Karangasem Banjar Aas Deep Well Water Project
-
Upload
erich-french -
Category
Documents
-
view
40 -
download
3
description
Transcript of Karangasem Banjar Aas Deep Well Water Project
Karangasem Banjar Aas Deep Well Water Project
Deep well (Bore) for Br Aas Community Bale for local water distribution
TITLE | 2
Project Description & Scope
Description; • The Br Aas deep well project focuses specifically on the drilling of
a well at the Banjar and installation of a well pump and tank to provide a reliable source of clean water to the (~ 200) families of the Aas community – Part 1 (this project)
• The overall Aas water project is to install a piped distribution network up the mountain to those of the community most in need. – Part 2
Project Scope• Drill a well nominally 40m deep in hard rock.• Install a submersible pump (2m3/hr) which will use power from the
Banjar Hall• Install a 3300Lt receiving tank with outlet to provide water at the
community centre.
TITLE | 3
Project Funding & Team
Funding; • RC Ignacio – California - Cash via the Sunset
foundation• $US 6000.00 Project Budget• Rp 68.182.100Team• Sunset; Allan Starr• RC Colorado Springs; Rich Foss• Other Members: Ping – from Culik
TITLE | 4
Financial Budget & Current Status
Activity Status Budget IDR Actual
• Well Drilling Contract – fixed price Complete 60.000.000 60.000.000
• Submersible Pump & installation• Pump Building/Cover• Receiving Tank and fittings
UnderwayNot StartedUnderway
5.000.000 500.000 1.500.000
• Power for Pump Underway 1,000.000
• Misc
TOTAL
Underway 182.000
68.182.100
Budget Comment - may be under pressure as the power connection cost is unknown at this point
TITLE | 5
Project Status Snapshot
Project Scope and IssuesScope: Bore a deep well and install a submersible pump and
receiving tank at the Banjar to supply water to the local community
Issues:
• Securing a competent Boring contractor with local experience and able to guarantee water – no water no money. Fixed price contract
• Ensuring cash flow for the contractor
• Power supply for the pump
• Pump selection and installation
Project Summary• Beneficiary: Br Aas
• Funding: Rotary Club Ignacio, CA Found.
• Funding Obtained: Rp68.182.100
• Estimated Cost: ~ Rp68.182.100
• Disbursed to Date: Rp60.000.000
• Planned Schedule: Commence April, complete July
• Actual and Expected Schedule: Complete Nov 2014
• Special skills or needs: primarily drilling contractor
Current Status & Look AheadPlanned Key Milestones
Select contractor March 14
Kepala Dusun & Adat agreement April complete
Bore Contractor establishment April complete
Bore capacity test Plan June Act Aug complete
Sponsor interim report & Visit 10/14 complete
Pump & tank installation Nov 14
Final report and Follow-up visit Dec 14
Current Outlook
Budget Bore Good Power Cost
Schedule Slow
Community Dusun Good
RC sponsor Visit Complete
Resources Ok
TITLE | 6
Br Aas - Why
TITLE | 7
The Bore is Successful
TITLE | 8
Project Stewardship
CONTROLS
• Is approver separate from person making payments? NO but two RC members from different clubs managing project.
• Is bank account reconciled by other than check signor? Yes
• To what extent is cash vs. checks being used or anticipated on the project? All EFT or cash
• What efforts were done to reduce the use of cash? Minor difficult in region
• Was bank account established within Rotary guidelines? Club acct
POTENTIAL CONFLICTS OF INTEREST
• Key actual or potential suppliers and possible conflicts? None
• Any rotary member’s association with the village, school, agency? NO
• Any waivers approved or being sought from Rotary Int’l? NO