Karangasem Banjar Aas Deep Well Water Project

8
Karangasem Banjar Aas Deep Well Water Project Deep well (Bore) for Br Aas Community Bale for local water distribution

description

Karangasem Banjar Aas Deep Well Water Project. Deep well (Bore) for Br Aas Community Bale for local water distribution. Project Description & Scope. Description; - PowerPoint PPT Presentation

Transcript of Karangasem Banjar Aas Deep Well Water Project

Page 1: Karangasem  Banjar Aas Deep Well Water Project

Karangasem Banjar Aas Deep Well Water Project

Deep well (Bore) for Br Aas Community Bale for local water distribution

Page 2: Karangasem  Banjar Aas Deep Well Water Project

TITLE | 2

Project Description & Scope

Description; • The Br Aas deep well project focuses specifically on the drilling of

a well at the Banjar and installation of a well pump and tank to provide a reliable source of clean water to the (~ 200) families of the Aas community – Part 1 (this project)

• The overall Aas water project is to install a piped distribution network up the mountain to those of the community most in need. – Part 2

Project Scope• Drill a well nominally 40m deep in hard rock.• Install a submersible pump (2m3/hr) which will use power from the

Banjar Hall• Install a 3300Lt receiving tank with outlet to provide water at the

community centre.

Page 3: Karangasem  Banjar Aas Deep Well Water Project

TITLE | 3

Project Funding & Team

Funding; • RC Ignacio – California - Cash via the Sunset

foundation• $US 6000.00 Project Budget• Rp 68.182.100Team• Sunset; Allan Starr• RC Colorado Springs; Rich Foss• Other Members: Ping – from Culik

Page 4: Karangasem  Banjar Aas Deep Well Water Project

TITLE | 4

Financial Budget & Current Status

Activity Status Budget IDR Actual

• Well Drilling Contract – fixed price Complete 60.000.000 60.000.000

• Submersible Pump & installation• Pump Building/Cover• Receiving Tank and fittings

UnderwayNot StartedUnderway

5.000.000 500.000 1.500.000

• Power for Pump Underway 1,000.000

• Misc

TOTAL

Underway 182.000

68.182.100

Budget Comment - may be under pressure as the power connection cost is unknown at this point

Page 5: Karangasem  Banjar Aas Deep Well Water Project

TITLE | 5

Project Status Snapshot

Project Scope and IssuesScope: Bore a deep well and install a submersible pump and

receiving tank at the Banjar to supply water to the local community

Issues:

• Securing a competent Boring contractor with local experience and able to guarantee water – no water no money. Fixed price contract

• Ensuring cash flow for the contractor

• Power supply for the pump

• Pump selection and installation

Project Summary• Beneficiary: Br Aas

• Funding: Rotary Club Ignacio, CA Found.

• Funding Obtained: Rp68.182.100

• Estimated Cost: ~ Rp68.182.100

• Disbursed to Date: Rp60.000.000

• Planned Schedule: Commence April, complete July

• Actual and Expected Schedule: Complete Nov 2014

• Special skills or needs: primarily drilling contractor

Current Status & Look AheadPlanned Key Milestones

Select contractor March 14

Kepala Dusun & Adat agreement April complete

Bore Contractor establishment April complete

Bore capacity test Plan June Act Aug complete

Sponsor interim report & Visit 10/14 complete

Pump & tank installation Nov 14

Final report and Follow-up visit Dec 14

Current Outlook

Budget Bore Good Power Cost

Schedule Slow

Community Dusun Good

RC sponsor Visit Complete

Resources Ok

Page 6: Karangasem  Banjar Aas Deep Well Water Project

TITLE | 6

Br Aas - Why

Page 7: Karangasem  Banjar Aas Deep Well Water Project

TITLE | 7

The Bore is Successful

Page 8: Karangasem  Banjar Aas Deep Well Water Project

TITLE | 8

Project Stewardship

CONTROLS

• Is approver separate from person making payments? NO but two RC members from different clubs managing project.

• Is bank account reconciled by other than check signor? Yes

• To what extent is cash vs. checks being used or anticipated on the project? All EFT or cash

• What efforts were done to reduce the use of cash? Minor difficult in region

• Was bank account established within Rotary guidelines? Club acct

POTENTIAL CONFLICTS OF INTEREST

• Key actual or potential suppliers and possible conflicts? None

• Any rotary member’s association with the village, school, agency? NO

• Any waivers approved or being sought from Rotary Int’l? NO