Jason D. Eady
Transcript of Jason D. Eady
The Investment Building
12-story office building380,000 square feet totalLocated in Washington, D.C.
Jason D. Eady The Investment Building
ContentsBuilding Background
o Design Teamo Existing Structure Systemo Architectureo Construction and Cost Implications
Depth: Structural Steelo Proposed Structural Systemo Design Loadso Gravity Designo Lateral Systemo Final Designo Cost
Breadth A: Mechanicalo Increase in Plenum Spaceo Steel Joistso Castellated Beams
Breadth B: Architectureo Integration of Beaux-Arts Façade o Low Floor-to-Ceiling Heightso Decrease in Diameter of Atria o Integration of Concrete Parking Garage
Conclusion
Acknowledgements
Questions
Jason D. Eady The Investment Building
ContentsBuilding Background
o Design Teamo Existing Structure Systemo Architectureo Construction and Cost Implications
Depth: Structural Steelo Proposed Structural Systemo Design Loadso Gravity Designo Lateral Systemo Final Designo Cost
Breadth A: Mechanicalo Increase in Plenum Spaceo Steel Joistso Castellated Beams
Breadth B: Architectureo Integration of Beaux-Arts Façade o Low Floor-to-Ceiling Heightso Decrease in Diameter of Atria o Integration of Concrete Parking Garage
Conclusion
Acknowledgements
Questions
Jason D. Eady The Investment Building
Design TeamGeneral Contractor: The Clark Construction Group, Inc.
Design Architect: Cesar Pelli & Associates, Inc.
Architect of Record: Shalom Barnes Associates, PC
MEP Engineers: B & A Consulting Engineers
Structural Engineers: Tadjer-Cohen-Edelson, Assoc
Civil Engineers: A. Morton Thomas & Associates
Fire & Life Safety Engineers: Schirmer Engineering Corporation
Owner/Developer: The Kaempfer Company
Jason D. Eady The Investment Building
Existing Structural SystemLateral System – monolithically poured slab and columns that transfer moments from the two-way reinforced slab to the columns
Gravity System – Two-way reinforced concrete flat slab with drop panels
Typical Bay Strip – 30’ x 30’ exterior bays and 30’ x 26’ interior bays
Foundations – Level P3 slab-on-grade, 18’ x 18’ typical spread footings
Concrete – Normal weight 3 ksi compressive strength concrete on 8” slabs on levels 2-5 and 7-10. Normal weight 4ksi compressive strength for 9” and 10” slabs and walls and columns
Jason D. Eady The Investment Building
Architecture1501 K Street Washington, DC 20005
Restored 1920s Beaux-Arts façade
50 foot diameter Atria
Penthouse Roof
Increased floor-to-floor heights
Jason D. Eady The Investment Building
Construction and Cost
Delivery Method - Design-Bid-BuildContract – GMP of $38,146,000Construction Duration – 3 ½ yearsCost of project- $38.1 M total- $3.0 M in soft costs
Jason D. Eady The Investment Building
Construction and Cost
$38.1MTotal Project Cost
$15,500,000$3,200,000$2,000,000$2,800,000$1,500,000$3,800,000$5,200,000$4,100,000
Structural SystemHVACElectricalPlumbingElevatorsPre-CastSite ManagementPost-tensioned Concrete
(Parking Garage)
Approximate Major Building System Cost
Jason D. Eady The Investment Building
ContentsBuilding Background
o Design Teamo Existing Structure Systemo Architectureo Construction and Cost Implications
Depth: Structural Steel o Proposed Structural Systemo Design Loadso Gravity Designo Lateral Systemo Final Designo Cost
Breadth A: Mechanicalo Increase in Plenum Spaceo Steel Joistso Castellated Beams
Breadth B: Architectureo Integration of Beaux-Arts Façade o Low Floor-to-Ceiling Heightso Decrease in Diameter of Atria o Integration of Concrete Parking Garage
Conclusion
Acknowledgements
Questions
Jason D. Eady The Investment Building
Alternative Structural System
Composite Steel Deck with Concrete Slab and Wide-Flange Beams
Jason D. Eady The Investment Building
Alternative Structural System
Advantages of Composite Steel System- Light- Economical- Longer spans- Easy and Quick to Erect- Less Site Labor- Earlier Delivery Time
Jason D. Eady The Investment Building
Design LoadsDesign Wind Loads
Lateral Load on structural frame 13.02 PSFRoof uplift 20 PSF
Code minimum design loads based on the following:
Basic Wind Speed, V = 70MPHWind load importance factor, I = 1.0Wind exposure (typical) = BWind design pressure, P, varies with building
height, used maximum value of 13.02 PSF for entire height
Seismic DesignCode minimum design loads based on the
following:Peak velocity-related acceleration, Av = 0.05Peak acceleration, Aa = 0.05Seismic hazard exposure group = Group ASeismic performance category = A
Design Gravity LoadsTypical Floor:
Superimposed Dead Loads-MEP, electrical, ceiling, etc. 62.07 PSF Partitions 20 PSF
Live Loads-Office area 60 PSF** Corridor, stairs and lobby 100 PSF
**(BOCA requires 50 PSF for offices)
Roof : Superimposed Dead Loads-
MEP, electrical, ceiling, etc. 12 PSFRoofing, insulation, etc. 18 PSF
Live Load – Snow (minimum) 17.5 PSF (+ drift)Code minimum snow load based on the
following:Ground snow load, Pg = 25 PSFFlat roof snow load = Pf = 17.5 PSFSnow exposure Factor, Ce = 0.7
Load Summary for Composite Steel System
Jason D. Eady The Investment Building
Gravity Design
30’ x 30’ column spacing in both the N-S and E-W directionsBays adjacent to South façade are 30’ x 22’Bays adjacent to the East façade are 24’ x 30’4” Slab- USD 2” Lok-floor Composite Deck with 18 gage thickness- 2” concrete topping for 1 ½ hour fire proofing
Jason D. Eady The Investment Building
Gravity Design
Live Load Distribution- Areas of high circulation: 100 PSF - Other Areas: 60 PSF
Jason D. Eady The Investment Building
Lateral System
Rigid Braced Frames- Type PR Connection: Beam-to-girder
> 5/8” thick end plate> Six 1/2” diameter A-325 bolts
- Type FR Connection: Girder-to-column> 7/8” thick end plate> Six 7/8” diameter A-325 bolts
Jason D. Eady The Investment Building
Lateral System
Type PR connection (shear connection)
between beams and girders
Type FR connection (rigid connection)
between girders and columns
Jason D. Eady The Investment Building
Lateral System
Advantages of FR and PR Connections- Plate is shop welded to beam before it is
delivered to the construction site- Fewer bolts are required - Fast erection
Jason D. Eady The Investment Building
Costs
$34,448,000Total Project Cost
$11,848,300$3,200,000$2,000,000$2,800,000$1,500,000$3,800,000$5,200,000$4,100,000
$68,300$150,000$150,000$125,000$38,000$440,000$25,000$180,000
$680,000$550,000$250,000$375,000$467,000$960,000
$3,675,000$650,000
$11,100,000$2,500,000$1,600,000$2,300,000$995,000
$2,400,000$1,500,000$3,300,000
Structural Steel SystemHVACElectricalPlumbingElevatorsPre-castSite ManagementPost-tension Concrete
(Parking Garage)
TotalEquipmentLaborMaterialBuilding System
Jason D. Eady The Investment Building
ContentsBuilding Background
o Design Teamo Existing Structure Systemo Architectureo Construction and Cost Implications
Depth: Structural Steelo Proposed Structural Systemo Design Loadso Gravity Designo Lateral Systemo Final Designo Cost
Breadth A: Mechanicalo Increase in Plenum Spaceo Steel Joistso Castellated Beams
Breadth B: Architectureo Integration of Beaux-Arts Façade o Low Floor-to-Ceiling Heightso Decrease in Diameter of Atria o Integration of Concrete Parking Garage
Conclusion
Acknowledgements
Questions
Jason D. Eady The Investment Building
Mechanical
Mechanical System- Power Induction VAV System using
fresh air from outside
- Variable air handling units, fans, heating coils and plate and frame heat exchangers
- 10” insulated ducts
Jason D. Eady The Investment Building
Mechanical
Issue – The composite steel system and the mechanical system increases the floor thickness (plenum space).
Jason D. Eady The Investment Building
Increase in Plenum Space
Plenum space for existing concrete system
Jason D. Eady The Investment Building
Increase in Plenum Space
Plenum space for composite steel system
Jason D. Eady The Investment Building
Increase in Plenum Space
Disadvantages of Composite Steel System- 6” increase in plenum space- Maximum floor-to-ceiling heights – 8’-1”
(8’-7” for the concrete system)- Interference of plenum space with some
window openings in the façade
Jason D. Eady The Investment Building
Increase in Plenum Space
Possible Solutions:- Steel joists- Castellated beams
Jason D. Eady The Investment Building
Steel Joists
- Composite interaction is required.
- 26” deep joists are required to adequately support gravity loads.
Jason D. Eady The Investment Building
Steel Joists
Disadvantages- Plenum space increases to 2’-6” including
the 4” thick slab- Floor-to-ceiling heights decrease to 7’-10”
Jason D. Eady The Investment Building
Steel Joists
Therefore, it is not feasible to use steel joists, since- Plenum space is greater than the plenum
space of the composite steel system containing wide-flanged section
- Floor-to-ceiling heights decrease further
Jason D. Eady The Investment Building
Castellated Beams
Advantages:- Light - Strong- Cheap- Easy to assemble at the construction site- Aesthetically pleasing - Passage of mechanical ducts
Jason D. Eady The Investment Building
Castellated Beams
To adequately carry gravity loads,- HE- 500-B is required as a
substitute for W10 x 22 beamsNominal depth – 1’ – 8”
- HE- 450 B is required as a substitute for W10 x 19 beamsNominal depth – 1’ – 6”
Jason D. Eady The Investment Building
Castellated Beams
Results considering the HE- 500-B: - Plenum space including 4” slab is
2’-0”- Floor-to-ceiling height is 8’-4”
(Floor-to-ceiling heights are 8’-1” using wide-flange sections)
Jason D. Eady The Investment Building
Castellated Beams
Recommendation:Since the plenum spacing required for castellated beams is less than the plenum space required for wide-flange sections, castellated beams are an excellent solution for integrating the mechanical and structural elements in the plenum space.
Jason D. Eady The Investment Building
ContentsBuilding Background
o Design Teamo Existing Structure Systemo Architectureo Construction and Cost Implications
Depth: Structural Steelo Proposed Structural Systemo Design Loadso Gravity Designo Lateral Systemo Final Designo Cost
Breadth A: Mechanicalo Increase in Plenum Spaceo Steel Joistso Castellated Beams
Breadth B: Architectureo Integration of Beaux-Arts Façade o Low Floor-to-Ceiling Heightso Decrease in Diameter of Atria o Integration of Concrete Parking Garage
Conclusion
Acknowledgements
Questions
Jason D. Eady The Investment Building
Architecture
Issues:- Integration of Beaux-Arts Façade - Low Floor-to-Ceiling Heights- Decrease in Diameter of Atria - Integration of Concrete Parking Garage
Jason D. Eady The Investment Building
Integration of Beaux-Arts Façade
Issue:Coinciding of Column/façade window opening
Jason D. Eady The Investment Building
Integration of Beaux-Arts Façade
Solution:- Most columns were place in same
locations as they are in existing structural system (typical 30’ spacing)
- Other columns were place in location where they do not interfere with window openings
Jason D. Eady The Investment Building
Low Floor-to-Ceiling Heights
Issue:- Constant floor-to-floor heights- Increase in plenum space
- Low finished ceilings (8’-1”)- Coinciding of plenum space and façade
window openings
Jason D. Eady The Investment Building
Low Floor-to-Ceiling Heights
Solution:- Use castellated beams to decrease
plenum space- Floor-to-ceiling heights increase to
8’-4” with castellated beams
Jason D. Eady The Investment Building
Decrease in Diameter of Atria
Issue:Because structural elements supporting the atria are to carry equal amount of gravity loads, the geometry of the elements supporting the atria needs to be symmetric.
Jason D. Eady The Investment Building
Decrease in Diameter of Atria
Solution:Diameter of atria decreases by 7’-7” to symmetrically support gravity loads imposed on the atria.
Diameter of atria in existing system: 50’-0”Diameter of atria in composite steel System: 42’-7”
Jason D. Eady The Investment Building
Integration of Concrete Parking Garage
Issues:- Coinciding of concrete/steel columns- Loss of parking spaces
Jason D. Eady The Investment Building
Integration of Concrete Parking Garage
Solution:- offset center of west most column of
superstructure west 4’-6” off center of the west-most column in parking garage
- offset north-most columns of superstructure 3’-0” off center of the north-most columns of the parking garage
Jason D. Eady The Investment Building
Integration of Concrete Parking Garage
Jason D. Eady The Investment BuildingSuperstructure superimposed on concrete parking garage
ContentsBuilding Background
o Design Teamo Existing Structure Systemo Architectureo Construction and Cost Implications
Depth: Structural Steelo Loadso Gravity Designo Lateral Systemo Final Designo Cost
Breadth A: Mechanicalo Increase in Plenum Spaceo Steel Joistso Castellated Beams
Breadth B: Architectureo Integration of Beaux-Arts Façade o Low Floor-to-Ceiling Heightso Decrease in Diameter of Atria o Integration of Concrete Parking Garage
Conclusion
Acknowledgements
Questions
Jason D. Eady The Investment Building
ConclusionIt is recommended to utilize the Composite Steel System as a alternative superstructure
Reasons:- $3.6 M cheaper than existing system- Quick erection resulting in faster delivery
> Early opening> Owner begins earning revenue immediately
- Mechanical System integrates well- No major impacts on the building’s architecture
Jason D. Eady The Investment Building
Thank you
FacultyDr. Louis GeschwindnerDr. Kevin ParfittDr. Thomas BoothbyJohnathan DoughertyDr. Moses Ling
ProfessionalsBrian FlegelSteve Kalthoff
PeersPaula MartinezShauna Koenig
Family and friendsGODMomAunt PhyllisUncle LeonJulie Vastyan
Jason D. Eady The Investment Building