ITS Bulding Project - progress update April 2016
-
Upload
institute-for-transport-studies-its -
Category
Education
-
view
420 -
download
3
Transcript of ITS Bulding Project - progress update April 2016
![Page 1: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/1.jpg)
Progress Update Week ending 15th April
![Page 2: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/2.jpg)
Programme Update - ITS For Period : Mon 14th March – Friday 15th April
- Completed new dormer construction within roof and associated external render
- Completed Bauder roofing to new build structure and continued works to existing re-roof
- Completed external brickwork to new-build structure & began stripping scaffold
- Completed floor screed pour to all floors and construction of internal lift shift
- Commenced internal partitions within new and existing buildings
- Commenced ceiling works to existing building & internal/external decorations
![Page 3: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/3.jpg)
Progress Photos
Internal wall linings completed within new build structure
![Page 4: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/4.jpg)
Progress Photos
Internal decorations commenced to all rooms in existing building (including cornice repairs)
![Page 5: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/5.jpg)
Progress Photos
New roof dormer constructed and externally rendered
![Page 6: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/6.jpg)
Progress Photos Roof to new-build structure complete and re-roofing to existing building ongoing – installation of new ‘Velux’ roof lights also commenced
![Page 7: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/7.jpg)
Progress Photos
1st fix M&E continued to new build structure
![Page 8: ITS Bulding Project - progress update April 2016](https://reader036.fdocuments.net/reader036/viewer/2022062820/58a40e5e1a28ab7d758b5907/html5/thumbnails/8.jpg)
Next Few Weeks………..A look ahead to works commencing within the next 4 weeks :
- Commence installation of new passenger lift
- Complete works to existing re-roof and associated areas
- Continue 2nd fix joinery including hanging the doors throughout the existing building
- Complete necessary sub-station cabling works to energise new mains panel board
- Commence the installation of lighting within the existing building
- Commence installation of curtain walling/glazing to new build structure
- Continue internal decorations and complete all external decorations