KAGRA Toward joining O 3 1 The extreme Universe viewed in very-high-energy gamma-rays 2018 Masatake OHASHI (ICRR)

Transcript of KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … ·...

Page 1: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

KAGRA – Toward joining O3

1The extreme Universe viewed in very-high-energy gamma-rays 2018

Masatake OHASHI (ICRR)

Page 2: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

Schedule of KAGRA

2

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Project start

Tunnel Excavation

iKAGRA

bKAGRA

First operation

3km Cryogenic Interferometer

Final installation

Commissioning and Observation

iKAGRA

3km Michelson Interferometer

The extreme Universe viewed in very-high-energy gamma-rays 2018

Page 3: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

Toward joining O3

3

acceleration

• We have decided to accelerate KAGRA schedule to join O3.

The extreme Universe viewed in very-high-energy gamma-rays 2018

Page 4: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

Required Items

Sensitivity (10W, x4 O1 excess)

DRFPMI (RSE)(42 Mpc)

PRFPMI(27 Mpc)

FPMI(9.5 / 16 Mpc)

ALS (green lock) ◎ ○ ×(better to have)

f3 AM (MZI *) ◎ ○ ×

Extra locking simulation × ◎ ×

SRC ASC ◎ × ×

SRM ◎ ○(Blank or move OMMT)

○(Blank or move OMMT)

OMC △ △ △

Comment SRC ASC might be tough f1 will be 1/10, no SRC mode cleaning

PRM: tilt or blank or move IMMTNo PRC jitter attenuation

◎: Necessary for locking○: Can be omitted with extra work△: Can be omitted with sensitivity degradation×: Not necessary

* AM generation with 45 deg tilted EOM is not possible with wedged EOM

4The extreme Universe viewed in very-high-energy gamma-rays 2018

Page 5: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

Noise Curves

5

Various possibilities of KAGRA's sensitivity

Enomoto and Michimura made 3 noise curves of KAGRA with BNS range of(1.3, 9.6, 42)Mpc. We interpolate these curves to obtain noise curves for other ranges. For LIGO/Virgo, LIGO: 120Mpc, Virgo 60Mpc (taken from arXiv:1304.0670v6)

LIGO(120Mpc)

Virgo(60Mpc)KAGRA(20Mpc)KAGRA(10Mpc)KAGRA(5Mpc)KAGRA(1Mpc)

(Living Reviews in Relativity; 21:3; 2018)

The extreme Universe viewed in very-high-energy gamma-rays 2018

Page 6: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

2018 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2019 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

ETMX Install

Ph

ase

1

Op

era

tion

ITMX InstallXarm COM.

ITMY arrives

Toyama Univ.8/27

Post

COM.

ETMX cooling

Measurements

ITMX cool

DRFPMI COM.

bKAGRA phase-2 schedule

ITMY

Instal

O3start O3end

Middle

Baffle

2018/8/20 chief meeting

High Power Laser, IMC, IMM

Green Lock System

Output Mode Cleaner, OMMT, OFI

ITMX Type-A Tower install ITMY Type-A Tower install

SR2, 3, M install

ITMX arrives

Toyama Univ.5/7

ETMYTake out Re-Instal

ITMY

Contr

ETMX

cool

DRFPMI

ASC/Laser

power upFPMI

ASC

OR

I/ETMYcooling

X-end

BRT

Y-

end

WA

BX-front WAB &

NAB install

Y

front/en

d NAB

Y-end

BRT

Y-front WAB cool test

X-end

Pcal

install

Y-end Pcal install &

test

ETMXTake outRe-Install

X-end Pcal test

Check

point

Check

point

Check

point

X-

end

NAB

ETMY

Type-A

Tower

Retune

Center,

I/ETMX

Beam

Align.

Pump.

Center, I/ETMY

Beam Align, Pump

ETM

Y

Contr

ITMX

contr

Post COM.

Middle

Baffle

X-

end

WA

B

ITMY

Assemble

Center, I/ETMY

Beam Alignment

Pumping

ETMXTake outRe-Install

I/ETMY

cooling

Y

front

WA

B

Yarm COM.

DRMI COM.

ETMX Control,

Alignment,

Pumping

FPMI

6

Page 7: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

2018 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2019 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

ETMX Install

Ph

ase

1

Op

era

tion

ITMX InstallXarm COM.

ITMY arrives

Toyama Univ.8/27

Post

COM.

ETMX cooling

Measurements

ITMX cool

DRFPMI COM.

bKAGRA phase-2 schedule

ITMY

Instal

O3start O3end

Middle

Baffle

2018/8/20 chief meeting

High Power Laser, IMC, IMM

Green Lock System

Output Mode Cleaner, OMMT, OFI

ITMX Type-A Tower install ITMY Type-A Tower install

SR2, 3, M install

ITMX arrives

Toyama Univ.5/7

ETMYTake out Re-Instal

ITMY

Contr

ETMX

cool

DRFPMI

ASC/Laser

power upFPMI

ASC

OR

I/ETMYcooling

X-end

BRT

Y-

end

WA

BX-front WAB &

NAB install

Y

front/en

d NAB

Y-end

BRT

Y-front WAB cool test

X-end

Pcal

install

Y-end Pcal install &

test

ETMXTake outRe-Install

X-end Pcal test

Check

point

Check

point

Check

point

X-

end

NAB

ETMY

Type-A

Tower

Retune

Center,

I/ETMX

Beam

Align.

Pump.

Center, I/ETMY

Beam Align, Pump

ETM

Y

Contr

ITMX

contr

Post COM.

Middle

Baffle

X-

end

WA

B

ITMY

Assemble

Center, I/ETMY

Beam Alignment

Pumping

ETMXTake outRe-Install

I/ETMY

cooling

Y

front

WA

B

Yarm COM.

DRMI COM.

ETMX Control,

Alignment,

Pumping

Outline of the schedule

• Installation will be completed by the end of March 2019.

• Commissioning will start from September 2018 along with installation works.

• Commissioning of the first full interferometer configuration (FPMI) will start from March

2019. After then, we start DRFPMI or FPMI, depending on results of three checking points

planned on the end of September, December and March.

X-arm

Y-arm

FPMI

7

Page 8: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

2018 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2019 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

ETMX Install

Ph

ase

1

Op

era

tion

ITMX InstallXarm COM.

ITMY arrives

Toyama Univ.8/27

Post

COM.

ETMX cooling

Measurements

ITMX cool

DRFPMI COM.

bKAGRA phase-2 schedule

ITMY

Instal

O3start O3end

Middle

Baffle

2018/8/20 chief meeting

High Power Laser, IMC, IMM

Green Lock System

Output Mode Cleaner, OMMT, OFI

ITMX Type-A Tower install ITMY Type-A Tower install

SR2, 3, M install

ITMX arrives

Toyama Univ.5/7

ETMYTake out Re-Instal

ITMY

Contr

ETMX

cool

DRFPMI

ASC/Laser

power upFPMI

ASC

OR

I/ETMYcooling

X-end

BRT

Y-

end

WA

BX-front WAB &

NAB install

Y

front/en

d NAB

Y-end

BRT

Y-front WAB cool test

X-end

Pcal

install

Y-end Pcal install &

test

ETMXTake outRe-Install

X-end Pcal test

Check

point

Check

point

Check

point

X-

end

NAB

ETMY

Type-A

Tower

Retune

Center,

I/ETMX

Beam

Align.

Pump.

Center, I/ETMY

Beam Align, Pump

ETM

Y

Contr

ITMX

contr

Post COM.

Middle

Baffle

X-

end

WA

B

ITMY

Assemble

Center, I/ETMY

Beam Alignment

Pumping

ETMXTake outRe-Install

I/ETMY

cooling

Y

front

WA

B

Yarm COM.

DRMI COM.

ETMX Control,

Alignment,

Pumping

Checkpoint at the end of September

If either ITMY, high power laser or green lock system is not available at this point,

FPMI is to be selected.

FPMI

8

Page 9: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

2018 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2019 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

ETMX Install

Ph

ase

1

Op

era

tion

ITMX InstallXarm COM.

ITMY arrives

Toyama Univ.8/27

Post

COM.

ETMX cooling

Measurements

ITMX cool

DRFPMI COM.

bKAGRA phase-2 schedule

ITMY

Instal

O3start O3end

Middle

Baffle

2018/8/20 chief meeting

High Power Laser, IMC, IMM

Green Lock System

Output Mode Cleaner, OMMT, OFI

ITMX Type-A Tower install ITMY Type-A Tower install

SR2, 3, M install

ITMX arrives

Toyama Univ.5/7

ETMYTake out Re-Instal

ITMY

Contr

ETMX

cool

DRFPMI

ASC/Laser

power upFPMI

ASC

OR

I/ETMYcooling

X-end

BRT

Y-

end

WA

BX-front WAB &

NAB install

Y

front/en

d NAB

Y-end

BRT

Y-front WAB cool test

X-end

Pcal

install

Y-end Pcal install &

test

ETMXTake outRe-Install

X-end Pcal test

Check

point

Check

point

Check

point

X-

end

NAB

ETMY

Type-A

Tower

Retune

Center,

I/ETMX

Beam

Align.

Pump.

Center, I/ETMY

Beam Align, Pump

ETM

Y

Contr

ITMX

contr

Post COM.

Middle

Baffle

X-

end

WA

B

ITMY

Assemble

Center, I/ETMY

Beam Alignment

Pumping

ETMXTake outRe-Install

I/ETMY

cooling

Y

front

WA

B

Yarm COM.

DRMI COM.

ETMX Control,

Alignment,

Pumping

Checkpoint at the end of December

If any serious delay or troubles in X-arm commissioning would be found,

FPMI is to be selected.

FPMI

9

Page 10: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

2018 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2019 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

ETMX Install

Ph

ase

1

Op

era

tion

ITMX InstallXarm COM.

ITMY arrives

Toyama Univ.8/27

Post

COM.

ETMX cooling

Measurements

ITMX cool

DRFPMI COM.

bKAGRA phase-2 schedule

ITMY

Instal

O3start O3end

Middle

Baffle

2018/8/20 chief meeting

High Power Laser, IMC, IMM

Green Lock System

Output Mode Cleaner, OMMT, OFI

ITMX Type-A Tower install ITMY Type-A Tower install

SR2, 3, M install

ITMX arrives

Toyama Univ.5/7

ETMYTake out Re-Instal

ITMY

Contr

ETMX

cool

DRFPMI

ASC/Laser

power upFPMI

ASC

OR

I/ETMYcooling

X-end

BRT

Y-

end

WA

BX-front WAB &

NAB install

Y

front/en

d NAB

Y-end

BRT

Y-front WAB cool test

X-end

Pcal

install

Y-end Pcal install &

test

ETMXTake outRe-Install

X-end Pcal test

Check

point

Check

point

Check

point

X-

end

NAB

ETMY

Type-A

Tower

Retune

Center,

I/ETMX

Beam

Align.

Pump.

Center, I/ETMY

Beam Align, Pump

ETM

Y

Contr

ITMX

contr

Post COM.

Middle

Baffle

X-

end

WA

B

ITMY

Assemble

Center, I/ETMY

Beam Alignment

Pumping

ETMXTake outRe-Install

I/ETMY

cooling

Y

front

WA

B

Yarm COM.

DRMI COM.

ETMX Control,

Alignment,

Pumping

Checkpoint at the end of March

DRFPMI will be selected if all the elements are available,

otherwise ASC (alignment sensing control) of FPMI is proceeded.

FPMI

10

Page 11: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

2018 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2019 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

ETMX Install

Ph

ase

1

Op

era

tion

ITMX InstallXarm COM.

ITMY arrives

Toyama Univ.8/27

Post

COM.

ETMX cooling

Measurements

ITMX cool

DRFPMI COM.

bKAGRA phase-2 schedule

ITMY

Instal

O3start O3end

Middle

Baffle

2018/8/20 chief meeting

High Power Laser, IMC, IMM

Green Lock System

Output Mode Cleaner, OMMT, OFI

ITMX Type-A Tower install ITMY Type-A Tower install

SR2, 3, M install

ITMX arrives

Toyama Univ.5/7

ETMYTake out Re-Instal

ITMY

Contr

ETMX

cool

DRFPMI

ASC/Laser

power upFPMI

ASC

OR

I/ETMYcooling

X-end

BRT

Y-

end

WA

BX-front WAB &

NAB install

Y

front/en

d NAB

Y-end

BRT

Y-front WAB cool test

X-end

Pcal

install

Y-end Pcal install &

test

ETMXTake outRe-Install

X-end Pcal test

Check

point

Check

point

Check

point

X-

end

NAB

ETMY

Type-A

Tower

Retune

Center,

I/ETMX

Beam

Align.

Pump.

Center, I/ETMY

Beam Align, Pump

ETM

Y

Contr

ITMX

contr

Post COM.

Middle

Baffle

X-

end

WA

B

ITMY

Assemble

Center, I/ETMY

Beam Alignment

Pumping

ETMXTake outRe-Install

I/ETMY

cooling

Y

front

WA

B

Yarm COM.

DRMI COM.

ETMX Control,

Alignment,

Pumping

FPMI

Data transfer rehearsal (test with L/V); possible schedule

• DMG & DAS are planning DTRs with dummy data before O3 starting.

KSC is in charge of scheduling and so on.

• DTRs shown on the bottom schedule will be using live KAGRA data.

DTRs may take a week or so.

DTR DTR DTR DTR11

Page 12: KAGRA Toward joining O3cta.scphys.kyoto-u.ac.jp/workshop/CTA-J/2018/presentations/4_CTA … · KAGRA –Toward joining O3 The extreme Universe viewed ... bKAGRA First operation 3km

Summary

• In the spring of 2019, we expect to complete the construction phase and move on to the commissioning phase. KAGRA plans to join O3 in the fall of 2019.

1212The extreme Universe viewed in very-high-energy gamma-rays 2018