Progress Update (Nr. 4)

Week ending 6th November

Page 3: ITS Building Project - progress update 4

Programme Update - ITS

For Period : Mon 26th October – Friday 6th October

- Completed excavations, reinforcement and formwork to perimeter retaining walls

- Completed installation of reinforcement to basement slab and concrete pour

- Commenced installation of holding down bolts in preparation for steelwork

- Completed internal damp-proofing works to basement walls

- Commenced internal builders work and the removal of remaining load bearing walls:

including installing necessary concrete lintels

- Continue first fix mechanical and electrical works within existing building to all floors

Page 4: ITS Building Project - progress update 4

Progress Photos – External

Basement floor slab & lift

pit concrete pour complete

Page 5: ITS Building Project - progress update 4

Progress Photos – External

Retaining wall steelwork

reinforcement installed

throughout perimeter walls

Page 6: ITS Building Project - progress update 4

Progress Photos – External

Retaining wall

formwork/shuttering

installed and also

temporary props positioned

in preparation for next

phase concrete pour

Page 7: ITS Building Project - progress update 4

Progress Photos – Internal

First fix mechanical and

electrical works continued

within the existing building

through all floors

Page 8: ITS Building Project - progress update 4

Progress Photos – Internal

Internal structural

builderswork ongoing

including installation of load

bearing lintels

Page 9: ITS Building Project - progress update 4

Progress Photos – Internal

Commenced infill of new

plasterboard ceilings to

rooms and corridors

throughout floors

Page 10: ITS Building Project - progress update 4

Next Few Weeks………..A look ahead to works commencing within the next 2 weeks :

- Complete excavations to new ground floor slab and pad foundations

- Complete concrete pours to perimeter retaining walls

- Commence ‘making good’ to walls within rooms of existing building

- Commence self level screeding and preparatory overboarding to existing sub-floors

- Continue internal builders work; including installing required lintels and steelwork

- Continue first fix mechanical and electrical works within existing building to all floors