Jupiters RWMP Scheme Number SRN00005 Annual Report for … · Turbidity Clarity Daily *
Transcript of Jupiters RWMP Scheme Number SRN00005 Annual Report for … · Turbidity Clarity Daily *
Jupiters RWMP Scheme Number SRN00005
Annual Report for FY14/15
Prepared by Jupiters Limited
December 2015
Overview of following annual report
Jupiters RWMP (Scheme Number SRN00005) was approved with regulatory conditions on 11th March 2011.
One of the conditions of Jupiters approved RWMP is that it must submit an annual report to the Queensland Water Supply
Regulator, Department of Energy and Water Supply
This annual report contains data for both Jupiters’ Recycle and Reverse Osmosis Water Treatment Plant. The report includes incidents where testing data has been unable to be carried out. Each incident is identified along with a reason for its
omission.
In accordance with Jupiters approved RWMP conditions it arranged for a 2 yearly regular internal audit of its RWMP. This annual report contains details of the audit which was undertaken on 4th March 2015.
Report Prepared By:
Stephen Gibson – Jupiters Hotel & Casino
Recycle Water Plant
Annual Data
During this reporting period there were 44 variances in the required weekly testing and 324 variances in the required taking
of the daily testing samples. A breakdown of the incidents causing the variations are shown on the next page
Frequency Value Samples
Required
Actual
TakenVariance Actual Value Min Max Mean
Escherichia coli Bacteria Weekly * <1 cfu/100mL 52 8 44 8 x <1 cfu/100mL <1 <1 <1
Free Chlorine Sufficient chlorine levels Daily * >0.5mg/L 365 41 324 41 x >0.5mg/L 0.77 1.88 0.99
Turbidity Clarity Daily * <2.0 NTU 366 41 324 41 x <2.0 NTU 0.01 1.76 0.47
R e c y c l e W a t e r P l a n tAnnual Report
1st July 2014 - 30th June 2015
Below is a snapshot of the weekly and daily water samples taken between 1st July 2014 - 30th June 2015
Parameters tested as per Water Quality Criteria For Production of Recycled Water
Parameter Indicator
Testing Requirements Testing Results Statistical Values
* PFU means Plaque Forming Unit * CFU means Colony Forming Unit * NTU means nephelometric turbidity units * mg/L means milligrams per litre
Variances
44 x Weekly Testing Variances and the 324 Daily Testing Variances were made up of 6 x incidents
Incident #1
Gold Coast Water was unable to supply Jupiters consistant flow and acceptable conductivity levels of recycled water from July 1 - April 12 (inclusive) resulting in
a non-consecutive total of 286 consecutive non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the non-consecutive 286 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #2
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from April 20 - April 24 (inclusive) resulting in 5 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 5 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #3
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from May 2 - May 6 (inclusive) resulting in 5 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 5 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #4
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from May 26 - May 31 (inclusive) resulting in 6 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 5 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Variances (cont.)
Incident #5
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from June 2 - June 21 (inclusive) resulting in 20 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 5 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #6
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from June 29 - June 30 (inclusive) resulting in 2 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 5 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Reverse Osmosis Plant
Annual Data
During this reporting period there were 47 variances in the required weekly testing and 336 variances in the required taking
of the daily testing samples. A breakdown of the incidents causing the variations are shown on the next page
Frequency Value Samples
Required
Actual
TakenVariance Actual Value Min Max Mean
Somatic coliphages Viruses Weekly * <1 pfu/100mL 52 5 47 5 x <1 pfu/100mL <1 <1 <1
F-RNA bacteriophages Viruses Weekly * <1 pfu/100mL 52 5 47 5 x <1 pfu/100mL <1 <1 <1
Escherichia coli Bacteria Weekly * <1 cfu/100mL 52 5 47 5 x <1 cfu/100mL <1 <1 <1
Clostridium perfringens Protozoa & Helmiths Weekly * <1 cfu/100mL 52 5 47 5 x <1 cfu/100mL <1 <1 <1
Free Chlorine Sufficient chlorine levels Daily * >0.5mg/L 365 29 336 29 x >0.5mg/L 1.17 2.70 1.78
Turbidity Clarity Daily * <2.0 NTU 365 29 336 29 x <2.0 NTU 0.01 0.40 0.01
R e v e r s e O s m o s i s W a t e r P l a n tAnnual Report
1st July 2014 - 30th June 2015
Below is a snapshot of the weekly and daily water samples taken between 1st July 2014 - 30th June 2015
Parameters tested as per Water Quality Criteria For Production of Recycled Water
Parameter Indicator
Testing Requirements Testing Results Statistical Values
* PFU means Plaque Forming Unit * CFU means Colony Forming Unit * NTU means nephelometric turbidity units * mg/L means milligrams per litre
Variances
47 x Weekly Testing Variances and the 336 Daily Testing Variances were made up of 5 x incidents
Incident #1
Gold Coast Water was unable to supply Jupiters consistant flow and acceptable conductivity levels of recycled water from July 1 - April 13 (inclusive) resulting in
a non-consecutive total of 287 consecutive non-operational days
Corrective Action Taken
The Reverse Osmosis Plant was turned off during the non-consecutive 287 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #2
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from April 17 - May 4 (inclusive) resulting in 18 non-operational days
Corrective Action Taken
The Reverse Osmosis Plant was turned off during the 18 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #3
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from May 26 - May 31 (inclusive) resulting in 6 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 6 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #4
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from June 2 - June 22 (inclusive) resulting in 21 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 21 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
Incident #5
Gold Coast Water was unable to supply Jupiters consistant flow levels of recycled water from June 27 - June 30 (inclusive) resulting in 4 non-operational days
Corrective Action Taken
The Recycled Water Plant was turned off during the 4 non-operational days and it's recycle water supply was replaced with potable water
Corrective Action Taken to Stop Reoccurrences
No corrective action required by Jupiters Hotel & Casino
2 Yearly Regular Internal Audit
MWH Consultants was engaged to undertake a 2 Yearly Regular Internal Audit of the Jupiters Limited Recycled Water
Management Plan. The audit was undertaken on 4th March 2015 and covered the level of compliance with the approved
RWMP and associated documents and procedures, legislation and regulatory guidelines and notices issued by the Department
of Energy and Water Supply. The audit also reviewed the non-compliances that were raised during the 3 Yearly External
Audit which was undertaken by Viridis Consultants Pty Ltd on 18th February 2014
The audit found 2 items of minor non-compliance and 4 compliant observations. The audit also included recommendations to
address each of the minor non-conformances and observations. The audit, along with an Action Plan stating how Jupiters
proposes to implement all recommendations stated in the audit was submitted to DEWS on 16th April 2015.
The following tables are extracts from the Action Plan submitted to DEWS outlining recommendations for the 2 items of
minor non-compliance, the 4 compliant observations and how they were actioned. Note, when the Action Plan was submitted
to DEWS minor compliance number 1 & observation number 2 & 4 were already completed.
Issue 1 Minor Non-conformance 1 Approval condition 6.4 identifies a summary of regular reviews is to be included in the annual report for the year that the review is completed
Reference RWMP Approval with Regulator Conditions - condition 6.4 Regular Reviews
Findings
A review of the Jupiter’s RWMP was undertaken following the 2013 internal audit and included in RWMP v6 (and subsequently v7). However, a summary of the review was not sighted in the FY2013/14 Annual Report on the Jupiters Limited website. It should be noted that a summary of the External Audit (Feb, 2014) was included in the Annual Report
Recommendations Ensure that all future reviews are summarised in the Annual Report
Jupiters Response Jupiters to create a re-occurring job in its AMPRO maintenance program that will flag all future reviews are to be summarised in its annual reports
Target Date Completed
Issue 2 Minor Non-conformance 2 Approval condition 6.5 identifies the water quality criteria required for open space irrigation with unrestricted access and associated monitoring parameters and frequencies.
Reference RWMP Approval with Regulator Conditions - condition 6.5 Water quality criteria - open space irrigation with unrestricted access
Findings
Jupiters staff advised that verification monitoring of E.coli was no longer being undertaken for the Class A irrigation water following amendments to the Act in 2014. Due to various supply and quality issues with the source water, the RWTP was offline between 7 February 2014 to 16 November 2014. Irrigation water was supplied from potable over that period. Since the RWTP has been back online from 17 November 2014, no verification monitoring has been undertaken. Under the transition to the new framework, if an existing recycled water management plan covers both higher and lower exposure uses, only the parts of the plan that relate to the higher exposure uses will continue to have effect (https://www.dews.qld.gov.au/policies-initiatives/water-sector-reform/regulatory-reform/recycled-water).
Recommendations Liaise with the Regulator to get a clear understanding of the requirements under the amendments to the Act and request amendment to the approval condition to reflect these changes
Jupiters Response At the time of the audit Jupiters RW plant was closed. Once the plant recommenced operation on April 2015 Jupiters re-commenced monitoring of E.coli for its Class A irrigation water, negating the need to liaise with regulator as per auditor’s recommendation
Target Date April 2015
Completion Date 7th April 2015
Issue 3 Observation (compliant) 1 Recycled Water Use Agreement in Appendix 1 is not current
Reference Appendix 1
Findings A new Recycled Water Use Agreement has been negotiated and signed with Gold Coast Water
Recommendations Include the latest Recycled Water Use Agreement in the next RWMP review.
Jupiters Response Will include in next RWMP review
Target Date June 2015
Completion Date 24th June 2015
Issue 4 Observation (compliant) 2 Process Flow Diagram (PFD) contains minor errors
Reference Figure 1 Jupiters Limited RWMP
Findings
PFD identifies 3D Trasar in the legend. The 3D Trasar system is no longer used. This should be Convergent Controller Max 5.
PFD identifies weekly E.coli testing at the Class A verification point (irrigation water). This testing is no longer being undertaken following amendments to the Act in May 2014.
It is important that the PFD is accurate and current as it is identifies the points of supply and is referred to in the conditions of approval.
Recommendations Update the PFD during the next RWMP review to reflect current system and monitoring accurately
Jupiters Response
Reference of 3D Traser in legend to be replaced with Convergent Controller Max 5
Effective immediately, Jupiters has decided to continue E.coli sampling at the Class A verification point (irrigation water) even when its RW plant is only feeding its irrigation system. Therefore no change to PFD in regards to the Class A verification point (irrigation water).
Target Date Completed
Issue 5 Observation (compliant) 3 General currency of some information throughout RWMP is out of date
Reference Throughout RWMP
Findings
Some references to Nalco remain in text
Water use data is from 2012
Source water data is from 2011/12
References to Class A verification monitoring that is no longer undertaken
References to cross connection checks
Training and Awareness Programs have changed
HACCP Plan still refers to Class A verification
Recommendations Update the RWMP during the next review to make information current. The next required ‘regular review’ is due August 2016 (required at least every 3 years). Jupiters should seek advice from the Regulator regarding when updated conditions of approval will be provided so that they can be included in any review.
Jupiters Response The RWMP is referencing Nalco and data relating to some of the steps involved in getting the approved RWMP. However, will review
Target Date June 2015
Completion Date 24th June 2015
Issue 6 Observation (compliant) 4 RW 6 Recycled water flusherette system refers to old cross connection procedure (conductivity testing)
Reference RW 6 Recycled water flusherette system
Findings RW6 Recycled water flusherette system needs updating with new cross connection procedure (dye testing)
Recommendations Update RW 6 to delete reference to old test and replace with new dye cross connection test
Jupiters Response Jupiters to update RW6 as per recommendation
Target Date 30/06/15
Completion Date Completed
Conclusion During operation in this reporting period Jupiters scheme water quality was 100% compliant in accordance with the Water
Supply (Safety and Reliability) Act 2008
Between 1st July 2014 and 12th April 2015 Jupiters experienced inconstant water quality and flow of its supply from Gold Coast Water. As a result, during this reporting period Jupiters closed both its Recycle Water and Reverse Osmosis Plants.
On 13th April 2015 Jupiters Recycle Water Plant went back on-line followed by the Reverse Osmosis Plant on 14th April 2015. However, up until the end of this reporting period, 30th June 2015, Jupiters still experienced supply issues from Gold Coast Water. This resulted in both plants being closed at various times, these times are documented under the heading of
“Variances” listed in this report.
As per section 578 of the Act a copy of this annual report can be viewed online at Jupiters home page
www.jupitersgoldcoast.com.au/Pages/default.aspx
Alternatively to arrange to inspect a hard copy at Jupiters during normal business hours, or receive a free hard copy, contact Jupiters on
(07) 5592 8674