Kania SOM / Brennan Hall
description
Transcript of Kania SOM / Brennan Hall
April 14, 2004 Architectural Engineering Senior Thesis
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallProject Background
Introduction
Five-story office/classroom building
68,500 square feet
$12.3 million project
1st and 2nd floors primarily classrooms
3rd and 4th floors primarily faculty offices
5th floor executive board room and catering facilities
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallProject Background
Project Team
Owner – University of Scranton
Architects – Burkavage Design Associates
Structural Engineer – QproQ Engineering, Inc.
Geotechnical Consultant – Geo-Science Engineering
General Contractor – Sordoni Construction Services
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallProject Background
Construction
Started March 1999
Completed August 2000
CM at risk delivery method
Adjacent dorms constructed at same time
Subcontractor lump sum bids
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallProject Background
Structure
Structural steel framing
Fully rigid moments frames
Concrete-filled composite metal deck
Column spread and continuous wall footings
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallProject Background
Information Technology
Showcase instructional technologies and conference center flexibility
Touch screen control of lighting, computing, and audio/video components
Overhead projector, motorized screens, image visualizers, DVD & CD players
High-end video displays, theatre like sound and video conferencing in executive conference center
Auditorium featuring theatre like audio and video environments
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Loads
From AISC “Manual of Steel Construction”
Dead loadsRoof dead (no ballast) 16.7 psfRoof dead (with ballast) 26.7 psfFloor dead 100 psf
From ASCE 7-02
Live loadsCorridors 80 psfClassrooms 40 psfOffices 50 psf
Snow load 30 psf
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Loads
As Calculated by RAM Frame
Wind loads N-S E-WRoof level 12.2 kips 14.4 kipsFifth Floor 21.5 kips 22.9 kipsFourth Floor 20.5 kips 21.7 kipsThird Floor 21.7 kips 19.9 kipsSecond Floor 22.5 kips 18.3 kipsTotal 98.4 kips 97.2 kips
Seismic loadsTotal Building Weight 5690 kipsN-S Base Shear 246.7 psfE-W Base Shear 284.5 psf
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Lateral System
AdvantagesEliminate high cost of steel moment connectionsReduce steel erection time by eliminating steel moment connections
Six reinforced concrete shear wallsFour located on the perimeter
Extend all five floorsTwo located in the interior
Only extend four floorsVery rigid, very small deflections
Massive walls and footings to resist overturning moments
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Lateral System
Picture of shear wall model from RAM
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Lateral System
Shear wall design summary table
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Lateral System
Deflection summary table
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Replace wide flange infill beams with open web steel joists
AdvantagesReduce weight of floor systemImprove efficiency of floor system
ConcernsFire ProtectionFloor Vibrations
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Typical joist layout
Diagram of typical floor layout
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Fire ProtectionDesign No. G708 from U.L. “Fire Resistance Directory”
2 hour fire rating
W8X28 min. beam sizeNormal weight concrete, f’c = 3500 psiForm deck with 2 ½” pitch, ½” corrugationsmin. 16K6 joists spaced at 3’-6” max.Spray-applied fire resistive materialMetal lath (optional)
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Fire ProtectionDesign No. G708 from U.L. “Fire Resistance Directory”
Diagram of fire rated assembly
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Floor VibrationsCalculations based on AISC’s Design Guide 11
Applied loadsLive load 11 psfMisc. 4 psf
Joist mode frequency 7.8 HzGirder mode frequency 6.0 HzCombined mode frequency 4.8 Hz
Walking stiffness evaluationAcceleration limit 0.43%gLess than office limit of0.5%g
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Material Costs
Moment connections removed
Steel beams removed
Steel columns removed
Spread footings removed
Reinforced concrete shear walls added
Spread footings added
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Material Costs
Material cost summary table
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Construction Schedule
Time saved in steel erectionNo moment connectionsFewer steel members
Time for concrete walls to reach 75% strengthSteel attached to concrete walls
Cost of steel erection crew
Cost of concrete frp crew
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Construction Schedule
Modified construction schedule
Extra construction timeExtra construction cost
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Final Cost Figures
Material costs
Extra construction cost
Final cost savings
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallWireless LAN Breadth Study
Wireless LAN
AdvantagesLess wire and cable throughout buildingMore flexible systemReduce overhead costs caused by moves, extensions to networks, adding individualsCan serve as hotspot for students with laptopsCan connect other buildings to same network
Installing network in older buildings is easy
802.11a64 users per access pointLower possibility of interferenceGood for; dormitories, computer labs, conference rooms, VoIP
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallWireless LAN Breadth Study
Access Points
64 users per access pointConnected via ethernet to wired backbone
Diagram showing approximate locations of wireless access points
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallWireless LAN Breadth Study
IP Phones
PC Based PhonesSoftware that allows all computers to be used as internet protocol phonesEach individual’s extension follows them to any computer he/she is logged on toProvides every feature that standard phones offerTeleconferencing capabilities
Desktop IP PhonesConnected via ethernet to wired backboneLocated in secretary/waiting areas
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallWireless LAN Breadth Study
Interactive Whiteboards
Replaces chalkboard, overhead projector and screenCan function simply as a whiteboardCan display computer imagesCan save handwritten notes to print or post on course websites
Picture of interactive whiteboard
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallWireless LAN Breadth Study
Video Conferencing
Built in conferencing with multiple video and audio sitesDual LCD monitorsAdd a PC to the meetingSee live PC presentations and presenter simultaneously
Picture of video conferencing unit
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallConclusions
Conclusions
Conclusions yet to come
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallAcknowledgements
I would like to thank
James Kerns, PE, QproQ EngineeringJames Devers, AIA, U of S Physical PlantDavid Wilson, AIA, U of S Physical PlantFrancis Kranick, U of S Physical PlantRonald Skutnick, Uof S Network ResourcesAndrew Shedlock, Sordoni ConstructionDon Flynn, Burkavage Design Associates
For all of the time and information they have contributed to this project.
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
Kania SOM / Brennan HallQuestions
?