IWG Update

5
IWG Update August 2014 ISAS Danielle Johnson

description

IWG Update. August 2014 ISAS Danielle Johnson. IWG Meeting BAL-002-WECC-2. BAL-002-WECC-2 Standard when implemented in October 2014 will no longer require the Contingency Reserve Responsible entity to be stated on the e-tag. SAR submitted for INT-011-WECC-RBP-2 Ten Minute Recallable - PowerPoint PPT Presentation

Transcript of IWG Update

Page 1: IWG Update

IWG Update

August 2014 ISAS

Danielle Johnson

Page 2: IWG Update

IWG Meeting BAL-002-WECC-2

BAL-002-WECC-2 Standard when implemented in October 2014 will no longer require the Contingency Reserve Responsible entity to be stated on the e-tag.

–SAR submitted for INT-011-WECC-RBP-2 Ten Minute Recallable

Removal of WR1 #3 and #4 Drafting team being formed

Page 3: IWG Update

IWG Meeting BAL-002-WECC-2

Recommend changes to INT-009-WECC-2 Capacity Tag FunctionalityWhere it states on demand spinning change to operating reserves - spinningWhere it states on demand non spinning change to operating reserve - supplemental

Page 4: IWG Update

IWG Meeting Charter Review

Charter completed and posted for comment.

– Pending approval

Page 5: IWG Update

WIAB Test 2014

– Only received one volunteer to conduct 2014 WIAB TestWAPA Rocky Mountain Region

Is an annual test needed?– Can the test be conducted

biannually?