Ivy Ridge Trail Feasibility Study - April 2014

download Ivy Ridge Trail Feasibility Study - April 2014

of 60

Transcript of Ivy Ridge Trail Feasibility Study - April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    1/60

    IVY RIDGE TRAIL

    FEASIBILITY STUDY

    prepared for

    Manayunk Development

    Corporation

    by

    Whitman, Requardt & Associates

    Interface Studio

    A.D. Marble & Company

    Ruggiero Plante Land Design

    April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    2/60

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    3/60

    IVY RIDGE TRAIL FEASIBILITY STUDY

    ACKNOWLEDGEMENTS

    Manayunk Development Corporation (MDC)commissioned the preparation of this feasibility study for the design and planning of the Ivy Ridge Trail.

    The project was led by Kay Sykora, Director, Destination Schuylkill River.

    MDC is a non-profit community development corporation formed to encourage economic development that benefits the entire community.

    Incorporated in 1985 and first staffed in 1988, MDC was originally known as the New Manayunk Corporation. The New Manayunk Corporation took

    responsibility for parking, the Canal and capital projects within the district. A separate entity, the Business Association of Manayunk (BAM), worked to

    promote the district by creating a number of festivals including the Main Street Stroll, the Manayunk Arts Festival, and the Indian Summer Festival. In

    1992, BAM and the New Manayunk Corporation were merged to form MDC. Under MDC, the functions of the original two groups have continued and

    grown.

    This project was financed in part by a grant from the Community Conservation Partnerships Program, Environmental Stewardship Fund, under the

    administration of the Pennsylvania Department of Conservation and Natural Resources, Bureau of Recreation and Conservation.

    The project was also financed in part by the William Penn Foundation.

    The feasibility study was developed in close coordination with the following stakeholder groups:

    Bicycle Coalition of Greater Philadelphia

    Canton Street residents

    City of Philadelphia Department of Parks and Recreation

    City of Philadelphia Department of StreetsDelaware Valley Regional Planning Commission

    Friends of the Ivy Ridge Trail

    Ivy Ridge Green

    Manayunk Development Corporation

    Pennsylvania Department of Conservation and Natural Resources

    Philadelphia City Planning Commission

    Southeastern Pennsylvania Transportation Authority

    April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    4/60

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    5/60

    IVY RIDGE TRAIL FEASIBILITY STUDY

    TABLE OF CONTENTS

    Introduction............................................................................................................................................................................................................................ 1

    Background............................................................................................................................................................................................................................. 4

    Process ................................................................................................................................................................................................................................. 13

    Trail user experience ............................................................................................................................................................................................................ 17

    Trail segments ...................................................................................................................................................................................................................... 19

    Leverington Avenue bridge area

    Canton Street areaFountain Street area

    Ivy Ridge station

    Schuylkill River Trail / canal towpath connection alternatives ............................................................................................................................................ 34

    Amenities, materials, and landscape.................................................................................................................................................................................... 38

    Safety, maintenance, and operations .................................................................................................................................................................................. 42

    Final design requirements .................................................................................................................................................................................................... 43

    Costs and implementation ................................................................................................................................................................................................... 46

    Appendix summary of public comments ................................................................................................................................................... following page 47

    April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    6/60

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    7/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Introduction

    INTRODUCTION

    The primary goal of the Ivy Ridge Trail study is to provide a safe,

    user friendly pedestrian and bicycle connection between the

    Manayunk Bridge Trail and the Umbria Street bike lanes at Ivy

    Ridge Station. This trail connection will enhance the Greater

    Philadelphia Regional Trail Network (also known as the

    Circuit) by adding approximately eight tenths of a mile of a

    hard-surface, accessible trail, as an alternative to the unpaved

    section of the Schuylkill River Trail. Although this segment is

    relatively short, as an extension of the Manayunk Bridge Trail,

    this rail-to-trail provides a key link in the network while meeting

    the goals of the Philadelphia Trail Network as outlined in the

    2013 City of Philadelphia Trail Master Plan.

    In order for this goal to be achieved, a successful trail study fullyengages the public early in the design process. The purpose of

    this planning effort was to develop a plan that has been fully

    vetted through a series of public meetings and achieves the goals of the project while meeting the wants and needs of the community.

    In addition to developing a plan based on public input, the purpose of this plan is to develop a concept design that has been sufficiently advanced to

    provide concept level costs and potential implementation steps. Performing a detailed concept design reduces the level of uncertainty as the project

    moves into final design. Planning-level cost estimates allow the project to be broken into phases for stakeholders to obtain funding for final design

    and construction.

    This report was funded by grants from the Community Conservation Partnerships Program, Environmental Stewardship Fund, under the

    administration of the Pennsylvania Department of Conservation and Natural Resources, Bureau of Recreation and Conservation; the Delaware Valley

    Regional Planning Commission (DVRPC); and the William Penn Foundation.

    April 2014 1

    http://www.dcnr.state.pa.us/
  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    8/60

    Introduction IVY RIDGE TRAIL FEASIBILITY STUDY

    Benefits of trails

    In general, trails offer a number of benefits to a community. This is particularly true of the Ivy Ridge Trail and potential surrounding connections.

    Recreation, Health and Fitness

    Americans place a high priority on having trails and open space in their community for recreation purposes. Trails encourage healthier lifestyles by

    serving as nearby outdoor fitness resources for walking, jogging, bicycling, and other forms of exercise. As an extension of the Manayunk Bridge Trail,

    the Ivy Ridge Trail provides a unique opportunity to provide a connection between the urban setting of Philadelphia and the suburban, natural, rolling

    hills of Lower Merion, allowing for distinctly different recreational opportunities for residents of both communities.

    Transportation Choices

    Many Americans are choosing to reduce or eliminate motor vehicle use. Transportation is typically the second largest cost in a household budget,

    behind only housing. Increasing gasoline prices, traffic congestion, and interest in sustainability also factor into reduced car usage. Trails provide

    people safe means to travel without a car. The Ivy Ridge Trail is expected to serve as a commuter corridor as well as a destination. The direct trail

    connections proposed in this report link the Cynwyd Heritage Trail in Lower Merion Township via the Manayunk Bridge to the south with the existing

    Umbria Street bike lanes to the north, providing a continued linear commuter connection paralleling I-76, which is prone to daily congestion. Just as

    important as the linear trail extension is the proposed trail

    connections to the community via the Schuylkill River Trail (SRT)

    which is heavily used as a commuter route connecting the many

    major employment centers along the Schuylkill River.

    Safety and Community

    Trails encourage safe and interpersonal interaction by linking

    neighborhoods. Trails also ensure that people who wish to travel

    without a car have a safe means to do so without walking or riding

    in motor vehicle traffic. Direct connections with the Ivy RidgeStation will also allow users to safely walk or ride to public transit.

    Equity

    Trails provide safe, comfortable opportunities for people who cant

    drive to travel to their destinations. Making these facilities

    accessible ensures that people with mobility impairments can enjoy

    them as well.

    2 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    9/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Introduction

    Project Partners

    A Study Committee composed of project stakeholders representing community interests guided the entire course of the study. The committee met on

    a monthly basis to discuss the design process and determine preferred alternatives based on public input. The study committee consisted of the

    following organizations:

    Southeastern Pennsylvania Transportation Authority (SEPTA) property owner, lessor

    Philadelphia Parks and Recreation lessee, responsible for trail maintenance and operations

    Delaware Valley Regional Planning Commission (DVRPC) design funding source

    Manayunk Development Corporation grant applicant and community coordination lead

    Philadelphia Bicycle Coalition bicycle community representation

    Friends of Ivy Ridge Trail and local residents community representation

    April 2014 3

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    10/60

    Background IVY RIDGE TRAIL FEASIBILITY STUDY

    BACKGROUND

    History

    The Ivy Ridge Trail corridor has a long history of various freight and commuter rail use since the early 1800s. The original alignment was owned by the

    Pennsylvania Schuylkill Valley Railroad (PSV) and extended from Philadelphia to Reading paralleling the Philadelphia & Reading Railroad. In 1902 the

    Pennsylvania Railroad (PRR) purchased the Pennsylvania Schuylkill Valley Railroad. Soon after the PRR replaced the steel structure built in 1884 with

    the current S-shaped structure, constructed in 1918, to allow for heavier train use. In 1976, SEPTA took over the rail corridor and ran commuter trains

    as part of its R6 regional rail line. SEPTA built the Ivy Ridge Station in 1980 and ran commuter trains for ten years until structural concerns with the

    Manayunk Bridge led to discontinuation of rail service beyond the Cynwyd station. SEPTA rehabilitated the bridge in 1999. However, commuter

    service has not been restored and the Ivy Ridge Station was removed in 2012. An adjacent Ivy Ridge Station on the Manayunk/Norristown Line, down

    the hill from the previous station, continues to serve commuters.

    4 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    11/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Background

    Land use

    Historically, Manayunk was known for being a manufacturing village. When looking at the 1942 land use map, much of the area north of Parker Street

    along the rail line was not yet developed. The area south of Parker Street, however, contained a mix of industrial uses, including coal storage, the

    Manayunk Plush Manufacturing Company, the Glen Willow Ice Manufacturing Company, the S.S. Keeley & Sons Lumber Yard, and the Container

    Corporation of America. Parcels in the area also included many residential properties, particularly fronting Canton and Umbria Streets. By 1962, thearea north of Parker Street had started to fill in with auto-related commercial properties, but still remained largely vacant.

    1942 land use: Philadelphia Geo History 1962 land use: Philadelphia Geo History

    April 2014 5

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    12/60

    Background IVY RIDGE TRAIL FEASIBILITY STUDY

    Today many of the residential properties have remained the same. However, many of the active industrial properties have left the area, leaving large

    swaths of vacant land. Redevelopment of some of these properties is taking place, such as the proposed 168 apartments at Umbria Village at the

    former location of the Glen Will Ice Manufacturing Company.

    6 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    13/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Background

    Cultural resources

    The proposed Ivy Ridge Trail comprises the former right-of-way of the Pennsylvania Railroad Schuylkill Valley Branch, which was previously

    determined not eligible for listing in the National Register of Historic Places and does not contribute to the National Register-listed Manayunk Historic

    District. The former railroad corridor no longer retains features such as rails and catenaries that were associated with the active use of the rail line.

    A review of the Pennsylvania Historical and Museum Commission (PHMC) Cultural Resources Geographic Information System (CRGIS) revealed the

    presence of nine other historic resources with previous eligibility determinations in the vicinity of the project area:

    Manayunk Main Street Historic District (Listed)

    Manayunk Bridge (Eligible, Not Contributing)

    Schuylkill Navigation Company Canal/Manayunk Canal (Eligible and Contributing)

    Philadelphia, Georgetown & Norristown Railroad (Eligible, contributing status is undetermined)

    S.S. Keeley & Sons Mill, 100 Leverington Street (Eligible and Contributing)

    Leverington Avenue Bridge (Not Eligible, Not Contributing)

    Fountain Street Bridge (Not Eligible, Not Contributing)

    Green Lane Bridge (Not Eligible, Contributing)

    James Dobson School (Listed)

    Section 106 of the National Historic Preservation Act of 1966 (NHPA) requires Federal agencies to take into account the effects of their undertakings

    on historic properties. In order to complete the Section 106 process for the project (assuming Federal funds may be used), an Area of Potential Effect

    (APE) should be finalized that includes all areas of potential direct effects as well as all resources within the viewshed of the proposed improvements.

    Coordination should be initiated with PHMC and consulting parties in order to identify any other potential historic resources within the project area

    and evaluate the effects of the project on historic resources. As the project limits extend within the National Register-listed Manayunk Historic District

    and are adjacent to the National Register-eligible Philadelphia, Georgetown & Norristown Railroad, efforts may need to be made to minimize the

    impacts of the improvements on the surrounding historic resources. It is anticipated that effects will be minimal due to the nature of the project along

    an existing railroad right-of-way, and the majority of the project improvements taking place at a distance from known historic resources.

    Archaeology

    As previously mentioned, the APE should be finalized to include all areas of potential direct effects in relation to the proposed development as they

    pertain to potential archaeological resources. Considering the nature of the project along an existing railroad right-of-way placed on ballast, and along

    existing roads and sidewalks for access, it is anticipated that the potential for the presence of unrecorded archaeological resources is extremely low.

    However, in the event project designs include areas outside the railroad right-of-way, further evaluation of archaeological potential will be necessary.

    For example, the proposed project limits include a forested area southeast of the Ivy Ridge Station parking lot and an access area to the Leverington

    Avenue bridge that could require further investigation. Prior to the onset of any project-related activities, coordination with the PHMC will be

    initiated.

    April 2014 7

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    14/60

    Background IVY RIDGE TRAIL FEASIBILITY STUDY

    8 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    15/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Background

    Connectivity to regional trail network

    Phase one of this project includes the final design of the

    Manayunk Bridge, completed in 2013. Scheduled to open

    in 2015, the bridge will connect the Cynwyd Heritage Trail

    with an entrance at Dupont Street that is suitable forbicycle and pedestrian traffic. This first phase will make it

    possible for residents in Lower Merion Township to access

    Manayunk shops and restaurants by walking or biking

    without having to interact with the two active railroad lines

    and major highway that currently exist in their path.

    This report is focused on the second phase of the project,

    the Ivy Ridge Trail. This trail will connect the Manayunk

    Bridge with the Ivy Ridge Station and the Umbria Street

    bike lanes. This connection is an integral part of The Circuit,

    a trail planning initiative to integrate 750 miles of bicycle

    and pedestrian paths in the Greater Philadelphia Region,and includes the Schuylkill River Trail, the Cynwyd Heritage

    Trail and the Wissahickon Valley Trail. The Ivy Trail will

    directly connect to the following regional trails:

    Schuylkill River Trail and the Manayunk Towpath - The

    Schuylkill River Trail, once completed, will be a 130-mile

    multi-use trail that will connect Philadelphia and Pottsville.

    From the north, the off-road trail currently comes to an

    end at the intersection of Nixon Street and Port Royal

    Avenue. Users continue on Nixon Street until its end,

    making a slight right to access the Manayunk Towpath justnorth of the Flat Rock Dam. The towpath continues along

    the Manayunk Canal until its end at Lock Street, where

    users can access Main Street, following it to connect to the

    Wissahickon Valley Trail and the Kelly Drive path at Ridge

    Avenue.

    Cynwyd Heritage Trail - This 2.5-mile trail starts at the

    Cynwyd SEPTA Station and runs to Belmont Avenue and

    Rock Hill Road. It is the first piece of the former Ivy RidgeSource: Philadelphia Trail Master Plan, 2013

    April 2014 9

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    16/60

    Background IVY RIDGE TRAIL FEASIBILITY STUDY

    Branch to be completed. It opened in October 2011 and has separate bicycle and pedestrian trails. Users of the Ivy Ridge Trail will be able to access

    this trail directly via the Manayunk Bridge. They can then continue on until its end at the Cynwyd SEPTA Station, or continue down to the other side of

    the Schuylkill River via the proposed Cynwyd Spur. In the future, this spur will connect to the Wissahickon Valley Trail and Kelly Drive via the Pencoyd

    Bridge as part of proposed development project in Lower Merion Township, allowing Schuylkill River Trail users to avoid Main Street in Manayunk.

    10 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    17/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Background

    Structural Evaluation

    On July 24, 2012, the project team performed a visual inspection of the Ivy Ridge Trail site to determine the conditions of the existing structures and

    discuss options for a trail across those structures. The visual inspection was performed from under and on those spans which were readily accessible

    from the ground or street. The following SEPTA-owned structures were evaluated:

    High Street / Leverington Avenue bridge approach retaining wall Elevated rail bed with ballast fill

    Leverington Avenue bridge Concrete arch structure

    April 2014 11

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    18/60

    Background IVY RIDGE TRAIL FEASIBILITY STUDY

    Fountain Street bridge Concrete encased steel girder

    Full descriptions of each structure and proposed modifications can be found in subsequent sections of this report.

    As a result of the visual inspection of the aforementioned structures it was determined that there are no significant structural issues that should

    prevent development of the Ivy Ridge Trail. As these structures were originally designed to carry railroad loads, which are far more than expected

    from a trail, it is the project teams opinion that structural analysis of these spans will not be required. The key issues to be addressed are the railing

    and protective fence requirements across the structures, as well as SEPTA drainage and waterproofing requirements. Each system must meet

    standards for structural integrity and functionality, as well as possess properties that will support the goal of providing the public with a safe and

    aesthetically pleasing trail.

    12 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    19/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Process

    PROCESS

    A fully engaged public during the feasibility and

    concept stage is one of the most essential

    aspects of successful trail development. The

    project embarked on an ambitious publicinvolvement program. The following public

    involvement activities were undertaken. More

    detailed information on the alternatives that

    were considered may be found in subsequent

    sections of this report.

    A stakeholder committee, composed of the

    project partners representing community

    interests, guided the entire course of the study.

    The committee met frequently to discuss the

    design process and determine preferredalternatives based on public input to ensure

    meaningful stakeholder involvement in the

    conduct of this study.

    The project team held three public meetings

    throughout the concept design process. A full

    summary of all public correspondence can be

    found in the appendix.

    April 2014 13

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    20/60

    Process IVY RIDGE TRAIL FEASIBILITY STUDY

    Public Meeting No. 1, November 19, 2012

    The goal of this meeting, held at the Manayunk Brewing Company, was to introduce the project to the public and obtain input on the publics needs

    and desires for the trail. The design team presented the project limits and the following requirements of the trail as determined by the steering

    committee:

    The trail must have a hard surface so that it is viable for both commuting and recreation

    The trail must link the Umbria Street bike lanes with the Manayunk Bridge

    The trail must be safe and secure

    The trail must fall within SEPTAs right-of-way

    The trail must be financially reasonable to build

    The trail must be easy to maintain

    The project was broken down into four distinct areas and aerial photo mapping was presented

    for each area for discussion and markup. No concepts were presented by the design team at

    this time, as the primary purpose was to generate ideas based on the publics input. Based on

    input received from this meeting, the steering committee felt it was necessary to hold anadditional public meeting with the residents along Canton Street to discuss parking impacts.

    Meeting with Canton Street residents

    Currently, there are many automobiles parked on the SEPTA parcel at Canton Street. Concerns

    over loss of parking prompted a separate meeting discussing parking scenarios with nearby residents. Residents agreed that maximizing parking at this

    location was a priority. Also discussed at this meeting was the potential for changing traffic direction to one way along Canton Street in order to limit

    14 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    21/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Process

    the amount of pavement needed for two travel lanes and utilize the extra pavement for parking. It was decided that, because of the excessive traffic

    on Leverington and Umbria Streets, this option was not viable.

    Public Meeting No. 2, April 22, 2013

    The second public workshop was held at the North Light Community Center in Manayunk. The design team presented alternatives to the trail design

    for each of the four sections of the trail. These alternatives included:

    Path separation: The Cynwyd Heritage Trail and the Manayunk Bridge both have separate pedestrian and bicycle lanes. Public criticism of the

    way the lanes are actually being used, where pedestrians use the bike lanes and vice versa, prompted a discussion of whether or not splitting

    the width of the trail by mode of travel was necessary for the Ivy Ridge Trail.

    Path width: Two different path widths were explored during this process: 16 feet and 20 feet. While a 20-foot path would offer the option of

    two bicyclists being able to ride comfortably side-by-side in both directions, a 16-foot path might be scaled more appropriately for the

    community.

    Path connections: Several scenarios on how to access the Manayunk Towpath were explored as part of this process. Solutions include a

    simple stairway down to the Fountain Street steps, a long ramp traversing the hillside down to the base of the Fountain Street steps, cutting

    through Leverington Park to the Towpath entrance on Main Street from the Canton Street entrance, as well as other options for navigating

    from the Canton Street entrance down to the Manayunk Towpath entrance. Parking on Canton Street: The same scenarios for parking on Canton Street that were presented to the Canton Street neighbors were

    presented during this workshop.

    After the alternatives were presented, comment cards were

    handed out. Participants were asked to respond to large format

    prints of each of the trail sections and alternatives. The cards

    had two columns, one for stating elements they liked about each

    design, and one for elements they would rather see. A full list of

    these responses can be seen in the appendix. In general,

    participants preferred creating landscaping along otherwise

    unused space along Canton Street, 90-degree parking on CantonStreet, landscaping on the Leverington Avenue bridge, and a

    connection to the Towpath via Fountain Street, preferably one

    that could readily be negotiated by bicyclists. Some additional

    suggestions included providing bicycle parking at the Ivy Ridge

    Station; making the Umbria Street connection as safe as possible

    with traffic calming measures; creating clear signage that

    includes trail maps, digital QR codes and historical information;

    and residential permit parking along Canton Street to alleviate

    trailhead parking concerns.

    April 2014 15

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    22/60

    Process IVY RIDGE TRAIL FEASIBILITY STUDY

    Meeting No. 3, July 7, 2013

    The final public meeting was a presentation of preferred alternatives at the North Light

    Community Center. After the presentation, concerns were raised regarding the ramp down to

    the Fountain Street steps and its connection to the steps. Neighbors who maintain the steps

    would like the proposed interventions not to interfere with their work. Other concerns were

    echoed from the last meeting in making sure the Umbria Street intersection was as safe as

    possible.

    16 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    23/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail User Experience

    TRAIL USER EXPERIENCE

    Several trail types and configurations were evaluated during the design process. Through public input and stakeholder comments it was determined

    that a minimum width of 16 feet would create a safe multi-use trail environment for all potential users. Each corridor segment was evaluated for

    various trail applications based on available space and constraints. The following trail design alternatives were developed for the Leverington Bridge

    section and evaluated for potential conflicts, constructability, and ease of maintenance.

    A. 25-foot fully paved multi-use trail

    B. 16-foot fully paved multi-use trail with landscaping

    C. Separated 8-foot pedestrian and 12-foot bicycle trails

    April 2014 17

    T il U E i IVY RIDGE TRAIL FEASIBILITY STUDY

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    24/60

    Trail User Experience IVY RIDGE TRAIL FEASIBILITY STUDY

    Stakeholders felt that the 16-foot-wide section would be scaled more appropriately for a

    typical trail experience and would allow for landscaping and site amenities along the length of

    the trail. While the separate paths were supported by some in the community because of

    perceived safety advantages, the narrow landscaping strip would not be enough to sustain

    plantings. In later discussions, certain users

    asked that a two-foot soft surface, such as

    gravel, be included parallel to the trail for as

    a soft surface for joggers.

    If it is determined during final design that

    plantings are not feasible on the Leverington

    Bridge part of the trail due to structural and

    drainage constraints, a fully-paved section

    may be used.

    The Manayunk Bridge trail includes sections

    that separate bicycles and pedestrians, and

    care must be taken when transitioning between the shared section of the Ivy Ridge Trail andthe separate trails of the Manayunk Bridge.

    While the Ivy Ridge Trail is proposed to consist of an asphalt trail surface, the Manayunk

    Bridge Trail includes multiple paving types, and a transition needs to be considered during

    final design. Trail surface type will depend on the drainage requirements of the Leverington

    Bridge and will determine whether this transition should occur at the termination of the

    Manayunk Bridge Trail or once the trail is off structure at Canton Street.

    One of the requirements of the trail is to provide accessibility in accordance with the latest

    appropriate design standards and guidelines. The following must be followed during final

    design:

    o Americans with Disabilities Act (ADA) Accessibility Guidelines

    o U.S. Access Board, Draft Public Right-of-Way Accessibility Guidelines

    o U.S. Access Board Accessibility Guidelines for Outdoor Developed Areas

    o City of Philadelphia Streets Department ADA standards

    o PennDOT District 6-0 ADA Design Guidance (depending on funding source)

    o Federal Highway Administration Manual on Uniform Traffic Control Devices (MUTCD)

    18 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    25/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

    TRAIL SEGMENTS

    Early in the design process the design team determined there were four distinctly different segments of the inactive rail corridor that would define the

    trail based on existing structures, land use, ease of construction, and connectivity.

    April 2014 19

    Trail Segments IVY RIDGE TRAIL FEASIBILITY STUDY

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    26/60

    Trail Segments IVY RIDGE TRAIL FEASIBILITY STUDY

    Leverington Avenue Bridge Area. The Leverington Avenue section extendsapproximately two tenths of a mile along the elevated, inactive SEPTA railbed from the Manayunk Bridge Trail terminus at Dupont and High streets across Leverington Avenue to Canton Street.

    The first segment of this elevated section consists of railroad ballast

    retained by stone and concrete retaining walls on either side. Overhead

    catenary towers carry active PECO and Amtrak high voltage transmission

    lines. The steel rails have been removed by SEPTA, but the railroad ties

    remain in place on the eastern half of the corridor. Remnants of the

    Pennsylvania Railroad Manayunk East Station platform can be found just

    beyond the northern end of the steel through-plate girder structure

    over SEPTAs Norristown line.

    The Leverington Avenue

    bridge was constructed in the

    early 1900s and consists of

    four concrete arch spandrels

    varying in length. The surfaceout-to-out width is

    approximately 28 feet

    extending from outer edge of

    the parapets. The existing

    ballast width is approximately

    25 feet and was considered

    the effective width for the

    trail design.

    20 April 2014

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    27/60

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    28/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    29/60

    The transition from the MBT to the Ivy Ridge Trail will need to be seamless to maintain a visual connection to the Manayunk Bridge as well as to

    provide a safe transition of the trail surfaces if required. A continuation of design elements and pavement types will allow for this smooth transition.

    Due to this section being elevated, protective fencing will be required the

    entire length of this segment. Proposed fencing should consist of similar

    materials and design parameters as being proposed for the MBT. The fencing

    as well as all metal objects shall be bonded and grounded to meet theoverhead utility requirements.

    Drainage along the trail will be required to adequately drain the trail, as well

    as properly drain the existing structure. Proposed trench drains as well as

    scuppers shall be added if required. An eight- to ten-foot width along the

    elevated approach section provides an opportunity for green space which may possibly be used to capture runoff from the paved trail. This method of

    collecting drainage may significantly reduce costs by eliminating the need for engineered trench drains. Landscape areas will need to incorporate

    native plants in a low maintenance setting that does not require watering.

    April 2014 23

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    30/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    31/60

    Canton Street Area The Canton Street area extends approximately 0.15

    mile from Leverington Avenue to Wright Street.

    Existing conditions:

    The trail runs diagonally from the end of the Leverington Avenue bridge

    across the SEPTA property between Canton Street and a private parkinglot behind the buildings facing Umbria Street. Since SEPTA removed the

    rails the property has been used by the community as a parking area,

    often filled to capacity with numerous cars randomly scattered

    throughout the parcel. The asphalt pavement along Canton Street is in

    disrepair and full depth pavement reconstruction should be considered.

    Proposed conditions:

    Precautions should also be taken to ensure the safety of trail users as

    they cross Wright Street. Options could include a raised crossing and/or

    bollards to prevent drivers from using the trail. Trail users may also crossCanton Street at the top of the hill that leads down to Leverington

    Avenue to connect to the

    Towpath. This crossing is

    particularly challenging due to

    poor visibility. Potential pavement markings, lighting, and/or raised crossings should be considered during

    final design.

    This area provides special opportunities for landscaping at the potential trailhead near the end of the

    Leverington Avenue bridge. The formalized parking area could be lined with trees not just to beautify the

    area, but to help delineate the parking and prevent vehicles from encroaching on the trail. This area may

    have similar soil contamination issues to the Leverington Avenue bridge section, so soil may need to be

    remediated.

    A variety of plans were presented to the residents of Canton Street to determine how to address parking. Currently, approximately 80 cars use the

    SEPTA owned property for parking. A major concern of the residents was what would happen to this parking when the trail is developed. After a series

    of discussions, the residents preferred an option that would include parallel parking on the residential side of Canton Street, with paved and striped

    90-degree parking on the trail side. This would allow for approximately 70 formalized parking spaces. Further study will be needed to determine if

    permit parking for residents would be an option to alleviate parking concerns for the adjacent residents. Because the parking is not strictly a part of

    the trail project, alternative funding sources may need to be utilized for construction related to the parking.

    April 2014 25

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    32/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    33/60

    Opportunities:

    Landscape and pedestrian amenities The Canton Street area will serve as an access point for the Ivy Ridge Trail as well as the Manayunk

    Bridge Trail. As such, there is an opportunity to provide trail head site amenities including signage, landscape, seating, and sculpture. The

    area currently has no landscaping, so street trees could provide much needed beautification as well as a benefit to the environment.

    Parking Parking may be considered an opportunity as well as a challenge. The proposed plans include formalizing existing parking alongCanton Street with the potential to provide dedicated residential sticker parking for the residents along Canton Street.

    Challenges:

    Relatively high cost Potential improvements to the parking and Canton Street may include curbing, full depth pavement and striping.

    Environmental remediation Further soil testing is required in this area to determine the presence of contaminants.

    April 2014 27

    Trail Segments IVY RIDGE TRAIL FEASIBILITY STUDY

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    34/60

    Fountain Street Area The Fountain Street area extends approximately 0.2 mile from Wright Street across the Fountain Street steps to the Ivy Ridge

    Station parking lot.

    Existing conditions:

    The Fountain Street area is the most secluded area of the alignment as well

    as the widest section of the corridor. The area is bound by SEPTAsNorristown line and a strip of undeveloped, steeply-sloped wooded land to

    the west and mixed use residential properties to the east. The railroad ties

    and steel rails have been removed and the ballast remains in place. Catenary

    poles remain and will provide the outer limits for the trail.

    The Fountain Street steps are City owned and provide pedestrian access

    from Umbria Street to the canal. Stone drainage channels and storm sewer

    infrastructure exist on both side of the steps. The community has adopted

    the maintenance of the area and has constructed a native plant garden in

    the areas adjacent to the steps.

    28 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    35/60

    Structural Evaluation

    Fountain Street bridge - The single-span reinforced concrete slab bridge spans a pedestrian walkway that

    connects Umbria Street to the Schuylkill River Trail/Towpath. Although the walkway below consists primarily of

    concrete steps, it is also being used by bicyclists, as has been witnessed during site visits. The bridge is in

    satisfactory condition with no structural concerns. Approximately 5% of the deck underside exhibits scaling or

    spalling with exposed reinforcement bars. It is recommended to patch these areas in order to eliminate hazardsto public safety associated with continued deterioration of the deck underside and falling concrete. The curbs

    of the bridge are in good condition with negligible deterioration. It may be possible to mount the proposed

    hand railing or fence directly to the existing curbs. It may be necessary to extend the proposed hand railing at

    the southwest and southeast quadrants adjacent to the bridge to eliminate safety concerns associated with

    steep embankments in these areas.

    There has been some discussion as to whether or not an access ramp leading from Umbria Street to track level of the Fountain Street bridge should be

    built. This ramp would require the construction of a retaining wall as well as significant utility coordination, or possible relocation due to the presence

    of a sanitary sewer and overhead utility wires that parallel the walkway.

    April 2014 29

    Trail Segments IVY RIDGE TRAIL FEASIBILITY STUDY

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    36/60

    Proposed conditions

    Trail Alignment Two alternative trail alignments were initially evaluated for the Fountain Street area. The first was a 16 foot wide single paved

    surface with pavement markings separating pedestrians and bicycles. The second alternative included a landscaped buffer and a total paved surface

    width of 20 feet. A final preferred alternative was developed to include a 16 foot wide shared use trail with a soft surface buffer for joggers. Due to

    the wide flat area there is an opportunity to meander the trail through this segment for visual interest and creation of areas for site amenities and

    landscaping.

    Landscaping The existing landscape character of this section includes dense

    trees on the southwest side of the trail and lighter, screening landscaping alongthe back yards of houses on the northeast side. Additional screening should be

    coordinated with the adjacent property owners.

    The Fountain Street steps are landscaped and maintained by the community.

    Improvements to the bicycle and pedestrian infrastructure should be installed

    with the preservation of these community resources in mind. Further discussions

    of proposed improvements for the Fountain Street steps can be found in the

    connection alternatives section of this document.

    30 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    37/60

    Opportunities:

    Low cost Excluding the potential Fountain Street step connections, the Fountain Street segment will be relatively low cost to provide a

    simple paved shared use trail extending from Canton Street to the Ivy Ridge Station.

    Connections to the Schuylkill River Trail / Towpath See connection alternatives section of this document.

    Challenges:

    Right-of-way encroachments Several of the adjacent property owners have fence lines and other items that encroach into the SEPTA right

    of way. Further coordination with property owners may be required.

    Prohibiting vehicular access Bollards or other devices should be included to deter vehicles from accessing the trail. Coordination with

    emergency services should occur during final design to ensure access is maintained.

    Environmental remediation Further soil testing is required in this area to determine the presence of contaminants.

    April 2014 31

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    38/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Trail Segments

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    39/60

    To meet ADA requirements for the transition from the lower lot to the upper lot,

    low retaining walls and railings may be required.

    Minor adjustments to the upper parking lot will be required to provide a safe

    pedestrian crossing through the parking lot. Potential safety improvements could

    include a raised crosswalk to improve motorist awareness of the trail. As a de

    facto trailhead, this section provides an opportunity to include user amenitiessuch as bike parking, benches, garbage cans, and public art.

    Umbria Street Crossing - Safety measures must be taken to ensure the safety of

    trail users when interacting with vehicles. Where the trail crosses the upper lot, a

    raised crossing could be included. Tactile

    safety features will be employed at the

    crosswalk ramps on Umbria Street, and a

    highly visible crosswalk, potentially with a

    unique pattern designating the trail, will

    help users cross Umbria Street safely. Some

    concerns were expressed about the safety features at Umbria Street. Suggestions included flashers for stop

    signs or a traffic signal. Further traffic study, outside the scope of this project, will be needed to determine

    whether additional traffic controls are needed and, if so, who will maintain them.

    Opportunities:

    Future trail connections to points north and Shawmont

    Connections to Umbria Street bike lanes

    Connection to Ivy Ridge Station provides multi-modal enhancements

    Challenges:

    Minimize impacts to existing parking

    Minimize pedestrian/vehicular conflicts within the parking lot

    Moderate cost of retaining walls and ramp

    April 2014 33

    Connection Alternatives IVY RIDGE TRAIL FEASIBILITY STUDY

    /

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    40/60

    SCHUYLKILL RIVER TRAIL / CANAL TOWPATH CONNECTION ALTERNATIVES

    Canton Street/Leverington Avenue/High Street connections - The area where the Leverington Avenue bridge ends at Canton Street provides an

    opportunity to connect to the Towpath. Several options were considered for this connection. The first would include bike lanes on either side, which

    would connect to shared lane markings for bicyclists (Sharrows) on Canton Street and High Street. This would allow people to ride off the Ivy Ridge

    Trail at Canton Street, down a bike lane on the northwest side of Leverington Avenue, to a shared-use path on Main Street that would connect to the

    Towpath; or to ride off the Towpath at Main Street, up the southeast side of Leverington Avenue, and up High Street to the trail access at Dupont

    Street. This could be an interim phase before building a more permanent and expensive connection.

    34 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Connection Alternatives

    As a later option a two way shared use path could be constructed from Main Street along either side of Leverington Avenue connecting to Canton

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    41/60

    As a later option, a two-way, shared-use path could be constructed from Main Street along either side of Leverington Avenue connecting to Canton

    Street or High Street. The Canton Street connection on the northwest side would allow for a safer crossing of Main Street and a shorter overall

    connection, but would include a steep grade on Canton Street (approximately 15%). An off-road connection parallel to Canton Street would require a

    new retaining wall and fill on the north side of Leverington Park, as well as potential land acquisition from neighboring properties which could be very

    expensive, so it was determined Canton Street should be marked or signed as a shared street. The High Street connection would be less expensive and

    have a more manageable slope, but would have a less desirable connection across Main Street and a longer path overall. The Canton Street

    connection emerged as the preferred alternative.

    Opportunities:

    The Canton Street/High Street connection is critical to linking the Ivy Ridge Trail to the Schuylkill River Trail and downtown Manayunk

    Interim striping option could be implemented independently, is cost effective, and would provide access to the Manayunk Bridge Trail via

    high street prior to construction of the Ivy Ridge Trail

    Challenges:

    Traffic/safety conflicts along Leverington Avenue, Canton Street, High Street and Main Street

    Limited available right of way for implementation of off-road facilities

    Steep grades on Canton Street and Leverington Avenue

    Increased costs to implement off-road improvements

    April 2014 35

    Connection Alternatives IVY RIDGE TRAIL FEASIBILITY STUDY

    Fountain Street Connector the Fountain Street steps though not designed for cyclists provide a pedestrian connection between Umbria Street and

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    42/60

    Fountain StreetConnector the Fountain Street steps, though not designed for cyclists, provide a pedestrian connection between Umbria Street and

    the Towpath. Several alternatives were evaluated to connect the Ivy Ridge Trail to the Schuylkill River Trail/ Towpath via the Fountain Street steps.

    One option would be to include a stairwell at the bridge passing over the

    Fountain Street steps. This would impact the least amount of space and could

    potentially have the lowest cost. However, it would require riders to

    dismount and would not provide an ADA-accessible route. A bike trough couldbe included that would allow cyclists to walk their bikes down the steps. If this

    becomes the preferred option, further coordination with the community

    during final design is required to determine the location of the steps that least

    impacts the landscape.

    Another option would be a path that would connect from the Ivy Ridge Trail

    near the southern end of the Ivy Ridge Station parking lot. This path would

    traverse the wooded slope and be made up of segments of moderate slope

    (8.33%) with regularly spaced landings and would include a switchback

    adjacent to the lower section of the Fountain Street steps. The construction

    of this structure would require significant grading for the retaining walls, as

    well as railings for ADA compliance. Terraced gardens could be incorporated

    into the design to mitigate impacts to the Fountain Street landscape.

    Opportunities:

    Direct off-road accessible connection to Schuylkill River Trail/Towpath

    Challenges:

    Meeting ADA grade requirements

    Costs associated with grading, switchback retaining walls

    Minimizing disturbance to Fountain Street steps/gardens

    An additional connection to the towpath was evaluated via Parker Street andthe Umbria Village apartment development currently under construction.

    Initial discussions with the developer included providing an ADA accessible

    trail through the property connecting directly to the towpath. However, as of

    the date of this report, construction only included a set of steps with a bike

    trough requiring bicyclists to dismount.

    36 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Connection Alternatives

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    43/60

    Proposed switchback and terraced gardens adjacent to the Fountain Street steps

    April 2014 37

    Amenities, Materials, and Landscape IVY RIDGE TRAIL FEASIBILITY STUDY

    AMENITIES MATERIALS AND LANDSCAPE

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    44/60

    AMENITIES, MATERIALS, AND LANDSCAPE

    Site Amenities

    In addition to providing a key transportation link in the Citys regional trail network, the Ivy Ridge Trail has the potential to become a premier

    destination in this part of Philadelphia. As an extension of the Manayunk Bridge Trail, the Ivy Ridge Trail should include design elements that are

    similar and complement the historic nature of the rail corridor and the community while ensuring accessibility, including ADA compliance, for a wide

    range of users.

    Seating Seating should be added at trailhead locations and resting areas along the trail. The Leverington Avenue bridge segment provides

    opportunities for resting areas and outward views. Benches should be pre-approved by Philadelphia Parks and Recreation or the entity that is

    determined to be responsible for long term maintenance of the trail.

    Lighting Future funding for lighting should be considered for safety. Conduits for future lighting are being proposed for the Manayunk Bridge Trail

    and once funds are available for lighting the bridge, continuing that lighting along the Ivy Ridge Trail should be considered for safety and security.

    38 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Amenities, Materials, and Landscape

    Public Art/Sculpture The incorporation of public art can play an important role along the Ivy Ridge Trail to provide aesthetics, a sense of place, and a

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    45/60

    connection to the community. Public art has also proven to provide an economic benefit to the community through attracting visitors as well as

    deterring vandalism and graffiti in some instances. Although the purpose of this planning study is to provide a safe trail for transportation and

    recreation purposes, it is recommended that further discussions be held with the Association for Public Art and other local art organizations to

    evaluate opportunities for incorporating art into the trail and its surroundings.

    April 2014 39

    Amenities, Materials, and Landscape IVY RIDGE TRAIL FEASIBILITY STUDY

    Pavement materials The trail surface must meet the loading requirements of maintenance

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    46/60

    vehicles for overhead utilities as well as emergency vehicles. Transition from the concrete

    separated trails of the Manayunk Bridge should occur seamlessly and safely. It is anticipated that

    the Ivy Ridge Trail will transfer from a concrete trail surface

    to an asphalt trail surface once off structure. One

    opportunity to continue the use of concrete is to incorporate

    a concrete band at the trail edge as shown in the adjacent

    photo. This treatment provides an aesthetic linear visual

    element as well as a clean edge making it easier to maintain

    the trail surface over time. Exposed aggregate treatment

    similar to what is proposed for the pedestrian side of the

    Manayunk Bridge Trail could be incorporated where the transition occurs.

    Fencing Protective fencing will be required along the entire length of the elevated Leverington Avenue bridge segment as well as a short portion on

    the Fountain Street bridge. A similar treatment as proposed for the Manayunk Bridge should be incorporated for aesthetics and safety. Materials

    include; Galvanized steel angle posts with a handrail and welded wire mesh infill panels. The height of the fence should be 4-8 over its entire length.

    Other Materials Railroad ties and rails can be

    incorporated into the design to provide aesthetic edge

    treatments and reflect the history of railroad use

    through the corridor.

    40 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Amenities, Materials, and Landscape

    Landscape pallette Landscaping shall be designed to meet the following requirements:

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    47/60

    Low maintenance - Plantings should be selected from the Philadelphia Parks and

    Recreation native plant list for their ability to thrive in urban conditions.

    Seasonal interest Low maintenance does not mean plant material cannot be colorful.

    Careful selection of species that provide seasonal interest should be incorporated intothe design.

    Water quality Stormwater treatment may not be a requirement for the trail, however

    plant beds should be designed to collect surface runoff from the trail to minimize

    the need for irrigation and to treat runoff.

    Safe environment for users Proposed vegetation should be carefully placed and

    existing vegetation carefully managed to not interfere with the safety of the trail.

    A narrow strip of low plantings capable of handling occasional foot traffic should

    be placed adjacent to the trail and larger plantings should be set back far enough

    to keep a clear line of sight for trail users.

    April 2014 41

    Safety, Maintenance, and Operations IVY RIDGE TRAIL FEASIBILITY STUDY

    SAFETY, MAINTENANCE, AND OPERATIONS

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    48/60

    Like the adjacent Manayunk Bridge Trail, the final design of the Ivy Ridge Trail must account for maintenance and operations concerns. These may

    include:

    General operations- A number of public agencies have participated in the development of this

    feasibility study. This study recommends that the agencies develop a memorandum ofagreement regarding ownership, operations, and maintenance as early as possible to ensure

    that its provisions will be in place prior to completion of the trail. The participating agencies will

    undoubtedly also look for partnership opportunities, such as a friends group and/or corporate

    sponsorship, to provide ongoing maintenance. Operational responsibilities to be identified at

    this stage include trail and landscape maintenance, emergency vehicle access, policing

    responsibilities, graffiti removal, snow removal, and ADA compliance. The final design of the

    trail will need to address these issues to minimize ongoing operational costs.

    Lighting and security- The need for lighting and security elements such as cameras, call boxes,

    and policing will be dependent on the practices of the agency that operates and maintains the

    trail. At the present time,use of the Manayunk

    Bridge Trail will be

    limited to daylight hours,

    so lighting is not

    provided and the bridge

    will be gated at night.

    Access to the Ivy Ridge

    Trail cannot be as easily

    secured, so lighting and

    security will be especially

    important. The final trail design should incorporate elements of Crime

    Prevention Through Environmental Design (CPTED), such as good sight lines,

    clear delineation of public and private areas, and ease of maintenance. Amount

    of use and visibility are both important factors.

    Photo source: Ivy Ridge Green

    Photo source: Ivy Ridge Green

    42 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Final Design Requirements

    FINAL DESIGN REQUIREMENTS

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    49/60

    The following tasks are anticipated during final design:

    Permitting

    Chapter 102 (25 Pa. Code) is the Pennsylvania state regulation for erosion and sediment control and stormwater management. Projects disturbing oneor more acres must obtain authorization through a National Pollutant Discharge Elimination System (NPDES) Permit for Stormwater Discharges

    Associated with Construction Activities before beginning any earth disturbance activity. It is anticipated that the Ivy Ridge Trail project will result in

    greater than one acre of ground disturbance associated with the construction of the trail and associated access features, including parking lots and

    trailhead access areas. Due to the potential for soil contamination, it is also anticipated that an Individual NPDES permit will be required.

    It is recommended that a pre-proposal meeting be conducted with the Southeast Region of the Pennsylvania Department of Environmental Protection

    and the Philadelphia Water Department (PWD) to initiate the project file with these agencies.

    Soil testing/hazardous waste treatment

    Due to the nature of the project along an inactive railroad, soil contamination is anticipated. A Phase I Environmental Site Assessment (ESA) using theASTM (American Society for Testing and Materials) Standard 1527-05 as guidance for the proposed project will be required. The Phase I ESA will

    include a review of all existing records and databases for the properties scheduled for acquisition and any adjacent properties of concern. If any

    evidence of contamination is found, Federal, State, and local environmental health regulatory agencies should be contacted to obtain information on

    permits and enforcement actions. A potential contaminant inventory of known hazardous waste sites or areas of contamination will be included. The

    Phase I ESA will determine whether additional field work, soil and groundwater testing, or laboratory analysis will be required.

    Based on experience from the Manayunk Bridge Trail project, it is anticipated that a Phase II Environmental Site Assessment (ESA) will be required due

    to the potential for soil contamination. Historically, railroad beds have exhibited contamination associated with the operation of railroad trains.

    Contaminants can include volatile organic compounds (VOCs), semi-volatile organic compounds (SVOCs), metals, herbicides, asbestos, and

    polychlorinated biphenyls (PCBs). Soil sampling should be considered to ensure or limit exposure pathways of potential contaminants to future

    recreational users of the proposed trail. The investigation should include the submission and approval of a sampling plan to SEPTA, the sample

    collection and delivery to laboratory, and preparation of a Phase II ESA Report.

    Soil borings for structures

    Soil borings should be performed along the corridor where proposed structures are anticipated requiring soil analysis for footing design. Structural

    elements may include overhead lighting, retaining walls, ramps, steps, significant art or sculpture, fencing subject to wind loads, and others as

    required.

    April 2014 43

    Final Design Requirements IVY RIDGE TRAIL FEASIBILITY STUDY

    Utility coordination

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    50/60

    A Pennsylvania One Call is required during final design to identify all existing utilities and potential conflicts within the corridor. Depending on the

    funding source, coordination may also need to occur with the Pennsylvania Public Utilities Commission (PUC) throughout the design process. The

    existing catenary towers carry high voltage PECO and Amtrak lines as well as SEPTA signal wire. Design information and coordination for the

    requirements of these utilities occurred during the Manayunk Bridge Trail project and should apply to the Ivy Ridge Trail. Other utility clearances may

    be required depending on the final design and construction funding sources.

    Traffic studies

    The completion of the trail itself does not require any additional traffic analysis. However, additional traffic studies may be required for trail

    connection alternatives at Canton Street, Leverington Avenue, Main Street, High Street, and the Umbria Street crossing.

    Environmental clearance

    Preliminary design approval for the Ivy Ridge Trail will require resolution of several environmental issues, notably review by DCNRs Wild and Scenic

    Rivers program, and Section 4(f) review. The project lies within the Schuylkill River Pennsylvania Scenic Rivers Corridor System. This requires that the

    project design be reviewed to be consistent with the protection of river values, including its aesthetic and recreational values.

    Section 4(f) permits the use of publicly-owned parks, recreational areas, wildlife or waterfowl refuges, or any significant historic sites for

    transportation use only when it has been determined that there is no feasible and prudent alternative to such use, and the project includes all

    possible planning to minimize harm to the property resulting from such use. If there are no feasible and prudent alternatives to avoid the use of

    Section 4(f) resources, mitigation measures will be developed.

    There are two potential Section 4(f) resources present within the project study area, including the Manayunk Historic District and the Schuylkill River

    Trail (SRT). If the proposed trail will result in the use of the Section 4(f) properties, a Section 4(f) Evaluation would be warranted. However, it is

    anticipated that the project will have no adverse effect on any historic resources and that the project will have a de minimis use on the SRT.

    Therefore, it is anticipated that the PennDOT Section 4(f) de minimisor No Use checklists will be sufficient to clear any Section 4(f) use.

    Stormwater/erosion and sediment control

    For all earth disturbance activities exceeding 5,000 square feet, an adequate erosion and sediment control (E&SC) plan must be properly designed and

    implemented. The plan must show how the land is to be protected against accelerated erosion through the use of E&SC Best Management Practices

    (BMPs). Examples of E&SC BMPs include: silt fence, mulch, diversion ditches, sediment traps and basins, and the planting of grasses or similar

    vegetation. The plan must show the site, location of the BMPs, and timing and sequence of their installation for maximum erosion control.

    44 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Final Design Requirements

    In addition to an E&SC Plan, a Post-Construction Stormwater Management (PCSWM) Plan is required for all construction activities requiring an NPDES

    Permit. The PCSWM Plan will need to include PCSWM BMPs designed to maximize infiltration technologies, minimize point source discharges to

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    51/60

    surface waters, preserve the integrity of stream channels and protect the physical, biological and chemical qualities of the receiving waters.

    As part of the Individual NPDES permit, an approved E&SC and PCSWM plan will be provided to the PADEP and PWD for review and approval. In

    addition, all projects that generate an earth disturbance of 5,000 square feet or more must submit an Existing Resources and Site Analysis (ERSA)

    worksheet and attachments to PWD through the PWD Plan Review website.

    Construction plans, specifications, and estimates

    Final construction plans and specifications should be prepared in accordance with the anticipated funding source for design and construction. For the

    purpose of this report, it is assumed final design will fol low PennDOT standards and design approvals. Design submissions and approvals may include:

    Safety Review

    ADA Compliance Review

    Right-of-Way Clearance

    Utility Clearance

    Traffic Review

    Lighting Review (If lighting is proposed)

    Construction Review

    PS&E Review (Contract Management)

    In addition to PennDOT reviews the project will need to be reviewed concurrently with Philadelphia Parks and Recreation, Philadelphia Streets

    Department (specifically the Departments Bridge Unit), and SEPTA.

    April 2014 45

    Costs and Implementation IVY RIDGE TRAIL FEASIBILITY STUDY

    COSTS AND IMPLEMENTATION

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    52/60

    Potential funding sources

    Although no funding has been secured for the final design or construction of the Ivy Ridge Trail, the project has been listed as a medium priority

    project in the 2013 Philadelphia Trail Master Plan due to the availability of right-of-way, current planning studies, and relatively low cost of

    implementation. Based on this ranking, City funding for this project is in the 5-10 year stage. However, the Manayunk Bridge Trail is scheduled forconstruction in 2014, and upon completion of this t rail momentum will build as trail users will want to continue along the corridor to the northwest.

    Potential public funding sources include:

    Future Federal Transportation Investment Generating Economic Recovery (TIGER) grants

    Discretionary grant programs, such as the Delaware Valley Regional Planning Commission (DVRPC) and William Penn Foundation Regional

    Trail Program

    PA Department of Conservation and Natural Resources (DCNR) grants

    PA Department of Environmental Protection Coastal Zone Management grants

    City of Philadelphia capital funds through Philadelphia Parks and Recreation and the Department of Commerce

    Potential private funding Private funding for trails is typically easier to obtain when there are large corporations or developers that will benefit from

    trail use through increased property values or alternative modes of transportation for potential employees. Although there are none of these large

    corporations directly within the area of the trail, private funding should be further investigated as a potential funding source.

    Project costs

    The following page contains a summary of anticipated costs to design and build the Ivy Ridge Trail as described within this report. Costs were

    developed from recent bid unit prices from PennDOTs Engineering and Construction Management System (ECMS). Estimated prices are based on

    2014 costs and inflation should be considered accordingly. The following additional project costs have been accounted for in the project costs below:

    Construction engineering - 18% of the design item costs Mobilization - 5% of the design item costs

    Contingency - 20% of the design item costs

    This report does not include construction costs for connecting the Ivy Ridge Trail to the Schuylkill River Trail. Further planning and design, including

    survey and property ownership verification, is needed to develop accurate construction costs for these trail connections.

    46 April 2014

    IVY RIDGE TRAIL FEASIBILITY STUDY Costs and Implementation

    Final design

    Final design is estimated to be 10 15% of the total design item construction price excluding construction engineering Design costs include the

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    53/60

    Final design is estimated to be 10-15% of the total design item construction price excluding construction engineering. Design costs include the

    following anticipated services and fees:

    Development bid ready plans, specifications, and estimates

    SEPTA right-of entry agreement and railroad protective liability insurance Soil samples @ $1000 per sample

    Soil borings @ $1500 per sample

    Environmental permitting fees

    Construction administration services

    Total design fee $450,000

    Construction

    Overall project construction items anticipated to be required for the overall trail project $100,000

    Inspectors field office/equipment package

    Maintenance and protection of traffic

    Railroad right of entry fees and insurance

    Construction costs per trail segment:

    Leverington Avenue bridge area $2,500,000

    Canton Street area $650,000

    Canton Street parking improvements $100,000

    Fountain Street area $700,000

    Ivy Ridge Station area $200,000

    Planning-level cost estimate for designing and constructing the Ivy Ridge Trail $4,700,000

    April 2014 47

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    54/60

    IVY RIDGE TRAIL FEASIBILITY STUDY Appendix Summary of Public Comments

    COMMENTS FROM MARKED UP PLANS

    Canton Street Section

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    55/60

    Provide lighting

    Increase visibility at Wright St./ Canton St.

    Cut through traffic south on Wright St. Need safe crossing (at Wright St. & Trail).

    Make Canton St. one way. Convert all parking to parallel parking only.

    Add street trees.

    Need green space, public art, playground at Canton St.

    Add community garden with ROW.

    Canton St. Provide good access to tow path via Leverington Avenue.

    Mark the entrance to tow path better.

    High St. & Leverington Ave. intersection is a death trap.

    Leverington Bridge Section

    Provide access ramp to Canton St.

    Utilize space of old station. Provide a dog park.

    Do not take away parking at SEPTA lot.

    Why do we need two sets of stairs?

    Why do we need a ramp?

    Emergency vehicles can cross at Canton St.

    Connect direct to green lane via old railroad steps.

    Fountain Street Section

    Provide traffic signal at trail access point from Umbria Street (at station parking).

    Should be more than a stop sign.

    Provide traffic calming devices, safer pedestrian and cycle crossing and more visible crosswalk at Fountain and Umbria Streets intersection. Ramp connecting Fountain Street to the Ivy Ridge Trail at grade with Umbria Street.

    Provide traffic calming at Fountain Street.

    More lights please! Thanks for the cleanup!

    Provide ramp through undeveloped property between Gates and Fountain Streets to access tow path through Fountain Street underpass of

    Norristown Lane.

    Access tow path via Gate Street ROW.

    Appendix Summary of Public Comments IVY RIDGE TRAIL FEASIBILITY STUDY

    Ivy Ridge Station Lot Section

    Sell this as the High Line South!

    Traffic calming for bike at trail entrance to parking lot (coming off of Ivy Ridge Trail).

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    56/60

    g p g ( g y g )

    Use old rail ROW within travel lane? Cars currently park along travel lane.

    Cut into hill and provide new trail outside of parking limits.

    Cars travel too fast through parking lot.

    Add bike here? (not sure) Convert area where old station was removed to Transit Caf.

    Add bike parking at old station location.

    Provide ramp down to Parker Avenue adjacent to rail corridor.

    Add 4-way stop at Parker Avenue. This intersection is unsafe!

    The existing bike lanes on Umbria Street will get more use and maybe more dangerous.

    Parker Avenue will need light or new development on river.

    Can children use the trail to get to school?

    Lamonte Street is unsafe for pedestrians.

    Umbria Street backup in the morning hours approaching Leverington.

    Would like to see the path follow the old ROW through the parking lot.

    Connect to tow path via Parker Avenue.

    IVY RIDGE TRAIL FEASIBILITY STUDY Appendix Summary of Public Comments

    PUBLIC MEETING NO. 2

    April 22, 2013

    Manayunk North Light Community Center

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    57/60

    I like:Fountain Street connection to the towpath.

    Because:Fountain Street connection from Fountain Street to the Ivy Ridge Trail. Fountain Street is a key connecting street into the neighborhood

    and need to connect to the trail.

    I like:Landscaping on Canton Street.

    Because:Bank is seriously eroding and paving will increase the runoff problem.

    I would rather see:Parallel/head-in Canton Street Parking (70-75 spaces)

    Because:As a Canton St. resident, Im painfully aware of the scarcity of on-street parking and any path plan needs to offer the most possible

    spaces. Im also looking forward to the City raking up the leaves from all the new trees.

    I like:The entire concept.

    Because:It connects the area with trails. The wider concept for the trail because the trail traffic will grow and the room will be needed. More

    people are biking trails.

    I would rather see:A shorter connection where possible.

    Because:People will always take what appears to be a shorter route even though it may be steeper.

    I would rather see: Option C/D.

    Because:Safety!! A buffer between walkers and cyclists will go a long way for safety. (On the Leverington Ave. Bridge Area board.)

    I like: A connection to Fountain Street steps and the towpath.

    Because:It will provide another access point to the towpath in addition to just either end (@ Main & @ Shawmont)

    I like: Buffer strip between bike and ped paths.

    Because:It will largely prevent conflicts. Example: On the boardwalk in Ocean City, NJ, pedestrians ignore the painted bike symbols and risk

    collisions.

    I like: Purple connector from Fountain Street to towpath.

    Because:It provides safe bicycle and handicap access.

    I like: Buffer in middle (C) Leverington Ave. Bridge onward.

    Because:Safety reasons. Sometimes cyclists and pedestrians dont mix. Also, connection @ Fountain St. steps a good idea to gain access to

    towpath.

    I would rather see: 1. Connection at Ivy Ridge Station to the canal path. 2. Traffic calming on Umbria Street including the Shawmont/Umbria

    intersection.

    Because:Public access and public safety.

    Appendix Summary of Public Comments IVY RIDGE TRAIL FEASIBILITY STUDY

    I like: Improved organization of Ivy Ridge Station (?)

    I would rather see:Bikes directed to Lemont Street, Same as vehicles. Pedestrians given access to Umbria.

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    58/60

    Sent by email:

    To help alleviate weekend parking concerns, promote free weekend parking at the Ivy Ridge SEPTA stop. I did not see it listed as a permit

    parking lot.http://www.septa.org/parking/permit.html

    Consider adding bike parking facilities at Ivy Ridge.

    The new trail will be dumping even more cyclists on to the already dangerous bike lanes on Umbria Street. Traffic calming is needed it is all

    too common for motor vehicles to exceed 50 mph on Umbria. All-way stop signs are needed at the intersections with Domino Lane, Autumn

    River Run (at The Glen at Shawmont apartments), and the extremely dangerous Shawmont Avenue intersection. The entrance to the Umbria

    Golf Center, 7200 Umbria, endangers west-bound cyclists as motor vehicles use the bike lane to get around vehicles turning left into the golf

    center. Several SeeClickFix links are listed below that illustrate the Umbria Street bike lane problems. Also, I would think that the residents of

    the Glen would appreciate a three-way stop at their intersection with Umbria as left-hand turns onto Umbria are risky due to speeding east-

    bound traffic. (From Wikipedia - SeeClickFixis a web tool that allows citizens to report non-emergency neighborhood issues, which are

    communicated tolocal government,as a form of communityactivism.It has an associated freemobile phoneapplication).

    To help separate cyclists from pedestrians and runners, consider a wider trail with multiple surfaces that help to define user lanes,

    especially at the Ivy Ridge station. For example, in front of Boathouse Row, the trail is asphalt in the center, with brick pavers on the outer

    sides. Peds and runners tend to stay to the outer edge lanes, using the brick pavers, while cyclists stay on the center asphalt. Also, hard-

    pack surfaces on the outside of the paved trail would be preferred by runners, also helping to relieve contention between trail users.

    Access to the Manayunk Canal Path from Umbria Street/Parker Avenue: In attempting to secure public access through the under-

    construction Station at Manayunk, emphasize the need for police and emergency access, as well as handicap access, to this somewhat

    remote section of the canal path.

    Consider the use of QRs (matrix barcodes) on trail signage for info on the trail, nearby history, and local info (parking, food, hotels, hostels,

    etc. even possibly a source of revenue from advertisers).

    Increased signage and publicity to make the public aware of the trail I spend a lot of time on the Schuylkill River Trail talking to trail users

    and am always disappointed to find that so many have only recently become aware of this treasure. There has been an effort for increased

    signage such as on Ridge Avenue, but more needs to be done. For example, when coming into Manayunk from Lower Merion on the Green

    Lane bridge, new signage to the SRT, the canal path, and the Manayunk Bridge would greatly increase awareness.

    http://www.septa.org/parking/permit.htmlhttp://en.wikipedia.org/wiki/Local_governmenthttp://en.wikipedia.org/wiki/Local_governmenthttp://en.wikipedia.org/wiki/Local_governmenthttp://en.wikipedia.org/wiki/Activismhttp://en.wikipedia.org/wiki/Activismhttp://en.wikipedia.org/wiki/Activismhttp://en.wikipedia.org/wiki/Mobile_phonehttp://en.wikipedia.org/wiki/Mobile_phonehttp://en.wikipedia.org/wiki/Mobile_phonehttp://en.wikipedia.org/wiki/Mobile_phonehttp://en.wikipedia.org/wiki/Activismhttp://en.wikipedia.org/wiki/Local_governmenthttp://www.septa.org/parking/permit.html
  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    59/60

  • 8/11/2019 Ivy Ridge Trail Feasibility Study - April 2014

    60/60

    MANAYUNK

    DEVELOPMENT

    CORPORATION

    DESTINATION

    SCHUYLKILL

    RIVER

    4312MAINSTREET

    PHILADELPHIA,PA19127

    215.482.9565

    WWW.MANAYUNK.ORG

    WHITMAN,REQUARDT&ASSOCIATES,LLP

    THREEMILLROAD,SUITE309

    WILMINGTON,DE19806

    302.571.9001WWW.WRALLP.COM