Kania SOM / Brennan Hall

37
April 14, 2004 Architectural Engineering Senior Thesis

description

Kania SOM / Brennan Hall. University of Scranton - Scranton, Pennsylvania. Douglas Wisniewski Structural Option. Kania SOM / Brennan Hall. Presentation Outline. Project Background Introduction Project Team Construction Structure Information Technology. Wireless LAN Breadth Study - PowerPoint PPT Presentation

Transcript of Kania SOM / Brennan Hall

Page 1: Kania SOM / Brennan Hall

April 14, 2004 Architectural Engineering Senior Thesis

Page 2: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallPresentation Outline

Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology

Structural Depth StudyLoadsLateral SystemGravity System

Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures

Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing

Conclusions

Acknowledgements

Questions

Page 3: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallProject Background

Introduction

Five-story office/classroom building

68,500 square feet

$12.3 million project

1st and 2nd floors primarily classrooms

3rd and 4th floors primarily faculty offices

5th floor executive board room and catering facilities

Page 4: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallProject Background

Project Team

Owner – University of Scranton

Architects – Burkavage Design Associates

Structural Engineer – QproQ Engineering, Inc.

Geotechnical Consultant – Geo-Science Engineering

General Contractor – Sordoni Construction Services

Page 5: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallProject Background

Construction

Started March 1999

Completed August 2000

CM at risk delivery method

Adjacent dorms constructed at same time

Subcontractor lump sum bids

Page 6: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallProject Background

Structure

Structural steel framing

Fully rigid moments frames

Concrete-filled composite metal deck

Column spread and continuous wall footings

Page 7: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallProject Background

Information Technology

Showcase instructional technologies and conference center flexibility

Touch screen control of lighting, computing, and audio/video components

Overhead projector, motorized screens, image visualizers, DVD & CD players

High-end video displays, theatre like sound and video conferencing in executive conference center

Auditorium featuring theatre like audio and video environments

Page 8: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallPresentation Outline

Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology

Structural Depth StudyLoadsLateral SystemGravity System

Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures

Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing

Conclusions

Acknowledgements

Questions

Page 9: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Loads

From AISC “Manual of Steel Construction”

Dead loadsRoof dead (no ballast) 16.7 psfRoof dead (with ballast) 26.7 psfFloor dead 100 psf

From ASCE 7-02

Live loadsCorridors 80 psfClassrooms 40 psfOffices 50 psf

Snow load 30 psf

Page 10: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Loads

As Calculated by RAM Frame

Wind loads N-S E-WRoof level 12.2 kips 14.4 kipsFifth Floor 21.5 kips 22.9 kipsFourth Floor 20.5 kips 21.7 kipsThird Floor 21.7 kips 19.9 kipsSecond Floor 22.5 kips 18.3 kipsTotal 98.4 kips 97.2 kips

Seismic loadsTotal Building Weight 5690 kipsN-S Base Shear 246.7 psfE-W Base Shear 284.5 psf

Page 11: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Lateral System

AdvantagesEliminate high cost of steel moment connectionsReduce steel erection time by eliminating steel moment connections

Six reinforced concrete shear wallsFour located on the perimeter

Extend all five floorsTwo located in the interior

Only extend four floorsVery rigid, very small deflections

Massive walls and footings to resist overturning moments

Page 12: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Lateral System

Picture of shear wall model from RAM

Page 13: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Lateral System

Shear wall design summary table

Page 14: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Lateral System

Deflection summary table

Page 15: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Gravity System

Replace wide flange infill beams with open web steel joists

AdvantagesReduce weight of floor systemImprove efficiency of floor system

ConcernsFire ProtectionFloor Vibrations

Page 16: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Gravity System

Typical joist layout

Diagram of typical floor layout

Page 17: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Gravity System

Fire ProtectionDesign No. G708 from U.L. “Fire Resistance Directory”

2 hour fire rating

W8X28 min. beam sizeNormal weight concrete, f’c = 3500 psiForm deck with 2 ½” pitch, ½” corrugationsmin. 16K6 joists spaced at 3’-6” max.Spray-applied fire resistive materialMetal lath (optional)

Page 18: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Gravity System

Fire ProtectionDesign No. G708 from U.L. “Fire Resistance Directory”

Diagram of fire rated assembly

Page 19: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallStructural Depth Study

Gravity System

Floor VibrationsCalculations based on AISC’s Design Guide 11

Applied loadsLive load 11 psfMisc. 4 psf

Joist mode frequency 7.8 HzGirder mode frequency 6.0 HzCombined mode frequency 4.8 Hz

Walking stiffness evaluationAcceleration limit 0.43%gLess than office limit of0.5%g

Page 20: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallPresentation Outline

Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology

Structural Depth StudyLoadsLateral SystemGravity System

Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures

Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing

Conclusions

Acknowledgements

Questions

Page 21: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallScheduling/Cost Breadth Study

Material Costs

Moment connections removed

Steel beams removed

Steel columns removed

Spread footings removed

Reinforced concrete shear walls added

Spread footings added

Page 22: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallScheduling/Cost Breadth Study

Material Costs

Material cost summary table

Page 23: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallScheduling/Cost Breadth Study

Construction Schedule

Time saved in steel erectionNo moment connectionsFewer steel members

Time for concrete walls to reach 75% strengthSteel attached to concrete walls

Cost of steel erection crew

Cost of concrete frp crew

Page 24: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallScheduling/Cost Breadth Study

Construction Schedule

Modified construction schedule

Extra construction timeExtra construction cost

Page 25: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallScheduling/Cost Breadth Study

Final Cost Figures

Material costs

Extra construction cost

Final cost savings

Page 26: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallPresentation Outline

Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology

Structural Depth StudyLoadsLateral SystemGravity System

Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures

Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing

Conclusions

Acknowledgements

Questions

Page 27: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallWireless LAN Breadth Study

Wireless LAN

AdvantagesLess wire and cable throughout buildingMore flexible systemReduce overhead costs caused by moves, extensions to networks, adding individualsCan serve as hotspot for students with laptopsCan connect other buildings to same network

Installing network in older buildings is easy

802.11a64 users per access pointLower possibility of interferenceGood for; dormitories, computer labs, conference rooms, VoIP

Page 28: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallWireless LAN Breadth Study

Access Points

64 users per access pointConnected via ethernet to wired backbone

Diagram showing approximate locations of wireless access points

Page 29: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallWireless LAN Breadth Study

IP Phones

PC Based PhonesSoftware that allows all computers to be used as internet protocol phonesEach individual’s extension follows them to any computer he/she is logged on toProvides every feature that standard phones offerTeleconferencing capabilities

Desktop IP PhonesConnected via ethernet to wired backboneLocated in secretary/waiting areas

Page 30: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallWireless LAN Breadth Study

Interactive Whiteboards

Replaces chalkboard, overhead projector and screenCan function simply as a whiteboardCan display computer imagesCan save handwritten notes to print or post on course websites

Picture of interactive whiteboard

Page 31: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallWireless LAN Breadth Study

Video Conferencing

Built in conferencing with multiple video and audio sitesDual LCD monitorsAdd a PC to the meetingSee live PC presentations and presenter simultaneously

Picture of video conferencing unit

Page 32: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallPresentation Outline

Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology

Structural Depth StudyLoadsLateral SystemGravity System

Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures

Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing

Conclusions

Acknowledgements

Questions

Page 33: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallConclusions

Conclusions

Conclusions yet to come

Page 34: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallPresentation Outline

Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology

Structural Depth StudyLoadsLateral SystemGravity System

Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures

Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing

Conclusions

Acknowledgements

Questions

Page 35: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallAcknowledgements

I would like to thank

James Kerns, PE, QproQ EngineeringJames Devers, AIA, U of S Physical PlantDavid Wilson, AIA, U of S Physical PlantFrancis Kranick, U of S Physical PlantRonald Skutnick, Uof S Network ResourcesAndrew Shedlock, Sordoni ConstructionDon Flynn, Burkavage Design Associates

For all of the time and information they have contributed to this project.

Page 36: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallPresentation Outline

Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology

Structural Depth StudyLoadsLateral SystemGravity System

Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures

Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing

Conclusions

Acknowledgements

Questions

Page 37: Kania SOM / Brennan Hall

Douglas Wisniewski Architectural Engineering Senior Thesis

Kania SOM / Brennan HallQuestions

?