Unified Government of Wyandotte County/Kansas City Kansas Proposed 2009 Budget July 10, 2008.
Kansas City, Kansas Public Schools 2016-2021 Bond ...€¦ · 2016-2021 Bond Referendum Challenges...
Transcript of Kansas City, Kansas Public Schools 2016-2021 Bond ...€¦ · 2016-2021 Bond Referendum Challenges...
KansasCity,KansasPublicSchools2016-2021BondReferendum
ChallengesandRecommendations
ShallUnifiedSchoolDistrictNo.500,WyandotteCounty,Kansas(KansasCity),issuegeneralobligationbondsinanamountnottoexceed$235,000,000,topaythecoststopurchaseandimprovesites,todemolishcertainexistingfacilities,andtoacquire,construct,equip,furnish,repair,remodelandmakeadditionstobuildingsusedforschooldistrictpurposes,andallothernecessaryimprovementsrelatedthereto,andtopayfeesandexpensesrelatedthereto;allpursuanttotheprovisionsofK.S.A.10-101etseq.;K.S.A.25-2018(f);K.S.A.72-6761;andK.S.A.75-2315etseq.?
February,2018
2
HistoryoftheNovember,2016BondReferendumIn2015,withschoolbuildingsthataveraged57yearsofage,theKansasCity,KansasPublicSchoolsdecidedthatitwasimportanttotakestockofthefacilitiesneedsofthedistrict,andthecapacityofexistingbuildingstomeetthoseneeds.Thedistrictengagedexpertsinthefieldsofengineering,architecture,andconstructiontoanalyzeschoolfacilitiesandproduceacomprehensivefacilitiesstudy.This18-monthstudyidentifiedover$500millioninfacilitiesneeds.Whatwasclearwasthatithadbecomeincreasinglydifficultforsomeofthedistrict’sfacilitiestomeetthelearningneedsofdistrictstudents.Subsequentpollingofthecommunityindicatedthatthecommunitywassupportiveofaplantoaddressthesefacilitiesneeds,butthatthecommunitywouldonlysupportsuchaplanifitdidnotincreasetaxes.Inordertodevelopaplantoimprovedistrictfacilitieswithoutraisingtaxes,thedistrictbroughttogetheradiverse,talentedandengagedgroupofcommunityvolunteers,includingparents,communitymembers,currentandretirededucators,businesspeople,non-profitleadersandrepresentativesoftheUnifiedGovernmentofWyandotteCounty,toformaCommunityVisioningCommittee.Thecommitteeexaminedinformationprovidedbyateamofexperts(includingarchitects,engineersandschoolplanners),andassistedthedistrictindevelopingalong-rangefacilitiesplan.ThecommitteeultimatelyrecommendedthattheBoardofEducationaskthevoterstoapprovea$235million,no-tax-increasebondreferendum.Thisreferendumwasapprovedby79%ofvotersinNovember,2016.What’sintheplan:
• Safetyandsecurityenhancementsatallschools,includingnewsecuredentrances• Twonewelementaryschoolsandtwonewmiddleschools,replacingexisting
buildingso NorthwestMiddleSchoolo CombinedCoronado/WestMiddleSchoolo CombinedBethel/WhiteChurchMiddleSchoolo WelbornElementarySchool
• HighschoolCollegeandCareerAcademyspacesandtwonewmodernsciencelabsineachhighschool
• Middleschoolcareerexplorationspacestoenhancestudentopportunitiestodiscovercareeroptions
• Kitchenconstructionandupgradesatonemiddleandsixelementaryschools• Nineelementaryschoolswillreceiveplaygroundimprovementsspecifictotheneeds
ofeachschool• Buildingremodelsandrenovations
Additionalconsideration:BondproceedsmustbeexpendedaccordingtoaschedulesetforthbytheIRS,ortheylosetheirtax-exemptstatus,whichwouldleadtolitigationwiththebondholders.Spendableproceedsmustbeexpendedaccordingtothefollowingschedule:Year1–10%spent;Year2–30%spent;Year3–60%spent;Year5–85%spent.
3
NewConstruction–NorthwestMiddleandWhiteChurch/BethelElementary:ChallengesandSolutions
DesignChallenges–TheoriginalplanforthebondapprovedbyvotersinKansasCity,KansasinNovemberof2016includedanewNorthwestMiddleSchool(builtonthesiteoftheexistingNorthwestMiddleSchool)andanewcombinedWhiteChurch/BethelElementarySchool(builtoneithertheWhiteChurchorBethelsites.)However,afterathoroughexaminationofeachofthepotentialconstructionsites,theBoardofEducationwasadvisedofchallengesinvolvingpotentialconstructionforNorthwestMiddleSchoolandthecombinedWhiteChurch/Bethelschoolconstructionprojects,duringameetingonJuly10,2017.
• WhiteChurch/BethelElementary–Originally,thecombinedschoolwasplannedfortheWhiteChurchsite.However,furtherexaminationofthesitedeterminedthatanewelementaryschoolwouldnotfitontheWhiteChurchsite,duetothecloseproximityoftheadjacentcemetery.(Thedistrictwasadvisedthattherewasastrongpossibilitythatunmarkedgravesexistedbeyondthecurrentfootprintofthecemetery.)ConsiderationwasgiventomovingtheconstructiontotheBethelsite.However,thatsiteonlyhasasinglepointofaccess,andconstructiononthatsitewouldcreateanunacceptableriskbymixingconstructiontrafficwithschooltrafficthroughthatsinglepointofaccess(includingschoolbuses,parentvehicles,andstudentwalkers.)Thedecisionwasmadetobeginlookingforotherpropertiestolocatethecombinedelementaryschool.
• NorthwestMiddle/WarehouseandCentralKitchen–TheoriginalplanwastobuildthenewNorthwestMiddleSchoolbuildingontheexistingNorthwestsite,whilecontinuingtousetheNorthwestsiteforschoolduringconstruction.However,itwasdeterminedthatitwasnotpossibletoorientandfitthenewschoolontheexistingpropertywhilemaintainingoperationoftheexistingschool.Itwasfurtherdeterminedthatthenewschoolwouldfitonlandcurrentlyownedbythedistrictatthebottomofthehill,wheretheexistingwarehouseandcentralkitchenarelocated,butthatwouldrequirerelocatingbothfacilitiesoftheexistingfacilities.
Challenges…Solutions
• TheBoardofEducationauthorizedtheadministrationtoengagearealtorandseekandrecommendpropertytopurchaseforanewwarehouseandcentralkitchenandanewelementaryschoolattheSeptember12meeting.
TheAdministrationhiredateamofprofessionalstobegintheprocessofsearchingforandacquiringproperty.Thisteamwasresponsibleforlocatingsuitableproperties,performingduediligenceonallproperties,andpresentingpotentialoptionstotheadministration,whichwouldthenputaproposalbeforetheBoardofEducation.
4
ProfessionalTeam• RealEstateAgent–KCRegionalHomes,Inc.• DirectorofFacilities–KCKPublicSchools• CivilEngineer–MKECEngineering• ConstructionTeam–JEDunn• Architectural/DesignTeam-HTK
Thisteamwaschargedwithlocatingsuitableproperties,andperformingduediligence.TheBoardofEducationreceivedanupdateontheprogressofthepropertysearchonSeptember26,2017.AdditionalupdatesweregivenattheOctober19,November14andNovember28,2017BoardofEducationmeetings.PreliminarySearchforPropertiesforWarehouse/CentralKitchen
Themembersoftheteamreviewedmorethanadozenproperties,inordertodeterminetheirsuitabilityforrelocatingtheWarehouse/hutandCentralKitchen.ImportantconsiderationsfortheWarehouse/HutandCentralKitchenincluded:
• Warehouseo 15,000squarefeetofspaceo 3-4loadingdocksatappropriateheightforloadingandunloadingtruckso Accesstomainarterialstreets
• CentralKitcheno 10-15,000squarefeetofspaceo 2loadingdocksatappropriateheightforloadingandunloadingtruckso Centrallocationwithaccesstomainarterialstreetso Sufficientpowerforkitchenoperations
Thefollowingpropertieswerereviewed:
22N.6thStreet,-$550,000-Warehouse• 10,400SFofSpace
o Didnotmeetspaceneedsforthewarehouseo Onlyonedock,notraisedo Only400ampsofpower
33rdandParallelproperty–notlisted–CentralStatesConferenceCenterownership–Warehouse/Kitchen
• Theownerwasnotwillingtoselltheproperty
5
927S.7thStreet-$805,000-Warehouse• 23,688SFofSpace(partofitleasedout)
o Alldockslowtoground,concernaboutaccesswithtruckso Notenoughpowero Concernedaboutdrainageonsite,waterinfiltrationo Roofoverentrywasinverypoorconditiono Suitableofficespace
1510S.42ndStreet-$1,395,000-Warehouse
• 40,000SFofSpaceo Toolarge,morethanhalfofspacenotuseable,demo15,000SF($62,000)o Concernedaboutofficespace,appearedtohavewaterinfiltration,have
totearoutandredoallofspace–obviousmoldthroughouto Askingpricetoohigh
3850Fairbanks-$2,200,000-Warehouse
• 12,724SFofSpaceo Endedupbeingsoldo Askingprice–prohibitive
7849Splitlog-$495,000–Warehouse/Kitchen
• 2.74acres–lando Notinterestedinlocationforwarehouse/kitchen–havetobuildboth
3627MinnesotaAve-$120,000
• 6.48acres–lando Concernedaboutusabilityofallofland–slopesdownonbackside–50’
dropo Concernedaboutwhatisbeingdumpedonthebackhalfofproperty–
havetoconfirmo Ownersoldpropertypriortousbeingabletocompletepreliminarydue
diligence
1112Cheyenne-$750,000-Warehouse• 15,000SFofspace
o Interiorclean,openo Availabledocksfortruckdeliverieso Goodlocationforwarehouseonly(notbigenoughforkitchentoo)o Officespaceneedstoberedoneo Electricalandroofingupgrades,nowaterinfiltrationthatwasnoticeable
6
1929N.9thStreet-$249,000–Warehouse/Hut• 8,415SFofSpace
o Notlargeenoughforwarehouse
5938StateAvenue-$495,000–Warehouse/Hut• 7500SFofSpace
o Soldbeforewecouldlookatit
3138LeavenworthRoad-$50,000–Warehouse/Hut• Approximately7acresofland
o PublicsharedaccessthroughWestgateshoppingareao Pipelinethatrunsthroughtheproperty,limitinguseofsomeofthe
propertyo Accessonbackside–59thstreet–difficultfortruckstoaccesso Havetobuildwithlimitedspace
5604StateAvenue-$225,000(originalasking)–Kitchenlocation• 5.68acresofProperty
o ExistingBowlingalley–demo(estimatedat$50,000)o Negotiatedsalepriceto$195,000(requestedownertoconsiderdonation
ofproperty,declined)o Sewersrunthroughmiddleofproperty,mayhavetorelocatewithnew
building?o Enoughpropertytobuildkitchenandlocationiscentrallylocated
Warehouse/KitchenComparables/Viewed
Location SquareFootage Cost Av.Cost/SFAv.
Cost/Acre22N.6thStreet 10,400 $550,000 $52.8833rd&Parallel(Land) 12acres notlisted927S.7thSt 23,688 $805,000 $33.981510S.42ndSt 40,000 $1,395,000 $34.883850Fairbanks 12,724 $2,200,000 $172.907849Splitlog 2.74 $495,000 180,657$3627Minnesota 6.48 $120,000 18,519$1112Cheyenne 15,000 $750,000 $50.001929N.9thSt 8,415 $249,000 $29.595938StateAve 7,500 $495,000 $66.003138LeavenworthRd 7.00 $50,000 7,143$5604StateAve 5.68 $195,000 34,331$
Average $62.89 $60,162
7
PreliminaryDueDiligence(Seebelow)• Administrationreviewedpropertieswithrealtorandcompletedpreliminarydue
diligencetodetermineusability.Twopropertieswerelocated:o DistrictcompletedpreliminaryduediligenceandmadeanofferfortheState
AvenuepropertyonSeptember29,2017forCentralKitcheno Districtcompletedpreliminaryduediligenceandmadeanofferforthe
CheyennepropertyonOctober4,2017forWarehouse
RecommendationsmadebyAdministration• BoardApprovedPropertyAcquisition:
o 1112Cheyenne–Warehouse–November14,2017o 5640StateAvenue–CentralKitchen–November14,2017
PreliminaryDueDiligenceProcess–Warehouse/CentralKitchenPriortoContractfinalization,theAdministrationperformedduediligence,inordertoensurethatthepropertiesweresuitableforpurchaseandconstruction.
1) EngageRealtor–toseekpropertiesforreviewwithestablishedcriteria
2) DirectorofPhysicalPropertiesdidpreliminaryreviewprocess• LocationandSquarefootage
o Accessiblelocationwithaccesstomainarterialstreetso Sufficientsquarefootageforwarehouse/centralkitchen
• AvailabilityofUtilitieso Sewers,water,electricityandgas
• Encumbranceso Easements–gas,highpowervoltagelines,etc.
• Topography/OtherPossibleDevelopmentIssueso Cut/Fill
• Accesso Conditionandtypeofstreetaccess
• OtherObstacleso Floodplain
3) CivilEngineer,Construction/DesignTeamworkedtogethertoreview
preliminaryduediligenceasrequested.
8
PropertyReview–NewWhiteChurch/BethelElementaryThefollowingpropertieswerereviewedtodeterminesuitabilityforthenewWhiteChurch/Bethelelementaryschool:
8840LeavenworthRoad-$110,000Acres–14.32
• Thepropertyhadasteeptopography,withacreekrunningthroughit.Itwouldrequireapumpstationforsewer
3008N.91stSt-NotListedwouldsellAcres–8.7
• Thepropertyisinafloodplain• Topographyonthesiteincludesaverysteepbackhalfofproperty,along
withastreamrunningthroughproperty
9240Parallel-$250,000Acres–10.15
• Notenoughacreagetobuildduetotopographyissues;Rearlotaccess
1501N.90thSt-NotListedAcres–50
• Discussed–ownerdecidedwantedtoselltoadeveloper
8741Parallel-$2,404,799Acres–18.4
• CostProhibitive–Morethantwiceasexpensiveasnexthighestproperty
8846StateAve-$950,000Acres–9.4
• Thepropertywasextremelynarrow(330’wide)andnotsuitableforaschool
3308N.75th-$255,000Acres–16.68
• TopographyofthepropertyallslopestotheNorthwest• Theterrainwasrugged,withpossibly6acresuseable.Inaddition,sewerson
LeavenworthRd,mayneedpumpsystem
1841N.94thSt.-$520,354Acres–9.6
• ThepropertyislocatedoutsidecurrentboundariesofWhiteChurc/Bethelattendanceareas.Inaddition,acreekrunsthroughtheproperty,andtheterrainissteep
9
8919LeavenworthRoad-$250,000Acres–.939
• Havetocouplewithtwootheradjacentproperties
8927LeavenworthRoad–(MakeOffer)Acres–.987
• Sameowner-• Havetocouplewithtwootheradjacentproperties
3033and2913N.89thTerr–(Makeoffer)Acres–4.661
• Bankowned–didnotmakeoffer–afterreviewingproperty
2906N.89thTerr-WyCoLandBankAcres–1.66
• Didnotpursueafterlookingatproperty
8833Waverly-$750,000Acres–14.7
• PropertytopographydoesslopefromcenterofpropertytotheNorthandWest,thereareaccessissuesoffof91stStreetthatcanandneedtobeaddressedtoensuresafeentryintotheproposedschoolproperty
• Flattensoutatcrest
PreliminaryDueDiligenceProcessPriortoContractfinalization,theAdministrationperformedduediligence,inordertoensurethatthepropertiesweresuitableforpurchaseandconstruction.
1. EngageRealtor–toseekpropertiesforreviewwithestablishedcriteria
2. DirectorofPhysicalPropertiesdidpreliminaryreviewprocess• LocationandAcreage
o Withinattendanceboundarieso 10+acresforconstruction
• AvailabilityofUtilitieso Sewers,water,electricityandgas
• Encumbranceso Easements–gas,highpowervoltagelines,etc.
• Topography/OtherPossibleDevelopmentIssueso Cut/Fill
10
• Accesso Conditionandtypeofstreetaccess
• OtherObstacleso Floodplain
3. CivilEngineer,Construction/DesignTeamworkedtogethertoreviewpreliminary
duediligenceasrequested.
Properties–Comparables
NewElementarySchoolSite–PendingApprovedContract
DueDiligence–8833Waverly(14.7Acres)
1. PropertyAppraisal(101pages)• CompletedbyValbridgePropertyAdvisors• ValueConclusion(Appraisal)$670,000• Selleragreedtoreduceaskingpricetoappraisedvalue
Properties-Comparables8833Waverly
Acres ListPrice AvCost/Ac8833 Waverly 15 750,000$ 50,000$9800 ParallelPky 2.77 959,271$ $346,3078500 StateAve 11 2,395,800$ $217,80013755 ParallelPky 14.89 1,005,722$ $67,5438542 StateAve 1.42 309,276$ $217,8009746 ParallelPky 2.88 996,072$ $345,85810108 ParallelPky 0.94 163,785$ $174,2392300 N.99thSt 4.81 838,094$ $174,2403124 N.103rdTerr 7.38 849,000$ $115,0418846 StateAve 9.4 950,000$ $101,0648932 StateAve 1.23 135,000$ $109,756
11
o CredentialsfortheAppraiser§ RecommendedbyRealEstateBroker(KCRegionalHomes,Inc.)§ ComprehensiveappraisalshouldbedonebyafirmthatholdstheMAI
certificationDescriptionofMAIDesignationbyAppraisalInstitute:
2. SoilBorings(37pages)• CompletedbyKansasCityTestingandEngineering(KCTE)• SoilBoringsfreeofrockandtypicalofareasoils.
3. MeetingwiththeUGStaff–UrbanPlanningandLandUse
• Mr.ClementsandBrianHill,EngineermetwiththeUnifiedGovernmentPlanningstafftoreviewproperty.
• Noconcernsidentified
12
4. PhaseIEnvironmental(256pages)CompletedbyKansasCityTestingandEngineering(KCTE)
5. TitleCommitment(4pages)• CompletedbyStewartTitleCompany• Noconcerns–1930’slease–senttoattorney
6. Survey• CompletedbyMKEC–EngineeringSuccess• Utilitiesavailablealong91stStreet• Offsiteconnectiontosanitarysewer–havetoaccesstemporaryeasementfrom
adjacentpropertyowner
7. Access• SiteAccessevaluatedfrom91stStreet• Estimatedcostsforsiteaccessforsafety-$350,000-$500,000
RecommendationmadebyAdministration• BoardApprovedPropertyAcquisition:
o 8833Waverly–ElementarySchool–pendingduediligence/contractcontingencies–December12,2017
13
BudgetSincetheapprovalofthebondinNovember,2017,thedistricthasupdatedfiguresforthebond,andanticipatesusingsavingsfromtheWelbornprojecttocovertheadditionalcostsofWhiteChurch/Bethelproject.
1.BudgetedCostsforNewElementary• $18,453,580• SavingsfrombidsonWelbornproject-$1,689,188• EstimatedtotalWelbornprojectcostsavings-$1,795,607
2.EstimatedAdditionalCosts
• $670,000–PropertyAcquisition• $450,000–Access• $125,000–Clearing• $1,245,000–TOTAL
3.TotalSavingsinBondProjectstodate:
• $18,574,820RecommendationtoBoardandSubsequentBoardAction–January23,2017TheadministrationrecommendedthattheBoardofEducationacquirethepropertyon8833Waverlyforthelocationofthenewelementaryschool(WhiteChurch/Bethel)pertheamendedcostof$670,000.TheBoardofEducationvotedtotablethatrecommendation,andtoengagetheservicesofanewappraiser,whowouldconductanewappraisaloftheWaverlyproperty.AdministrationpresentedtotheBoardalistofqualifiedappraisers,recommendedbyfourdifferentfinancialfirms,allofwhomholdthecovetedMAIdesignation.TheBoardchosenottoselectanappraiserfromthatlist,andinsteadselectedanappraiserfromKansasCity,Missouri,whoagreedtoperformtheappraisal.Inasubsequente-mailcommunicationwiththeChiefofOperationsthatappraiseracknowledgedthathewasnotqualifiedtoperformthenecessaryservices,andaskedtowithdrawfromthecontract.