July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

14
© 2016 Avistas | www.avistas.com | Private & Confidential ICT – The Achilles Heel of Commercial Construction July 11 th , 2016 Presented by: Bill Morgan – CEO & Consulting Principal

Transcript of July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Page 1: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

© 2016 Avistas  |  www.avistas.com | Private & Confidential

ICT – The Achilles Heel of Commercial Construction 

July 11th, 2016

Presented by: Bill Morgan – CEO & Consulting Principal

Page 2: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Avistas

• 14 Year‐Old Independent Management & Technology Advisors

• International Practice • Specialize in Secure Information & 

Communications Technologies (ICT) accelerating growth and transformation.

© 2016 Avistas  |  www.avistas.com | Private & Confidential 2

Page 3: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Avistas Master Plans Secure ICT ‐ Illustrative Projects Vital for Agile Critical Infrastructure

Smart City Operator

“Smart Cities”“Smart Power”

National Power Grid – 11 Time Zones

“Smart Natural Gas” DistributionEAC/Rwanda ‐ “Smart Countries”

“Smart Island”Wireless Broadband Overlay

33© 2016 Avistas  |  www.avistas.com | Private & Confidential

Page 4: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

ICT Master Plan ‐ J.C. Penney Company HQ

© 2016 Avistas  |  www.avistas.com | Private & Confidential 4

• Relocated from New York in 1995

• 3 Year Planning Cycle• Occupied Temporary 

Office Space Across Dallas• Designed to Support 

10,000+ Employees• Site Selection Keyed on 

split LATA for Redundancies

• Largest Fiber‐to‐the‐Desktop in the World

• Original Copper Cabling Still in Place (Cat 5e UTP)

• Modular Phone System Survived 20+ Years With Upgrades

Page 5: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

$5 BILLION MILE

© 2016 Avistas  |  www.avistas.com | Private & Confidential 5

• 1 Mile • 4 Mixed Use 

Developments • $5+ Billion USD in 

Capital Investment

Page 6: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Avistas Streamlines Enterprise Operations

©2016 Avistas  |  www.avistas.com | Private & Confidential 6

Page 7: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

ICT Roles in Development & Relocations

ICT Master Planning for new construction, renovation, “Smart Cities”, Global Economic Development & Revitalization Initiatives all include:

© 2016 Avistas  |  www.avistas.com | Private & Confidential 7

Protect Revenues, Reduce Risk, Optimize

• Program & Project Management• Technology & Operations Architecture 

Development• Technical Spaces, Data Center 

Requirements and Design• Physical Layer Cabling & Routing• Integrated Network Infrastructure• Voice & Video over TCP/IP• Audio/Visual Requirements and Design

• Security & Building Management Systems

• Wireless Infrastructures• Sensors & Internet of Things• Business Continuity and Disaster 

Recovery• Team Development and Management• Transition to new facility with no 

business interruptions

Page 8: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Real Estate Perspective Construction Project (CapEx Oriented)

© 2016 Avistas  |  www.avistas.com | Private & Confidential 8

Real Estate “Concept – to – Cash” Cycle:  6 – 18+ Months(Based on Square Footage & Tenant Business Complexity)

Certificate of Occupancy

Move InContract Broker / Developer

Contract Architect

Retain General Contractor

Schematic Design

Design Development

Construction Documents

Procurement RFP (Subs)

Construction Inspections

Real Estate Transaction Drivers (Change Management)1. Corporate Growth & Expansion 2. Corporate Consolidation, Restructuring or Austerity 3. Merger, Acquisition or Divestiture4. Current Lease Expiration & New Economic Development Incentives

Capital Project Drivers1. Space & Functional Requirements (sq. ft. ) 2. Location & Amenities 3. Value - Incentives

Typical Partners 1. Legal2. Broker/Developer

Architect• General Contractor

3. Independent Management & Technology Advisor

Corporate Economics & Risk Objectives 1. Grow Revenue2. Increased Profitability (While Minimizing Expenses)3. Mitigate Risks

Page 9: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

ICT Perspective – Achilles HeelBusiness Continuity (OpEx Protection & CapEx Management)

© 2016 Avistas  |  www.avistas.com | Private & Confidential 9

Revenue Growth, Continuity of Operations, Customer DelightPreserve Operational Integrity:  People, Process & Technology

Agile Change Management

Certificate of Occupancy

Move InContract Broker / Developer

Contract Architect

Retain General Contractor

Schematic Design

Design Development

Construction Documents

Procurement RFP (Subs)

Construction Inspections

Client Staff – Avistas is an independent representative1. Infrastructure Technology (Move, Merge/Upgrade, Replace or Outsource) 2. Applications (Move, Upgrade, Merge, Replace or Outsource)3. Business Processes (Maintain, Merge/Enhance, Outsource)4. Staffing & Support (Hire, Fire, Assimilate, Train, Outsource)5. Develop OpEx & CapEx Budgets (non-linear, based on licensing, seats, storage, processors, concurrent sessions, etc.)

a) Operations Budgeting & Planningb) Capital Budgeting & Planning

Systems Acceptance

Process Assurance

Performance Reporting

TrainingRetainAvistas

SpecifyTechnical

Spaces

Refine BusinessContinuity Plan

Operations Master

Planning

CD’s, Network & Application

DesignDocuments

Implementation Management &Construction Coordination

Power, Infrastructure & Systems Testing

MoveCoordination

Technology Procurements (e.g. circuits, hardware, software, apps & services)

Technology Program

Development

Finalize OPEX & CAPEX

Page 10: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Partnering to Assure SuccessTeam Avistas – Your “ICT Program Manager”

© 2016 Avistas  |  www.avistas.com | Private & Confidential 10

Team Avistas Broker/DeveloperOperational

Requirements

Planning & InitialBudgets (CAPEX &

OPEX)

DetailedDesign &

Specifications

Scheduling

Procurement

Implementation Management

• Business Continuity• Disaster Recovery• Master Planning- Data Center- Call Center- Technical Spaces- Collaboration Spaces

Board RoomsConference RoomsTraining Rooms

- Networks- Telephones- Applications- Processing & Storage

• “Green” Design- Power- Computing Systems- Infrastructure CablingWireless Audio Visual Systems Security

Architect

Civil Engineers

Structural Engineers

MEP Engineers

General Contractor& Trades

• Site Planning• Construction− Shell Building − Interiors

• Mechanical/HVAC• Plumbing• Electrical

CAPEXManagement -

Facilities

CAPEX & OPEXManagement Operations &

Facilities

Technology Requirements

Packages

ConstructionCoordinationand Testing

Development/Relocation Client

Page 11: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Infrastructure Objectives:  Target 10+ Year Life Cycles• Define Operational and Technology Requirements• Develop Rational Architecture and Designs for New Facility• Provide the Best Overall Value to the Company• Maintain Transparent LAN/WAN Operations

– Minimum End User Disruption– Minimum Applications/Services Interruption

• Provide Effective Program and Project Management– Integrated Teaming with the Client– Meticulous Planning– Business Continuity and Rollback Plans– Change Management– Construction and Implementation Coordination and Control 

© 2016 Avistas  |  www.avistas.com | Private & Confidential 11

Page 12: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

© 2016 Avistas  |  www.avistas.com | Private & Confidential 12

Page 13: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

Small Technical SpacesHuge Revenue Impact

© 2016 Avistas  |  www.avistas.com | Private & Confidential 13

500 sq. ft. Data Center- 10 IBM Blade Center Racks- Mixed processors and disk- 3 Blade Centers per rack- 1 Networking Cabinet

Power:- Blade Centers

- 2,900 Watts per Blade Center- 30 Blade Centers- 87,000 watts

- Network Units (routing & switching) - 6,000 Watts per Network Unit- 2 network units- 12,000 watts

-UPS rating – 120KVA-Losses – 9,900 watts

- Total Approx. 108,900 watts

Weight:- 350 lbs per Blade Center- 250 lbs per rack- UPS – 3,000 lbs- Batteries – 5,000 lbs- Total Approx. 19,000 lbs

Emergency Services:- 48 hour run times- Fuel dispatch within 24 hours

Summary:- 218 watts per square foot for systems(office space is < 5 watts per square foot)

- 31 tons of cooling (30% more power)- Total power requirement – 140Kw

(165KVA)

Business Impact• $2,000,000 in hardware and software

installed• $200,000+ in annual support costs• Supports 1,000 – 5,000 employees

enterprise-wide• Supports $1+ billion in client transactions

and annual revenue

Services Companies Require Careful ConsiderationA major Internet Service Provider:Developed $150 million facilityInstalled $1 billion in equipmentGenerates over $4 billion in annual

revenues

Local DFW Financial Services Companies:“A” Generates $4 million per hour

unrecoverable revenue“B” Generates $5 million per day

unrecoverable revenue

24' 3" x 25' 3"

UPS 120kva

NetworkSystems

IBM Blade Center Systems

IBM Blade Center Systems

Examples – Typical “Small Technical Space”

Page 14: July 11 , th 2016 ICT –The Achilles Heel of Commercial ...

© 2016 Avistas  |  www.avistas.com | Private & Confidential

Questions?

Thank You!  

Bill Morgan, Avistas ‐ CEO & Consulting Principal(214) 544‐0400 | www.avistas.com