Just In Time
ACMA Presentation
![Page 3: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/3.jpg)
Group Members
• SUBMITTED TO:• PROF Faisal Abbas
• SUBMITTED by• ZUL-NU-RAIN 0009• WAQAR SALEEM 0079• ZAFAR IQBAL 0087
![Page 4: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/4.jpg)
What Is JIT
• Management philosophy (produce only what is needed when it is needed)
• A highly coordinated processing system in which goods move through the system, and services are performed, just as they are needed
• Represents Pull type system e.g kanban
![Page 5: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/5.jpg)
History of JIT Manufacturing
• Evolved in Japan after World War II, as a result of their diminishing market share in the auto industry.
• Toyota Motor Company- Birthplace of the JIT Philosophy Under Taiichi Ohno.
• JIT is now on the rise in American Industries.
![Page 6: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/6.jpg)
Definition
• JIT is a manufacturing philosophy involving an integrated set of procedures/activities designed to achieve a high volume of production using minimal inventories
![Page 7: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/7.jpg)
More Introduction
• Raw materials, parts & sub assemblies are pulled through the manufacturing process when they are needed.
• Simply put, JIT is a philosophy of “make what is needed … when it is needed”.
![Page 8: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/8.jpg)
Goal of JIT
• The ultimate goal of JIT is a balanced system.
• Achieves a smooth, rapid flow of materials through the system
• Eliminate disruptions• Make system flexible• Eliminate waste, especially excess
inventory
![Page 9: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/9.jpg)
Big vs. Little JIT
• Big JIT – broad focus– Vendor relations– Human relations– Technology management– Materials and inventory management
• Little JIT – narrow focus– Scheduling materials– Scheduling services of production
![Page 10: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/10.jpg)
What JIT Does
• Eliminates waste • Achieves streamlined production • Eliminate disruptions in production …
caused by poor quality, schedule changes, late deliveries.
• Makes the manufacturing delivery system flexible by allowing it to handle a variety of products and changes in the level of output
• Reduces setup and delivery times
![Page 11: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/11.jpg)
SEVEN WastesTHE SEVEN TYPES OF WASTE OR MUDA
Waste Definition
Overproduction Manufacturing an item before it is needed.
3. Waiting Wasteful time incurred when product is not being moved or processed.
4. Transportation Excessive movement and material handling of product between processes.
5. Motion Unnecessary effort related to the ergonomics of bending, stretching, reaching, lifting, and walking.
Inventory Excess inventory hides problems on the shop floor, consumes space, increases lead times, and inhibits communication.
Defects Quality defects result in rework and scrap, and add wasteful costs to the system in the form of lost capacity, rescheduling effort, increased inspection, and loss of customer good will.
Underutilization of Employees
Failure of the firm to learn from and capitalize on its employees’ knowledge and creativity impedes long term efforts to eliminate waste.
![Page 12: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/12.jpg)
Sources of Waste
• Overproduction
• Waiting time
• Unnecessary transportation
• Processing waste
• Inefficient work methods
• Product defects
![Page 13: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/13.jpg)
Strategies For Minimizing Waste By Using JIT
• Manufacturing in smaller lot sizes reduces excess inventory
• Reducing inventory levels allows the problems to be uncovered … thus creating opportunities for manufacturing process improvement
![Page 14: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/14.jpg)
Principles Of JIT Manufacturing
• Total Quality Management
• Production Management
• Supplier Management
• Inventory Management
![Page 15: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/15.jpg)
1st Principle Of JIT
Total Quality Management
![Page 16: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/16.jpg)
Total Quality Management
• Seek long-term commitment to quality efforts with continuous improvement
• Quality must be a higher priority than cost
• Minimizing waste
![Page 17: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/17.jpg)
Total Quality Management• Eliminate Quality Inspectors
• Quality is everyone’s responsibility
• Do it right the first time
![Page 18: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/18.jpg)
2nd Principle Of JIT
Production Management
![Page 19: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/19.jpg)
Production Management
• Pull System vs. Push System– Pull = Made to order– Push = Made for inventory
• Flexibility of the system
• Design For Testability – In the process– Poka-Yoke= Mistake-proofing– Throughout entire process
![Page 20: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/20.jpg)
Production Management
• Reduced lot sizes= Shorter cycle times
• Eliminate disruptions in the process
• Standardized Parts/ Simplicity
![Page 21: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/21.jpg)
Production Management
• Communication Techniques– Completion of task-Kanban – Problem- Siren/light
• Stopping the process if something goes wrong =Jidoka
• Preventive Maintenance
![Page 22: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/22.jpg)
3rd Principle Of JIT
Supplier Management
![Page 23: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/23.jpg)
Supplier Management
• Establish Long Term Relationships with few suppliers.
• Delivery of Parts = 100% Defect Free– Where they are needed– When they are needed– The exact quantity
• Work Together
![Page 24: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/24.jpg)
Supplier Management
• Elimination inspection of parts
• Communicate problems to suppliers in a positive manner.
![Page 25: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/25.jpg)
4th Principle Of JIT
Inventory Management
![Page 26: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/26.jpg)
Inventory Management
• Eliminate Safety Stock = Zero Inventory
• JIT is not an inventory control system
• Reduction in inventory opens up space
![Page 27: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/27.jpg)
• Inventory hides problems in a process.
• Water Level = Inventory• Rocks = Problems in the
system• Boat = Company Operations
![Page 28: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/28.jpg)
JIT Manufacturing Building Blocks
• Product design
• Process design
• Personnel/organizationalelements
• Manufacturing planning and control
![Page 29: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/29.jpg)
1. Product Design• Standard parts
• Design Simplification
• Highly capable production systems
• Concurrentengineering
![Page 30: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/30.jpg)
Design Simplification
![Page 31: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/31.jpg)
2. Process Design
• Small lot sizes
• Setup time reduction
• Limited work in process
• Quality improvement
• Production flexibility
• Little inventory storage
![Page 32: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/32.jpg)
Quality Improvement
• Autonomation
– Automatic detection of defects during production
• Jidoka
– Japanese term for autonomation
![Page 33: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/33.jpg)
Production Flexibility• Reduce downtime by reducing changeover
time
• Use preventive maintenance to reduce breakdowns
• Cross-train workers to help clear bottlenecks
• Use many small units of capacity• Reserve capacity for important customers
![Page 34: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/34.jpg)
3. Personnel/Organizational Elements
• Workers as assets
• Cross-trained workers
• Continuous improvement
• Leadership
![Page 35: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/35.jpg)
4. Manufacturing Planning and Control
• Pull systems
• Visual systems (kanban)
• Close vendor relationships
• Reduced transaction processing (delays in delievery)
• Preventive maintenance
![Page 36: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/36.jpg)
Comparison of JIT and Traditional
Factor Traditional JIT
Inventory Much to offset forecast errors, late deliveries
Minimal necessary to operate
Deliveries Large Small
Lot sizes Large Small
Setup; runs Few, long runs Many, short runs
Vendors Long-term relationships are unusual
Partners
Workers Necessary to do the work
Assets
![Page 37: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/37.jpg)
JIT in Services
The basic goal of the demand flow technology in the service organization is to provide optimum response to the customer with the highest quality service and lowest possible cost.
![Page 38: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/38.jpg)
Benefits of JIT Systems
• Increased equipment utilization
• Reduced scrap and rework
• Reduced space requirements
• Pressure for good vendor relationships
• Reduced need for indirect labor
![Page 39: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/39.jpg)
ADVANTAGES
• Reduced Setup time , also known as ‘Changeover’ time.
• Funds tied up in inventories can be used elsewhere.
• Storage area used up can be utilized.
• Throughput Time is reduced resulting in greater output
• Production scheduling and work hour consistency is synchronized with demand.
![Page 40: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/40.jpg)
• Supplies come in regular intervals throughout the production day
• The risk of inventory breaking/expiring is reduced largely.
• Inventory flow becomes simpler and easier to manage due to smaller lot sizes.
• Cuts the risk of supply system problems.
![Page 41: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/41.jpg)
Disadvantages
• Every job is a ‘High Stress’ Rush order
• Balanced systems MUST be in place
• Setup times will greatly impact throughput
• Any problem will lead to unhappy customers (either internal or external)
![Page 42: Just in time](https://reader035.fdocuments.net/reader035/viewer/2022062511/54bd844a4a79590a318b4584/html5/thumbnails/42.jpg)