Progress Update Week ending 15th April
Programme Update - ITS For Period : Mon 14th March – Friday 15th April
- Completed new dormer construction within roof and associated external render
- Completed Bauder roofing to new build structure and continued works to existing re-roof
- Completed external brickwork to new-build structure & began stripping scaffold
- Completed floor screed pour to all floors and construction of internal lift shift
- Commenced internal partitions within new and existing buildings
- Commenced ceiling works to existing building & internal/external decorations
Progress Photos
Internal wall linings completed within new build structure
Progress Photos
Internal decorations commenced to all rooms in existing building (including cornice repairs)
Progress Photos
New roof dormer constructed and externally rendered
Progress Photos Roof to new-build structure complete and re-roofing to existing building ongoing – installation of new ‘Velux’ roof lights also commenced
Progress Photos
1st fix M&E continued to new build structure
Next Few Weeks………..A look ahead to works commencing within the next 4 weeks :
- Commence installation of new passenger lift
- Complete works to existing re-roof and associated areas
- Continue 2nd fix joinery including hanging the doors throughout the existing building
- Complete necessary sub-station cabling works to energise new mains panel board
- Commence the installation of lighting within the existing building
- Commence installation of curtain walling/glazing to new build structure
- Continue internal decorations and complete all external decorations