharaunda

Work completed on 25.09.2012.36640 30-Oct-12

A/A on 17.07.2012 for Rs. 2.63 lacs. 29974 20-Aug-12

Work allotted on 28.07.2012 to Aman Const. co. 30046 20-Aug-12

Work Plan: Heavy Patchwork (EC 2 lacs)9229 07-Oct-11

Constructed 04/1994. Crust 150mm. Path 5 karam. PC done in 01/2010.

9228 07-Oct-11

H - 4205 Shekhupura To Khora Kheri 4.36201) km.Gharaunda

Constructed 8/1995. Crust 150mm. CC (0.360 km) + PC (4.00 km) done 2/2010. (287.59 sqm) patches done 23/08/2011 to 25/08/2011 (64 K). No patch.

9107 07-Oct-11

H - 4206 Kaimla To Pundri 3.38202) km.Gharaunda

Constructed 2/1995. Crust 150mm. PC (entire) done . 1/2010. (82.33 sqm) patches done 25/08/2011 to 27/08/2011 (20 K). No patch.

9108 07-Oct-11

H - 4208 Dinger Majra Road To Shamshanghat 0.33203) km.Gharaunda

Patchless.14978 16-Nov-11

Constructed 1/1998. Crust 150mm. Path 5 karam. PC done in 3/2008.

14442 15-Nov-11

H - 4210 Garhi Baral To Dera Kashyap 0.27204) km.Gharaunda

Patchless.14979 16-Nov-11

Constructed 9/1998. Path 5 Karam. Crust 150mm. PC done on 3/2008.

14486 15-Nov-11

H - 4213 Bijna To Samalkha 2.09205) km.Gharaunda

Work completed on 30.09.2012.36643 30-Oct-12

A/A on 17.07.2012 for Rs. 5.53 lacs. 29982 20-Aug-12

work Allotted on 24.07.2012 to Aman const. co. 30043 20-Aug-12

Constructed 5/1999. Crust 150mm. Path 5 karam. S/R done in 3/2008.

14202 15-Nov-11

Work Plan:100m (Bijna Phirni ) GSB+pavers; (EC. 5 lacs). Rest is Patchless.

9671 10-Oct-11

H - 4215 Harizan Basti To Shamshanghat At Dinger Majra 0.58206) km.Gharaunda

Patchless.14980 16-Nov-11

Constructed 5/2000. Path 5 Karam. Crust 150mm. PC done on 1/2010.

14487 15-Nov-11

H - 4216 Kalehri To Pundri 3.23207) km.Gharaunda

Constructed 10/2000. Crust 150mm. PC (entire) done 1/2010. (180.90 sqm) patches done 25/08/2011 to 27/08/2011 (47 K). No patch.

9110 07-Oct-11

Tuesday, April 02, 2013 Page 32 of 65

Page 33: Karnal Distt. Link Roads

H - 4217 Garh Sarnai To Pundri 2.38208) km.Gharaunda

Constructed 11/2000. Crust 150mm. CC (0.178 km) + PC (2.20 km) done 10/2009. (145.11 sqm) patches done 25/08/2011 to 27/08/2011 (38 K). No patch.

9111 07-Oct-11

H - 4218 G.T.Road To Garhi Multan 1.76209) km.Gharaunda

Patchless.14981 16-Nov-11

Constructed 1/2001. Path 5 Karam. Crust 150mm. PC done on 1/2010.

14488 15-Nov-11

H - 4219 Shekpura To Shiv Mandir 2.26210) km.Gharaunda

Patchless.14982 16-Nov-11

Constructed 11/2001. Path 5 Karam. Crust 150mm. PC done on 1/2010.

14489 15-Nov-11

H - 4221 Munak Road Staundi To Vet. Hospitial 0.47211) km.Gharaunda

Patchless.14983 16-Nov-11

Constructed 1/2001. Path 4 Karam. Crust 150mm. PC done on 1/2010.

14490 15-Nov-11

H - 4222 Raipur Jattan To Badshahpur 1.05212) km.Gharaunda

Patchless.14984 16-Nov-11

Constructed 12/2001. Path 5 Karam. Crust 150mm. 14491 15-Nov-11

H - 4223 Dadlana School To Bus Stand 0.42213) km.Gharaunda

Concrete intact.14985 16-Nov-11

Constructed 9/2001. Path 4 Karam. Crust 150mm. Later on CC laid by Gram Panchayat on entire length.

14492 15-Nov-11

H - 4224 Gagsina To Kapron 2.86214) km.Gharaunda

Constructed 12/2001. Crust 150mm. PC(entire) done 1/2010. (198.05 sqm) patches done 26/08/2011 to 28/08/2011 (44 K). No patch.

9112 07-Oct-11

H - 4225 Staundi To Picholiya 4.63215) km.Gharaunda

Work complete on 30.09.2012.36587 30-Oct-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost of Sh. Vipin Malik.

21930 03-Apr-12

75 mm WBM + PC (Rs. 45.87 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Not started, Tender at risk & cost on 8/12/2011.

14945 16-Nov-11

Constructed 12/2002. Crust 150mm. Path 5 Karam.14493 15-Nov-11

H - 4226 Saini Wala Mandir To Barsat 0.65216) km.Gharaunda

Patchless.14986 16-Nov-11

Constructed 4/2002. Crust 150mm. Path 3 Karam.14494 15-Nov-11

H - 4227 Alipur Kalsa To Khotpura 3.90217) km.Gharaunda

Tuesday, April 02, 2013 Page 33 of 65

Page 34: Karnal Distt. Link Roads

Sh. Sushil Kr, JE reported that Actual length is 3.90 instead of 3.09.29501 16-Aug-12

Constructed 1/2002. Crust 150mm. CC (0.05 km ) + PC (3.04 km ) done 1/2010. (213.75 sqm) patches done 26/08/2011 to 28/08/2011 (52 K). No patch.

9113 07-Oct-11

H - 4229 Panori To Gharaunda 4.30218) km.Gharaunda

Road is Patchless.21911 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19134 18-Feb-12

Patches yet to be awarded. (EC 1.89 lacs)9239 16-Nov-11

Constructed 03/2002 . Crust 150mm . CC in Gharaunda side RD4193 to 4300m+PC done in 02/2010. Path 5 Karam.

9238 07-Oct-11

H - 4230 Bastara To Kutail 3.16219) km.Gharaunda

Work completed on 30.08.2012.36588 30-Oct-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost.21933 03-Apr-12

75 mm WBM + PC (Rs. 31.13 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Some material supplied, but work Tender at risk & cost on 8/12/2011.

14946 16-Nov-11

Constructed 7/2002. Crust 150mm. Path 5 Karam.14495 15-Nov-11

H - 4231 Kalram To Bastara 2.56220) km.Gharaunda

Work completed on 15.09.2012.36589 30-Oct-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost.21935 03-Apr-12

75 mm WBM + PC (Rs. 25.22 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Not started, Tender at risk & cost on 8/12/2011.

14947 16-Nov-11

Constructed 9/2002. Crust 150mm. Path 5 Karam.14496 15-Nov-11

H - 4232 Shahjanpur To Munak Khora Kheri Road 2.59221) km.Gharaunda

Work completed on 15.10.2012.36590 30-Oct-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost.21936 03-Apr-12

75 mm WBM + PC (Rs. 26.11 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Not started, Tender at risk & cost on 8/12/2011.

14948 16-Nov-11

Constructed 6/2002. Crust 150mm. Path 5 Karam.14497 15-Nov-11

H - 4233 Muank Kheri To Gagsina Anchla Road 1.37222) km.Gharaunda

Work completed on 15.10.2012.36644 30-Oct-12

AA for Rs. 10.64 lacs on 23.08.12 & work awarded to S.K const. on 29.08.12.

32346 04-Sep-12

Work Plan:WBM patches+ PC in entire (EC 9 lacs).9241 07-Oct-11

Constructed 11/2002. Crust 150mm. Path 5 karam.9240 07-Oct-11

H - 4234 Ghari To Belhera 0.15223) km.Gharaunda

work completed by PWD B&R.30118 20-Aug-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost.21938 03-Apr-12

75 mm WBM + PC (Rs. 1.50 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Not started, Tender at risk & cost on 8/12/2011.

14949 16-Nov-11

Tuesday, April 02, 2013 Page 34 of 65

Page 35: Karnal Distt. Link Roads

Constructed 6/2003. Crust 150mm. Path 5 Karam.14498 15-Nov-11

H - 4235 App. Road To Mundi Garhi 0.80224) km.Gharaunda

Work completed on 15.10.2012.36591 30-Oct-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost.21939 03-Apr-12

75 mm WBM + PC (Rs. 23.83 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Some material supplied, but work Tender at risk & cost on 8/12/2011.

14950 16-Nov-11

Constructed 6/2003. Crust 150mm. Path 4 Karam.14499 15-Nov-11

H - 4236 Barsat To Village Behlolpur 1.76225) km.Gharaunda

Work completed on 15.09.2012.36592 30-Oct-12

Work allotted on 5/3/2012 (M/s S.K. Construction Co.) at risk & cost. Work not started.

21940 03-Apr-12

75 mm WBM + PC (Rs. 17.54 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Not started, Tender at risk & cost on 8/12/2011.

14951 16-Nov-11

Constructed 5/2003. Crust 150mm. Path 5 Karam.14500 15-Nov-11

H - 4237 Gagsina To Picholiya Head 3.44226) km.Gharaunda

Work completed on 15/10/2012.36593 30-Oct-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost.21941 03-Apr-12

75 mm WBM + PC (Rs. 33.49 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Not started, Tender at risk & cost on 8/12/2011.

14952 16-Nov-11

Constructed 2/2003. Crust 150mm. Path 3 Karam.14501 15-Nov-11

H - 4238 Begam Pur To Dera Nishan Singh 1.78227) km.Gharaunda

Work complete on 28.10.2012.36645 30-Oct-12

AA on 7/9/2012 for Rs. 17.77 lacs. Tender approved.32422 10-Sep-12

T/Approved, tenders on 21.06.201223866 22-May-12

Work Plan: RD0 to 1000m 75mm WBM ; in rest patches+PC in entire length (EC 18 lacs).

9243 07-Oct-11

Constructed 11/2003. Path 5 karam. Crust 150mm .9242 07-Oct-11

H - 4241 Lalupur Bridge Via Embenkment 2.80228) km.Gharaunda

Work completed on 30.09.2012.36594 30-Oct-12

Tender allotted on 5.3.2012 (M/s S.K. Contractor) at risk & cost.21943 03-Apr-12

75 mm WBM + PC (Rs. 27.82 lacs) sanctioned on 15/10/2010. Awarded to Vipin Malik cont. on 20/5/2011. Not started, Tender at risk & cost on 8/12/2011.

14953 16-Nov-11

Constructed 4/2004. Crust 150mm. Path 4 Karam.14502 15-Nov-11

H - 4242 Staundi To Bijna 2.96229) km.Gharaunda

Road is Patchless.21912 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19135 18-Feb-12

Patches yet to be awarded. (EC 1.30 lacs)9249 16-Nov-11

Constructed 06/2004. Crust 150mm. Path 5 Karam.9248 07-Oct-11

Tuesday, April 02, 2013 Page 35 of 65

Page 36: Karnal Distt. Link Roads

H - 4245 Begampu/ Refinery Town Ship Dadlana 0.86230) km.Gharaunda

Road is Patchless.21913 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19136 18-Feb-12

Patches yet to be awarded. (EC 38 K)9251 16-Nov-11

Constructed 05/2009. Crust 225mm. Path 3 Karam.9250 07-Oct-11

H - 4248 Subri To Karnal Kujpura Road 2.70231) km.Gharaunda

Repair of berms to be done under MGNREGA scheme.37143 08-Nov-12

Work completed on 15.10.2012.36646 30-Oct-12

A/A on 17.07.2012 for Rs. 5.07 lacs. 29980 20-Aug-12

Work Allotted on 28.07.2012 to Harjeet Singh. 30052 20-Aug-12

Work Plan: Heavy patchwork (EC 4 lacs).9253 07-Oct-11

Constructed 03/1994. Crust 150mm. Path 4 & 6 karam. CC in RD0 to 315m (Subri Phirni)+PC done in 03/2008.

9252 07-Oct-11

H - 4249 Kalweri To Newal 1.83232) km.Gharaunda

Work completed on 15.10.2012.36648 30-Oct-12

A/A on 17.07.2012 for Rs. 3.97 lacs. 29977 20-Aug-12

Work Allotted on 28.07.2012 to Harjeet Singh. 30053 20-Aug-12

Work Plan: Heavy patchwork (EC 3 lacs).9255 07-Oct-11

Constructed 03/1997. Crust 150mm. Path 4 karam. PC done in 12/2007.

9254 07-Oct-11

H - 4250 App.Road To Vill.Mehmodpur 0.61233) km.Gharaunda

Patchless.14987 16-Nov-11

Constructed 4/2001. Crust 150mm. Path 4 Karam. PC done in 30/4/2007.

14503 15-Nov-11

H - 4251 Nai Chundipur To Purani Chundipur 0.98234) km.Gharaunda

AA on 7/9/2012 for Rs. 11.92 lacs. Work allotted on 24.09.2012 (S.K Const. Co. ), Work completed on 23/12/2012.

36649 30-Oct-12

Work Plan: Patches. Overlay with 75mm WBM + PC. Both to be done one after other. (EC 11 lacs).

9257 07-Oct-11

Constructed 12/2003. Crust 150mm. Path 5 karam.9256 07-Oct-11

H - 4253 Mohidin Pur To Rasulpur 2.49235) km.Gharaunda

AA on 7/9/2012 for Rs. 30.05 lacs. Work allotted on 24.09.2012 (SK cost. Co.), work completed on 23/12/2012.

36652 12-Feb-13

Work Plan: Patches. Overlay with 75mm WBM + PC. Both to be done one after other. (EC 31 lacs).

9259 07-Oct-11

Constructed 08/2004. Crust 150mm. Path 5 & 9 karam.9258 07-Oct-11

H - 4256 Gogripur To Kheri Naru 3.32236) km.Gharaunda

(263 sqm) patches done 31/10/2011 to 27/12/2011 ( 50 K).16672 02-Jan-12

Patches yet to be awarded. (EC 60 K).9261 16-Nov-11

Tuesday, April 02, 2013 Page 36 of 65

Page 37: Karnal Distt. Link Roads

Constructed 03/1992. Crust 150mm . CC 135m (Kheri Naru pirni)+PC done in 01/2010. Path 4, 5 Karam.

9260 07-Oct-11

H - 4258 Bajida Jattan To Gogripur 1.59237) km.Gharaunda

Work completed on 27.09.2012.36654 30-Oct-12

A/A on 17.07.2012 for Rs. 1.45 lacs. 29971 20-Aug-12

work allotted on 28.07.2012 to Harjeet Singh. 30054 20-Aug-12

Work Plan: Patches (EC. 1.10 lacs).9263 07-Oct-11

Constructed 04/1994. Crust 150mm. Path 4 & 6 karam. PC done in 03/2004.

9262 07-Oct-11

H - 4259 Bhuslli To Kharkalil 2.20238) km.Gharaunda

Work completed on 25.10.2012.36656 30-Oct-12

A/A on 16.07.2012 for Rs. 24.58 lacs. 29964 20-Aug-12

Work allotted on 16.07.2012 to S.K Contractor. 30028 20-Aug-12

Work Plan:75mm WBM+PC in entire length. (EC 20 lacs)9265 07-Oct-11

Constructed 1994. Crust 150mm. Path 4 karam. PC done in 08/2004.9264 07-Oct-11

H - 4260 Sohana To Sector -6 0.75239) km.Gharaunda

Work completed on 21.10.2012.36595 30-Oct-12

75 mm WBM + PC (Rs. 35.43 lacs) sanctioned on 15/10/2010. Allotted on 9/8/2011 (Harjit).

14954 16-Nov-11

Constructed 1/1995. Crust 150mm. Path 5 Karam. CC (in Phirni) & Patch + PC in 8/2007.

14504 15-Nov-11

H - 4262 Kambopura To Uncha Samana 2.80240) km.Gharaunda

Work completed on 25.10.2012.36657 30-Oct-12

work allotted on 16.07.2012 to Harjeet Singh. 30027 20-Aug-12

A/A on 16.07.2012 for Rs. 32.25 lacs. 29965 20-Aug-12

Work Plan: 75mm WBM+PC in entire length. (EC 25 lacs)9267 07-Oct-11

Constructed 08/1994. Crust 150mm. Path 5 karam. PC done in 03/2004.

9266 07-Oct-11

Earth mining by SOMA company.14520 05-Oct-11

H - 4265 Approach Road Of Sports Stadium Village Bastara 0.34241) km.Gharaunda

Work completed on 25.09.2012.36658 30-Oct-12

A/A on 17.07.2012 for Rs. 1.30 lacs. Work allotted on 28.07.2012 to Harjeet Singh.

29968 20-Aug-12

Work Plan: Heavy Patchwork (EC 1 lacs).9271 07-Oct-11

Constructed 07/2009. Crust 225mm. Path 5 karam.9270 07-Oct-11

H - 4266 Appraoch Road To Sports Stadium Gagsina 0.11242) km.Gharaunda

Patchless.14988 16-Nov-11

Constructed 12/2009. Crust 225mm. Path 5 Karam. 14505 15-Nov-11

H - 4267 Metaling Of Ramp Of Western Yamuna Main Branch In Gogripur To Munak Road

0.15243) km.Gharaunda

Tuesday, April 02, 2013 Page 37 of 65

Page 38: Karnal Distt. Link Roads

Patchless.14989 16-Nov-11

Constructed - 2010. Crust 225mm. Path irrigation Deptt. Land14506 15-Nov-11

H - 4680 Ballah To Padha 5.65244) km.Assandh

A/A granted on 20.08.09 for Rs. 11.34 lacs allotted on 24.12.09 to agency Sh. Prabhu Dayal.

21950 04-Apr-12

Work completed on 31.03.1222021 04-Apr-12

H - 4686 Anchla To Village Kheri Munak 2.12245) km.Assandh

Work completed on 20.10.2012.34288 31-Oct-12

Work allotted on 25/7/2012 (S.K. Trader). Likely completion 30/9/2012.

27599 03-Aug-12

Action under clause II & III taken final measurment awaited. Tender to be called soon.

16546 02-Jan-12

A/A on 13.08.09 for Rs. 41.03 lacs. Path 5 & 6 K .Crust 225mm. Allotted on 24.12.09 to Mohan Kumar. WBM completed, painting road surface in 1.5 Km. completed. Likely completion by 15/12/2011.

9731 16-Nov-11

H - 4692 Dakwala Roran To Meerut Road 3.04246) km.Gharaunda

Completed on 30.11.2011. Bill finalled.19070 18-Feb-12

A/A on 11.06.09 for Rs. 59.81 lacs. Path 5 &6 K .Crust 225mm. Allotted on 24.12.09 to Deepak Ghai. Work upto WBM completed. Painting in 1 Km. completed. . Likely completion by 30.11.11

9737 12-Oct-11

H - 4694 Baragoan To Makhu Majra 2.37247) km.Indri

Completed 30.11.2011.19072 18-Feb-12

A/A on 12.08.09 for Rs. 43.36 lacs. Path 11 & 5 Karam. Crust 225mm. Allotted on 24.12.09 to Chopra Constn. Co; 1st Coat painting completed. Likely date of completion 30.11.11.

9739 12-Oct-11

H - 5041 Kheri Munak To Gagseena Anchla Road-II 0.80248) km.Gharaunda

Work completed on 25.10.2012.36659 30-Oct-12

A/A for Rs. 6.11 lacs on 17.08.12 & work awarded to S.K contractor.32379 04-Sep-12

Work Plan: Patches +PC in entire length (EC 8 lacs)9273 07-Oct-11

Constructed 03/2004. Crust 150mm. Path 5, 7 Karam.9272 07-Oct-11

H - 5042 Dera Balbir Singh To Dera Sahib Singh 0.50249) km.Assandh

Patchless.14990 16-Nov-11

Constructed 4/2009. No SR done, Path-5karam, Crust-225 mm, width-5.49m

8664 07-Oct-11

H - 5043 Const. Of Road From Arya Samaj Mandir To Pingli Road (Main Phirni Of Vill. Goghripur)

0.87250) km.Gharaunda

Patchless.14991 16-Nov-11

Completion-2 july-2010, No SR done, Path-5karam, Crust-150 mm, width-5.49m

8665 07-Oct-11

H - 5099 Pangala To P.C. Rahra 2.66251) km.Assandh

Tuesday, April 02, 2013 Page 38 of 65

Page 39: Karnal Distt. Link Roads

Bill not finalled dueto H-468141573 04-Mar-13

Work completed on 25/7/2012 except berms.29094 08-Aug-12

Pulled EE that why he delayed PC work. EE assures work will be completed by 20/7/2012.

26653 10-Jul-12

A/A on 20.08.09 for Rs. 50.15 lacs, path 5 & 6 karam, crust 225mm. Allotted on 09.11.09 to Prabhu Dayal.

21954 04-Apr-12

H - 5206 Nasirpur To Kunda Kalan 2.37252) km.Indri

Patchless.14992 16-Nov-11

Constructed 2/2009. No SR done, Path-4 & 8karam, Crust-225 mm, width-5.49m

8666 07-Oct-11

H - 5207 Phirni Portion Of Vill. Bajida Jattan 0.41253) km.Gharaunda

A/A on 15.06.2012 for Rs. 18.34 lacs. Work allotted on 20.06.2012 to Rajesh contractor.

29948 20-Aug-12

Work Plan: 410m (Bajida Jattan ) GSB+pavers (EC 20 lacs). DE cost is 18.35 lacs.

9275 07-Oct-11

Constructed 1991. Crust 225mm. Path 5 & 4 karam. PC done in 07/2004.

9274 07-Oct-11

H - 5209 Road Leading To Kutail 0.75254) km.Gharaunda

Work completed.32384 04-Sep-12

A/A on 15.06.2012 for Rs. 33.43 lacs. 29956 20-Aug-12

0.40km completed. 29938 20-Aug-12

Work allotted on 20/6/2012.29052 27-Jul-12

Work Plan: GSB+pavers in entire. (EC 37 lacs).9277 07-Oct-11

Constructed by Market Committee during 1982. Crust 150mm. Path 5 Karam. PC done in 02/2004. The road is Kutali Phirni.

9276 07-Oct-11

H - 5744 Lathron to Sikri 1.45255) km.Nilokheri (SC)

Work completed on 30/9/2012.36217 21-Oct-12

Work completed except cc in phirni portion (350 m).31856 23-Aug-12

350 m CC in Lathron, 75 mm jWBM + PC in 1100m (RS. 20.55 lacs) sanctioned on 15/10/2010. Awarded to Harjit cont. on 9/8/2011. 1.45 WBM completed.

31819 23-Aug-12

Constructed 06/2002. Crust 150mm WBM.14516 15-Nov-11

616.38 km. Sub Total:

Maintained by PWD

H - 4239 Barana To Garhi Basak 4.131) km.Gharaunda

PWD road ID 2513.19086 18-Feb-12

Work Plan:Under PMGSY by PWD(B&R).9245 07-Oct-11

Constructed 30/2004. Crust 150mm. Path 5 karam. Later on road widened to 5.49m under PMGSY by PWD(B&R).

9244 07-Oct-11

4.13 km. Sub Total:

Old SR - Unawarded

Indri

Tuesday, April 02, 2013 Page 39 of 65

Page 40: Karnal Distt. Link Roads

H - 3949 Ramba To Kheri Man Singh 2.221) km.Indri

Tender received on 26/2/2013 & under process in HO.42688 15-Mar-13

A/A accorded for Rs. 16,23,600/- on 08.01.2013.39794 08-Jan-13

Constructed 12/2002. Crust 150mm. 75mm WBM + PC (entire) done 2/2010. (281.11sqm) patches done 30/08/11 to 4/09/2011 (56 K ). No patch.

9081 07-Oct-11

2.22 km. Sub Total:

Ordinary repairs required / ongoing

H - 3922 Karnal Garhi Birbal Road To Kalsora Japti Chhapra Road Via Govt. High School

0.711) km.Indri

Repair of berms to be done under MGNREGA scheme.37139 08-Nov-12

In RD 140 to 500m (Phirni of Kalsora) water is reported to be coming on road.

20563 02-Mar-12

Constructed 11/1999. Crust 150mm. CC(140 m) + PC (570 m) done in 3/2008. (47.32sqm) patches done during 2/09/2011 to 6/09/2001 (10 k) . No patch.

9076 07-Oct-11

H - 6807 G.T. Road to Malikpur 2.502) km.Gharaunda

On 16.1.2013, DC, Karnal demanded the patch work.40396 06-Feb-13

Constructed by PWD as a deposit work of IOC as onetime development work as social obligation to people of area. Path 4 karam. Crust 225mm (150mm by PWD + 75mm by HSAMB on 28/11/2012). Hon'ble CM has directed vide note dt. 23.12.2012 to be taken up by HSAMB.

40393 05-Feb-13

3.21 km. Sub Total:

Work Plan - Awarded

H - 3904 Nandi To P.C.Ghari Birbal 3.061) km.Indri

Work upto WBM completed. Likely date of completion 7/4/2013.32414 15-Mar-13

Repair of berms to be done under MGNREGA scheme.37140 08-Nov-12

AA on 7/9/2012 for Rs. 35.51 lacs. Work allotted on 12.10.12 ( S.K Const. Co.), work not started yet.

36599 30-Oct-12

Work Plan:75mm WBM+PC in entire length.(EC. 33 lacs).9283 07-Oct-11

Constructed- 1994, Path- 5 Karam, Crust-150mm, Patch + PC in 07/2006 in entire length. Road falls in Yamuna Belt and damaged due to traffic diversion in 7/10 to 9/10.

8482 04-Oct-11

H - 3944 Chhaper To Bhoot Majra 1.842) km.Indri

Work upto metalling completed. Likely to be completed upto 15/4/2013.

40772 15-Mar-13

Repair of berms to be done under MGNREGA scheme.37135 08-Nov-12

AA on 7/9/2012 for Rs. 21.03 lacs. Work allotted on 24.09.2012 (S.K const. Co.)

36603 30-Oct-12

Work Plan:75mm WBM+PC in entire length (EC. 19 lacs).9307 07-Oct-11

Constructed 05/2004. Crust 150mm. Path 4 karam.9306 07-Oct-11

H - 3954 Darar To Bara Gaon 4.823) km.Indri

Tuesday, April 02, 2013 Page 40 of 65

Page 41: Karnal Distt. Link Roads

WBM completed. likely date of completion 15.4.2013.36605 15-Mar-13

A/A for Rs. 57.84 on 17.08.12 , work alloted on 17.08.12 to bath co-op society.

32284 04-Sep-12

Work Plan:75mm WBM+PC in entire length (EC. 53 lacs).9315 07-Oct-11

Constructed 06/2004. Crust 150mm. Path 5 karam.9314 07-Oct-11

H - 3958 Uchani To Indri Road 0.664) km.Indri

PC left & likely to be completed by 7/4/2013.40773 15-Mar-13

AA for Rs. 18.03 lacs on 23.08.12,work awarded on 24.08.12 to Kamal cont.co.

32285 04-Sep-12

Work Plan:255m (Uchani Phirni) GSB+pavers; in rest 75mm WBM+ PC in entire length (EC. 17lacs).

9319 07-Oct-11

Constructed 04/2004. Crust 150mm. Path 4 karam.9318 07-Oct-11

H - 3960 Abdulapur To Kurali 1.535) km.Indri

Paver block completed. WBM + PC left, likely date of completion 31/3/2013.

36607 12-Feb-13

A/A on 23.07.2012 for Rs. 43.46 lacs.29942 20-Aug-12

Work allotted to Rajesh const. co. on 24.07.201230064 20-Aug-12

Work Plan:495m (Kurali Phirni RD0 to 495m)) GSB+pavers; In 47m 6' high R/W (RD 315 to 362m) in phirni Kurali: in rest 75mm WBM+PC (EC. 38 lacs).

9321 07-Oct-11

Constructed 10/2004. Crust 150mm. Path 4 karam.9320 07-Oct-11

H - 4007 Singra To Jalala Veeran 4.346) km.Nilokheri (SC)

PC left & likely to be completed by 31/3/2013.42691 15-Mar-13

Work started by the agency (The Bath Co.Op L&C Society) on 18.10.12.

36218 21-Oct-12

Work Plan: Heavy patchwork (EC. 4 lacs). A/A on 17.07.2012 for Rs. 7.02 lacs.

31871 23-Aug-12

Constructed 05/2005. Crust 150mm. Path 5 karam.9350 07-Oct-11

H - 4021 Nidana To Kurak 2.507) km.Nilokheri (SC)

PC work left. Likely to be completed upto 7/4/2013.36612 15-Mar-13

Constructed 03/1994. Crust 150mm. Path 5 karam. PC done in 06/2005.

9368 07-Oct-11

H - 4135 Bye Pass To Vill. Salwan 0.968) km.Assandh

Paver block in progress. WBM + PC left. Likely date of completion 7/4/2013.

32324 15-Mar-13

Work allotted on 21.08.2012 to harjeet const. co. A/A on 20/08/2012 for Rs. 46.92.

30084 20-Aug-12

Work Plan:760m (Salwan Phirni) GSB+pavers; in rest PC. (EC 40 lacs).

9169 07-Oct-11

Constructed 11/2004. Crust 150mm. Path 5 Karam.9168 07-Oct-11

H - 4193 Bastara To N.G.M At Gharuanda 2.469) km.Gharaunda

AA on 5/01/2013 for Rs. 28.36 lacs. Work allotted on 16/1/2013. WBM work completed. Likely date of completion 15/4/2013.

40009 15-Mar-13

Tuesday, April 02, 2013 Page 41 of 65

Page 42: Karnal Distt. Link Roads

Tender Case approved by EIC on 5/12/2012 & sent to CA for AA.39329 20-Dec-12

Constructed 07/1991. Crust 150mm. Path 5 karam. PC done in 05/2004.

9216 07-Oct-11

Work Plan:75mm WBM+PC (EC 30 lacs)9217 07-Oct-11

H - 4198 Kaimla To Kohand 2.3410) km.Gharaunda

AA on 5/1/2013 for Rs. 23.24 lacs. Work allotted on 16/1/2013. Stone metal & patches work completed. Likely date of completion 15/4/2013.

40010 15-Mar-13

Work Plan:120m (Towards Kohand Side RD 2220 to 2340m)GSB+pavers; in rest patches+PC in entire length (EC 24 lacs).

9221 07-Oct-11

Constructed 10/1993. Crust 150mm. Path 5 karam. 75mm WBM in 1730 mtr+PC done in 01/2006.

9220 07-Oct-11

H - 4204 Barana To Pundri 3.7711) km.Gharaunda

Paver block completed. WBM patch left. Likely date of completion 31/3/2013.

36642 15-Mar-13

Work alloted on 21.08.12 to S.K contractor A/A- 42.92 lac on 17.08.12.

32338 04-Sep-12

Work Plan:250m (Towards Vill. Pundri side ) GSB+pavers; in rest WBM Patches+ PC in entire length (EC 39 lacs).

9231 07-Oct-11

Constructed 10/1994. Path 5 karam. 75mm WBM+PC in entire length done in 02/2006. Mining belt. Crust 225mm.

9230 07-Oct-11

H - 4207 Amritpur To Lalupur 5.8012) km.Gharaunda

Paver block completed. WBM + PC left, likely date of completion 15/4/2013.

32339 15-Mar-13

A/A on 20.07.2012 for Rs. 44.84 lacs. Work allotted to Satish kumar on 24.07.2012.

30095 20-Aug-12

Work Plan:500m (Lalupur Phirni) GSB+pavers; 75mm WBM (RD 4000 to 5300m) + PC in 1300m, rest Patches (EC 40 lacs).

9233 07-Oct-11

Constructed 03/1997. Crust 150mm. Path 4 karam. PC done in 01/2007.

9232 07-Oct-11

H - 4209 Palheri To Faridpur 2.7513) km.Gharaunda

Work allotted on 30.10.12 (SK const. co.). Paver block & WBM completed. PC left. Likely date of completion 17/4/2013.

36668 15-Mar-13

Work Plan: 300m (towards Vill. Faridpur side) GSB+pavers; in rest 75mm WBM+PC (EC 42 lacs).

9235 07-Oct-11

Constructed 08/1998. Crust 150mm. Path 5 karam. PC done in 08/2006. Mining belt.

9234 07-Oct-11

36.83 km. Sub Total:

Work Plan - Unawarded

H - 4139 Dera Manpura To Assandh Road 3.201) km.Assandh

AA on 8/3/2013 for Rs. 3.02 lacs. Tender received on 11/1/13 & under process in Circle Office.

42695 15-Mar-13

Work not finalized.29025 27-Jul-12

T/Approved, tenders on 06.06.201223839 22-May-12

Tuesday, April 02, 2013 Page 42 of 65

Page 43: Karnal Distt. Link Roads

Work Plan: Patches (EC 3 lacs).9175 07-Oct-11

Constructed 09/2004. Path 5 karam. Execpt 300m length balance due to NOC not received from Irringation Department (Change of Alignment Service Road of Kurlan Minor). Crust 150mm WBM.

9174 07-Oct-11

H - 4240 Dadupur Rangran To Uncha Samana 2.892) km.Gharaunda

RCE for construction of bridge is under process in HO.42697 15-Mar-13

75mm WBM + PC is to be done after construction of Bridge.36809 05-Nov-12

Discussed with SE (Karnal), EE (Karnal) & SE (Road). The 75m WBM & PC in deferred till the Construction of Bridge. The road be patched. For bridge, Irrigation Deptt. to give cost WP is amended to that extend.

36806 05-Nov-12

Work Plan: RD1244 to 1339m Bridge to be constructed:75mm WBM + PC in rest (EC 60 lacs)

9247 07-Oct-11

Constructed 03/2004. Crust 150mm. Path 5 karam. Originally Bridge not provided by the Irrigation Deptt. In RD1244 to 1339m. RD0to 350m CC laid by Gram Panchayat.

9246 07-Oct-11

Earth mining by SOMA company.14519 05-Oct-11

6.09 km. Sub Total:

Transferred

Transferred to MC

H - 3968 G.T. Road To Baldi Via School 0.831) km.Indri

Constructed 12/1998. Path-5karam, Crust-225 mm. SR 31.12.09.8572 07-Oct-11

H - 3969 G.T. Road To Village Jhanjhari 0.322) km.Karnal

Completion-12 June-1995, Path-5karam, Crust-225 mm 8573 07-Oct-11

SR completed on 20.10.2009 with an exp. of Rs. 2.96 lacs2308 22-Aug-11

H - 3984 Jarifafarm To Uchana 2.363) km.Karnal

Constructed 12/1994. Path-5karam, Crust-225 mm. Patches + PC done in 2002. PC in 1/2010 (Expenditure 10.95 lacs).

8574 07-Oct-11

H - 3985 Phoosgarh To Sec-7 1.484) km.Karnal

Constructed 10/1993. Path-4karam, Crust-150 mm8575 07-Oct-11

SR completed on 20.12.2006 with an exp. of Rs. 6.90 lacs2307 22-Aug-11

H - 3989 Periphery Road To Village Baldi 0.645) km.Karnal

Constructed 12/1999. Path-3karam, Crust-150 mm.8576 07-Oct-11

SR completed on 29.01.2010 with an exp. of Rs. 6.532309 22-Aug-11

H - 3992 Sec-6 To Dera Prem Singh 0.646) km.Karnal

Constructed 10/2001. Path-4karam, Crust-225 mm8577 07-Oct-11

SR completed on 29.01.2010 with an exp. of Rs. 2.97 lacs2310 22-Aug-11

H - 4004 Nissing G.M. To Nissing- Gonder Road 1.107) km.Nilokheri (SC)

Tuesday, April 02, 2013 Page 43 of 65

Page 44: Karnal Distt. Link Roads

Constructed 1982. Path 6 Karam. Crust 150mm. 75mm WBM + PC done 12/2004.

14463 15-Nov-11

H - 4263 Phoosgarh To Shekhpura Sohana Road 1.358) km.Gharaunda

Transferred to MC on 1.6.2012.24439 01-Jun-12

Road is Patchless.21914 03-Apr-12

WBM patch done PC patch left likely date 31.032012.19137 18-Feb-12

Patches yet to be awarded. (EC 60 K)9269 16-Nov-11

Constructed 2001. Crust 150mm . Path 5 Karam.9268 07-Oct-11

H - 4270 Daha To Madanpur 2.189) km.Gharaunda

Constructed 9/1995. Path-4karam, Crust-150 mm. PC done in 5/2006.

8578 07-Oct-11

H - 4271 Madanpur To Bajida Jattan 0.4010) km.Gharaunda

Constructed 9/1997. Path-4karam, Crust-150 mm. SR Nil. Transferred to MC

8579 07-Oct-11

H - 4272 Madanpur School To Bajida Jattan 0.5011) km.Gharaunda

Constructed 3/1997. Path-4karam, Crust-225 mm. Transferred to MC

8580 07-Oct-11

H - 4273 Budha Khera To Phoosgarh 3.3312) km.Gharaunda

Constructed 2/2002. Path-5karam, Crust-150 mm. No SR done.8581 07-Oct-11

H - 5208 Widening Of Road Phirni Phoosgarh 1.2013) km.Karnal

Transferred to MC on 1.6.201224440 01-Jun-12

T/Approved, tenders on 21.06.201223937 22-May-12

Work Plan:75mm WBM+PC in 500m length; in rest patches (EC 10 lacs)

9341 07-Oct-11

Constructed 1981 (by Market Committee). Crust 150mm. Path 4 karam. PC done in 1996.Built up area in 500m.

9340 07-Oct-11

H - 6518 Sector 6 To Sohana 2.5014) km.Gharaunda

2.5km length transfer to MC on _________.25855 22-Jun-12

Work not started. Non availability material work held up.25854 22-May-12

75 mm WBM + PC (Rs. 35.43 lacs) sanctioned on 15/10/2010. Allotted on 9/8/2011 (Harjit).

25853 16-Nov-11

Constructed 1/1995. Crust 150mm. Path 5 Karam. CC (in Phirni) & Patch + PC in 8/2007.

25852 15-Nov-11

18.83 km. Sub Total:

Transferred to PWD (938 roads)

H - 3902 Taprian To Chaprian 1.801) km.Indri

PWD has allotted works worth 30.6 lacs.43578 20-Mar-13

PWD has allotted works worth 30.6 lacs.43210 19-Mar-13

Transferred to PWD. PWD RoadID : 884414440 15-Nov-11

Tuesday, April 02, 2013 Page 44 of 65

Page 45: Karnal Distt. Link Roads

Constructed 7/1990. No SR done, Path-6karam, Crust-150 mm.8582 07-Oct-11

H - 3903 Bibi Pur Jattan To Kamal Pur Roran 3.092) km.Indri

PWD has allotted works worth 52.53 lacs.43591 20-Mar-13

PWD has allotted works worth 52.53 lacs.43209 19-Mar-13

Transferred to PWD. PWD RoadID : 884514439 15-Nov-11

Constructed 5/1991. SR 15.04.07 with PC, Path-6karam, Crust-150 mm.

8583 07-Oct-11

H - 3905 Bibipur Jattan To Nagla Roran 3.803) km.Indri

PWD has allotted works worth 79.9 lacs.43605 20-Mar-13

PWD has allotted works worth 79.9 lacs.43208 19-Mar-13

Constructed 2/1994. SR 29.01.10, Path-8karam, Crust-225 mm.8584 07-Oct-11

Transferred to PWD. PWD RoadID : 88467698 03-Oct-11

H - 3906 Garhi Birbal To Shergarh 3.104) km.Indri

PWD has allotted works worth 57.8 lacs.43560 20-Mar-13

PWD has allotted works worth 57.8 lacs.43207 19-Mar-13

Constructed 3/1994. SR 10.12.07, Path-12karam, Crust-150 mm8585 07-Oct-11

Transferred to PWD. PWD RoadID : 88477701 03-Oct-11

H - 3909 Hanori To Bhoji 3.885) km.Indri

PWD has allotted works worth 71.4 lacs.43590 20-Mar-13

PWD has allotted works worth 71.4 lacs.43205 19-Mar-13

Constructed 4/1994. SR 20.03.04, Path-6,8 & 10karam, Crust-150 mm

8586 07-Oct-11

Transferred to PWD. PWD RoadID : 88487706 03-Oct-11

H - 3910 Chourni To Samora 2.736) km.Indri

PWD has allotted works worth 46.41 lacs.43584 20-Mar-13

PWD has allotted works worth 46.41 lacs.43174 19-Mar-13

Constructed 3/1995. SR 29.01.10, Path-6karam, Crust-225 mm8587 07-Oct-11

Transferred to PWD. PWD RoadID : 88497697 03-Oct-11

H - 3913 Chand Samand To Bir Majri 1.447) km.Indri

PWD has allotted works worth 25.5 lacs.43589 20-Mar-13

PWD has allotted works worth 25.5 lacs.43211 19-Mar-13

Constructed 6/1997. SR 30.09.06, Path-6 & 8karam, Crust-150 mm8588 07-Oct-11

Transferred to PWD. PWD RoadID : 88507699 03-Oct-11

H - 3915 Garhi Sadhan To Panjokhera 2.088) km.Indri

PWD has allotted works worth 35.7 lacs.43582 20-Mar-13

PWD has allotted works worth 35.7 lacs.43183 19-Mar-13

Constructed 3/1998. SR 30.09.06, Path-6karam, Crust-150 mm8589 07-Oct-11

Transferred to PWD. PWD RoadID : 88517702 03-Oct-11

Indri

Tuesday, April 02, 2013 Page 45 of 65

Page 46: Karnal Distt. Link Roads

H - 3932 Biana To Shahpur 2.339) km.Indri

PWD has allotted works worth 42.5 lacs.43588 20-Mar-13

PWD has allotted works worth 42.5 lacs.43182 19-Mar-13

Constructed 8/2001. SR 29.09.10, Path-6karam, Crust-150 mm8590 07-Oct-11

Transferred to PWD. PWD RoadID : 88527696 03-Oct-11

H - 3947 Pathera To Rajepur 0.7510) km.Indri

PWD has allotted works worth 12.75 lacs.43593 20-Mar-13

PWD has allotted works worth 12.75 lacs.43181 19-Mar-13

Constructed 3/2008. No SR done, Path-6 & 8karam, Crust-225 mm8591 07-Oct-11

Transferred to PWD. PWD RoadID : 88537704 03-Oct-11

H - 3950 Ganger To G.T. Road 1.3011) km.Indri

PWD has allotted works worth 22.1 lacs.43583 20-Mar-13

PWD has allotted works worth 22.1 lacs.43203 19-Mar-13

Constructed 7/2001.SR 29.01.10, Path-6, Crust-225 mm8592 07-Oct-11

Transferred to PWD. PWD RoadID : 88548243 03-Oct-11

Transferred to PWD (B&R) on 16/3/2010.7109 30-Sep-11

H - 3959 Salaru To Taprana 2.4812) km.Indri

PWD has allotted works worth 42.16 lacs.43566 20-Mar-13

PWD has allotted works worth 42.16 lacs.43201 19-Mar-13

Constructed 9/2005. No SR done, Path-6karam, Crust-150 mm8594 07-Oct-11

Transferred to PWD. PWD RoadID : 88577695 03-Oct-11

H - 3963 Nagla Roran To Gheer 2.5613) km.Indri

PWD has allotted works worth 81.6 lacs.43592 20-Mar-13

PWD has allotted works worth 81.6 lacs.43200 19-Mar-13

Constructed 12/2009. No SR done, Path-6karam, Crust-225 mm. CC in phirni of village Gheer.

8595 07-Oct-11

Transferred to PWD. PWD RoadID : 88588248 03-Oct-11

H - 3974 Kachwa To Behlolpur 4.0414) km.Karnal

PWD has allotted works worth 69.7 lacs.43600 20-Mar-13

PWD has allotted works worth 69.7 lacs.43199 19-Mar-13

Constructed 12/1993. Path-9karam, Crust-150 mm8596 07-Oct-11

Transferred to PWD on 17/4/2010. PWD RoadID : 88428242 03-Oct-11

SR completed on 31.03.2008 with an exp. of Rs. 16.16 lacs2303 22-Aug-11

H - 3994 Guniana To Nissing 3.5315) km.Nilokheri (SC)

PWD has allotted works worth 60.01 lacs.43602 20-Mar-13

PWD has allotted works worth 60.01 lacs.43198 19-Mar-13

Constructed 5/1991. Path-6karam, Crust-225 mm8598 07-Oct-11

Transferred to PWD. PWD RoadID : 88757859 03-Oct-11

Nilokheri (SC)

Tuesday, April 02, 2013 Page 46 of 65

Page 47: Karnal Distt. Link Roads

H - 3998 Singra To G.M. Nissing 3.7716) km.Nilokheri (SC)

PWD has allotted works worth 59.5 lacs.43603 20-Mar-13

PWD has allotted works worth 59.5 lacs.43186 19-Mar-13

Constructed 7/1995. Path-6 & 11karam, Crust-150 mm8599 07-Oct-11

Transferred to PWD. PWD RoadID : 88768246 03-Oct-11

H - 4002 Gonder To Guniana Road 5.0417) km.Nilokheri (SC)

PWD has allotted works worth 85.68 lacs.43579 20-Mar-13

PWD has allotted works worth 85.68 lacs.43196 19-Mar-13

Constructed 7/2002. Path-6karam, Crust-225 mm8600 07-Oct-11

Transferred to PWD. PWD RoadID : 88777858 03-Oct-11

H - 4015 Takhana To Taraori 0.8718) km.Nilokheri (SC)

PWD has allotted works worth 14.79 lacs.43577 20-Mar-13

PWD has allotted works worth 14.79 lacs.43194 19-Mar-13

Constructed 3/1990. Path-6karam, Crust-150 mm8602 07-Oct-11

Transferred to PWD. PWD RoadID : 88797852 03-Oct-11

H - 4017 Nidana To Pakhana 2.4719) km.Nilokheri (SC)

PWD has allotted works worth 41.99 lacs.43565 20-Mar-13

PWD has allotted works worth 41.99 lacs.43193 19-Mar-13

Constructed 9/1993. Path-6karam, Crust-150 mm. SR 10.09.05.8603 07-Oct-11

Transferred to PWD. PWD RoadID : 88807853 03-Oct-11

H - 4019 Sohlan To Sonkra 4.1020) km.Nilokheri (SC)

PWD has allotted works worth 69.7 lacs.43597 20-Mar-13

PWD has allotted works worth 69.7 lacs.43192 19-Mar-13

Constructed 1/1994. Path-6karam, Crust-225 mm8604 07-Oct-11

Transferred to PWD. PWD RoadID : 88817861 03-Oct-11

H - 4029 Amupur To Sitamai 3.9021) km.Nilokheri (SC)

PWD has allotted works worth 66.3 lacs.43580 20-Mar-13

PWD has allotted works worth 66.3 lacs.43191 19-Mar-13

Constructed 12/1995. Path-13karam, Crust-150 mm8605 07-Oct-11

Transferred to PWD. PWD RoadID : 88827856 03-Oct-11

H - 4030 Ramana To Bhola Khalsa 3.7722) km.Nilokheri (SC)

PWD has allotted works worth 68 lacs.43598 20-Mar-13

PWD has allotted works worth 68 lacs.43190 19-Mar-13

Constructed 11/1996. Path-6karam, Crust-150 mm. SR 08.07.07.8606 07-Oct-11

Transferred to PWD. PWD RoadID : 88837855 03-Oct-11

H - 4032 Pakhana To Chandan Khera 0.8623) km.Nilokheri (SC)

PWD has allotted works worth 14.62 lacs.43574 20-Mar-13

Tuesday, April 02, 2013 Page 47 of 65

Page 48: Karnal Distt. Link Roads

PWD has allotted works worth 14.62 lacs.43189 19-Mar-13

Constructed 5/1998. Path-6karam, Crust-150 mm. SR done in 3/2008 (Expenditure 4.40 lacs).

8607 07-Oct-11

Transferred to PWD. PWD RoadID : 88857854 03-Oct-11

H - 4038 Sonkra To Sandhu Farm 1.7824) km.Nilokheri (SC)

PWD has allotted works worth 30.26 lacs.43581 20-Mar-13

PWD has allotted works worth 30.26 lacs.43188 19-Mar-13

Constructed 3/2003. Path-6karam, Crust-150 mm. SR Nil.8608 07-Oct-11

Transferred to PWD. PWD RoadID : 88847845 03-Oct-11

H - 4039 Rambha To Sham Garh 3.1825) km.Nilokheri (SC)

PWD has allotted works worth 56.95 lacs.43561 20-Mar-13

PWD has allotted works worth 56.95 lacs.43187 19-Mar-13

Constructed 7/2003. Path-6karam, Crust-150 mm. SR Nil.8609 07-Oct-11

Transferred to PWD. PWD RoadID : 88867848 03-Oct-11

H - 4046 Barsalu To Bairsal 3.4826) km.Nilokheri (SC)

PWD has allotted works worth 61.2 lacs.43585 20-Mar-13

PWD has allotted works worth 61.2 lacs.43184 19-Mar-13

Constructed 1/1994. Path-6karam, Crust-150 mm. SR done in 12/2007 (Expenditure 13.62 lacs).

8610 07-Oct-11

Transferred to PWD. PWD RoadID : 88877847 03-Oct-11

H - 4050 Amargarh To Sikri 1.0027) km.Nilokheri (SC)

PWD has allotted works worth 17 lacs.43587 20-Mar-13

PWD has allotted works worth 17 lacs.43204 19-Mar-13

Constructed 2/1998. Path-6karam, Crust-150 mm. PC done in 11/2006.

8611 07-Oct-11

Transferred to PWD. PWD RoadID : 88887846 03-Oct-11

H - 4055 Sheedpur To Taraori Road 1.5128) km.Nilokheri (SC)

PWD has allotted works worth 25.67 lacs.43569 20-Mar-13

PWD has allotted works worth 25.67 lacs.43176 19-Mar-13

Constructed 11/2000. Path-6karam, Crust-225 mm. SR in 10/2009 (Expenditure 7.51 lacs).

8613 07-Oct-11

Transferred to PWD. PWD RoadID : 88907851 03-Oct-11

H - 4065 Gorgarh To Gumto 2.6029) km.Nilokheri (SC)

PWD has allotted works worth 44.2 lacs.43567 20-Mar-13

PWD has allotted works worth 44.2 lacs.43197 19-Mar-13

Constructed 5/2004. Path-6 & 7karam, Crust-150 mm. SR Nil.8614 07-Oct-11

Transferred to PWD. PWD RoadID : 88918250 03-Oct-11

H - 4072 Hathira To Pastana.-I 1.7130) km.Nilokheri (SC)

PWD has allotted works worth 32.64 lacs.43599 20-Mar-13

Tuesday, April 02, 2013 Page 48 of 65

Page 49: Karnal Distt. Link Roads

PWD has allotted works worth 32.64 lacs.43195 19-Mar-13

Constructed 9/1997. SR-2008, Path-7karam, Crust-150 mm8615 07-Oct-11

Transferred to PWD. PWD RoadID : 88927850 03-Oct-11

H - 4080 Karsa To Pastana 1.9231) km.Nilokheri (SC)

PWD has allotted works worth 32.64 lacs.43596 20-Mar-13

PWD has allotted works worth 32.64 lacs.43166 19-Mar-13

Constructed 6/2003. SR-2008, Path-6karam, Crust-150 mm8616 07-Oct-11

Transferred to PWD on 17/4/2010. PWD RoadID : 88937849 03-Oct-11

H - 4087 Shapur To Kalampur 1.9532) km.Nilokheri (SC)

PWD has allotted works worth 33.15 lacs.43573 20-Mar-13

PWD has allotted works worth 33.15 lacs.43167 19-Mar-13

Constructed 12/1997. SR 09.2004, Path-6karam, Crust-150 mm8617 07-Oct-11

Transferred to PWD. PWD RoadID : 88948239 03-Oct-11

H - 4155 Dacher To Acchanpur 4.0233) km.Assandh

PWD has allotted works worth 68.34 lacs.43570 20-Mar-13

PWD has allotted works worth 68.34 lacs.43168 19-Mar-13

Constructed 12/2002. No SR done, Path-6karam, Crust-150 mm8630 07-Oct-11

Transferred to PWD. PWD RoadID : 88688244 03-Oct-11

H - 4156 Achanpur To Rugsana 2.4934) km.Assandh

PWD has allotted works worth 42.16 lacs.43562 20-Mar-13

PWD has allotted works worth 42.16 lacs.43169 19-Mar-13

Constructed 8/2002. No SR done, Path-6karam, Crust-150 mm8631 07-Oct-11

Transferred to PWD. PWD RoadID : 88698245 03-Oct-11

H - 4161 Sirsi To Assandh Road Via Dadupur 3.3335) km.Assandh

PWD has allotted works worth 56.61 lacs.43564 20-Mar-13

PWD has allotted works worth 56.61 lacs.43170 19-Mar-13

Constructed 10/1998. SR 15.04.05, Path-6karam, Crust-150 mm8632 07-Oct-11

Transferred to PWD. PWD RoadID : 88717426 03-Oct-11

H - 4169 Aungad To Hathlana 4.2836) km.Assandh

PWD has allotted works worth 72.76 lacs.43563 20-Mar-13

PWD has allotted works worth 72.76 lacs.43171 19-Mar-13

Constructed 8/2002. No SR done, Path-6karam, Crust-150 mm8635 07-Oct-11

Transferred to PWD. PWD RoadID : 88727425 03-Oct-11

H - 4177 Jundla To Aungad Via Dera Kartar Singh 5.9437) km.Assandh

PWD has allotted works worth 100.98 lacs.43601 20-Mar-13

PWD has allotted works worth 100.98 lacs.43172 19-Mar-13

Constructed 4/2009. No SR done, Path-6karam, Crust-150 mm8636 07-Oct-11

Transferred to PWD. PWD RoadID : 88747428 03-Oct-11

Tuesday, April 02, 2013 Page 49 of 65

Page 50: Karnal Distt. Link Roads

H - 4228 Fazilpur To Kairwali 3.2338) km.Gharaunda

PWD has allotted works worth 55.25 lacs.43586 20-Mar-13

PWD has allotted works worth 55.25 lacs.43173 19-Mar-13

Constructed 3/2002. SR 29.01.10, Path-6karam, Crust-225 mm8644 07-Oct-11

Transferred to PWD. PWD RoadID : 88597624 03-Oct-11

H - 4246 Sarfabad To Rasulpur Kalan 1.8439) km.Gharaunda

PWD has allotted works worth 31.28 lacs.43576 20-Mar-13

PWD has allotted works worth 31.28 lacs.43185 19-Mar-13

Constructed 9/1992. SR 17.01.05, Path-7karam, Crust-150 mm8647 07-Oct-11

Transferred to PWD. PWD RoadID : 88607625 03-Oct-11

H - 4247 Kalweri To Subri 1.7440) km.Gharaunda

PWD has allotted works worth 36.55 lacs.43571 20-Mar-13

PWD has allotted works worth 36.55 lacs.43175 19-Mar-13

Constructed 5/1994. SR 31.03.08, Path-6karam, Crust-150 mm8648 07-Oct-11

Transferred to PWD. PWD RoadID : 88618249 03-Oct-11

H - 4252 Subri To Rasul Pur Kalan 1.7741) km.Gharaunda

PWD has allotted works worth 30.09 lacs.43575 20-Mar-13

PWD has allotted works worth 30.09 lacs.43177 19-Mar-13

T/Approved, tenders on 21.06.201223872 22-May-12

Constructed 2/2005. No SR done, Path-6karam, Crust-150 mm8649 07-Oct-11

Transferred to PWD. PWD RoadID : 88637629 03-Oct-11

H - 4257 Bajida Jattan To Rishi Nagar 4.7042) km.Gharaunda

PWD has allotted works worth 150 lacs.43572 20-Mar-13

PWD has allotted works worth 150 lacs.43178 19-Mar-13

Constructed2/1994. SR 01.2007, Path-5karam, Crust-150 mm8650 07-Oct-11

Transferred to PWD. PWD RoadID : 88658237 03-Oct-11

H - 4261 Bajida Rly Station To Sirsi 0.8043) km.Gharaunda

PWD has allotted works worth 13.6 lacs.43568 20-Mar-13

PWD has allotted works worth 13.6 lacs.43179 19-Mar-13

Constructed 11/1994. SR 26.06.05, Path-9karam, Crust-150 mm8651 07-Oct-11

Transferred to PWD. PWD RoadID : 88668238 03-Oct-11

H - 4264 Bhusli To Samalkha 3.0444) km.Gharaunda

PWD has allotted works worth 62.05 lacs.43595 20-Mar-13

PWD has allotted works worth 62.05 lacs.43180 19-Mar-13

Constructed 7/2004. No SR done, Path-6karam, Crust-150 mm8652 07-Oct-11

Transferred to PWD. PWD RoadID : 88677626 03-Oct-11

120.00 km. Sub Total:

Tuesday, April 02, 2013 Page 50 of 65

Page 51: Karnal Distt. Link Roads

Transferred to PWD (Individual)

H - 4160 Aungad To Kathleri 0.801) km.Assandh

PWD road ID 7270.19085 18-Feb-12

Constructed 1997. Path-6karam, Crust-150 mm. 75mm WBM + PC done in 2/2010 (Expenditure 13.37 lacs).

8571 07-Oct-11

H - 4183 Kurlan To Kabulpur Khera 3.122) km.Assandh

Transferred to PWD. PWD ID: 8919.24441 01-Jun-12

Constructed 6/2010. Crust 225mm. (259.59 sqm) patches done 9/08/2011 to 13/08/2011 (50 K). No patch.

9103 07-Oct-11

3.92 km. Sub Total:

New Construction going on

New Construction - Awarded

H - 4681 Chochra To Pangala 2.281) km.Assandh

All work completed on 23/12/2012 except 250m Where disputed emerged.

40014 12-Feb-13

Upto WBM complete, likely date of completion 30.11.12.36672 31-Oct-12

A/A on 20.08.09 for Rs. 46.66 lacs. Path 5,6 & 7 K . Crust 225mm. Allotted on 09.11.09 (Prabhu Dayal).

9726 12-Oct-11

H - 4682 Thari To Jabala 2.962) km.Assandh

Work completed except berms, likely date of completion 15/4/2013.36673 12-Feb-13

Likely date 30.06.12, supply of stone soling completed 1 km21972 04-Apr-12

A/A granted on 12.04.10 for Rs. 51.26 lacs, Path 6 & 7 karam. Crust 225mm. allotted on 14.07.10 to Deepak Ghai, E/W complete.

14913 16-Nov-11

H - 4687 Dupedi To Dinoli 4.283) km.Assandh

EW in 4km. Supply of GSB in progress.40776 12-Feb-13

R/A/A on 01.01.2013 for Rs. 1.50 crore.39745 03-Jan-13

Tender approved on 28/12/2012 (M/s S.K. Contractors).39668 01-Jan-13

DNIT & estimate submitted on 21.05.2012 by SE30131 20-Aug-12

A/A on 21.01.11 Rs. 92.87 lacs, path 6 karam, crust 400mm21957 04-Apr-12

R/A/A on 6.01.12(Rs. 129.87 lacs), D/Estimate HQ for T/S.22002 04-Apr-12

H - 4690 Chochra To Uplana 5.234) km.Assandh

Contractor says entire road except form 500m ready for PC.41574 04-Mar-13

Stone soling complete, metal 0.5km complete. Likely date of completion 31/3/2013

36674 31-Oct-12

A/A on 21.01.11 for Rs. 116.77 lacs,path 6 karam, crust 225mm. Allotted on 10.08.11 to Deepak Ghai

21955 04-Apr-12

H - 5033 Bhamberhari To Bansa 6.285) km.Assandh

E/W complete in 4 km.40015 13-Feb-13

Tuesday, April 02, 2013 Page 51 of 65

Page 52: Karnal Distt. Link Roads

Tender approved on 21/12/2012 (M/s S.K. Contractor). R/A/A on 27.12.2012 for Rs. 4.36 crore.

39741 03-Jan-13

A/A on 12.08.11 for Rs. 392.01 lacs. Path 6k & 8k .Crust 400 mm . D/E Technically sanctioned for Rs. 380.90 lacs on 31/10/2011.

9744 16-Nov-11

H - 5036 Devi Mandir To Ashwa Megh Tirath Salwan 0.416) km.Assandh

Supply of GSB in progress.40777 13-Feb-13

R/A/A on 27.12.2012 for Rs. 13.20 lacs.39743 03-Jan-13

Tender approved on 31/12/2012 (M/s Eashaan Infrastructure).39737 02-Jan-13

Tender case approved by EIC on 6/12/2012 & sent to CA for RAA.39334 20-Dec-12

DNIT & Detailed estimate submitted to SE with now specification. 30141 20-Aug-12

A/A on 11.08.11 for Rs. 10.01 lacs , Path 5 & 6 karam, crust 400mm.21953 04-Apr-12

H - 5037 Goghripur (Karnal- Munak Road) To Ngm Karnal 1.657) km.Gharaunda

GSB completed on 07/01/2013. Likely date of completion 30/4/2013.

40016 13-Feb-13

EW completed in entire length.26652 10-Jul-12

Land dispute solved in Jan, 2012. Work allotted on 08.05.2012. Schedule date of completion. 07.11.2012

23928 22-May-12

A/A on 08.09.11 for Rs. 70.00 lacs. Path 4 & 6 K . Crust 400 mm . Conditinal A/A accorded to get the land transfer from the Gram Panchayat. Transfer of mutation of land still awaited. Matter being persued with Gram Panchayat / Distt. Administration.

9748 12-Oct-11

H - 5175 Jarifabad To Jundla 3.528) km.Assandh

GSB complete in entire reach.36675 04-Mar-13

Work allotted on 03.05.2012. Tender approved on 17.04.2012 for Rs. 114.00 lacs (Sh. Deepak Ghai Contractor)

23935 22-May-12

R/A/A on 19.04.2012 for Rs. 1.11 crore22515 24-Apr-12

A/A on 01.08.11 for Rs. 97.74 lacs. Path 3 & 6 K . (Panchayat has transferred 2 karam land). Crust 400 mm. D/E technically sanctioned on 5.10.11. Tenders invited on 8/12/2011.

9756 16-Nov-11

26.61 km. Sub Total:

New Construction - Unawarded

H - 4088 Rukanpur To Bhani Kalan (Balance portion) 0.461) km.Nilokheri (SC)

Agency left work. Earnest money forfieted. Tender re-invited on 5/3/2013

40775 12-Feb-13

R/A/A on 15.01.2013 for Rs. 17.78 lacs. Path -4 karam.40043 22-Jan-13

Tender approved on 21/12/2012. (M/s Aman Construction Company).

39612 24-Dec-12

For balance portion of 0.57km, where there was dispute earlier, AA for 14.02 lacs issued on 30/4/2012.

31816 23-Aug-12

1.9km Constructed 3/1998. Crust 150mm. PC(entire) done 12/2007. (156.40 sqm) patches done 27/08/2011 to 29/08/2011 (32 K). No patch.

9092 07-Oct-11

H - 4683 Anchala To Picholia 3.612) km.Assandh

Tuesday, April 02, 2013 Page 52 of 65

Page 53: Karnal Distt. Link Roads

Tender received on 23/1/2013 & under process40767 12-Feb-13

A/A granted on 23.03.10 for Rs.74.35 lacs. Path 4 & 5 Karam. Crust 225mm. Allotted on 14.07.10 to Sh. Jitender Singh. E/W executed in 2954m.

4209 16-Nov-11

H - 4684 Ardana To Gangatehri 6.393) km.Assandh

Tender approved on 14/2/2013 (M/s S.K. Contractor)-conditionally. R/A/A on 18.02.2013 for RS. 2.55 crore.

41060 14-Feb-13

Tender received on 26.10.2012 and under process in division office. Ext. validity upto 15/2/2013.

36676 12-Feb-13

Technical approved 208.14 lacs on 28.05.12. DNIT approved 204.33 lacs on 9.07.12.

26737 12-Jul-12

A/A in supersession on 30.01.12 for Rs. 186.66 lacs21951 04-Apr-12

A/A on 28.10.10 for Rs. 155.82 lacs. Path 6&8 K .Crust 400 mm. R/R/C estimate amounting to Rs. 206 lacs.

9729 16-Nov-11

H - 4685 Jalala Veeran To Behlolpur (West South Side Of Village Jalala Phirni)

0.374) km.Nilokheri (SC)

No tender received on 19.12.11, 27.02.2012, 28.03.2012, 25.09.2012 & 22.11.12. Tender re-invited for 26.02.2013.

31836 12-Feb-13

Case for revised A/A submitted on 29.05.2012.30129 20-Aug-12

A/A on 21.12.10 for Rs. 9.11 lacs. Path 5 & 6 K . Crust 225mm. Tender reinvited for 4th time on 22/11/2011.

9730 16-Nov-11

H - 4688 Bahri To Mund 4.065) km.Assandh

EW in progress.39744 12-Feb-13

Tender approved on 28/12/2012 (M/s S.K. Contratcor). R/A/A on 27.12.2012 for Rs. 1.32 crore.

39738 02-Jan-13

R/A/A on 30.01.12 for Rs. 112.58 lacs, D/Estimate is in HQ for T/S.22001 04-Apr-12

A/A on 21.01.11 for Rs. 79.29 lacs. Path 5 & 6 K.Crust 400 mm . Estimate submitted with revised specification amounting to Rs. 109 lacs for arranging R/A/A.

9733 16-Nov-11

H - 4689 Jalmana To Thari 2.256) km.Assandh

Tender received on 26/1/2013 & under process in HO.36679 12-Feb-13

A/A on 21.01.11 for Rs. 51.35 lacs, path 6 karam, crust 400mm21956 04-Apr-12

R/A/A on 18.11.2011 for Rs. 63.27 lacs.15843 08-Dec-11

H - 4691 Aungadh To Gonder 5.307) km.Assandh

Tender to be received on 26/2/2013.40768 12-Feb-13

R/A/A accorded for Rs. 334.387 lacs on 02.01.2013. This cost includes Rs. 164 lacs for const. of bridge by irrigation department and road cost is 156 lacs.

39739 02-Jan-13

A/A on 10.01.11 for Rs. 225.68 lacs. Path 5&6 K .Crust 400 mm .9736 12-Oct-11

H - 4693 Sonkra To Galibkheri 1.538) km.Nilokheri (SC)

No tender received on 23.08.12, 25.09.12, 22/11/2012 & 23.08.2012.. Now to be received on 26/2/2013.

32371 12-Feb-13

A/A on 08.11.10 for Rs. 30.75 lacs, path 5 karam, crust 400mm. A/A issued in Aug., 2008.

31833 23-Aug-12

Tuesday, April 02, 2013 Page 53 of 65

Page 54: Karnal Distt. Link Roads

H - 4695 Gharpur To Yamuna Ghat 0.959) km.Indri

No tender received on 31.01.12, 27.02.12, 28.03.12, 18.04.12, 25.09.12 & 22/11/2012, now invited on 26/2/2013.

21976 12-Feb-13

A/A on 20.08.09 for Rs. 17.39 lacs. Path 7 K. Crust 225mm . Allotted to Mohan Lal on 24/12/2009. Work not started. Being included in group of 3 roads, tenders for balance work invited on 22/11/2011 at the risk & cost of previous agency.

9740 16-Nov-11

H - 4696 Kamalpur To Churni 1.9210) km.Indri

No tender received on 31.01.12, 27.02.12, 28.03.12, 18.04.12, 23.08.2012, 25.09.2012, 22.11.12. Now re-invited on 26/2/2013.

21977 12-Feb-13

A/A on 02.09.09 for Rs. 38.37 lacs. Path 5 K .Crust 225mm . Earth work partially completed. Agency left the work. Tender re-invited on 22.11.11 at risk and cost.

9741 16-Nov-11

H - 4697 Sayid Chappra Via Dera Halwana Sikligran 1.5711) km.Indri

No tender received on 31.01.12, 27.02.12, 28.03.12,18.04.12, 23.08.2012, 25.09.2012, 22.11.12. Now re-invited on 26/2/2013.

21978 12-Feb-13

A/A on 26.08.09 for Rs. 28.41 lacs. Path 5 K .Crust 225mm. Allotted to The Madhan Co.Op Ltd. on 4/6/2010. Earth work completed. Agency left the work. Tender re-invited on 22.11.11 at risk and cost.

9742 16-Nov-11

H - 4698 Ghor Garh To Kheri Man Singh 1.9112) km.Indri

No tender received on 31.01.12, 27.02.12, 28.03.12, 18.04.12, 23.08.12, 25.09.2012, 22.11.12. now re-invited on 26/2/2013.

21979 12-Feb-13

A/A on 28.08.09 for Rs. 34.63 lacs. Path 6 K.Crust 225mm. Allotted to Jitender Singh on 9/6/2010. Earth work completed. Agency left the work. Tender re-invited on 22/11/2011 at risk and cost.

9743 16-Nov-11

H - 5038 Gagseena Anchla Road To Bansa 4.6613) km.Gharaunda

Tender re-invited on 26/2/2013.40769 12-Feb-13

A/A on 14.01.2013 for Rs. 1.48 crore.40046 22-Jan-13

CM has approved the road on 17/12/2012 & reiterated his earlier order dated 18/01/2012 on pre-page 9/N keeping in view the fact that the available path is just marginally less than the prescribed HSAMB norms.

39626 27-Dec-12

Path 22' in 1.94km, rest 7k. No distance shortened. Cost is 1.48 crore. Upward of E-In-C.

27668 18-Jul-12

Estimate Rs. 103.40 lacs. Path 5 &7 K Crust 225mm . R/C/E sent to Govt. vide C.A. No. 205 dt. 3.5.11.

9749 12-Oct-11

H - 5100 Pucca Road In Skindrabad 0.4114) km.Indri

No tender received on 31.01.12, 27.02.12, 28.03.12,18.04.12, 23.08.12, 25.09.12, 22/11/2012, now re-invited on 26/2/2013.

21980 12-Feb-13

A/A on 20.08.09 for Rs. 7.84 lacs. Path 6 K .Crust 225mm. Earth work in 150 m completed. Agency left the work. Tender re-invited on 22/11/2011 at risk and cost.

9753 16-Nov-11

H - 5101 Shergarh To Dhano Kheri 2.5015) km.Indri

No tender received on 31.01.12, 27.02.12, 28.03.12, 18.04.12, 23.08.12, 25.09.12, 22/11/2012. Now to be re-invited on 26/2/2013.

21981 12-Feb-13

Tuesday, April 02, 2013 Page 54 of 65

Page 55: Karnal Distt. Link Roads

A/A on 20.08.09 for Rs. 48.15 lacs. Path 10 K .Crust 225mm. Earth work in 1 km completed. Agency left the work. Tender re-invited on 22/11/2011 at risk and cost.

9754 16-Nov-11

H - 5102 Samora To Bibipur 2.7316) km.Indri

No tender received on 31.01.12, 27.02.12, 28.03.12, 18.04.12, 23.08.12, 25.09.12, 22.11.2013. Now to ber re-invited on 26/2/2013.

21982 12-Feb-13

No tender received on 23.08.12 & now to be received on 25.09.12.32382 04-Sep-12

A/A on 28.08.09 for Rs. 58.78 lacs. Path 6 K .Crust 225mm. alloted on 9.6.10 to Sh, Jitender Singh. Retaining wall completed in length 91.50 Rmt. Agency left the work. Tender re-invited on 22/11/2011 at risk and cost.

9755 16-Nov-11

H - 5786 Assandh Bye Pass on Bank of Drain around Assandh City 7.6017) km.Assandh

Tender invited on 26/2/2013.40770 12-Feb-13

AA on 5/10/2012 for Rs. 321 lacs.36320 23-Oct-12

CM announcement no. 3827. Estimated cost: 7.7 crore out of which irrigation charges Rs. 4.48 crore. RCE upward of EIC on 19.9.2012.

33036 19-Sep-12

Estimate Rs. 33.62 crore in Head Office. NOC from Irrigation is awaited.

27611 17-Jul-12

EE Karnal confirmed Proposal for transfer to PWD(B&R) under consideration with Govt. Not falls in the policy of the Board.

21134 16-Mar-12

Approved on 21.01.11(N.O.C. required from Irri. Deptt.)14562 16-Nov-11

H - 6312 G.T.Road Nilokheri to Kassan Basti Via Peer Baba Verma Hatchery upto road connected NGM Nilokher.

0.9318) km.Nilokheri (SC)

AA on 6/3/2013 for Rs. 22.83 lacs.42160 11-Mar-13

Estimate under query of EIC for cost.40137 25-Jan-13

CM approved the const. of this road on 13.12.12. 39882 09-Jan-13

NOC received from Irrigation department. Case is with Government.32818 17-Sep-12

R/C/E PS Agri. to Govt. vide no. 1219 dated 11.06.1228742 27-Jul-12

C.M. desired on 8.06.2011 for construction of road.20501 21-Feb-12

H - 6762 Approach road to Sports Stadium, Gogripur 0.3119) km.Gharaunda

A/A accorded for Rs. 5,05,800/- on 15.03.201342185 12-Mar-13

49.45 km. Sub Total:

Planned - New Construction

Approved by Government but AA pending

H - 6396 Chochra to Chochra Pangala road. 0.401) km.Assandh

Hon'ble CM has apporved the road on 18.02.2013.43975 28-Mar-13

P/R PS Agri. To Govt. vide no. 1663 dated 24.07.1228637 27-Jul-12

Path 6k. 1 km distance shortened.27921 20-Jul-12

Recommended by MLA Assandh Path is 6 karam.22526 24-Apr-12

H - 6528 Guniana to Bastali Jhaal (upto Karnal Kaithal road) 2.252) km.Karnal

Tuesday, April 02, 2013 Page 55 of 65

Page 56: Karnal Distt. Link Roads

Govt. has approved this road on 01.03.2013.42647 15-Mar-13

Case is with MOS to AM vide no.340 dt. 20.07.12.38706 18-Dec-12

No path but Gurukul Samiti to give 5k land free of cost (resolution received). No distance shortened.

29439 14-Aug-12

CA to PS Agri. no. 383 on 9.07.1228607 27-Jul-12

Recommended by MP Rohtak.25964 25-Jun-12

H - 6670 Thal to Kheri Sarfali 2.763) km.Assandh

Hon'ble CM has approved this road on 13.02.2013.41291 18-Feb-13

Case is with CM sett. Vide AM office no. 1191 dt. 03.12. 12.38871 18-Dec-12

Recommended by MP, Karnal. Path 27' 6" & 28' 11". 0.8km distance shortened to PC, Rahra. Upward of EIC on 10/9/2012.

32436 10-Sep-12

5.41 km. Sub Total:

Dropped

Dropped

H - 5039 G.T. Road Gharaunda To Malikpur 1.331) km.Gharaunda

A/A withdrawn on 03.10.2012 being non feasible due to non avialibility of path.

33738 03-Oct-12

A/A on 02.07.08 for Rs. 46.88 lacs. Path 3,4&6 K. Crust 225mm. Additional land not transferred by the Gram Panchayat , case submitted to H.O. for declaring the work non feasible.

9750 12-Oct-11

H - 5779 Nissing Brass road to Brass Prem Khera road 0.652) km.Nilokheri (SC)

Declared non feasible by CE, HSAMB on 25.10.1014555 16-Nov-11

H - 6225 Bhod Sham to Jhambha High School 2.083) km.Nilokheri (SC)

Path is less. CP RD 20 to 80 no path. Less than in 670m.32817 17-Sep-12

Request filed as not as per Board policy.31884 24-Aug-12

Case of non-feasible sent to Head office in March 2012.30149 20-Aug-12

Representation of Gram Panchayat through office of C.M. Haryana on 04.08.11.

16202 27-Dec-11

H - 6687 Brahman Majra to village Dabarthala 2.324) km.Nilokheri (SC)

P/R filed on 01.10.201233739 03-Oct-12

CP RD 0-1240=32' 1", 1420-1950= 32'6", in rest 26'6" wide, no distance shortened, less path, not falls in policy. Upward of EIC on 26.09.2012.

33331 26-Sep-12

Consolidated path RD 0-1240 =32' 6", 1240-1420 =26' 6", 1420-1950=32' 6". No distance shortened, case for fulfill the case sent to EIC on 25.09.2012.

33188 25-Sep-12

Request of Gram Panchayat received through DC Karnal. Path is 5 and 6 karam.

32665 14-Sep-12

6.38 km. Sub Total:

Planned - New Construction

Tuesday, April 02, 2013 Page 56 of 65

Page 57: Karnal Distt. Link Roads

Approved by Government - Conditionally

H - 6323 Gagseena-Kapron road to village Shajanpur. 2.731) km.Gharaunda

EE was asked to send the R/C/E as Hon'ble CM has approved the road subject to the condition that avaaviale path is not less than 5 Karam.

40675 08-Feb-13

CM has approved the road subject to the condition that available path is not less than 5 karam.

39651 27-Dec-12

Case is with MOS to AM vide no. 510 dt. 24.09.12.38815 18-Dec-12

Path 5k but in 1.635 to 2.73km path is 23' 9". Land ownsers ready to give land free of cost affidavits in file. 2km distance shortened. Upward of EIC on 10/9/2012.

32463 10-Sep-12

Recommended by MP Rohtak path is RD 0 - 1320 = 27'-6", 1320 to 1635+=Gram Panchyat land, 1635 to 2730 mtr+= 23'- 9".

21274 21-Mar-12

2.73 km. Sub Total:

Approved by Government but AA pending - Land Issue

H - 5784 Padda to Achala 5.501) km.Assandh

CM has approved the road on 13/12/2012 by subject to the condition that the Gram Panchayat shall provide land free of cost so that it becomes 5 karam.

41734 06-Mar-13

Case is with CM sett. Vide AM office no. 761 dt. 20.06.12.38790 18-Dec-12

CA to PS Agri. no. 279 on 08.06.1228518 27-Jul-12

PWD (B&R) is requested to take up the matter by EE (Karnal).27610 17-Jul-12

Approved on 21.01.11 with the direction to transfer PWD(B&R)14560 16-Nov-11

5.50 km. Sub Total:

Planned

H - 6855 Faridpur to Barsat 2.151) km.Gharaunda

Desired by CM, path is 6 karam.42666 15-Mar-13

2.15 km. Sub Total:

PR in Field Office

H - 6778 Bhambharheri to Shiv Mandir 1.771) km.Karnal

P/R sent to CA vide memo no. 871 dated 20.03.2013.44001 29-Mar-13

PR returned to EE Karnal for compliance.41583 04-Mar-13

In Meeting dated 11.1.2013, MP Rohtak asked for construction of this road.

39960 11-Jan-13

1.77 km. Sub Total:

PR in Head Office

H - 6426 Raod to Residence of Balbir Singh village Singara1) km.Karnal

Re-submit on 12/2/2013.40764 12-Feb-13

Not traceable in HO, EE has been asked to submit fresh PR.37868 27-Nov-12

CP less than 4k.32821 17-Sep-12

Tuesday, April 02, 2013 Page 57 of 65

Page 58: Karnal Distt. Link Roads

On the request of Sartaz Singh CM ordered on 13.03.2012 for examination and necessary action may be taken.

22940 07-May-12

km. Sub Total:

PR Upward of Engineer-In-Chief

H - 5034 Balrangran To Bansa 4.681) km.Assandh

Case sent to Govt. (sent to AM on 02.01.2013) for appropriate decision. Road does not fall in the policy of the board due to no distance shortened. Total cost Rs. 310 lacs (road work 127 lacs, cost of bridge 183 lacs). Bridge to be constructed by irrigation department on Indri drain 76 m long.

39740 02-Jan-13

Hon'ble CM has approved this road on 23.11.2010. Path is more than 27' 6" in entire length. No distance shortened. Hon'ble CM approved this road on 23.11.2010 with the condition to fulfill the norm.

33334 26-Sep-12

H - 5040 Sirsi To Jundla 3.962) km.Assandh

Case to be sent to Govt. for declaring it non feasible due to no path in RD 0 to 400m . Case is under process in H.O.

9751 12-Oct-11

Case to be sent on 15.09.11 by the EE, Karnal for non feasibility of this road

4232 06-Sep-11

H - 5255 Shekhpur To Padda3) km.Assandh

Sent to CA on 26/11/2012 for approval of Govt. The proposal fulfills all norms.

37727 26-Nov-12

CM approved on 13/09/2011.14040 31-Oct-11

MP Rohtak raised demand for this road on 3/9/2011.3968 05-Sep-11

H - 5781 Anand Vihar colony(Kabristan) to proposed Gogripur NGM , Karnal

1.704) km.Karnal

Path RD 0 to 1600m = 85', RD 1600-1700 no conslodation path exists. Panchayat land of Gogripur. Sent to Govt. CA no. 435 dated 25.08.11

32815 17-Sep-12

H - 5788 Bassi Akbarpur to Saderpur 3.105) km.Gharaunda

Path RD 100 to 1300m=7k, 1300 to 3100 =6k. Sent to Govt. CA no. 201 dated 15.03.10

32816 17-Sep-12

H - 6420 Firni of village Rugsana 0.966) km.Assandh

Case sent to Govt. for appropriate orders.41589 04-Mar-13

Path 0 to 960m = 21' wide.41588 04-Mar-13

Road does not fall in the policy being phirni. PR in HQ since 14/6/2012.

32819 17-Sep-12

On the request of Gram Panchyat CM ordered on 04.04.2012 to examin and put up .

22934 07-May-12

H - 6529 Assandh - Kaithal road to vill. Mund 4.777) km.Assandh

Case sent to Govt. vide CA memo no. 18 dated 14.01.2013.41390 19-Feb-13

EE reported that case has been re-submitted on 26.11.2012.39445 24-Dec-12

Tuesday, April 02, 2013 Page 58 of 65

Page 59: Karnal Distt. Link Roads

Consolidation path RD 0-1975=22', 1975-3225=22', 3225-4770=22'. 2km disatnce shortered. Estimated cost 140 lacs. Case is return to EE Karnal to attach recommendation of MLA. Unsafe bridge with RD also to be determined.

36312 23-Oct-12

Recommended by MLA Assandh available path for RD 0 to 1975= 4 karam, 1975 to 3225= 5 karam, 3225 to 4850= 4 karam.

25965 25-Jun-12

H - 6715 Beerdhandhari to Taraori 1.988) km.Nilokheri (SC)

Case sent to Govt. Vide CA memo no. 38 dated 31.01.2013. Path above 27' 6" wide , 1km distance shortened.

40203 19-Feb-13

Case returned back to EE karnal to submited properly visible sizra plan, CP should be marked RD wise. Available straight path at 90 degree.

34601 17-Oct-12

Recommended by MP, Karnal.33735 03-Oct-12

H - 6741 Shekhpura to Padha 1.609) km.Assandh

Case sent to Govt. vide CA memo no. 657 dated 18.12.12. Road falls in the policy of the board.

41395 19-Feb-13

Re-submit on 12/2/2013.40765 12-Feb-13

Hon'ble CM ordered on 13.09.2011 to take up the construction of 50 nos. roads. This road is at Sr. No 4. Path is 82' straight.

37541 16-Nov-12

H - 6748 Manglora to Nagla Megha 2.1010) km.Gharaunda

Case sent to Govt. vide CA memo no. 28 dated 29.01.2013.41391 19-Feb-13

Desired by Hon'ble CM on the request of Gram Panchayat Manglora. CP-6 karam diagonally.

38190 10-Dec-12

H - 6749 Jai Singh Pura to Phaphrana 4.2211) km.Assandh

Case sent to Govt. vide CA memo no. 27 dated 29.01.2013.41392 19-Feb-13

Recommended by MLA, Assandh Constituency CP 6 and 7 karam diagonally.

38191 10-Dec-12

H - 6750 Phaphrana to village Salwan 3.3512) km.Assandh

Sent to Govt. vide CA memo no 50 dated 31.01.2013. Path RD 1620-1876=25' 11" & 1876-2276= 26' 10" in rest ok, 0.370 km distance shortened.

40200 19-Feb-13

Recommended by MLA, Assandh Constituency CP 5, 6 and 7 karam diagonally.

38192 10-Dec-12

H - 6752 Tharwa majra to Kabul pur khera (Faizpur Khera) 3.5313) km.Assandh

PR submitted to CA on 27/12/2012. Path 22' wide in RD 183 to 1755m, RD 2178 to 2900m & in RD 3115 to 3550m. Distance of 1.18 km is shortended to reach PC Kurlan.

39616 27-Dec-12

Request of Gram panchayat received from the office of Hon'ble CM for action as desire. Available path is 0-183 5 karam, 183 to 1755 4 karam , 1755 to 2178 4.39 karam, 2178 to 2900 4 karam, 2900 to 3115 6 karam, 3115 to 3530 4 karam.

39310 20-Dec-12

H - 6766 Aungadh Jundla road to Aungadh Hathlana road. 0.3614) km.Assandh

Case sent to Govt. vide CA memo no. 26 dated 29.01.2013.41393 19-Feb-13

Recommended by MLA Assandh, Path is 30'-8"39803 08-Jan-13

Tuesday, April 02, 2013 Page 59 of 65

Page 60: Karnal Distt. Link Roads

H - 6791 Barsat-Barana PWD road to Shamshan Ghat, Faridpur 0.9815) km.Gharaunda

Case sent to Govt. vide CA memo no. 61 dated 06.02.2013.41394 19-Feb-13

Recommended by Hon'ble Agriculture Minister, Haryana. Path 0 to 474=27' 6", 475 to 975=22'.

40209 30-Jan-13

H - 6809 Salwan to Hafed sugar mil Assandh along Hansi Bhutana Canal

4.4316) km.Assandh

Case sent to CA on 14.02.2013. Distance shortened 2.07km. Road does not fall in the policy of the Board, as land belongs to Irrigation Deptt.

41059 14-Feb-13

Requested by Sh. Jagbir Sandhu, Ex-president, Gagsina. On 7.1.2013 CM desired appropriate action be taken.

40669 07-Feb-13

H - 6857 Phirni portion in village Jabala 0.5217) km.Assandh

Case sent to Govt. on 1/4/2013 for appropriate order.44055 02-Apr-13

Recommended by MLA Assandh Path is 5 karam.43734 22-Mar-13

42.24 km. Sub Total:

PR with AM Office

H - 6473 Guniana to Karnal-Brass Kaithal Road 2.111) km.Karnal

P/R with Hon'ble AM vide MOS no. 529 dated 13.12.12.39758 04-Jan-13

CP RD 0-1005= 32', 1005-2110= 27' 6". No distance shortened. Estimate cost RS. 80 lacs.

36795 05-Nov-12

Villagers request through D.C. Karnal.24446 06-Jun-12

2.11 km. Sub Total:

PR with CM Office

H - 6513 Nathauri to Kalri Jagir 2.781) km.Indri

Case is with MOS to AM vide no. 371 dt.24.07.12. Case is with CM sett. Vide AM office no. 1220 dt. 10.12..12.

38840 18-Dec-12

On 07.12.2012 Agriculture Minister asked that EE should explain as to different noting on page 3 ( Road ID 5558) and different report on page 2 ( Road ID 6513). Case returned to EE (Road).

38311 13-Dec-12

Case return to field office.38308 13-Dec-12

P/R PS Agri. to Govt. vide no. 1540 dated 10.07.1228712 27-Jul-12

CA to PS Agri. no. 396 on 9.07.1228620 27-Jul-12

Path is 33'. 2km distance shortened. Upward of EIC on 2/7/2012.26459 02-Jul-12

Path is RD 0 to 1060mtr 33' straight RD 1060 to 1825mtr 60' straight RD 1825 to 2780mtr=47' straight 2km distance shortened road fall in policy. EE not mentioned who has recommended the road

25507 18-Jun-12

2.78 km. Sub Total:

PR with PSA Office

H - 6395 Chochra-uplana road to Chochra-Choz Karsa road 2.241) km.Assandh

CP RD 0-840=33', 840 - 2238= 27' 6". Case sent to PSA on 13.03.2013.

42194 13-Mar-13

Tuesday, April 02, 2013 Page 60 of 65

Page 61: Karnal Distt. Link Roads

Sent to HQ on 12/2/2013.40779 13-Feb-13

EE asked to mention actual path available and GPS track on 25.04.2012.

37866 27-Nov-12

Recommended by MLA Assandh Path is 5 & 6 karam.22525 24-Apr-12

2.24 km. Sub Total:

Rejected by Government

H - 5035 Chocra To Kumar Killa 1.821) km.Assandh

CM has not approved the proposal on 23/12/2011 as the available path (RD 0 - 160m, 5 karam, 160 - 460m 4 karam, 460 - 1120m 6 karam.

16875 04-Jan-12

Estimate Rs. 37.60 lacs. Sent to Govt. vide C.A. No. 413 on 12.8.11. Road leading to fields only.

9746 12-Oct-11

H - 5630 Barani to Barana 2.382) km.Nilokheri (SC)

Govt. has not approved as per orders dated 13.12.2012.39222 20-Dec-12

RD 1120 to 2100m no consolidation path exists. Panchayat gave resolution to transfer the land. (Cost 61.24 lacs), Gram Panchayat ready to give additional land and case is with APSCM CM Sectt. No. 4293 dated 28.05.2012.

32814 17-Sep-12

Hon'ble C.M not approved on 10.05.2011 due to less path. Now Gram Panchayat resolved to provide 28' 6" land free of cost and the case is being sent to Govt. for approval.

8268 03-Oct-11

H - 5763 Munak to Panipat Refinery 4.163) km.Gharaunda

Declared non feasible by Govt.14539 16-Nov-11

H - 5775 Jani road to Jundla to Nirmal Dham and other Dera at Jundlla

1.724) km.Assandh

Non feasible by Govt. on 23.08.1014551 16-Nov-11

H - 5776 Biana to Fazilpur 3.155) km.Indri

Not approved on 6.08.1114552 16-Nov-11

H - 5777 Biana to Randoli 1.856) km.Indri

Not approved on 6.08.1114553 16-Nov-11

H - 5780 Mirgan to Dera Pehalwan 1.507) km.Karnal

Filled by Govt. on dated 21.01.1114556 16-Nov-11

H - 5782 Gurudwara Nanaksar Singra to Buddanpur Veeran 2.358) km.Assandh

CM has not approved the proposal due to non-availibilty of consolidation path prescribed in the norms of the HSAMB and also being Irrigation land.

39631 27-Dec-12

In 600m path 23', rest 5k. 3.5km distance shortened. Upward from EIC on 3/7/2012.

26508 03-Jul-12

Filled by Govt. on 26.08.1014558 16-Nov-11

Assandh

Tuesday, April 02, 2013 Page 61 of 65

Page 62: Karnal Distt. Link Roads

H - 5783 Bilona to Lalian 4.509) km.Assandh

Earlier approval now deapprovaed by the Govt. being parallel road.27609 17-Jul-12

Approved by on 21.01.1114559 16-Nov-11

H - 5785 Aungad road to Manjura road in Vill. Hatlana 0.2410) km.Assandh

Not approved on 19.07.1114561 16-Nov-11

H - 5787 Popra to Alewa 4.9011) km.Assandh

A.M. ordered on 16.12.2011 that the prposed road has in narrow and unsafe bridge. There is no need to construct this road.

17319 10-Jan-12

Sent to Govt. CA no. 321 dated 15.07.1114563 16-Nov-11

H - 6328 Dhumsi to Ladwa-Indri road 1.1512) km.Indri

Govt. has not approved as per orders dated 13.12.2012.39242 20-Dec-12

Path is less than 25' every where. 2km distance shortened. Upward of EIC on 2/7/2012.

26464 02-Jul-12

Recommended by Chairman Sh. Zila Parishad Karnal path is 0 to 880mtr= 6 karam, 880 to 1150mtr = 4 karam.

21279 21-Mar-12

H - 6358 Koer to Bhola Khalsa 3.3213) km.Nilokheri (SC)

Govt. has not approved as per orders dated 13.12.2012.39225 20-Dec-12

CA to PS Agri. no. 418 on 20.07.12.28636 27-Jul-12

Path 26.7' in 1.9km, rest ok. No distance shortened.27574 17-Jul-12

Recommended by M.P. Karnal Path is 5&7K.22352 11-Apr-12

H - 6377 Kabulpur Khera to Fafrana Thari road 1.2514) km.Assandh

Govt. has not approved as per orders dated 13.12.2012.39299 20-Dec-12

No path in 1 to 2.-3km. Rest 5.8k. No distance shortened. Upward of E-In-C.

27924 20-Jul-12

Request of Jagbir Sandhu received through office of C.M. Haryana. On 18.3.2012

22371 11-Apr-12

H - 6423 Nidana to Kachhawa 3.0015) km.Nilokheri (SC)

Not approved by Hon'ble CM vide orders dated 28.12.2012 due to less path.

39815 09-Jan-13

Path 21' 4" or 22'. No distance shortened. Upward of EIC on 18/9/2012.

32982 18-Sep-12

Three bridges at RD 220 (88' span), 1155 (65' span), 1965 (100' span).

32820 17-Sep-12

On the request of Gram Panchyat CM ordered on 04.04.2012 to examine and put up . PR awaited.

22937 07-May-12

H - 6526 Main PWD road up to Stadium Gurukul Mor Majra 0.2216) km.Assandh

CM has approved not approved on 18/2/2013.41727 06-Mar-13

Case sent upward of EIC on 17.08.2012.37869 27-Nov-12

Recommended by MP Rohtak no path available but Gurukul samiti ready to provide 5 karam path.

25863 22-Jun-12

Assandh

Tuesday, April 02, 2013 Page 62 of 65

Page 63: Karnal Distt. Link Roads

H - 6533 Assandh Jind road (Bandrala) to Asandh Kaithal road (upto Gurudawara)

3.1217) km.Assandh

Hon'ble CM has not approved the const. Of this road due to leading to religious place and no distance shortened, on 18.02.2013.

42186 12-Mar-13

Path is 5k. Roads to Religious place & no distance shortened. Upward of EIC on 2/7/2012.

26463 02-Jul-12

H - 6534 Amupur to Ramgarh 2.5518) km.Nilokheri (SC)

Not approved by Hon'ble CM vide orders dated 13.12.2012 due to less path.

39829 09-Jan-13

Path 18',22'. No distance shortened. P/R PS Agri. To Govt. vide no. 1536 dated 10.07.12

28708 27-Jul-12

MP karnal recommended the road.25970 25-Jun-12

H - 6535 Darbari primary school to proposed NVK link( Karnal - Kachwa NBK link (Karnal Kachwa road to Laloji Gurudwara on Karnal - Kaithal road).

0.4619) km.Karnal

CM has not approved the proposal due to non-availibilty of consolidation path prescribed in the norms of the HSAMB.

39634 27-Dec-12

Path 4k. No distance shortened, Upward from EIC on 3/7/2012.26497 03-Jul-12

Request of Gram panchyat through MLA Karnal CM ordered on 08.02.2012 to examin and put up. Available path form Rd 0 to 400m= 4 karam.

25971 25-Jun-12

H - 6699 Dera Gama to Assand Sirsal 1.3720) km.Assandh

Hon'ble CM has not approved the cosnt of the road on 14.03.2013.43960 28-Mar-13

Path 33' in entire 1.37 km length. Only 825m distance shortened. Road falls in policy of the board. Estimated cost. 41 lacs. Case submitted to Govt. from CA.

34609 17-Oct-12

Recommended by MLA, Assandh. Path is 7karam diagonal33109 24-Sep-12

H - 6714 Anjanthali to Saddiqpur 2.5121) km.Nilokheri (SC)

Not approved by Hon'ble CM vide orders dated 28.12.2012 due to less path.

39838 09-Jan-13

Recommended by Hon'ble Speaker. CP 0-1916 (21'-3"), 1916-2512 (22'). 2km distance shortened to reach NGM Nilokheri. Road does not fall in policy of board due to less consolidation path.

36316 23-Oct-12

H - 6724 Dacherchor Karsa road to Dera Fatehgarh 2.8622) km.Assandh

P/R filed as it does not fall in the policy of the board due to leading to dera.

39949 11-Jan-13

Upward of EIC on 27/11/2012 for decision of filing the case.37830 27-Nov-12

1604m distance shortened to reach NGM Nissing. Estimated cost Rs. 80 lacs. Leading to Dera.

37829 27-Nov-12

Path 0 to 2860m = 29' 8".37519 15-Nov-12

villagers requests through XEN ,HSAMB Karnal Path is 6 karam34617 18-Oct-12

50.38 km. Sub Total:

Planned - New Construction

Tuesday, April 02, 2013 Page 63 of 65

Page 64: Karnal Distt. Link Roads

Relates to other department

H - 5778 Jalala Veeran to Sambli 3.201) km.Nilokheri (SC)

Referred to PWD(B&R) on 21.01.1114554 16-Nov-11

3.20 km. Sub Total:

Tuesday, April 02, 2013 Page 64 of 65

Page 65: Karnal Distt. Link Roads

1094.12 km. Grand Total:

Tuesday, April 02, 2013 Page 65 of 65