July 7, 2008 SLAC Annual Program Review Page 1 Andrei Seryi, SLAC American Regional Team leader for...

26
July 7, 2008 SLAC Annual Program Review Page 1 Andrei Seryi, SLAC American Regional Team leader for BDS Deputy of ATF Spokesperson for ATF2 Global Design Effort technical area leader for BDS ATF/ATF2 experiment and BDS program
  • date post

    22-Dec-2015
  • Category

    Documents

  • view

    214
  • download

    2

Transcript of July 7, 2008 SLAC Annual Program Review Page 1 Andrei Seryi, SLAC American Regional Team leader for...

July 7, 2008 SLAC Annual Program Review Page 1

Andrei Seryi, SLAC

American Regional Team leader for BDSDeputy of ATF Spokesperson for ATF2

Global Design Effort technical area leader for BDS

ATF/ATF2 experiment and BDS program

July 7, 2008 SLAC Annual Program Review Page 2

Plan of the presentation

* FY2007 accomplishments

* New strategy, criteria & plan in TDP I & II

* FY2008 achievements

* FY2009 resources

* Five years plan

July 7, 2008 SLAC Annual Program Review Page 3

FY2007 accomplishments

* BDS design work* Progress in construction of ATF2 facility* Design & prototype of crab cavity system* MDI instrumentation studies at ESA facility * Detailed design of SC Final Doublet and prototype

development * Progress with Interaction Region integration efforts by

machine and detector groups* Organization of BDS international team & resources for

TDR phase design

July 7, 2008 SLAC Annual Program Review Page 4

BDS RDR design

14mr IR

Final FocusE-collimator

-collimator

Diagnostics

Tune-up dump

BeamSwitchYard

Sacrificial collimators

Extraction

grid: 100m*1m

Main dumpMuon wall

Tune-up & emergency Extraction

IR Integration

Crab cavityFD

July 7, 2008 SLAC Annual Program Review Page 5

ATF2Model of ILC final focus

Beamline, January 2008 May 2008

Summer 2007

HA PS

FD integration

ATF2 goals :(A) Small beam size ~37nm(B) nm stability of beam center

• ATF international collaboration: MOU signed by 20 institutions• ATF2 constructed as ILC model, with in-kind contributions• Start of beam commissioning: October 2008

July 7, 2008 SLAC Annual Program Review Page 6

Crab CavityUK-FNAL-SLAC crab-cavity collaboration

3d simulations by SLAC ACD

FNAL 3.9GHz transverse cavity achieved 7.5 MV/m

Challenges: damping of parasitic modes, tight phase stability, integration into IR

July 7, 2008 SLAC Annual Program Review Page 7

MDI instrumentation @ ESA

Study: BPM energy spectrometerSynch Stripe energy spectrometerCollimator design, wakefieldsIP BPMs/kickers—background studiesEMI (electro-magnetic interference)Bunch length diagnostics

July 7, 2008 SLAC Annual Program Review Page 8

IR integration

(old location)

Challenges: • Optimize IR and detector design ensuring efficient push-pull operation• Agree on Machine-Detector division of responsibility for space, parameters and devices

July 7, 2008 SLAC Annual Program Review Page 9

IRENG07

* Initiated and organized very successful IR engineering workshop

July 7, 2008 SLAC Annual Program Review Page 10

IRENG07: SC final double & its cryo system

Brett Parker et alBNL

Great progress (2007) on consistent design of the SC Final Doublet, suitable for push-pull operation ( “IR Eng. workshop, IRENG07”)

July 7, 2008 SLAC Annual Program Review Page 11

Alain Herve, CERN, et al

IRENG07: Optimization of Push-Pull design

IRENG07

July 7, 2008 SLAC Annual Program Review Page 12

BDS strategy

• Three critical directions:

–General BDS design–Test facilities, ATF2–Interaction Region optimization

In TDP I & II plan, the scope of work changed, and the focus is shifted

Earlier planned detailed design & engineering will not be performed

• Focus on a few critical directions. Selection criteria:

–Critical impact on performance versus cost; –Advanced ideas promising breakthrough in performance; –Broad impact and synergy with other worldwide projects

beam dumpphoton collidercrystal collimationcrab cavityMDI diagnostics …

IR interface document & designSC FD prototyping and vibration test ILC-like FD for ATF2 …

ATF2 commissioning & operation Develop methods to achieve small beam sizeDiagnostics, Laser Wires, Feedbacks …

Areas of key ART involvement indicated in bold font

SLAC involvement

July 7, 2008 SLAC Annual Program Review Page 13

FY2008 achievements

* ATF2 progress– Delivery of committed hardware to ATF2 and its commissioning (HA PS; FD;

BPM electronics)

– Initiated innovative Flight Simulator framework

* Beam dump design– started new collaboration with India, BARC

* Started development of “Interaction Region Interface Document”* Developed R&D plan for photon collider option* Initiated synergy explorations

– CLIC BDS design

– LHC crab cavity design

– Crystal collimation

* Engaged in cost reduction explorations

July 7, 2008 SLAC Annual Program Review Page 14

SLAC contributions to ATF2

* Hardware– 2 FFTB quads modified for FD– 2 FFTB sextupoles modified for FD – 3 SLC sextupoles modified for FF – 3 FF bends built by IHEP for SLAC, SLAC design– ~ 20 FF quadrupoles built to SLAC design and QC spec – ~30 refurbished FFTB movers – HA power supplies for ~30 magnets – BPM electronics for ~40 cavity BPMs – upgraded ODR monitor – upgraded FFTB wire scanner for IP

* Design, operation and commissioning– several people * 2-3 time per year at KEK + remote participation

July 7, 2008 SLAC Annual Program Review Page 15

High Availability Power Supplies

High Availability Power Supplies delivered, installed, connected and tested at ATF2 (May 2008)

SLAC High Availability Power Supplies are applicable to many future projects such as NSLS-2, LCLS…)

July 7, 2008 SLAC Annual Program Review Page 16

ATF2 final doublet

SBPMQC3

SBPMFFTB2.13

S3.00

SF1FF QF1FF

100 100

450.1 200

180

SBPMQC3

SBPMFFTB2.13

S3.00

SD0FF QD0FF

100 100

76.2

450.1200

18076.2

785380785380

2630

Sw

eeping

Hond

a Shintak

e

IP=>Table=2400

Modified FFTB quads* and sextupoles delivered to LAPP, Annecy, for final integration and stability study*) modification involved increase of aperture

and adjusting pole shape with shims

SLAC FD magnets at LAPP, June 2008

July 7, 2008 SLAC Annual Program Review Page 17

Cavity BPMs

Cavity BPMs and SLAC front-end electronics modules will provide sub-micron resolution of beam position at ATF2

ATF2 is one of the first beamlines to rely only on cavity BPMsExperience applicable to LCLS cavity BPM system, etc

May 2008

Prototype at PAL

July 7, 2008 SLAC Annual Program Review Page 18

ATF2 “Flight simulator”

SLAC-KEK remote participation shift for BBA at ATF ring

Remote participation, first used for ATF in 2007, is used more and more, and facilitate participation of collaborators in ATF2 workFlight Simulator address the next challenge: creating a method how collaborators can contribute to development of tuning tools without being at ATF and without connection to ATF control system

http://ilcagenda.linearcollider.org/conferenceDisplay.py?confId=2797

For details, see ATF2 Software review workshop, June 2008, LAL, Orsay

Glen White (LAL / SLAC)Glen White (LAL / SLAC)

FS based on Matlab and Lucretia accelerator toolbox

First tests of FS performed in May 2008

July 7, 2008 SLAC Annual Program Review Page 19

Dieter Walz, Ray Arnold, Satyamurthy Polepalle (BARC, India), John Amann, at SLAC beam dump area (February 2008)

Computational fluid dynamics study of heat removal by water vortex. Color map show temperature increase of 30 C. BARC

Beam dump design

Initiated collaboration with BARC, India, on beam dump design

Ongoing work on optimization of design for 17MW dump

July 7, 2008 SLAC Annual Program Review Page 20

IR integration

* Machine – Detector work on Interface issues and integration design is a critical area and a focus of efforts

* IR integration timescale– EPAC08 & Warsaw-08

• Interface document, draft

– LCWS 2008• Interface doc., updated draft

– LOI, April 2009• Interface document, completed

– Apr.2009 to ~May 2010• design according to Interface doc.

– ~May 2010: LHC & start of TDP-II• design according to Interf. doc and adjust to specific configuration of ILC

EPAC08

July 7, 2008 SLAC Annual Program Review Page 21

Synergy explorations

* CLIC BDS design– BDS/MDI design– Stability study

* LHC crab cavity design– ILC-LHC initiative: Oct. 2007– Ongoing collaborative design

* Crystal collimation– Potential for more robust

& shorter collimation system– Application as photon source

Discussed approach to CLIC stability

LHC-CC designs, Z.Li, L.Xiao, et al, SLAC

Volume reflection radiation of 200GeV e+ or e- on 0.6mm Si crystal (Rbend=10m)

e+e-

amorphous

Yu. Chesnokov et al, IHEP 2007-16

July 7, 2008 SLAC Annual Program Review Page 22

Cost reduction explorations

Min BDS 500GeV CM

~1.5km/side

Simplified IR

Merged dumps

July 7, 2008 SLAC Annual Program Review Page 23

BDS in GDE Technical Design Phase plan

Key SLACcontributions highlighted

July 7, 2008 SLAC Annual Program Review Page 24

FY2009 resources

* Allow continuation of work where ART & SLAC possess essential leadership and expertise and unique facilities

* Direct benefits: maintain leadership in key areas of US expertise, needed to reach the energy frontier

* Indirect benefit: synergy with US science– ATF2: advanced accelerator study and beam handling applicable to any single

path beamlines such as LCLS, XFEL…

– Instrumentation, high availability power supplies, etc., are applicable to many future projects such as NSLS-2, LCLS…

– IR and and FD design: synergy with LHC IR upgrade and Super-B IR

– Collimation and crab cavity research: synergy with LHC

July 7, 2008 SLAC Annual Program Review Page 25

FY09 FY10 FY11 FY12 FY13

Beam delivery overall design

IR IntegrationFinal Doublet SC prototypeVibration & stability study

SC FD tests at ATF2

IR and FD design for the specific ILC

configuration

BDS design for specific chosen

configuration of ILC Collimation, beam dump, crab cavity …

BDS subsystems studies at FACET

ATF2BDS prototypecommissioning & accelerator physics study

tests & studies of subsystems designed

for specific configuration

TDP I TDP II

BDS five year plan

July 7, 2008 SLAC Annual Program Review Page 26

Conclusion

* RDR design of BDS was produced by international team with essential contribution of ART & SLAC

* In TDP I and II, the strategy has changed* BDS activities are focused on three critical directions* Focus on key areas of US & SLAC expertise* Direct and indirect benefit for US science* BDS plans are integrated into TDP