iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting...

138
iTnews’ reconstructed NBN three-year plan Bringing transparency back to the rollout

Transcript of iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting...

Page 1: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

iTnews’ reconstructed NBN three-year planBringing transparency back to the rollout

Page 2: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

WHY WAS A NEW THREE-YEAR PLAN NEEDED?

When NBN Co culled its three-year construction plan five days before Christmas 2016, it laid down a challenge.

Removing the detailed document – which described the type of access technology an area would get and when – further eroded public oversight of a $49 billion+ project at a time when taxpayers found themselves even more exposed via a new $19.5 billion loan.

It’s taken the best part of two months and many late nights, but we’ve now fully reconstructed the only three-year construction plan ever published by NBN Co. This new version is current as of March 2, 2017.

Restoring this document provides a base level of transparency on a whole-of-project basis. We hope you find it useful.

Ry Crozier, iTnews journalist

Guide to interpreting the documentSuburbs are grouped by fibre or wireless serving area (FSA and WSA); those with a blank space in that field belong to the FSA listed closest above. States are denoted by their number: 2 is NSW, 3 is Victoria etc.

Additionally, since NBN Co published its three-year construction plan it has changed its performance metrics.

The old plan listed an ‘estimated time to commence construction date’ for each area within the rollout. It has since replaced this metric with ‘availability’, meaning when a service will become available. The two metrics aren’t comparable.

iTnews’ reconstructed NBN three-year plan 2

Page 3: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

iTnews’ reconstructed NBN three-year plan 3

1

Suburb FSA / WSA

3 year plan (Commence construction) Rollout Map New map (Availability) FTTC/x change Service

Premises in FSA / WSA

Alstonville 2ALS H2 2017 Flipped Jul-Dec 2018 FTTC FTTN 3400

Wollongbar Planned Jul-Dec 2018

Appin 2APN Q2 2016 Available FTTN 500

Otford 2APP H2 2017 Planned Jul-Dec 2018 FTTN 3100

Coalcliff Planned Jul-Dec 2018

Helensburgh Planned Jul-Dec 2018

Lilyvale Unclear

Stanwell Park Planned Jul-Dec 2018

Stanwell Tops Planned 2020

Ashbury 2ASH H1 2018 Planned Apr-Jun 2017 HFC 18700

Ashfield Planned Oct-Dec 2017 / Jan-Mar 2018

Croydon Planned Jul-Dec 2018

Haberfield Planned Apr-Jun 2017

Summer Hill Planned Apr-Jun 2017 / Oct-Dec 2017

Balgowlah 2BAL H1 2017 Planned Oct-Dec 2017 HFC 18200

Balgowlah Hts Planned Oct-Dec 2017

Clontarf Planned Oct-Dec 2017

Fairlight Planned Apr-Jun 2017

Manly Planned Jan-Jun 2019

Manly Vale Planned Jan-Mar 2018

North Balgowlah Planned Oct-Dec 2017

Seaforth Planned Oct-Dec 2017

Balmain 2BAM H1 2017 Available / Build comm Apr 2017 HFC 13200

Balmain East Available

Birchgrove Available

Lilyfield Available

Rozelle Build comm / Planned Jun 2017 / Jul-Dec 2018

Rozelle 2BAM H2 2017 Planned Jul-Dec 2018 FTTN 600

Bankstown 2BAN H2 2017 Planned Oct-Dec 2017 / Jan-Mar 2018 HFC 25300Bankstown Aerodrome Planned Jul-Dec 2018

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 4: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

2

Condell Park Planned Oct-Dec 2017

Georges Hall Available / Planned Jul-Sep 2017 / Jul-Dec 2018

Greenacre Planned Jul-Sep 2017 / Jul-Dec 2018

Mount Lewis Planned Jan-Mar 2018 / Jul-Dec 2018

Punchbowl Planned Oct-Dec 2017 / Jan-Jun 2018

Yagoona Planned Apr-Jun 2017

Bankstown 2BAN H2 2018 Unclear FTTN 2000

Captains Flat 2BAO Sep 2015 Build comm No date FW 540

Majors Creek Build comm No date

Mt Gillamatong Build comm No date

Braidwood 2BAO H2 2017 Planned Jan-Jun 2018 FTTN 800

Bega 2BEG H1 2017 Planned Jul-Dec 2018 FTTN 3100

Tathra Planned Jul-Dec 2018

Berowra 2BER Q2 2016 Planned Jul-Sept 2017 FTTN 4500

Berowra Hts Planned Jul-Sept 2017

Brooklyn Planned Jul-Sept 2017

Cowan Planned Jul-Sept 2017

Dangar Island Planned Jul-Sept 2017

Mt Kuringgai Planned Jul-Sept 2017

Boggabri 2BGI H2 2017 Planned Jan-Jun 2018 FTTN 600

Bungendore 2BGR H1 2017 Planned Oct-Dec 2017 FTTN 1300

Barham 2BHA H2 2017 Planned Jul-Dec 2018 FTTN 1300

Koondrook Planned Jul-Dec 2018

Bingara 2BIN H2 2017 Planned Jan-Jun 2018 FTTN 700

Blayney 2BLA Q1 2017 Build comm August 2017 FTTN 1500

Bellingen 2BLG H2 2017 Planned Jan-Jun 2018 FTTN 1500

Doonside 2BLK H2 2016 Planned Jul-Dec 2018 HFC 800

Ballina 2BLN H2 2017 Planned Jul-Dec 2018 FTTN 13600

Cumbalum Planned Jul-Dec 2018

East Ballina Planned Jul-Dec 2018

Lennox Head Planned Jul-Dec 2018

Skennars Head Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 4

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 5: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

3

West Ballina Planned Jul-Dec 2018

Bermagui 2BMG H1 2017 Planned Jan-Jun 2018 FTTN 1000

Bendalong 2BND H2 2017 Planned Jan-Jun 2018 FTTN 1000

Cunjurong Pt Planned Jan-Jun 2018

Manyana Planned Jan-Jun 2018

Broken Hill 2BNH H2 2017 Planned Jul-Dec 2018 FTTN 10600

Bombala 2BOM Q1 2017 Planned Jul-Sept 2017 FTTN 900

Bondi 2BON H1 2017 Planned Apr-Jun 2017 / Jan-Jun 2018 HFC 22400

Bondi Junction Planned Oct-Dec 2017 / Jan-Jun 2018

Bronte Planned Apr-Jun 2017 / Jan-Jun 2019

Queens Park Planned Jan-Mar 2017 / Oct-Dec 2017

Tamarama Planned Jul-Dec 2018

Waverley Planned Oct-Dec 2017

Woollahrah Available / Planned Now / Oct-Dec 2017

Banksmeadow 2BOT H1 2017 Planned Jan-Jun 2019 FTTC HFC 20300

Botany Planned Jan-Jun 2019 FTTC / FTTP

Botany Bay Planned Jan-Jun 2019 FTTP

Eastgardens Planned Jan-Jun 2018

Maroubra Planned Jul-Dec 2018

Pagewood Planned Jul-Dec 2018 some FTTP

Sth Coogee Planned Jul-Dec 2018 / Jan-Jun 2019

Banksmeadow 2BOT H2 2017 Planned Jan-Jun 2019 FTTN 800

Botany Bay - Jan-Jun 2019

Port Botany Planned Jan-Jun 2019

Boorowa 2BOW Q1 2017 Planned Oct-Dec 2017 FTTN 900

Berridale 2BRD Q3 2016 Build comm April 2017 FTTN 600

Austral 2BRG Q1 2017 Build comm FW 4070

Austral South Build comm

Badgerys Creek Nth Build comm

Bringelly Build comm

Bringelly North Build comm

Catherine Field Build comm

iTnews’ reconstructed NBN three-year plan 5

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 6: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

4

Catherine Field Nth Build comm

Denham Court Planned 2020

Rossmore Build comm

West Hoxton Build comm

Catherine Field 2BRG H2 2017 Unclear 2020 FTTN 400

Bourke 2BRK Q4 2016 Build comm April 2017 FTTN 1200

Balranald 2BRL Q4 2016 Build comm April 2017 FTTN 600

Branxton 2BRX Q1 2017 Planned Jul-Sept 2017 FTTN 3100

East Branxton Build comm Sept 2017

Greta Build comm Sept 2017

North Rothbury Planned Jul-Sept 2017

Rothbury Planned Jul-Sept 2017

Berry 2BRY H2 2017 Planned Jan-Jun 2019 FTTN 1100

Clarence 2BTH Sept 2015 Planned 2020 FW 750

Georges Plains Build comm -

Glanmire Planned 2020

Little Hartley Planned 2020

Mount Victoria Build comm /Plan Feb 2017 fixed

Abercrombie 2BTH Q3 2016 Build comm Apr 2017 FTTN 14200

Bathurst Planned Jul-Sept 2017

Eglinton Build comm Apr 2017

Gormans Hill Planned Jul-Sep 2017

Kelso Build comm Jul 2017

Llanarth Build comm Apr 2017

Mitchell Planned Jul-Sept 2017

Raglan Build comm Jul 2017

Robin Hill Planned Jul-Sept 2017

Sth Bathurst Planned Jul-Sept 2017

West Bathurst Build prep Apr-Jun 2017

White Rock Build comm

Windradyne Build prep Apr-Jun 2017

Batehaven 2BTM Q1 2017 Planned Oct-Dec 2017 FTTN 9100

iTnews’ reconstructed NBN three-year plan 6

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 7: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

5

Batemans Bay Planned Oct-Dec 2017

Catalina Planned Oct-Dec 2017

Denhams Beach Planned Oct-Dec 2017

Long Beach Planned Oct-Dec 2017

Maloneys Beach Planned Oct-Dec 2017

N Batemans Bay Planned Oct-Dec 2017

Sunshine Bay Planned Oct-Dec 2017

Surf Beach Planned Oct-Dec 2017

Surfside Planned Oct-Dec 2017

Bulahdelah 2BUL Q4 2016 Build comm Feb 2017 FTTN 700

Bulahdelah East 2BUL Q1 2017 Planned 2020 FW 270

Nerong Planned 2020

Homebush West 2BUR H2 2016 Planned Jan-Jun 2019 HFC 13300

North Strathfield Planned Jan-Jun 2019

Strathfield 2BUR H1 2018 Planned Jul-Dec 2018 FTTN 1200

Bawley Point 2BWL H1 2017 Planned Oct-Dec 2017 FTTN 600

Bangalow 2BYB Q1 2017 Planned Jul-Sept 2017 FTTN 7400

Byron Bay Planned Oct-Dec 2017

Ewingsdale Planned Oct-Dec 2017

Suffolk Park Planned Jul-Sept 2017

Camden Head 2CAH Q3 2016 Build comm May 2017 FTTN 5000

Dunbogan Build comm May 2017

Kendall Build comm May 2017

Kew Build comm May 2017

Lakewood Build comm May 2017

Laurieton Build comm May 2017

North Haven Build comm May 2017

West Haven Build comm May 2017

Callala Bay 2CAL Q4 2016 Build comm Apr 2017 FTTN 2300

Callala Beach Build comm Apr 2017

Comberton Flipped FW available

Canterbury 2CAM H2 2017 Available / Planned Jul-Dec 2018 FTTN 2600

iTnews’ reconstructed NBN three-year plan 7

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 8: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

6

Earlwood Planned Apr-Jun 2017 / Jul-Dec 2018

Canowindra 2CAN Q1 2017 Planned Jul-Sept 2017 FTTN 700

Carlingford 2CAR H1 2017 Planned Jul-Dec 2018 HFC 13300

Dundas Valley Planned Jul-Dec 2018

North Rocks Planned Jul-Dec 2018

Telopea Planned Jul-Dec 2018

West Pennant Hills Planned Jul-Dec 2018

Castle Hill 2CAS Q3 2016 Build comm Jan 2017 FTTP / FTTN 4000

Castle Hill 2CAS H1 2017 Planned Oct-Dec 2017 / Jan-Mar 2018 HFC 18400

Cherrybrook Planned Apr-Jun 2017 / Oct-Dec 2017

Glenhaven Planned Oct-Dec 2017

West Pennant Hills Planned Oct-Dec 2017

Cobar 2CBA Q1 2017 Planned Jul-Sept 2017 FTTN 2300

Aberdare 2CES Q1 2017 Build comm Oct 2017 FTTN 10200

Bellbird Planned Oct-Dec 2017

Bellbird Heights Planned Oct-Dec 2017

Cessnock Build comm Oct 2017

Ellalong Planned Oct-Dec 2017

Kearsley Build comm Oct 2017

Millfield Planned Oct-Dec 2017

Nulkaba Build comm Jun 2017

Paxton Planned Oct-Dec 2017

Artarmon 2CHA H1 2018 Planned Jul-Dec 2018 / Jan-Jun 2019 HFC 18600

Chatswood Planned Jul-Dec 2018 / Jan-Jun 2019

Chatswood West Planned Jan-Jun 2018

Roseville Planned Jan-Jun 2019

Adamstown Hts 2CHL Q3 2016 Build comm May 2017 FTTN 24200

Cardiff Build comm Apr 2017

Cardiff Heights Build comm Apr 2017

Cardiff South Build comm July 2017

Charlestown Build comm Mar 2017

Dudley Build comm Mar 2017

iTnews’ reconstructed NBN three-year plan 8

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 9: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

7

Garden Suburb Build comm Apr 2017

Gateshead Build comm Jun 2017

Glendale Build comm Jun 2017

Highfields Build comm Feb 2017

Hillsborough Planned Jul-Sept 2017

Kahibah Build comm Mar 2017

Kotara South Build comm Apr 2017

Lakelands Planned Jul-Sept 2017

Macquarie Hills Build comm July 2017

Redhead Build comm Mar 2017

Whitebridge Build comm Mar 2017

Coolamon 2CLM H1 2017 Planned Jan-Jun 2018 FTTN 800

Coonamble 2CMB Q1 2017 Planned Jul-Sept 2017 FTTN 1400

Bonnet Bay 2CMO H1 2017 Planned Apr-Jun 2017 HFC 18800

Como Planned Apr-Jun 2017

Jannali Planned Apr-Jun 2017

Kareela Planned Apr-Jun 2017

Kirrawee Flipped Jan-Jun 2019 FTTC/B

Loftus Flipped Jan-Jun 2019 FTTC

Oyster Bay Planned Apr-Jun 2017

Sutherland Planned Jan-Jun 2019 FTTC/B

Woronora Heights 2CMO H2 2017 Planned Jul-Dec 2018 FTTN 800

Coonabarabran 2CNA Q4 2016 Build comm Mar 2017 FTTN 1500

Cooma 2COM Q1 2017 Planned Jan-Jun 2018 FTTN 3500

Polo Flat Planned Jan-Jun 2018

Condobolin 2CON Q1 2017 Build prep Jul-Sept 2017 FTTN 1400

Coogee 2COO H2 2017 Planned Jan-Jun 2019 HFC 26000

Clovelly Planned Jan-Jun 2019

Randwick Planned Jan-Jun 2019

South Coogee Planned Jul-Dec 2018 some FTTN

Corowa 2COW H1 2017 Planned Jul-Sept 2017 FTTN 4700

Rutherglen Planned Oct-Dec 2017

iTnews’ reconstructed NBN three-year plan 9

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 10: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

8

Wahgunyah Planned Oct-Dec 2017

Coomba Park 2CPK Q4 2016 Build comm Feb 2017 FTTN 600

Coraki 2CRK H2 2017 Planned FW FTTN 500

Cremorne 2CRM H1 2017 Planned Jan-Mar 2017 / Apr-Jun 2017 HFC 14400

Cremorne Point Planned Jan-Mar 2017

Kurraba Point Planned Jan-Mar 2017

Neutral Bay Planned Jan-Mar 2017

Bundeena 2CRO H1 2017 Planned Jan-Jun 2019 FTTN 3600

Kurnell Planned Jan-Jun 2019

Cabramatta 2CRR H2 2016 Build comm / Planned Jun 2017 / Jul-Sep 2017 HFC 24700

Cabramatta WestAvailable / Build comm / Planned Avail / Feb 2017 / Jul-Dec 2018

Canley HeightsAvailable / Build comm / Planned Avail / Feb 2017 / Jul-Sep 2017

Canley Vale Available / Planned Now / Oct-Dec 2017

Carramar Planned Jul-Sep 2017

Fairfield Planned Jul-Sep 2017

Fairfield East Build comm / Planned May 2017 / Jul-Sep 2017

Fairfield Heights Available / Planned Now / Jul-Sep 2017

Lansdowne Planned May 2017

Lansvale Build comm May 2017

Villawood Build comm May 2017

Fairfield 2CRR H2 2017 Build comm Jul 2017 FTTN 1500

Cedar Point 2CSN Q4 2016 Planned 2020 FW 250

Doubtful Creek Planned 2020

Casino 2CSN H2 2017 Planned Jul-Dec 2018 FTTN 4700

Crescent Head 2CTH H1 2017 Planned Jan-Jun 2018 FTTN 700

Cootamundra 2CTM Mar 2016 Available FW 190

Cootamundra 2CTM H1 2017 Planned Jul-Dec 2018 FTTN 3000

Clarence Town 2CTW Q4 2016 Build comm Mar 2017 FTTN 500

Table Top 2CUL Q2 2016 Build comm FW 350

Culcairn 2CUL Q4 2016 Build comm Mar 2017 FTTN 500

Currarong 2CUR H1 2017 Planned Jan-Jun 2018 FTTN 500

Crookwell 2CWL H1 2017 Planned Oct-Dec 2017 FTTN 1200

iTnews’ reconstructed NBN three-year plan 10

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 11: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

9

Cowra 2CWR Q2 2016 Build comm Jan 2017 FTTN 4200

Darlinghurst 2CYS Q3 2016 Unclear FTTN 7400

Sydney Planned Jul-Sept 2017

Woolloomooloo Planned Apr-Jun 2017

Darlinghurst 2CYS H2 2017 Planned Apr-Jun 2017 / Jul-Sep 2017 HFC 13400

Woolloomooloo Planned Apr-Jun 2017

Barangaroo 2DAL Q3 2016 Unclear FTTN 15700

Dawes Point Planned Jul-Dec 2018 FTTC/B

Millers Point Planned Jul-Dec 2018 FTTC/B

Sydney Build prep May 2017 Some FTTB

The Rocks Planned Jul-Dec 2018 FTTC

Millers Point 2DAL H1 2018 Planned Jul-Dec 2018 FTTC/B HFC 4300

The Rocks Planned Jul-Dec 2018 FTTC

Dungog 2DGO Q4 2016 Build comm Feb 2017 FTTN 1200

Denman 2DNM Q1 2017 Planned Jul-Sept 2017 FTTN 900

Darlington Point 2DNP H1 2017 Build comm Nov 2017 FTTN 500

Deniliquin 2DNQ H2 2017 Planned Jul-Dec 2018 FTTN 3400

Douglas Park 2DPK H2 2017 Planned Jan-Jun 2018 FTTC FTTN 700

Wilton Planned Jan-Jun 2018

Dorrigo 2DRG H2 2017 Planned Jan-Jun 2018 FTTN 500

Abbotsford 2DRU H2 2017 Planned Jan-Jun 2019 HFC 16700

Chiswick Planned Jan-Jun 2019

Drummoyne Planned Jan-Jun 2019

Five Dock Planned Jan-Jun 2019

Rodd Point Planned Jan-Jun 2019

Russell Lea Planned Jan-Jun 2019

Wareemba Planned Jan-Jun 2019

Dural 2DUR H2 2016 Planned Jan-Jun 2018 FTTC HFC 1900

Annangrove 2DUR Q4 2016 Build comm FW 2490

Arcadia North Planned 2020

Dural East

Galston Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 11

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 12: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

10

Galston East Planned Jan-Jun 2018

Glenhaven Planned 2020

Glenorie Planned Jan-Jun 2018

Glenorie South Planned Jan-Jun 2018

Kenthurst Planned Jan-Jun 2018

Kenthurst West Planned Jan-Jun 2018

Middle Dural Planned Jan-Jun 2018

Nelson Build comm

Riverstone Unclear

Dural 2DUR H2 2017 Planned Jan-Jun 2018 FTTC FTTN 2700

Galston Planned Jan-Jun 2018 FTTC

Middle Dural Planned Jan-Jun 2018 FTTC

Centennial Park 2EAS H2 2017 Planned Apr-Jun 2017 HFC 23900

Darlinghurst Planned Apr-Jun 2017

Elizabeth Bay Planned Apr-Jun 2017

Moore Park Planned Apr-Jun 2017

Paddington Planned Apr-Jun 2017

Potts Point Planned Apr-Jun 2017

Rushcutters Bay Planned Jul-Sep 2017

Woolloomooloo Planned Apr-Jun 2017

Bellevue Hill 2EDG H1 2017 Available / Planned Now / Oct-Dec 2017 HFC 17200

Darling Point Build comm Jan 2017 6 Jan 2017

Double Bay Planned Jul-Sep 2017

Edgecliff Planned Jan 2017 6 Jan 2017

Paddington Planned Apr-Jun 2017

Point Piper Planned Jul-Sept 2017

Woollahra Available / Planned Now / Jul-Sept 2017

Eden 2EDN H2 2017 Planned Jan-Jun 2018 FTTN 1800

Engadine 2ENG H2 2017 Planned Jan-Mar 2018 HFC 9200

Heathcote Unclear

Yarrawarrah Planned Apr-Jun 2017

Cheltenham 2EPP H1 2018 Planned Oct-Dec 2017 HFC 14600

iTnews’ reconstructed NBN three-year plan 12

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 13: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

11

Epping Planned Apr-Jun 2017

Marsfield Planned Oct-Dec 2017

North Epping Planned Apr-Jun 2017

Abbotsbury 2ERP H2 2016 Planned Jul-Dec 2018 HFC 17100

Bonnyrigg Planned Jul-Dec 2018

Bonnyrigg Heights Planned Jul-Dec 2018

Bossley Park Planned Jul-Dec 2018

Cabramatta West Planned Jul-Dec 2018

Edensor Park Planned Jul-Dec 2018

Greenfield Park Planned Jul-Dec 2018

Horsley Park Planned Jul-Dec 2018

Mount Pritchard Planned Jul-Dec 2018

St Johns Park Planned Jul-Dec 2018

Cecil Hills 2ERP H2 2017 Planned Jul-Dec 2018 FTTN 3300

Cecil Park Planned Jul-Dec 2018

Horsley Park Planned Jul-Dec 2018

Kemps Creek Planned Jul-Dec 2018

Mount Vernon Planned Jul-Dec 2018

Doonbah 2ESH H2 2017 Flipped? FW FTTN 1800

Evans Head Planned Jan-Jun 2018Claremont Meadows 2ESP H2 2016 Planned Jan-Jun 2019 HFC 17700

Colyton Planned Jan-Jun 2019

Erskine Park Unclear

Oxley Park Planned Jan-Jun 2019

St Clair Available

St Marys Planned Jan-Jun 2019

St Marys 2ESP H2 2017 Planned Jan-Jun 2019 FTTN 500

Finley 2FNL H2 2017 Planned Jul-Dec 2018 FTTN 1200

Forbes 2FRB Q1 2017 Planned Apr-Jun 2017 FTTN 3600

Belrose 2FRE H2 2017 Planned Jan-Jun 2018 FTTN 500

Pyrmont 2GBE Q1 2017 Planned Jul-Dec 2018 FTTN 1700

Annandale 2GBE H1 2018 Planned Jul-Dec 2018 HFC 21600

iTnews’ reconstructed NBN three-year plan 13

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 14: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

12

Forest Lodge Planned Jul-Dec 2018

Glebe Planned Jul-Dec 2018

Pyrmont Planned Oct-Dec 2017 FTTB

Ultimo Planned Jul-Dec 2018

Gundagai 2GDA Q3 2016 Build comm Jan 2017 20 Jan 2017 FTTN 1100

South Gundagai Build comm Jan 2017 20 Jan 2017

Grenfell 2GFE Q1 2017 Planned Jul-Sept 2017 FTTN 1100

Griffith 2GFT Q3 2016 Build comm Jan 2017 20 Jan 2017 FTTN 8700

Yoogali Flipped FW

Gilgandra 2GIL Q1 2017 Build prep Apr-Jun 2017 FTTN 1400

Gloucester 2GLO Q4 2016 Build comm Aug 2017 FTTN 1400

Glen Innes 2GNI H2 2017 Planned Jul-Dec 2018 FTTN 2800

Clyde 2GRA H2 2017 Planned Jul-Dec 2018 FTTN 2200

Holroyd Planned Jul-Dec 2018

Culburra Beach 2GRE H2 2017 Planned Jul-Dec 2018 FTTN 3300

Greenwell Point Planned Jul-Dec 2018

Orient Point Planned Jul-Dec 2018

Clarenza 2GRN Q1 2017 Flipped? FW FTTN 9500

Grafton Planned Oct-Dec 2017

Junction Hill Planned Oct-Dec 2017

South Grafton Planned Oct-Dec 2017

Waterview Heights Planned Jul-Dec 2017

Guildford 2GUI H2 2016 Planned Jan-Jun 2019 FTTC HFC 15100

Guildford West Planned Jan-Jun 2019 FTTC

Merrylands West Planned Jan-Jun 2019 FTTC

Old Guildford Planned Jan-Jun 2019 FTTC

South Granville Planned Jan-Jun 2019 FTTC

Woodpark Planned Jan-Jun 2019 FTTC

Yennora Planned Jan-Jun 2019 FTTC

Gulgong 2GUL Sep 2015 Available FTTN 1000

Eurunderee 2GUL Q2 2016 Available FW 510

Kains Flat Build comm

iTnews’ reconstructed NBN three-year plan 14

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 15: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

13

Gunnedah 2GUN H1 2017 Planned Jan-Jun 2018 FTTN 4100

Guyra 2GYR H2 2017 Planned Jan-Jun 2018 FTTN 900

South Guyra Flipped FW

Bogangar 2HAP Q3 2016 Build comm Jun 2017 FTTN 5100

Cudgera Creek Planned 2020

Hastings Point Planned Jun 2017

Pottsville Planned Mar 2017

Harrington 2HAR Q4 2016 Build comm Feb 2017 FTTN 1800

Bundabah 2HAW H2 2017 Unclear FTTN 1500

Karuah Planned Jul-Dec 2018

North Arm Cove Unclear

Hay 2HAY Q3 2016 Build comm Feb 2017 FTTN 1400

Hay South Build comm Feb 2017

Brookvale 2HBD Q4 2016 Build comm May 2017 FTTN 2300

Allambie Heights 2HBD H1 2017 Planned Oct-Dec 2017 HFC 11100

Brookvale Planned Jan-Jun 2019

Curl Curl Planned Jan-Jun 2019

Freshwater Planned Jan-Jun 2019

North Curl Curl Planned Jan-Jun 2019

North Manly Planned Jan-Jun 2019

Queenscliff Planned Jan-Jun 2019

Henty 2HEN Q4 2016 Planned Mar 2017 FTTN 600

Pleasure Point 2HLS H2 2017 Planned Jan-Jun 2018 FTTN 600

Voyager Point Planned Jan-Jun 2018

Haymarket 2HMK H2 2017 Planned Jan-Jun 2019 FTTC/P HFC 13400

Surry Hills Planned Jul-Sep 2017 Some FTTB

Chippendale 2HMK H2 2017 Planned Jan-Jun 2019 FTTC FTTN 9000

Haymarket Planned Jan-Jun 2019 FTTC

Darlington Planned Jan-Jun 2018 FTTC

Surry Hills Planned Jan-Jun 2019

Ultimo Planned Jan-Jun 2019 FTTC/B

Holbrook 2HOL Q4 2016 Build comm Apr 2017 FTTN 700

iTnews’ reconstructed NBN three-year plan 15

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 16: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

14

Belfield 2HOM H1 2017 Planned Jan-Jun 2019 FTTC HFC 2700

Strathfield South Planned Jan-Jun 2018 FTTC

Homebush 2HOM H2 2017 Unclear FTTN 2100

Homebush West Unclear

Rookwood Unclear

Strathfield Unclear

Asquith 2HOR H1 2018 Planned Jan-Jun 2019 HFC 15900

Hornsby Planned Jan-Jun 2019

Hornsby Heights Planned Jan-Jun 2019

Mount Colah Planned Jan-Jun 2019

Waitara Planned Jul-Dec 2018

Howlong 2HOW H2 2017 Planned Jan-Jun 2018 FTTN 1300

Harden 2HRD H1 2017 Planned Jul-Sept 2017 FTTN 1000

Murrumburrah Unclear

Hillston 2HTO Q4 2016 Build comm May 2017 FTTN 900

Gladesville 2HUH H2 2016 Planned Jan-Jun 2019 FTTC HFC 18800

Hunters Hill Planned Jul-Dec 2018 FTTC

Lane Cove Planned Jan-Jun 2019

Lane Cove North Planned Jan-Jun 2019

Lane Cove West Planned Jan-Jun 2019

Linley Point Planned Jan-Jun 2019

Longueville Planned Jan-Jun 2019

Northwood Planned Jan-Jun 2019

Riverview Planned Jan-Jun 2019

Tennyson Point Planned Jan-Jun 2019 FTTC

Henley 2HUH Q1 2017 Planned Oct-Dec 2017 FTTN 3800

Hunters Hill Planned Oct-Dec 2017

Huntleys Cove Planned Oct-Dec 2017

Huntleys Point Planned Oct-Dec 2017

Woolwich Planned Oct-Dec 2017

Beverly Hills 2HUR H2 2018 Planned Jan-Jun 2019 HFC 25300

Hurstville Planned Jan-Jun 2019

iTnews’ reconstructed NBN three-year plan 16

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 17: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

15

Hurstville Grove Planned Jan-Jun 2019

Mortdale Planned Jan-Jun 2019

Oatley Planned Jan-Jun 2019

Penshurst Planned Jan-Jun 2019

Bow Bowing 2ING H1 2017 Planned Jul-Dec 2019 FTTN 8300

Denham Court Planned Jan-Jun 2018

Minto Planned Jul-Dec 2019

Minto Heights Planned Jul-Dec 2019

St Andrews Planned Jul-Dec 2019

Eagle Vale 2ING H1 2017 Planned Jul-Dec 2019 HFC 15900

Eschol Park Planned Jul-Dec 2019

Glenfield Planned Jan-Jun 2018

Ingleburn Available / Planned Now / Oct-Dec 2017

Kearns Planned Jul-Dec 2019

Long Point Planned Jan-Mar 2017

Macquarie Fields Planned Jan-Mar 2017

Raby Planned Jul-Dec 2019

Inverell 2IVL H2 2017 Planned Jul-Dec 2018 FTTN 4700

Jindabyne 2JNB Q3 2016 Build prep Apr-Jun 2017 FTTN 2100

Junee 2JUE Q1 2017 Planned Jul-Sept 2017 FTTN 1700

Casuarina 2KCL H2 2017 Planned Jul-Dec 2018 FTTN 7400

Chinderah Planned Jul-Dec 2018

Cudgen Planned Jul-Dec 2018

Kingscliff Planned Jul-Dec 2018

East Killara 2KIL H2 2017 Planned Jan-Jun 2019 HFC 15600

East Lindfield Planned Jan-Jun 2019

Gordon Planned Jan-Jun 2019

Killara Planned Jan-Jun 2019

Lindfield Planned Jan-Jun 2019

Roseville Planned Jan-Jun 2019

West Pymble Planned Jan-Jun 2019

Aldavilla 2KMS Q3 2016 Build comm May 2017 FTTN 4800

iTnews’ reconstructed NBN three-year plan 17

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 18: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

16

East Kempsey Build comm May 2017

Greenhill Build comm May 2017

Kempsey Build comm May 2017

South Kempsey Build comm May 2017

West Kempsey Build comm May 2017

Yarravel Build comm May 2017

Kempsey 2KMS Q3 2016 Available FW 170

Kandos 2KND Q4 2016 Build comm Jul 2017 FTTN 1300

Rylstone Build comm Jul 2017

Rosebery 2KNS Q1 2017 Planned Apr-Jun 2017 FTTN 800

Daceyville 2KNS H1 2018 Planned Jan-Jun 2019 HFC 15200

Eastlakes Planned Jan-Jun 2019

Kensington Planned Jan-Jun 2019

Kingsford Planned Jan-Jun 2019

Zetland Unclear

Bardwell Park 2KOG H2 2016 Planned Jan-Jun 2019 FTTC HFC 13000

Beverly Hills Planned Jul-Dec 2018 FTTC

Bexley North Planned Jan-Jun 2019 FTTC

Dolls Point Planned Jan-Jun 2019 FTTC

Kingsgrove Planned Jan-Jun 2019 FTTC

Ramsgate Beach Planned Jan-Jun 2019 FTTC

Sandringham Planned Jan-Jun 2019 FTTC

Sans Souci Planned Jan-Jun 2018 FTTC

Dolls Point 2KOG H2 2017 Planned Jan-Jun 2019 FTTN 500

Kootingal 2KOO H1 2017 Planned Oct-Dec 2017 FTTN 700

Bourkelands 2KRG H2 2017 Planned Jan-Jun 2019 FTTN 6600

Kooringal Available

Lake Albert Planned Jan-Jun 2019

Springvale Planned Jan-Jun 2019

Tatton Planned Jan-Jun 2019

Tolland Planned Jan-Jun 2019

Abermain 2KRI H2 2017 Planned Jul-Dec 2018 FTTN 6600

iTnews’ reconstructed NBN three-year plan 18

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 19: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

17

Cliftleigh Planned Jul-Dec 2018

Heddon Greta Planned Jul-Dec 2018

Kurri Kurri Planned Jul-Dec 2018

Neath Planned Jul-Dec 2018

Pelaw Main Planned Jul-Dec 2018

Stanford Merthyr Planned Jul-Dec 2018

Weston Planned Jul-Dec 2018

Geneva 2KYO H1 2018 Planned Jan-Jun 2018 FTTN 1500

Kyogle Planned Jan-Jun 2018

Mount Lewis 2LAK H1 2017 Planned Oct-Dec 2017 HFC 5700

Belmore 2LAK H2 2017 Unclear FTTN 900

Greenacre Planned Jan-Jun 2018

Lakemba Unclear

Punchbowl Unclear

Roselands Unclear

Wiley Park Unclear

Glenroy 2LAV Q4 2016 Build comm Jul 2017 FTTN 14100

Hamilton Valley Flipped? FW

Lavington Build comm Jul 2017

North Albury Build comm Jul 2017

Springdale Hts Build comm Jun 2017

Thurgoona Build comm Apr 2017

Wirlinga Flipped FW

Lake Cargelligo 2LCG Q1 2017 Planned Jul-Sept 2017 FTTN 600

Bonny Hills 2LCT H2 2017 Planned Jul-Dec 2018 FTTN 2600

Lake Cathie Planned Jul-Dec 2018

Bexhill 2LIS Q1 2017 Planned Oct-Dec 2017 FTTN 15300

Chilcotts Grass Planned Oct-Dec 2017

East Lismore Planned Oct-Dec 2017

Girards Hill Planned Jul-Dec 2017

Goonellabah Planned Oct-Dec 2017

Lismore Planned Oct-Dec 2017

iTnews’ reconstructed NBN three-year plan 19

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 20: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

18

Lismore Heights Planned Oct-Dec 2017

Loftville Flipped? FW

North Lismore Planned Oct-Dec 2017

Richmond Hill Planned Oct-Dec 2017

South Lismore Planned Jul-Dec 2017

Lightning Ridge 2LIT Q1 2017 Planned Oct-Dec 2017 FTTN 800

Casula 2LIV H1 2017 Planned Apr-Jun 2017 HFC 7000

Moorebank Planned Jan-Jun 2018

Warwick Farm Planned Jan-Jun 2018

Chipping Norton 2LIV H2 2017 Planned Jul-Dec 2018 FTTN 3900

Liverpool Unclear

Mount Pritchard Planned Jul-Dec 2018

Bowenfels 2LTG H2 2017 Planned Jul-Dec 2018 FTTN 6000

Hermitage Flat Planned Jul-Dec 2018

Lithgow Planned Jul-Dec 2018

Littleton Planned Jul-Dec 2018

Marrangaroo Planned Jul-Dec 2018

McKellars Park Planned Jul-Dec 2018

Morts Estate Planned Jul-Dec 2018

Oaky Park Planned Jul-Dec 2018

South Bowenfels Planned Jul-Dec 2018

South Littleton Planned Jul-Dec 2018

Vale of Clwydd Planned Jul-Dec 2018

Leeton 2LTO Q4 2016 Build comm Jun 2017 FTTN 3400

Bowraville 2MAC Q1 2017 Planned Jul-Sept 2017 FTTN 7500

Hyland Park Planned Oct-Dec 2017

Macksville Planned Oct-Dec 2017

Nambucca Heads Planned Jul-Sept 2017

North Macksville Planned Jul-Sept 2017

Scotts Head Planned Oct-Dec 2017

Valla Beach Planned Oct-Dec 2017

Brandy Hill 2MAI Oct 2015 Build comm FW 5760

iTnews’ reconstructed NBN three-year plan 20

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 21: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

19

Buchanan Planned

Clarence Town PlannedClarence Town South Planned

Duns Creek Available

Ellalong Unclear

Glen Oak Planned

Gresford South Build comm

Hexham Planned

Hinton South Build comm

Kitchener Build comm

Lenaghan Planned

Martins Creek Planned

Millfield Planned

Mount View Build comm

Mulbring Planned

Paterson Planned

Raymond Terrace Planned

Sawyers Gully Planned

Seaham Planned

Telarah Planned

Wallalong Build comm

Woodville South Available

Manilla 2MAN H2 2017 Planned Jul-Dec 2018 FTTN 1100

Chifley 2MAT H2 2017 Planned Jan-Jun 2019 HFC 10900

Hillsdale Planned Jan-Jun 2019

La Perouse Planned Jan-Jun 2019

Little Bay Planned Jan-Jun 2019

Matraville Planned Jan-Jun 2019

Phillip Bay Planned Jan-Jun 2019

Murrumbateman 2MBT Q4 2016 Build comm Feb 2017 FTTN 800

Mororo 2MCL Q3 2016 Build comm FW 480

Palmers Island Build comm

iTnews’ reconstructed NBN three-year plan 21

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 22: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

20

Gulmarrad 2MCL H1 2018 Planned Jan-Jun 2019 FTTN 2400

Maclean Planned Jan-Jun 2019

Townsend Planned Jan-Jun 2019Lemon Tree Passage 2MDW H2 2017 Planned Jul-Dec 2018 FTTN 6700

Mallabula Planned Jul-Dec 2018

Medowie Planned Jul-Dec 2018

Salt Ash Planned Jul-Dec 2018

Tanilba Bay Planned Jul-Dec 2018

Menai 2MEN H2 2017 Unclear FTTN 500

Alfords Point 2MEN H2 2018 Planned Jan-Mar 2018 HFC 3700

Illawong Planned Jan-Mar 2018

Menai Planned Jan-Mar 2018

Bald Hills 2MER Q3 2016 Planned FW 430

Broadwater Build comm

Nethercote Build comm

Berrambool 2MER H1 2017 Planned Jul-Dec 2018 FTTN 6100

Merimbula Planned Jul-Dec 2018

Pambula Planned Jul-Dec 2018

Pambula Beach Planned Jul-Dec 2018

South Pambula Planned Jul-Dec 2018

Tura Beach Planned Jul-Dec 2018

Kemps Creek North 2MGO Q1 2017 Planned FW 1280

Luddenham Planned

Mulgoa Planned

Mulgoa North Planned

Orchard Hills Planned

Wallacia Planned

Edmondson Park 2MIL Q1 2017 Build comm Jun 2017 FTTN 9800

Elizabeth Hills Planned Jul-Sept 2017

Horningsea Park Build comm May 2017

Hoxton Park Build comm May 2017

Middleton Grange Build comm Jun 2017

iTnews’ reconstructed NBN three-year plan 22

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 23: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

21

Prestons Planned Jul-Sept 2017

West Hoxton Build comm May 2017

Ashcroft 2MIL H2 2017 Available Now HFC 14000

Busby Planned Jan-Mar 2017

Cartwright Available Now

Green Valley Planned Oct-Dec 2017

Heckenberg Planned Jan-Mar 2017

Hinchinbrook Planned Oct-Dec 2017

Lurnea Available Now

Miller Planned Jan-Mar 2017

Sadleir Available Now

Caringbah 2MIR H2 2016 Planned Jul-Dec 2018 FTTC/N HFC 29400

Caringbah South Planned Jul-Dec 2018 FTTC

Dolans Bay Planned Jul-Dec 2018 FTTC

Grays Point Planned Jul-Dec 2018 FTTC

Gymea Planned Jul-Dec 2018 FTTC

Gymea Bay Planned Jul-Dec 2018 FTTC

Kangaroo Point Planned Jul-Dec 2018

Lilli Pilli Planned Jul-Dec 2018 FTTC

Miranda Planned Jul-Dec 2018 FTTC

Port Hacking Planned Jul-Dec 2018 FTTC

Sylvania Planned Jul-Dec 2018

Sylvania Waters Planned Jul-Dec 2018

Taren Point Planned Jul-Dec 2018

Yowie Bay Planned Jul-Dec 2018 FTTC

Taren Point 2MIR H2 2017 Planned Jul-Dec 2018 FTTN 1500

Bayview 2MON H2 2016 Planned Jul-Dec 2018 FTTC HFC 15800

Elanora Heights Planned Jul-Dec 2018 FTTC

Mona Vale Planned Jul-Dec 2018 FTTC/N

Narrabeen Planned Jul-Dec 2018

Newport Planned Jul-Dec 2018 FTTC

North Narrabeen Planned Jul-Dec 2018 FTTC

iTnews’ reconstructed NBN three-year plan 23

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 24: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

22

Warriewood Planned Jul-Dec 2018 FTTC

Church Point 2MON Q1 2017 Planned Jan-Jun 2018 FTTN 4100Great Mackerel Beach Planned 2020

Ingleside Planned Jan-Jun 2018

Scotland Island Planned Jan-Jun 2018

Warriewood Unclear

Mosman 2MOS H1 2017 Build comm Planned Apr-Jun 2017 HFC 12000

Berkshire Park 2MPK H1 2018 Planned Jul-Dec 2018 FTTC FTTN 1300

Windsor Downs Planned Jul-Dec 2018

Murrurundi 2MRD Q1 2017 Planned Jul-Sept 2017 FTTN 600

Moree 2MRE H2 2017 Planned Jan-Jun 2018 FTTN 4100

Marulan 2MRL Q4 2016 Planned FW 800

Tallong Build comm

Wingello Planned

Broulee 2MSP H2 2017 Planned Jul-Dec 2018 FTTN 3600

Malua Bay Planned Jul-Dec 2018 FTTC

Mossy Point Planned Jul-Dec 2018 FTTC

Tomakin Planned Jul-Dec 2018 FTTC

Aylmerton 2MTT Jan 2016 Build comm May 2017 FTTN 6000

Balaclava Build comm May 2017

Braemar Available

Colo Vale Build comm May 2017

Hilltop Build comm May 2017

Mittagong Available

Welby Available

Willow Vale Available

Yerrinbool Build comm May 2017

Berrima 2MTT Mar 2016 Available FW 1500

Bundanoon North Build comm

Burrawang Build comm

Exeter Planned

Moss Vale Planned

iTnews’ reconstructed NBN three-year plan 24

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 25: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

23

Billinudgel 2MUL H1 2018 Flipped FW FTTN 5500

Brunswick Heads Planned Jan-Jun 2019

Mullumbimby Planned Jul-Dec 2018 FTTC

Mullumbimby Creek Flipped FW

New Brighton Planned Jul-Dec 2018 FTTC

Ocean Shores Planned Jul-Dec 2018South Golden Beach Planned Jul-Dec 2018

Aberdeen 2MUS Q1 2017 Planned Oct-Dec 2017 FTTN 6400

Muswellbrook Planned Oct-Dec 2017

Blackheath 2MVI Q2 2016 Available FTTN 3800

Mount Victoria Build comm Feb 2017

Murwillumbah West 2MWB Q3 2016 Unclear FW 180

Bray Park 2MWB Q4 2016 Planned Jul-Sept 2017 FTTN 4700

Condong Planned Jul-Sept 2017

Dunbible Flipped FW available

Kielvale Planned Jul-Sept 2017

Murwillumbah Planned Jul-Sept 2017South Murwillumbah Planned Jul-Sept 2017

Beashel Hill 2MYA Q2 2016 Planned / Available FW 810

Bergalia Village Planned

Bodalla Build comm

Potato Head Build comm

Moruya 2MYA H1 2017 Planned Jan-Jun 2018 FTTN 2200

Moruya Heads Planned Jan-Jun 2018

Callaghan 2MYF Q3 2016 Build comm May 2017 FTTN 5400

Georgetown Build comm May 2017

Jesmond Build comm Feb 2017

Mayfield Available

Mayfield East Available

Mayfield West Unclear

North Lambton Build comm May 2017

Sandgate Available

iTnews’ reconstructed NBN three-year plan 25

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 26: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

24

Warabrook Available

Waratah Build comm May 2017

Waratah West Build comm May 2017

Black Head 2NAB Q4 2016 Build comm Feb 2017 FTTN 2800

Diamond Beach Build comm Feb 2017

Failford Build comm Feb 2017

Hallidays Point Build comm Feb 2017

Nabiac Build comm Feb 2017

Red Head Build comm Feb 2017

Tallwoods Village Build comm Feb 2017

Narrabri 2NBR H2 2017 Planned Jul-Dec 2018 FTTC FTTN 3200

Narrandera 2NDR Q4 2016 Build comm May 2017 FTTN 2300

Catherine Hill Bay 2NDS H2 2017 Planned Jul-Dec 2018 FTTN/P FTTN 8100

Caves Beach Planned Jul-Dec 2018

Gwandalan Planned Jul-Dec 2018

Nords Wharf Planned Jul-Dec 2018 FTTC

Summerland Point Planned Jul-Dec 2018 FTTC

Swansea Planned Jul-Dec 2018 FTTC

Swansea Heads Planned Jul-Dec 2018 FTTC

Camperdown 2NEW H2 2017 Planned Jan-Jun 2018 FTTN 1200

Enmore Planned Jan-Jun 2018

Erskineville Planned Jan-Jun 2018

Newtown Planned Jan-Jun 2018

St Peters Planned Jan-Jun 2018

Stanmore Planned Jan-Jun 2018

Sydenham Planned Jan-Jun 2018

Alexandria Build comm Jun 2017

Camperdown 2NEW H1 2018 Planned Apr-Jun 2017 HFC 2600

Enmore Planned Jan-Mar 2018

Erskineville Planned Jan-Jun 2018

Newtown Planned Jan-Jun 2018

St Peters Planned Oct-Dec 2017

iTnews’ reconstructed NBN three-year plan 26

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 27: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

25

Stanmore Planned Jan-Mar 2018

Sydenham Planned Oct-Dec 2017

Alexandria Planned Jan-Jun 2019

Anna Bay 2NLB Dec 2015 Build comm Feb 2017 FTTN 17900

Boat Harbour Build comm Feb 2017

Corlette Available

Fingal Bay Available

Fishermans Bay Build comm Feb 2017

Nelson Bay Available

One Mile Build comm Feb 2017

Salamander Bay Available

Shoal Bay Available

Soldiers Point Available

Taylors Beach Build comm Feb 2017

Adamstown 2NLT Q2 2016 Build comm May 2017 FTTN 28500

Adamstown Hts Build comm May 2017Birmingham Gardens Build comm Feb 2017

Elermore Vale Build comm May 2017

Fletcher Build comm Feb 2017

Jesmond Build comm May 2017

Kotara Build comm May 2017

Lambton Build comm Feb 2017

New Lambton Build comm Feb 2017New Lambton Heights Build comm May 2017

Rankin Park Build comm Jul-Sept 2017

Shortland Build comm Feb 2017

Wallsend Build comm May 2017

Camden 2NRL Q3 2016 Build comm Apr 2017 FTTN 6000

Camden Park Build comm Jan 2017

Camden South Build comm Jan 2017

Elderslie Build comm Jan 2017

Ellis Lane Build comm Apr 2017

iTnews’ reconstructed NBN three-year plan 27

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 28: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

26

Grasmere Build comm Apr 2017Belimbla Park South 2NRL Q1 2017 Build comm FW 1730

Cawdor West Build comm

Cobbitty Build comm

Glenmore West Unclear

Lakesland Build comm

Mount Hunter Build comm

Mowbray Park Build comm

Oakdale Build comm

The Oaks Build comm

Theresa Park West Build comm

Werombi Build comm

Werombi East Build comm

Dalmeny 2NRM H1 2017 Planned Jul-Dec 2018 FTTN 3700

Kianga Flipped? FW planned

Narooma Planned Jul-Dec 2018

North Narooma Planned Jul-Dec 2018

North Sydney 2NSY Q4 2016 Build comm Jun 2017 FTTN 2900

Nyngan 2NYG H1 2017 Planned Jan-Jun 2018 FTTC FTTN 1000

Koorainghat 2OBA Q3 2016 Flipped? FW available FTTN 2500

Old Bar Build comm Feb 2017

Wallabi Point Build comm Feb 2017

Oberon 2OBO Q1 2017 Planned Oct-Dec 2017 FTTN 1500

Kingswood 2ORC H2 2016 Planned Jul-Dec 2018 FTTC HFC 1600

Orchard Hills Planned Jul-Dec 2018 FTTC

Glenmore Park 2ORC H1 2018 Planned Jul-Dec 2018 FTTN 11200

Jamisontown Planned Jul-Dec 2018 FTTC

Kingswood Planned Jul-Dec 2018 FTTC

Mulgoa Available

Regentville Planned Jul-Dec 2018 FTTC

South Penrith Planned Jul-Dec 2018 FTTC/N

Parramatta 2PAR H1 2018 Planned Jul-Dec 2018 FTTN 1400

iTnews’ reconstructed NBN three-year plan 28

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 29: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

27

Lugarno 2PEA H1 2017 Planned Jul-Dec 2018 FTTC HFC 13000

Narwee Planned Jul-Dec 2018 FTTC

Peakhurst Planned Jul-Dec 2018 FTTC

Peakhurst Heights Planned Jul-Dec 2018 FTTC

Riverwood Planned Jul-Dec 2018 FTTC

Constitution Hill 2PEN H2 2017 Planned Jan-Jun 2018 HFC 23900

Girraween Planned Jan-Jun 2018

Greystanes Planned Jan-Jun 2018

Old Toongabbie Planned Jan-Jun 2018

Pendle Hill Planned Jan-Jun 2018South Wentworthville Planned Jan-Jun 2018

Toongabbie Planned Jan-Jun 2018

Wentworthville Planned Jan-Jun 2018

Pemulwuy 2PEN H1 2018 Planned Jan-Jun 2018 FTTN 2700

Dulwich Hill 2PET H2 2018 Planned Oct-Dec 2017 HFC 24100

Leichhardt Planned Apr-Jun 2017 / Jan-Mar 2018

Lewisham Planned Jan-Jun 2018

Marrickville Planned Oct-Dec 2017

Petersham Planned Oct-Dec 2017

Stanmore Planned Apr-Jun 2017 / Jan-Mar 2018

Cattai 2PIT Q4 2016 Build comm FW 2610

Cattai East Build comm

Ebenezer Build comm

Freemans Reach Build comm

Maraylya Planned

Maroota South Build comm

Oakville Planned

Pitt Town Build comm

Sackville Build comm

Sackville East Build comm

Sackville North Build comm

Scheyville Planned

iTnews’ reconstructed NBN three-year plan 29

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 30: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

28

Vineyard Planned

Wilberforce North Build comm

McGraths Hill 2PIT H2 2017 Planned Jan-Jun 2018 FTTN 2000

Pitt Town Planned Jan-Jun 2018

Vineyard Available

Peak Hill 2PKH Q4 2016 Build comm Feb 2017 FTTN 500

Parkes 2PKS Q4 2016 Build comm Feb 2017 FTTN 5300

Beecroft 2PNN H1 2017 Planned Apr-Jun 2017 / Oct-Dec 2017 HFC 14700

Cherrybrook Planned Apr-Jun 2017

Pennant Hills Planned Apr-Jun 2017

Thornleigh Planned Apr-Jun 2017

West Pennant Hills Planned Apr-Jun 2017

Westleigh Planned Apr-Jun 2017

Portland 2POR H2 2017 Planned Jul-Dec 2018 FTTN 900

Castlereagh 2PTH Q1 2017 Planned FW 2170

Castlereagh North Planned

Cranebrook North Build comm

Llandilo Build comm

Londonderry Build comm

Londonderry South Build comm

Yarramundi Planned

Yarramundi South Planned

Fernbank Creek 2PTM Q4 2016 Flipped? FW available FTTN 24000

North Shore Build comm Jul-Sept 2017

Port Macquarie Build comm Jul 2017

Riverside Build comm Jul-Sept 2017

North Turramurra 2PYM H2 2017 Planned Jan-Jun 2018 HFC 17400

Pymble Planned Jan-Jun 2018

South Turramurra Planned Jan-Jun 2018

St Ives Planned Jan-Jun 2018

St Ives Chase Planned Jan-Jun 2018

Turramurra Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 30

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 31: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

29

Warrawee Planned Jul-Dec 2018

West Pymble Planned Jan-Jun 2019

Quirindi 2QIR Q1 2017 Build comm Jul 2017 FTTN 1400

Acacia Gardens 2QUA H2 2016 Planned Oct-Dec 2017 FTTN HFC 14200

Dean Park Planned Oct-Dec 2017 FTTN

Kings Park Planned Jul-Dec 2018

Marayong Planned Jul-Dec 2018

Parklea Planned Oct-Dec 2017 FTTN

Quakers Hill Planned Jul-Dec 2018

Woodcroft Available

Acacia Gardens 2QUA H1 2017 Planned Oct-Dec 2017 FTTN 5500

Kings Park Planned Jul-Dec 2018

Parklea Planned Oct-Dec 2017

Stanhope Gardens Planned Oct-Dec 2017

Allawah 2RAM H2 2016 Planned Jul-Dec 2018 HFC 11000

Blakehurst Planned Jul-Dec 2018

Carss Park Planned Jul-Dec 2018

Connells Point Planned Jan-Jun 2018

Kyle Bay Planned Jan-Jun 2018

Ramsgate Planned Jan-Jun 2018 FTTC

Sans Souci Planned Jan-Jun 2018 FTTC

South Hurstville Planned Jan-Jun 2018

Robertson 2RBT H2 2017 Planned Jul-Dec 2018 FTTN 600

Agnes Banks 2RCH Oct 2015 Available FTTN 100

Bligh Park Available

Clarendon Available

Hobartville Available

Londonderry Available

Richmond Available

South Windsor Available

Windsor Available

Dundas 2RDL H1 2018 Planned Jan-Jun 2019 HFC 7100

iTnews’ reconstructed NBN three-year plan 31

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 32: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

30

Dundas Valley Planned Jan-Jun 2019

Ermington Planned Jan-Jun 2019

Rydalmere Planned Jan-Jun 2019

Telopea Planned Jan-Jun 2019

Rydalmere 2RDL H1 2018 Planned Jan-Jun 2019 FTTP, FTTN 700

Alexandria 2RED H2 2017 Build prep Jun 2017 FTTN 800

Redfern Planned Jan-Jun 2019

Surry Hills Planned Jan-Jun 2019

Waterloo Planned Jan-Jun 2019

Waterloo 2RED H1 2018 Planned Jan-Jun 2019 HFC 2100

Milperra 2REV Q1 2017 Planned Jan-Jun 2019 FTTC FTTN 1100

Arncliffe 2ROC H2 2016 Planned Jul-Dec 2018 FTTC HFC 28800

Banksia Planned Jul-Dec 2018

Bardwell Valley Planned Jul-Dec 2018 FTTC

Bexley Planned Jan-Jun 2019 FTTC

Brighton-le-Sands Planned Jan-Jun 2019 FTTC/B

Eastlakes Planned Jan-Jun 2019

Kyeemagh Planned Jul-Dec 2018 FTTC

Mascot Planned Apr-Jun 2017

Rockdale Planned Jul-Dec 2018 FTTC/B

Turrella Planned Jul-Dec 2018 FTTC

Wolli Creek Planned Mar 2017 FTTB/N

Eastlakes 2ROC H2 2017 Unclear FTTN 1200

Bellevue Hill 2ROS H1 2017 Available /Planned Now / Jul-Sep 2017 HFC 20500

Bondi Beach Planned Oct-Dec 2017

Dover Heights Planned Jan-Jun 2019

North Bondi Planned Oct-Dec 2017

Rose Bay Planned Jan-Jun 2019

Vaucluse Planned Jul-Dec 2018

Watsons Bay Planned Jul-Dec 2018

Dharruk 2ROT H2 2016 Planned Jan-Jun 2019 HFC 20800

Eastern Creek Planned Jul-Dec 2018 FTTC/N

iTnews’ reconstructed NBN three-year plan 32

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 33: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

31

Emerton Planned Apr-Jun 2017

Glendenning Planned Jan-Jun 2019

Hebersham Planned Jan-Jun 2019

Minchinbury Planned Jan-Jun 2019

Mount Druitt Planned Jan-Jun 2019

Oakhurst Planned Jan-Jun 2019

Plumpton Planned Jan-Jun 2019

Rooty Hill Planned Jan-Jun 2019

Whalan Planned Jan-Jun 2019

Ryde 2RYD Q4 2016 Build comm Jun 2017 FTTN 1900

Denistone 2RYD H1 2018 Planned Jan-Jun 2019 HFC 23100

Denistone East Planned Jul-Dec 2018

East Ryde Planned Jul-Dec 2018

Macquarie Park Build comm Jul-Dec 2018

Marsfield Planned Jul-Dec 2018

Meadowbank Planned Jul-Dec 2018

North Ryde Planned Jul-Dec 2018

Putney Planned Jul-Dec 2018

Ryde Planned Jul-Dec 2018

West Ryde Planned Jan-Jun 2019

Bream Beach 2SAN H1 2017 Planned Jan-Jun 2018 FTTN 10200

Erowal Bay Planned Jan-Jun 2018

Huskisson Planned Oct-Dec 2017

Old Erowal Bay Planned Jan-Jun 2018

Sanctuary Point Planned Jan-Jun 2018

St Georges Basin Planned Jan-Jun 2018

Vincentia Planned Oct-Dec 2017

Worrowing Heights Planned Jan-Jun 2018

Scone 2SCO Q1 2017 Planned Jul-Sept 2017 FTTN 2600

Bass Hill 2SEF H2 2016 Available /Planned Now / Jul-Sep 2017 HFC 4800

Georges Hall Available /Planned Now / Jul-Sep 2017

Lansdowne Build comm May 2017

iTnews’ reconstructed NBN three-year plan 33

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 34: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

32

Villawood Build comm May 2017

Birrong 2SEF H2 2017 Unclear FTTN 800

Chester Hill Unclear

Georges Hall Unclear

Lansdowne Unclear

Potts Hill Unclear

Regents Park Unclear

Sefton Unclear

Villawood Unclear

Yagoona Unclear

Bass Hill Unclear

Kings Langley 2SEV H1 2017 Planned Apr-Jun 2017 HFC 11300

Lalor Park Available / Plan Jul-Sep 2017

Seven Hills Available / Plan Jan-Jun 2018

Winston Hills Planned Jan-Jun 2019

Seven Hills 2SEV H2 2017 Available Jan-Jun 2018 FTTN 800

Ropes Crossing 2SHA H2 2017 Planned Jan-Jun 2019 FTTN 2200

Bidwill 2SHA H1 2018 Planned Jan-Mar 2018 HFC 14000

Blackett Planned Apr-Jun 2017

Emerton Planned Apr-Jun 2017

Hassall Grove Planned Jan-Mar 2018

Hebersham Planned Jan-Jun 2019

Lethbridge Park Planned Apr-Jun 2017

North St Marys Planned Jan-Jun 2019

Oakhurst Planned Jan-Jun 2019

Shalvey Planned Apr-Jun 2017

Tregear Planned Apr-Jun 2017

Werrington Planned Jan-Jun 2019

Werrington County Planned Jan-Jun 2019

Willmot Planned Apr-Jun 2017

Shoalhaven Heads 2SHO H2 2017 Planned Jan-Jun 2018 FTTN 1700

Breakfast Point 2SIL H1 2017 Planned Jan-Jun 2019 FTTN 9500

iTnews’ reconstructed NBN three-year plan 34

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 35: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

33

Liberty Grove Planned Jul-Dec 2018

Newington Planned Jul-Dec 2018 FTTC

Rhodes Planned 2020

Silverwater Planned Jul-Dec 2018Sydney Olympic Park Planned Jul-Dec 2018

Wentworth Point Planned Jan-Jun 2018

Rhodes 2SIL H2 2018 Planned 2020 HFC 3300

Winders Hill Build comm

Darlington 2SIN Q4 2016 Build comm Sep 2017 FTTN 6500

Glenridding Build comm Sep 2017

Hunterview Build comm Aug 2017

McDougalls Hill Build comm Sep 2017

Singleton Build comm Sep 2017

Singleton Heights Build comm Aug 2017

Wattle Ponds Build comm Aug 2017

Boomerang Beach 2SLK Q4 2016 Planned Jul-Sep 2017 FTTN 2100

Elizabeth Beach Planned Jul-Sep 2017

Smiths Lake Planned Jul-Sep 2017

Tarbuck Bay Planned Jul-Sep 2017

Emu Heights 2SPK H2 2016 Planned Jan-Jun 2019 FTTC HFC 3800

Emu Plains Planned Jan-Jun 2019 FTTC

Leonay Planned Jan-Jun 2019 FTTC

Blaxland 2SPK H2 2017 Planned Jan-Jun 2019 FTTN 19800Blue Mountains National Park Unclear

Faulconbridge Planned Jan-Jun 2019 FTTC

Glenbrook Planned Jan-Jun 2019 FTTC/NHawkesbury Heights Planned Jan-Jun 2019

Hazelbrook Planned Jan-Jun 2019 FTTC

Lapstone Planned Jan-Jun 2019 FTTC

Leonay Planned Jan-Jun 2019 FTTC

Linden Planned Jan-Jun 2019 FTTC

iTnews’ reconstructed NBN three-year plan 35

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 36: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

34

Mount Riverview Planned Jan-Jun 2019 FTTC

Springwood Planned Jan-Jun 2019 FTTC

Valley Heights Planned Jan-Jun 2019 FTTC

Warrimoo Planned Jan-Jun 2019 FTTC

Winmalee Planned Jan-Jun 2019

Woodford Planned Jan-Jun 2019 FTTC

Yellow Rock Planned Jan-Jun 2019 FTTC

Artarmon 2STL Q3 2016 Build comm Mar 2017 FTTN 1200

Crows Nest 2STL H1 2017 Build comm / Planned Jun 2017 / Oct-Dec 2017 HFC 13500

Greenwich Planned Oct-Dec 2017

Naremburn Planned Oct-Dec 2017

St Leonards Planned Oct-Dec 2017

Wollstonecraft Build comm Nov 2017

Berrara 2SUX Q3 2016 Build comm Jan 2017 FTTN 3100

Cudmirrah Build comm Jan 2017

Sussex Inlet Build comm Jan 2017

Arakoon 2SWR H1 2017 Planned Jul-Dec 2018 FTTN 3200

South West Rocks Planned Jul-Dec 2018

Balmoral West 2TAH Q1 2017 Build comm FW 1730

Bargo North Build comm

Bargo Build comm

Buxton East Build comm

Cawdor Build comm

Couridjah Build comm

Douglas Park Build comm

Hill Top South Planned

Menangle Build comm

Pheasants Nest Build comm

Razorback Planned

Razorback North Planned

Tahmoor East Build comm

Wedderburn South Planned

iTnews’ reconstructed NBN three-year plan 36

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 37: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

35

Calala 2TAM Q1 2017 Planned Jul-Dec 2017 FTTN 19100

East Tamworth Planned Oct-Dec 2017

Hillvue Planned Jan-Jun 2018

Kingswood Unclear

Moore Creek Flipped? FW

Nemingha Planned Flip FW

North Tamworth Planned Jul-Sep 2017

Oxley Vale Planned Jul-Sep 2017

South Tamworth Planned Jan-Jun 2018

Taminda Planned Oct-Dec 2017

Tamworth Planned Oct-Dec 2017

West Tamworth Planned Jan-Jun 2018

Westdale Planned Oct-Dec 2017

Beresfield 2TAR Q4 2016 Build prep Jul-Sep 2017 FTTN 6600

Chisholm Planned 2020

Hexham Build comm Jun 2017

Tarro Build prep Jul-Sep 2017

Thornton Build comm Jun 2017

Woodberry Build comm Jun 2017

Temora 2TEM H1 2017 Planned Jul-Dec 2018 FTTC FTTN 2200

Bilambil Heights 2TER Q1 2017 Planned Jul-Sep 2017 FTTN 3900

Terranora Planned Jul-Sep 2017

Tweed Heads West Planned Jul-Sep 2017

Hawks Nest 2TGN H2 2017 Planned Jul-Dec 2018 FTTN 4100

Pindimar Planned Jul-Dec 2018

Tea Gardens Planned Jul-Dec 2018

Tumbarumba 2TRB Q4 2016 Flipped FW build comm FTTN 600

Trangie 2TRG Q4 2016 Build comm Mar 2017 FTTN 500

Arcadia Vale 2TRT H2 2017 Planned Jan-Jun 2019 FTTC FTTN 12900

Awaba Planned Jan-Jun 2019

Balmoral Planned Jan-Jun 2019

Blackalls Park Planned Jan-Jun 2019 FTTC

iTnews’ reconstructed NBN three-year plan 37

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 38: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

36

Bolton Point Planned Jan-Jun 2019 FTTC

Buttaba Planned Jan-Jun 2019 FTTC

Carey Bay Planned Jan-Jun 2019 FTTC/N

Coal Point Planned Jan-Jun 2019 FTTC

Fassifern Planned Jan-Jun 2019

Fennell Bay Planned Jan-Jun 2019

Fishing Point Planned Jan-Jun 2019

Kilaben Bay Planned Jan-Jun 2019 FTTC

Marmong Point Available

Rathmines Planned Jan-Jun 2019 FTTC/N

Toronto Planned Jan-Jun 2019 FTTC

Wangi Wangi Planned Jan-Jun 2019 FTTC/N

Woodrising Planned Jan-Jun 2019 FTTC

Old Bonalbo 2TTF Q1 2017 Planned FW 440

Sandilands East Planned

Tabulam Build comm

Urbenville Planned

Tenterfield 2TTF H2 2017 Planned Jul-Dec 2018 FTTN 1700

Tuross Head 2TUH H2 2017 Planned Jan-Jun 2018 FTTN 1900

Tumut 2TUM Q3 2016 Build comm Jan 2017 FTTN 3100

Tocumwal 2TWA H2 2017 Planned Jul-Dec 2018 FTTN 1300

Banora Point 2TWH Q2 2016 Build comm May 2017 FTTN 21900

Bilinga Build comm Mar 2017

Coolangatta Available

Fingal Head Build comm Sep 2017

Tweed Heads Build comm Feb 2017Tweed Heads South Build comm Feb 2017

Tweed Heads West Planned Jul-Sep 2017

Burrill Lake 2ULL Q4 2016 Build comm Jul 2017 FTTN 9200

Dolphin Point Build comm Jul 2017

Kings Point Build comm Jul 2017

Milton Build comm Jul 2017

iTnews’ reconstructed NBN three-year plan 38

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 39: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

37

Mollymook Build comm Jul 2017

Mollymook Beach Build comm Jul 2017

Narrawallee Build comm Jul 2017

Ulladulla Build comm Jul 2017

Dulwich Hill 2UND H1 2018 Planned Oct-Dec 2017 HFC 13900

Earlwood Planned Apr-Jun 2017

Hurlstone Park Planned Oct-Dec 2017

Marrickville Planned Jan-Mar 2018

Tempe Planned Apr-Jun 2017

Mylestom 2URG Q1 2017 Planned Jul-Sep 2017 FTTN 1900

Raleigh Planned Jul-Sep 2017

Repton Planned Jul-Sep 2017

Urunga Planned Jul-Sep 2017

Uralla 2URL H2 2017 Planned Jul-Dec 2018 FTTN 1100

Bilpin 2URR Q1 2017 Planned FW 1660Blaxlands Ridges East Build commBlaxlands Ridges West Build commBlaxlands Ridges South Build comm

Kurmond Build comm

Kurmond East Build comm

Kurrajong East Planned

Kurrajong Heights Planned

Kurrajong Hills Planned

Sackville West Build comm

Tennyson Build comm

Bowen Mountain 2URR H2 2017 Flipped Jul-Dec 2018 FTTC FTTN 4200

Grose Vale Flipped Jul-Dec 2018 FTTC

Kurmond Flipped Jul-Dec 2018 FTTC

Kurrajong Flipped Jul-Dec 2018 FTTC

Kurrajong Heights Flipped Jul-Dec 2018 FTTC

North Richmond Planned Jul-Dec 2018 FTTN/P

iTnews’ reconstructed NBN three-year plan 39

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 40: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

38

The Slopes Planned Jul-Dec 2018

Broadwater 2WAD H1 2016 Flipped? FW build comm FTTN 600

Wardell Unclear

Lidsdale 2WAL H2 2017 Unclear FTTN 900

Wallerrawang Planned Jul-Dec 2018

Beechwood 2WAU Q4 2016 Build comm May 2017 FTTN 3400

Crosslands Build comm May 2017

King Creek Build prep Apr-Jun 2017

Rosewood Unclear

Wauchope Build comm Jul 2017

Cabramatta West 2WET H1 2017 Planned Jul-Dec 2018 HFC 12100

Fairfield West Available / Build comm Mar 2017

Prairiewood Available / Build comm Mar 2017

Smithfield Planned Jul-Sep 2017

Wakeley Build comm Feb 2017

Wetherill Park Planned Jul-Sep 2017

Freemans Reach 2WFC H1 2017 Planned Jul-Dec 2018 FTTC FTTN 2300

Glossodia Planned Jul-Dec 2018 FTTC

Wilberforce Planned Jul-Dec 2018 FTTC

Arrawarra 2WGL H1 2017 Planned Jul-Dec 2018 FTTN 6700Aarrawarra Headland Planned Jul-Dec 2018

Corindi Beach Planned Jul-Dec 2018

Emerald Beach Planned Jul-Dec 2018

Moonee Beach Planned Jul-Dec 2018

Mullaway Planned Jul-Dec 2018

Safety Beach Planned Jul-Dec 2018

Sandy Beach Planned Jul-Dec 2018

Woolgoolga Planned Jul-Dec 2018

Castle Cove 2WIL H2 2017 Planned Jan-Jun 2019 HFC 4600

Middle Cove Planned Jan-Jun 2019

North Willoughby Planned Jan-Jun 2019

Roseville Planned Jan-Jun 2019

iTnews’ reconstructed NBN three-year plan 40

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 41: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

39

Roseville Chase Planned Jan-Jun 2019

Walgett 2WLE H1 2017 Planned Jan-Jun 2018 FTTN 800

Walcha 2WLH H2 2017 Planned Jan-Jun 2018 FTTN 1500

Fern Bay 2WLL Q4 2016 Build comm / Pl Mar 2017 / 2020 FTTN 2700

Fullerton Cove Build comm Mar 2017

Kooragang Build comm Mar 2017

Stockton Planned Mar 2017

Anna Bay 2WLL Q1 2017 Planned FW 820

Fullerton Cove Planned

Salt Ash Planned

Swan Bay Planned

Warialda 2WRD H2 2017 Planned Jan-Jun 2018 FTTC FTTN 700

Normanhurst 2WRO H1 2018 Planned Jul-Dec 2018 HFC 10000

North Wahroonga Planned Jul-Dec 2018

Wahroonga Planned Jul-Dec 2018

Waitara Planned Jul-Dec 2018

Warrawee Planned Jan-Jun 2018

Ravenswood 2WRR Q1 2017 Planned Jul-Sep 2017 FTTN 900

Warren Planned Jul-Sep 2017

Werris Creek 2WSC H2 2017 Planned Jul-Dec 2018 FTTN 700

Wee Waa 2WWA H2 2017 Planned Jan-Jun 2018 FTTN 900

West Wyalong 2WWY Q4 2016 Build comm Apr 2017 FTTN 1700

Wyalong Build comm Apr 2017

Cooranbong 2WYO Q1 2017 Planned FW 2190

Dooralong Planned

Eraring Planned

Jilliby Planned

Kulnura Build comm

Mandalong Planned

Mangrove Mountain Planned

Mooney Mooney Planned

Mount White Planned

iTnews’ reconstructed NBN three-year plan 41

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 42: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

40

Somersby Build comm

Tangy Dangy Unclear

Wallarah Planned

Wyee Planned

Wyong Planned

Binalong 2YAS Sep 2015 Available FW 820

Mt Bowning Available

Mt Manton Build comm

Angourie 2YMB H1 2018 Planned Jan-Jun 2019 FTTN 5400

Freeburn Island Flipped Jan-Jun 2019 FTTC

Iluka Flipped Jan-Jun 2019 FTTC

Wooloweyah Flipped Jan-Jun 2019 FTTC

Yamba Flipped Jan-Jun 2019 FTTC

Apollo Bay 3ABA Q1 2017 Planned FW 310

Skenes Creek Unclear

Altona 3ALT H2 2016 Planned Jan-Jun 2019 HFC 5900

Seaholme Planned Jan-Jun 2019

Ararat 3ARA H1 2017 Planned Jan-Jun 2018 FTTC/N FTTN 3700

Aireys Inlet 3ASE Feb 2016 Planned Oct-Dec 2017 FTTN 5000

Anglesea Available

Fairhaven Planned Oct-Dec 2017

Avoca 3AVO H2 2017 Planned Jul-Dec 2018 FTTN 600

Alexandra 3AXD H1 2017 Planned Jan-Jun 2018 FTTN 1400

Bacchus Marsh 3BAC Q4 2016 Build comm FW 870

Bullengarook Build comm

Dales Creek Planned

Darley Build comm

Mt Blackwood Unclear

Myrniong Build comm

Bairnsdale 3BAI H1 2017 Planned Jan-Jun 2018 FTTN 6900

East Bairnsdale Planned Jan-Jun 2018

Eastwood Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 42

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 43: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

41

Lucknow Planned Jan-Jun 2018

Wy Yung Planned Jan-Jun 2018

Bayswater 3BAY H1 2017 Planned Jan-Jun 2018 HFC 22600

Bayswater North Planned Jan-Jun 2018

Boronia Planned Jan-Jun 2019

Heathmont Planned Oct-Dec 2017

The Basin Planned Jan-Jun 2019

Bayswater 3BAY H1 2017 Planned Apr-Jun 2017 FTTN 1200

Bundoora 3BDR H2 2016 Planned Jan-Jun 2019 HFC 6900

Kingsbury Planned Jul-Dec 2018

Bundoora 3BDR H2 2017 Planned Jan-Jun 2019 FTTN 600

Attwood 3BDW H2 2017 Planned Jul-Dec 2018 HFC 11200

Broadmeadows Planned Jul-Dec 2018

Coolaroo Planned Jul-Dec 2018

Dallas Planned Jul-Dec 2018

Jacana Planned Jul-Dec 2018

Meadow Heights Planned Jul-Dec 2018

Westmeadows Planned Jul-Dec 2018

Attwood 3BDW H2 2017 Planned Jan-Jun 2018 FTTN 10100

Campbellfield Planned Jan-Jun 2019 FTTC/N

Greenvale Planned Jan-Jun 2018

Meadow Heights Planned Jan-Jun 2018

Oaklands Junction Flipped? FW

Belgrave 3BEL H1 2018 Planned Jul-Dec 2018 FTTC/N FTTN 7600

Belgrave Heights Planned Jul-Dec 2018

Belgrave South Planned Jul-Dec 2018

Ferny Creek Planned Jul-Dec 2018

Kallista Planned Jul-Dec 2018

Sassafras Planned Jul-Dec 2018

Selby Planned Jul-Dec 2018

Sherbrooke Planned Jul-Dec 2018

Tecoma Planned Jul-Dec 2018 FTTC/N

iTnews’ reconstructed NBN three-year plan 43

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 44: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

42

Upwey Planned Jul-Dec 2018 FTTC/N

Bendigo 3BEN Q3 2016 Build comm May 2017 FTTN 34200

Big Hill Build comm Jun 2017

East Bendigo Build comm No date

Flora Hill Build comm No date

Golden Gully Build comm Jun 2017

Golden Square Build comm May 2017

Ironbark Build comm Mar 2017

Junortoun Build comm Feb 2017

Kangaroo Flat Build comm Feb 2017

Kennington Build comm Jun 2017

Long Gully Build comm May 2017

North Bendigo Build comm Mar 2017

Quarry Hill Build comm Jun 2017

Spring Gully Build comm No date

Strathdale Build comm Feb 2017

Strathfieldsaye Build comm May 2017

West Bendigo Build comm May 2017

White Hills Build comm Mar 2017

Junortoun 3BEN Q1 2017 Planned FW 560

Beaconsfield 3BEW Q4 2016 Build comm Sep 2017 FTTN 18300

Beaconsfield Upper Build comm Sep 2017

Berwick Build comm Jun 2017

Guys Hill Planned Jul-Sep 2017

Beaufort 3BFO H2 2017 Planned Jan-Jun 2018 FTTN 700

Bright 3BGH H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 2100

Porepunkah Planned Jul-Dec 2018

Brighton 3BGO H2 2016 Planned Oct-Dec 2017 HFC 15800

Brighton East Planned Jul-Dec 2018

Gardenvale Planned Jul-Dec 2018

Blairgowrie 3BLA Q4 2016 Build comm May 2017 FTTN 9300

Portsea Build comm Jun 2017

iTnews’ reconstructed NBN three-year plan 44

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 45: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

43

Sorrento Build comm May 2017

Blackburn 3BLB H1 2017 Planned Jul-Sep 2017 HFC 16500

Blackburn North Planned Oct-Dec 2017

Blackburn South Planned Jul-Sep 2017

Forest Hill Planned Apr-Jun 2017

Nunawading Planned Jan-Jun 2018

Nunawading 3BLB H2 2017 Unclear FTTN 900

Belmont 3BMT Q1 2017 Flipped Jul-Dec 2018 FTTC FTTN 23200

Connewarre Build comm No date

Grovedale Planned Jan-Jun 2018

Highton Planned Jul-Dec 2018 FTTC/N

Marshall Planned Jan-Jun 2018

Mount Duneed Flipped? FW BC

Wandana Heights Planned Jan-Jun 2018

Waurn Ponds Planned Jan-Jun 2018

Benalla 3BNL H1 2017 Planned Jul-Dec 2018 FTTC/N FTTN 5000

Bentleigh 3BNT H1 2016 Planned Jul-Dec 2018 HFC 18500

Caulfield South Build comm Jun 2017

Glen Huntly Build comm Jun 2017

McKinnon Build comm Jun 2017

Ormond Build comm Jun 2017

Box Hill 3BOX H1 2018 Planned Apr-Jun 2017 HFC 20600

Box Hill North Planned Jan-Jun 2018

Box Hill South Planned Jan-Jun 2019

Mont Albert Planned Jan-Mar 2018

Mont Albert North Planned Jan-Mar 2018

Surrey Hills Planned Jan-Mar 2018

Kilmore East 3BRF Q1 2017 Build comm FW 360

Sunday Creek Build comm

Box Hill South 3BUR H1 2017 Planned Jan-Jun 2019 HFC 10800

Burwood Planned Jan-Jun 2019

Beaconhills 3BWK Q1 2017 Planned FW 620

iTnews’ reconstructed NBN three-year plan 45

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 46: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

44

Nar Nar Goon North Build comm

Officer Planned

Pakenham Upper Planned

Beechworth 3BWT H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 1600

Balwyn 3CAN H1 2016 Available / Planned Now / Jul-Dec 2018 HFC 10700

Canterbury Available / Planned Now / Jan-Mar 2018

Surrey Hills Available / Planned Now / Jan-Mar 2018

Barooga 3CBM H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 3500

Cobram Planned Jul-Dec 2018 FTTC/N

Botanic Ridge 3CBN Q1 2017 Planned FW 2270

Cardinia Planned

Clyde North Planned

Devon Meadows PlannedDevon Meadows North Planned

Harkaway Planned

Narre Warren East Planned

Pearcedale Planned

Tooradin North Planned

Botanic Ridge 3CBN H2 2017 Planned Jan-Jun 2018 FTTN 4800

Clyde Planned Jan-Jun 2018 FTTC

Cranbourne Planned Jan-Jun 2018

Cranbourne East Planned Jan-Jun 2018 FTTC

Cranbourne West Planned Jan-Jun 2018

Devon Meadows Flipped FW planned

Coburg 3CBR H2 2016 Planned Jul-Dec 2018 FTTC HFC 13200

Coburg North Planned Jul-Dec 2018

Pascoe Vale Planned Jan-Jun 2018

Pascoe Vale South Planned Jan-Jun 2018

Coburg North 3CBR H2 2017 Planned Jul-Dec 2018 FTTC FTTN 1400

Charlton 3CHA H2 2017 Planned Jan-Jun 2018 FTTN 700

Churchill 3CHH Q4 2016 Build comm Mar 2017 FTTN 2100

Chiltern 3CHT H2 2017 Flipped? FW BC FTTN 600

iTnews’ reconstructed NBN three-year plan 46

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 47: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

45

Ashwood 3CLA H1 2017 Available / Planned Now / Apr-Jun 2017 HFC 25800

Chadstone Planned Jan-Jun 2018

Clarinda Planned Jan-Jun 2018

Clayton Planned Jan-Jun 2019

Clayton South Build comm / Planned Jun 2017 / Jan-Jun 2018

Huntingdale Planned Jan-Jun 2019

Mount Waverley Planned Jan-Mar 2018

Oakleigh East Planned Jan-Jun 2019

Clayton 3CLA H1 2018 Planned Jan-Jun 2019 FTTN 1100

Coleraine 3CLN Q1 2017 Build prep Apr-Jun 2017 FTTN 700

Clunes 3CLU Q3 2016 Build comm Feb 2017 FTTN 900

Camperdown 3CMP H1 2017 Planned Oct-Dec 2017 FTTN 1700

Pomborneit 3COB Nov 2015 Planned FW 110

Cobden 3COB Q1 2017 Build prep Oct-Dec 2017 FTTN 900

Cohuna 3COH Q1 2017 Planned Oct-Dec 2017 FTTN 1100

Corinella 3CRI Q4 2016 Build comm Apr 2017 FTTN 2500

Coronet Bay Build comm Apr 2017

Grantville Build comm Apr 2017

Pioneer Bay Build comm Apr 2017

Tenby Point Build comm Apr 2017

Croydon Hills 3CRO H2 2017 Planned Jul-Dec 2018 FTTC FTTN 1000

Croydon North Planned Jul-Dec 2018 FTTC

Croydon South Planned Jul-Dec 2018 FTTC

Kilsyth Planned Jan-Jun 2019 / 2020 FTTC

Kilsyth South Planned Jan-Jun 2018 or 2019 FTTC

Croydon Planned Jul-Dec 2018 FTTC

Croydon 3CRO H2 2018 Planned Jul-Dec 2018 HFC 18400

Croydon Hills Planned Jul-Dec 2018

Croydon North Planned Jan-Jun 2019

Croydon South Planned Jul-Dec 2018

Kilsyth Planend Jul-Dec 2018

Corryong 3CRY H2 2017 Planned Jan-Jun 2018 FTTN 700

iTnews’ reconstructed NBN three-year plan 47

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 48: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

46

Chelsea Heights 3CSE H2 2017 Planned Jan-Jun 2019 FTTC FTTN 500

Bonbeach 3CSE H2 2018 Planned Jan-Jun 2019 HFC 13200

Carrum Planned Jan-Jun 2019

Chelsea Planned Jan-Jun 2019

Chelsea Heights Planned Jan-Jun 2019

Edithvale Planned Jan-Jun 2019

Patterson Lakes Planned Jan-Jun 2019

Casterton 3CST H2 2017 Planned Jan-Jun 2018 FTTN 900

Beaumaris 3CTA H1 2017 Planned Jul-Dec 2018 HFC 20600

Black Rock Planned Jul-Dec 2018

Cheltenham Build comm Aug 2017

Mentone Build comm Jun 2017

Moorabbin Airport 3CTA H1 2018 Planned Jan-Jun 2018 FTTN 600

Fitzroy 3CWO H1 2018 Planned Jan-Jun 2019 FTTN 2100

Abbotsford 3CWO H1 2018 Planned Jan-Jun 2019 HFC 15200

Collingwood Planned Jan-Jun 2019

East Melbourne Planned Jan-Jun 2019

Fitzroy Planned Jan-Jun 2019

Dandenong 3DAD H2 2017 Planned Jan-Jun 2018 HFC 20200

Dandenong North Planned Jan-Mar 2018

Doveton Planned Apr-Jun 2017

Eumemmerring Planned Apr-Jun 2017

Dandenong South 3DAD H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 7500

Hallam Planned Jan-Jun 2018 FTTC

Rowville 3DAN H2 2017 Planned Jan-Mar 2018 FTTC/N FTTN 4300

Dimboola 3DBL H2 2017 Flipped FW BC FTTN 800

Doncaster East 3DNC H2 2017 Build comm Mar 2017 HFC 16800

Donvale Planned Apr-Jun 2017

Templestowe Planned Jan-Jun 2019

Donald 3DON H2 2017 Flipped FW BC FTTN 600

Balwyn 3DPD H1 2016 Available / Planned Now / Jul-Dec 2018 HFC 12000

Balwyn North Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 48

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 49: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

47

Deepdene Planned Jul-Dec 2018

Kew East Planned Jul-Dec 2018

Arthurs Seat 3DRO Q2 2016 Build comm Feb 2017 FTTN 8000

Dromana Build comm Feb 2017

Safety Beach Build comm Mar 2017

Sunshine West Planned Jan-Mar 2018

Burnside 3DRP H2 2017 Planned Jul-Dec 2018 FTTN 17800

Cairnlea Planned Jul-Dec 2018

Caroline Springs Planned Jul-Dec 2018

Derrimut Planned Jul-Dec 2018

Mount Cottrell Unclear

Rockbank Planned Jan-Jun 2018

Daylesford 3DYL Q3 2016 Build comm May 2017 FTTN 2800

Hepburn Build comm May 2017

Hepburn Springs Build comm May 2017

Musk Flipped? FW planned

California Gully 3EAH H1 2017 Planned Jan-Jun 2018 FTTC/N FTTN 7000

Eaglehawk Planned Jan-Jun 2018 FTTC/N

Jackass Flat Planned Jan-Jun 2018 FTTC/N

Maiden Gully Planned Jan-Jun 2018 FTTC

Marong Planned Jan-Jun 2018

Myers Flat Unclear

Sailors Gully Planned Jan-Jun 2018 FTTC

Echuca 3ECH Q4 2016 Build comm Apr 2017 FTTN 9700

Moama Build comm Jul 2017

Edenhope 3EDE H2 2017 Planned Jan-Jun 2018 FTTC FTTN 500

Eildon 3ELD H2 2017 Flipped? FW FTTN 600

Elmore 3ELM Q1 2017 Planned Jul-Sep 2017 FTTN 500

Eltham 3ELT H2 2017 Planned Apr-Jun 2017 HFC 10300

Eltham North Planned Apr-Jun 2017

Lower Plenty Planned Jan-Jun 2019

Montmorency Planned Jan-Jun 2019

iTnews’ reconstructed NBN three-year plan 49

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 50: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

48

Research 3ELT H1 2018 Planned Jan-Jun 2018 FTTN 1800

Avonsleigh 3EML Q1 2017 Planned Jul-Sep 2017 FTTN 6700

Clematis Planned Jul-Sep 2017

Cockatoo Planned Oct-Dec 2017

Emerald Planned Jul-Sep 2017

Gembrook Planned Oct-Dec 2017

Kallista Planned Jul-Dec 2018

Menzies Creek Planned Jul-Sep 2017

Monbulk Planned Oct-Dec 2017

The Patch Planned Oct-Dec 2017

Endeavour Hills 3END H1 2016 Build comm Jun 2017 HFC 7600

Lysterfield South 3END H2 2017 Unclear FTTN 2400

Narre Warren North Planned Jul-Dec 2018

Epping 3EPP H2 2017 Planned Jan-Jun 2018 FTTC FTTN 6100

Wollert Unclear

Ascot 3EPS H2 2017 Planned Jul-Dec 2018 FTTN 3400

Epsom Planned Jul-Dec 2018 FTTC

Huntly Planned Jul-Dec 2018 FTTC/N

White Hills Build comm Mar 2017

Euroa 3EUR H1 2017 Planned Jan-Jun 2018 FTTN 1700

Melbourne 3EXH Q4 2016 Planned Oct-Dec 2017 FTTN 11900

Melbourne 3EXH H2 2017 Planned Jan-Jun 2018 HFC 9300

McCrae 3FIN H1 2017 Planned Jan-Jun 2018 FTTN 15300

Rosebud Planned Jan-Jun 2018

Rosebud West Planned Jan-Jun 2018

Glenroy 3FKN H2 2016 Planned Jan-Jun 2019 FTTC HFC 15800

Hadfield Planned Jan-Jun 2019 FTTC

Oak Park Planned Jan-Jun 2019 FTTC

Pascoe Vale Planned Jan-Jun 2018 / Jan-Jun 2019 FTTC

Campbellfield 3FKN H2 2017 Planned Jan-Jun 2019 FTTC/N FTTN, FTTP 2900

Ferntree Gully 3FNT H2 2016 Build comm / Planned Jun 2017 HFC 13900

Lysterfield Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 50

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 51: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

49

Tremont Build comm May 2017Upper Ferntree Gully Available

Lysterfield 3FNT H2 2017 Planned Jan-Jun 2018 FTTN 1000

Foster 3FOS Q1 2017 Build comm Apr 2017 FTTN 700

Frankston 3FRT H2 2016 Planned Jan-Jun 2019 FTTC HFC 10800

Frankston South Planned Jan-Jun 2018 FTTC

Frankston 3FRT H2 2017 Planned Jan-Jun 2019 FTTC FTTN 2600

Footscray 3FSR H2 2016 Planned Jul-Dec 2018 FTTC/N HFC 10400

Maidstone Planned Jul-Dec 2018

West Footscray Planned Jul-Dec 2018 FTTC

Footscray 3FSR H1 2018 Planned Jul-Dec 2018 FTTC FTTN 1600

Kingsville Unclear

Seddon Unclear

Tottenham Build comm Mar 2017

West Footscray Planned Jul-Dec 2018 FTTC

Yarraville Unclear

Ascot Vale 3FTO H1 2017 Planned Jan-Jun 2019 HFC 24100

Flemington Planned Jan-Jun 2019

Kensington Planned Jan-Jun 2019

Moonee Ponds Planned Jan-Jun 2019

Travancore Planned Jan-Jun 2019

Kensington 3FTO H1 2018 Planned Jan-Jun 2019 FTTN 1800

Bunyip 3GAR Feb 2016 Build comm Feb 2017 FTTN 2200

Garfield Build comm Feb 2017

Longwarry Build comm Feb 2017

Briar Hill 3GBR H1 2017 Planned Jan-Jun 2019 HFC 19000

Greensborough Planned Jan-Jun 2019

Lower Plenty Planned Jan-Jun 2019

Macleod Planned Jan-Jun 2019

Montmorency Planned Jan-Jun 2019

Plenty Planned Jan-Jun 2019

St Helena Planned Jan-Jun 2019

iTnews’ reconstructed NBN three-year plan 51

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 52: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

50

Watsonia Planned Jan-Jun 2019

Watsonia North Planned Jan-Jun 2019

Yallambie Planned Jan-Jun 2019

Greensborough 3GBR H1 2018 Planned Jan-Jun 2019 FTTN 800

Bell Park 3GEE Q3 2016 Planned Jul-Dec 2018 FTTC/N FTTN 30300

Bell Post Hill Planned Jul-Dec 2018 FTTC/N

Breakwater Planned Jul-Dec 2018 FTTC/N

Drumcondra Planned Jul-Dec 2018 FTTC/N

East Geelong Planned Jul-Dec 2018 FTTC/N

Geelong Planned Apr 2017 / Jul-Dec 2018 FTTC/N

Geelong West Planned Jul-Dec 2018 FTTC/N

Hamlyn Heights Planned Jul-Dec 2018

Herne Hill Planned Jul-Dec 2018

Manifold Heights Planned Jul-Dec 2018 FTTC/N

Newtown PLanned Jul-Dec 2018 FTTC/N

North Geelong Planned Jan-Jun 2019

South Geelong Planned Jul-Dec 2018 FTTC/N

Thomson Planned Jul-Dec 2018

Camberwell 3HAW H2 2016 Planned Jan-Jun 2019 HFC 20300

Hawthorn Planned Jul-Dec 2018

Hawthorn East Planned Jan-Jun 2019

Alphington 3HDB H2 2017 Planned Jul-Sep 2017 HFC 26200

Bellfield Planned Jan-Jun 2018

Eaglemont Planned Jan-Jun 2018 FTTC, HFC

Heidelberg Planned Jan-Jun 2019 FTTC

Heidelberg Heights Planned Jan-Jun 2019 FTTC

Heidelberg West Planned Jan-Jun 2019 FTTC

Ivanhoe Planned Jan-Jun 2018

Ivanhoe East Planned Jan-Jun 2018

Rosanna Planned Jan-Jun 2019 FTTC

Viewbank Planned Jan-Jun 2019 FTTC

Yallambie Planned Jan-Jun 2019 FTTC, HFC

iTnews’ reconstructed NBN three-year plan 52

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 53: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

51

Macleod 3HDB H1 2018 Planned Jan-Jun 2019 FTTN 1800

Heathcote 3HEA H2 2017 Planned Jan-Jun 2018 FTTN 1200

Black Rock 3HGT H1 2016 Planned Apr-Jun 2017 HFC 22800

Hampton Planned Apr-Jun 2017

Hampton East Available

Highett Build comm May 2017

Moorabbin Available

Sandringham Planned Apr-Jun 2017

Moorabbin 3HGT H1 2018 Build comm Mar 2017 FTTN 2400

Hamilton 3HMO Q1 2017 Build comm Jul 2017 FTTN 4900

Horsham 3HRS Q1 2017 Planned Oct-Dec 2017 FTTN 7800

Nutfield 3HUR Q1 2017 Build comm FW 630

Yarrambat Build comm

Diamond Creek 3HUR H1 2017 Planned Oct-Dec 2017 FTTN 5600

Hurstbridge Planned Oct-Dec 2017

Wattle Glen Planned Oct-Dec 2017

Heywood 3HYW Q1 2017 Planned Jul-Sep 2017 FTTN 800

Kinglake 3KAK Q4 2016 Build comm Mar 2017 FTTN 1100

Kinglake Central Build comm Mar 2017

Kinglake West Build comm Mar 2017

Arthurs Creek 3KAK Q1 2017 Planned FW 1160

Flowerdale North Build comm

Hazeldene South Build comm

Hazeldene West Build comm

Kinglake Central PlannedPheasant Creek West Planned

Queenstown Planned

Smiths Gully East Planned

Kerang 3KER Jan 2016 Available FW 340

Koroop Available

Tragowel Available

Kerang 3KER Q1 2017 Planned Jul-Sep 2017 FTTN 2000

iTnews’ reconstructed NBN three-year plan 53

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 54: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

52

Kew East 3KEW H1 2016 Planned Jul-Dec 2018 HFC 7300

Noble Park 3KEY H1 2018 Planned Apr-Jun 2017 HFC 4500

Springvale South Planned Jan-Mar 2017

Keysborough 3KEY H1 2018 Planned Jul-Dec 2018 FTTN 1500

Noble Park Unclear

Springvale South Planned Jul-Dec 2020

Waterways Planned Jan-Jun 2018 FTTC

Albanvale 3KGP H2 2017 Planned Apr-Jun 2017 / Jul-Sep 2017 HFC 24200

Delahey Planned Jan-Jun 2018

Kealba Planned Apr-Jun 2017 / 2020

Keilor Downs Planned Apr-Jun 2017

Kings Park Planned Apr-Jun 2017

St Albans Planned Apr-Jun 2017 / 2020

Keilor 3KLO H2 2017 Planned Jan-Jun 2019 HFC 3100

Keilor East Planned Jul-Dec 2020

Keilor East 3KLO H2 2017 Planned Jan-Jun 2019 FTTC/N FTTN 600

Koroit 3KOR H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 800

Kyabram 3KYA Q1 2017 Build comm Sep 2017 FTTN 3700

Balaclava 3KYG H1 2016 Planned Jan-Jun 2019 HFC 17100

Caulfield North Planned Oct-Dec 2017

Kooyong Planned Jan-Jun 2018

Malvern Planned Jan-Mar 2018

St Kilda East Planned Jan-Jun 2018

Toorak Planned Jan-Jun 2018

Avalon 3LAR Q3 2016 Build comm Feb 2017 FTTN 17700

Corio Planned Jan-Jun 2019

Lara Build comm Feb 2017

Lovely Banks Build comm No date

Norlane Planned Jan-Jun 2019

North Shore Planned Jan-Jun 2019

Batesford 3LAR Q1 2017 Build comm FW 4050

Bell Post Hill Build comm

iTnews’ reconstructed NBN three-year plan 54

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 55: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

53

Gnarwarre Planned

Inverleigh Planned

Lara Planned

Lethbridge Planned

Little River Planned

Little River South Planned

Lovely Banks Build comm

Meredith Planned

Mt Cottrell Planned

Teesdale Build comm

Werribee North Planned

Werribee South Planned

Korumburra 3LEO Q1 2017 Planned Jul-Sep 2017 FTTN 4700

Leongatha Build comm Oct 2017

Lang Lang 3LGL Q1 2017 Build comm Mar 2017 FTTN 600

Chirnside Park 3LIL H2 2016 Planned Jan-Jun 2019 HFC 14100

Croydon North Planned Jan-Jun 2019

Lilydale Planned Jan-Jun 2018 FTTC

Mooroolbark Planned Jan-Jun 2019

Coldstream 3LIL H2 2017 Planned Jan-Jun 2018 FTTN 5200

Lilydale Planned Jan-Jun 2019

Kalimna 3LKE Q1 2017 Planned Oct-Dec 2017 FTTN 6300

Lake Bunga Planned Jul-Sep 2017

Lake Tyers Beach Flipped FW planned

Metung Planned Jul-Sep 2017

Docklands 3LON Q3 2016 Planned Jan-Jun 2019 FTTN 16500

Melbourne Planned Jul-Dec 2018 FTTB

Docklands 3LON H2 2017 Planned Jan-Jun 2019 FTTB HFC 8200

Loch Sport 3LSP H1 2017 Unclear FTTN 2400

Altona Meadows 3LTV H2 2016 Planned Jan-Jun 2019 FTTC HFC 9000

Laverton North 3LTV H2 2017 Planned Jan-Jun 2019 FTTC FTTN 6300

Truganina Unclear

iTnews’ reconstructed NBN three-year plan 55

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 56: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

54

Williams Landing Planned Jan-Jun 2019

Bangholme 3LYN Q1 2017 Planned Jan-Jun 2019 FTTC FTTN 15100

Dandenong South Build comm Sep 2017

Hampton Park Build comm Sep 2017

Lynbrook Build comm Jul-Sep 2017

Lyndhurst Build comm Jul-Sep 2017

Carisbrook 3MAB H1 2017 Planned Jan-Jun 2018 FTTN 4700

Maryborough Planned Jan-Jun 2018

Gisborne 3MAD Q2 2016 Build comm Feb 2017 FTTN 7000

Macedon Build comm / Planned Mar 2017 / Oct-Dec 2017

New Gisborne Build comm Feb 2017

Riddells Creek Planned Oct-Dec 2017

Woodend Build comm Mar 2017

Maidstone 3MAI H2 2017 Planned Jan-Jun 2019 HFC 7500

Maribyrnong Planned Jan-Jun 2019

Maribyrnong 3MAI H2 2017 Planned Jan-Jun 2019 FTTN 700

Mount Beauty 3MBE H2 2017 Planned Jan-Jun 2018 FTTN 1100

Tawonga South Planned Jan-Jun 2018

Mallacoota 3MCT H2 2017 Planned Jan-Jun 2018 FTTN 1100

Aspendale 3MDC H1 2017 Planned Jan-Jun 2019 HFC 18700

Aspendale Gardens Planned Jan-Jun 2019

Clarinda Planned Jul-Dec 2018

Dingley Village Planned Jul-Dec 2018

Heatherton Planned Jan-Jun 2018 FTTC/N/P

Mordialloc Planned Jan-Jun 2019

Parkdale Planned Jan-Jun 2019

Aspendale Gardens 3MDC H1 2018 Planned Jan-Jun 2018 FTTC FTTN 4200

Braeside Planned Jan-Jun 2018 FTTC/N

Dingley Village Planned Jan-Jun 2018 FTTC/N

Moorabbin Airport Planned Jan-Jun 2018 FTTC/N

Buronga 3MDU H1 2018 Planned Jul-Dec 2018 FTTN 19400

Cabarita Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 56

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 57: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

55

Gol Gol Planned Jul-Dec 2018

Irymple Planned Jul-Dec 2018 FTTC

Merbein Planned Jul-Dec 2018 FTTC

Mildura Planned Jul-Dec 2018 FTTC

Doreen 3MER Q1 2017 Planned Jul-Sep 2017 FTTN 9200

Mernda Build comm Jun 2017

Goughs Bay 3MFL Feb 2016 Available FW 350

Strathbogie South Planned

Mansfield 3MFL H2 2017 Flipped Jan-Jun 2018 FTTC/N FTTN 1900

Donvale 3MIT H2 2017 Build comm Mar 2017 HFC 13300

Mitcham Planned Jan-Jun 2018

Vermont Planned Apr-Jun 2017

Mitcham 3MIT H2 2017 Unclear FTTN 600

Maldon 3MLD H2 2017 Planned Jan-Jun 2018 FTTN 900

Brunswick West 3MLN H1 2017 Planned Jan-Mar 2018 HFC 14700

Coburg Planned Oct-Dec 2017

Pascoe Vale South Planned Oct-Dec 2017

Brunswick 3MLN H1 2018 Planned Jul-Dec 2018 FTTN 1800

Melton South 3MLT H2 2016 Unclear HFC 900

Brookfield 3MLT H1 2018 Build comm Aug 2018 FTTN 1500

Kurunjang Build comm No date

Melton Build comm No date

Melton South Build comm No date

Melton West Build comm Aug 2018

Leopold 3MOO Q3 2016 Build comm Feb 2017 FTTN 12000

Moolap Build comm Feb 2017

Newcomb Planned Jan-Jun 2019

St Albans Park Planned Jan-Jun 2019 FTTC/N

Whittington Planned Jan-Jun 2019

Bellbrae 3MOO Q1 2017 Planned FW 3740

Ceres Build comm

Drysdale Planned

iTnews’ reconstructed NBN three-year plan 57

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 58: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

56

Gherang Planned

Leopold Planned

Marcus Hill Planned

Moolap Planned

Moriac Planned

Mt Duneed Build comm

Mt Duneed North Build comm

Torquay East Planned

Wallington Planned

Mornington 3MOR Q3 2016 Build comm Feb 2017 FTTN 16900

Mount Martha Build comm May 2017

Frankston South 3MTE H2 2016 Planned Jan-Jun 2018 FTTC HFC 800

Baxter 3MTE H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 4200

Frankston South Planned Jan-Jun 2018 FTTC

Langwarrin South Planned Jan-Jun 2018 FTTC/N

Mount Eliza Planned Jan-Jun 2018 FTTC/N

Mortlake 3MTK H1 2017 Planned Oct-Dec 2017 FTTN 700

Don Valley East 3MTR Q1 2017 Planned FW 3210

Gembrook South Planned

Gladysdale North Planned

Gruyere South PlannedHoddles Creek South Planned

Macclesfield Planned

Monbulk East Planned

Seville Planned

Seville East Planned

Silvan North Planned

Silvan South Planned

Steels Creek East Planned

Woori Yallock South Planned

Kalorama 3MTR H2 2017 Planned Jan-Jun 2019 FTTN 7800

Montrose Planned Jan-Jun 2019 FTTC/N

iTnews’ reconstructed NBN three-year plan 58

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 59: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

57

Mount Dandenong Planned Jan-Jun 2019

Mount Evelyn Planned Jan-Jun 2019 FTTC/N

Olinda Planned Jan-Jun 2019 FTTC/N

Montrose 3MTR H2 2018 Planned Jan-Jun 2019 HFC 2500

Myrtleford 3MYF H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 1400

Nagambie 3NAG H2 2017 Planned Jan-Jun 2018 FTTN 1100

Nathalia 3NAT H1 2017 Planned FW BC FTTN 800

Cranbourne North 3NAW Q3 2016 Build comm Sep 2017 FTTN 12000

Narre Warren South Build comm Jul 2017

Cranbourne North 3NAW H2 2016 Unclear HFC 11700

Narre Warren Planned Jul-Sep 2017

Balwyn North 3NBA H1 2017 Planned Jul-Dec 2018 HFC 25300

Bulleen Planned Oct-Dec 2017

Doncaster Planned Jan-Mar 2017

Templestowe Lower Planned Oct-Dec 2017

Clifton Hill 3NCO H1 2017 Planned Oct-Dec 2017 HFC 22300

Fairfield Planned Jul-Sep 2017

Fitzroy North Planned Apr-Jun 2017

Northcote Finalising Jul-Sep 2017

Aberfeldie 3NES H2 2016 Available HFC 20700

Avondale Heights Available

Essendon Available / Planned some FTTC

Essendon North Planned Jan-Jun 2019 FTTC

Essendon West Planned Jan-Jun 2019

Keilor East Planned Jan-Jun 2019

Niddrie Planned Jan-Jun 2019 FTTC

Strathmore Planned Jan-Jun 2019

Essendon Fields 3NES H2 2017 Planned Jan-Jun 2019 FTTN 900

Nhill 3NHI H2 2017 Planned Jan-Jun 2018 FTTC FTTN 1000

Melbourne 3NME H1 2018 Planned Jan-Jun 2018 FTTN 2600

North Melbourne 3NME H2 2018 Planned Jan-Jun 2019 HFC 13200

West Melbourne Unclear

iTnews’ reconstructed NBN three-year plan 59

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 60: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

58

Numurkah 3NMK Q1 2017 Build prep Jul-Sep 2017 FTTN 2100

Brooklyn 3NPR Q3 2016 Build comm Feb 2017 FTTN 10600

Tottenham Build comm Feb 2017

Williamstown Available

Williamstown North Build comm Jan 2017

Altona North 3NPR H2 2016 Planned Jan-Jun 2019 FTTC HFC 13500

Brooklyn Planned Jan-Jun 2019

Newport Planned Jan-Jun 2019 FTTC

South Kingsville Planned Jan-Jun 2019 FTTC

Spotswood Planned Jan-Jun 2019 FTTC

Williamstown North Unclear

Malvern East 3OAK H1 2018 Unclear FTTN 700

Carnegie 3OAK H1 2018 Planned Jul-Seo 2017 HFC 15700

Hughesdale Planned Jan-Mar 2018

Murrumbeena Planned Apr-Jun 2017

Oakleigh Planned Jul-Dec 2018

Barwon Heads 3OCG Dec 2015 Available FTTN 13900

Breamlea Flipped FW planned

Mannerim Planned

Marcus Hill Build comm

Ocean Grove Available

Point Lonsdale Available

Queenscliff Available

Orbost 3ORB H2 2017 Planned Jan-Jun 2018 FTTN 1200

Ouyen 3OUY H1 2018 Planned Jul-Dec 2018 FTTN 700

Eagle Point 3PAY H2 2017 Planned Jul-Dec 2018 FTTN 3700

Newlands Arm Planned Jul-Dec 2018

Paynesville Planned Jul-Dec 2018

Raymond Island Planned Jul-Dec 2018

Point Cook 3PCO H1 2018 Planned Jan-Jun 2019 FTTN 11300

Seabrook Planned Jan-Jun 2019 FTTC

Albert Park 3PME H1 2017 Planned Jan-Jun 2019 HFC 13800

iTnews’ reconstructed NBN three-year plan 60

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 61: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

59

Middle Park Planned Jan-Jun 2019

Port Melbourne Planned Jan-Jun 2019

South Melbourne Planned Jan-Jun 2019

Southbank Unclear

Port Melbourne 3PME H1 2018 Planned Jan-Jun 2019 FTTC FTTN 3700

South Wharf Planned Jan-Jun 2019 FTTB

Port Fairy 3POF Q4 2016 Build comm Apr 2017 FTTN 2200

Portland 3PRL Q3 2016 Build comm Apr 2017 FTTN 5700

Portland North Build comm Apr 2017

Richmond 3RCM H2 2016 Planned Jul-Dec 2018 FTTC HFC 13000

Abbotsford 3RCM H1 2018 Planned Jul-Dec 2018 FTTC/B FTTN 6400

Burnley Planned Jul-Dec 2018 FTTC/N

Cremorne Planned Jul-Dec 2018 FTTC/N

Richmond Planned Jul-Dec 2018 FTTC/N

Rochester 3RCS Q1 2017 Build comm Jul 2017 FTTN 1500

Rosedale 3RDL Q1 2017 Flipped FW Available FTTN 600

Red Cliffs 3REF Q4 2016 Build comm Jul 2017 FTTN 1400

Kingsbury 3RES H1 2017 Planned Jul-Dec 2018 HFC 29700

Preston Planned Jul-Dec 2018

Reservoir Planned Jul-Dec 2018

Lancefield 3RMS Q2 2016 Build comm No date FTTN 2400

Romsey AvailableAshbourne North East 3RMS Q1 2017 Planned FW 1390

Lancefield North Planned

Newham North Planned

Newham South Planned

Romsey North West Planned

Woodend North Planned

Woodend South Planned

Bannerton Hill 3ROL Mar 2016 Build comm FW 390

Robinvale Build comm

Euston 3ROL Q1 2017 Build comm Jul 2017 FTTN 1300

iTnews’ reconstructed NBN three-year plan 61

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 62: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

60

Robinvale Build comm Jul 2017

Rushworth 3RUW Q1 2017 Flipped? FW available FTTN 500

Ringwood 3RWO H2 2017 Planned Jan-Jun 2018 HFC 15600

Ringwood East Planned Oct-Dec 2017

Ringwood North Planned Apr-Jun 2017

Rye 3RYE Q2 2016 Build comm Feb 2017 FTTN 13900

St Andrews Beach Build comm Mar 2017

Tootgarook Build comm Feb 2017

Mount Martha 3SAF Q4 2016 Build comm May 2017 FTTN 5000

Red Hill North 3SAF Q1 2017 Build comm FW 140

Sale 3SAL Q3 2016 Build comm Apr 2017 FTTN 7000

Knoxfield 3SCO H2 2016 Planned Jan-Jun 2019 HFC 22200

Rowville Available

Scoresby Planned Jan-Jun 2019

Wantirna Planned Apr-Jun 2017

Wantirna South Planned Apr-Jun 2017

Knoxfield 3SCO H2 2017 Planned Jan-Jun 2019 FTTN 1000

Hillside 3SDM H1 2017 Planned Jan-Jun 2019 FTTC/N FTTN 19100

Keilor Lodge Planned Jan-Jun 2019 FTTC/N

Plumpton Flipped? FW planned

Sydenham Planned Jan-Jun 2019 FTTC/N

Taylors Hill Planned Jan-Mar 2018

Taylors Lakes Planned Jan-Jun 2019 FTTC/N

Frankston North 3SEA H2 2016 Planned Jan-Jun 2019 FTTC HFC 12500

Seaford Planned Jan-Jun 2019 FTTC

Carrum Downs 3SEA H2 2017 Planned Jan-Jun 2019 FTTC/B FTTN 12400

Sandhurst Planned Jan-Jun 2019

Skye Planned Jan-Jun 2019

Alfredton 3SEB H2 2017 Planned Jul-Dec 2018 FTTN 11700

Bonshaw Planned Jul-Dec 2018

Cardigan Planned Jul-Dec 2018

Delacombe Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 62

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 63: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

61

Redan Planned Jul-Dec 2018

Sebastopol Planned Jul-Dec 2018

Seymour 3SEY H2 2017 Planned Jan-Jun 2018 FTTN 3100

Balnarring 3SHO Q2 2016 Build comm Apr 2017 FTTN 5100

Balnarring Beach Build comm Apr 2017

Flinders Build comm May 2017

Point Leo Build comm May 2017

Red Hill Build comm May 2017

Red Hill South Build comm May 2017

Shoreham Build comm May 2017

Somers Build comm Apr 2017

Arthurs Seat South 3SHO Q1 2017 Build comm FW 1850

Cape Schanck Planned

Main Ridge Build comm

Moonah Unclear

Red Hill South Planned

Shoreham Planned

Bentleigh East 3SOA H1 2017 Planned Apr-Jun 2017 HFC 13100

Oakleigh South Planned Jul-Sep 2017

Bittern 3SOM Q1 2017 Build comm Aug 2017 FTTN 14800

Crib Point Build comm Aug 2017

Hastings Build comm Jul 2017

Hmas Cerberus Build comm Aug 2017

Pearcedale Build comm Aug 2017

Somerville Build comm Aug 2011

Tyabb Build prep / Build comm Jul 2017 / Jul-Sep 2017

Devilbend 3SOM Q1 2017 Planned FW 1310

Hastings North Planned

Hastings West Planned

Merricks North Planned

Moorooduc Planned

Pearcedale West Planned

iTnews’ reconstructed NBN three-year plan 63

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 64: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

62

Tyabb Planned

Clayton South 3SPL H1 2017 Build comm Jun 2017 HFC 16800

Mulgrave Planned Apr-Jun 2017

Noble Park Planned Apr-Jun 2017

Springvale Build comm Jul-Sep 2017

Springvale South Planned Jul-Dec 2018

Springvale 3SPL H1 2018 Unclear FTTN 1900

Sandy Point 3SPT Q1 2017 Planned Jul-Sep 2017 FTTN 700

Albion 3SSN H2 2017 Planned Jan-Mar 2018 HFC 14900

Braybrook Planned Jan-Mar 2018

Sunshine Planned Jan-Mar 2018

Sunshine North Planned Jan-Mar 2018

Sunshine West Planned Jan-Mar 2018

Braybrook 3SSN H2 2017 Planned Jul-Dec 2018 FTTC FTTN 1900

Sunshine Planned Jan-Jun 2018

Sunshine North Planned Jan-Jun 2018

Sunshine West Planned Jan-Jun 2018

Albion Planned Jan-Jun 2018

St Arnaud 3STA H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 1400

Stawell 3STE H1 2017 Planned Jan-Jun 2018 FTTN 3200

Maffra 3STR Q3 2016 Build comm Mar 2017 FTTN 2700

Stratford Build comm Mar 2017

Diggers Rest 3SUN Mar 2016 Build comm Feb 2017 FTTP, FTTN 14400

Sunbury Available

Bulla 3SUN Q1 2017 Planned FW 3030

Diggers Rest Planned

Mickleham Build commMonegeetta North East Planned

Mt Holden Planned

New Gisborne PlannedNew Gisborne South Planned

Riddells Creek Planned

iTnews’ reconstructed NBN three-year plan 64

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 65: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

63

Riddells Creek North PlannedRiddells Creek West Planned

Toolern Vale Planned

Swan Hill 3SWI Q3 2016 Build comm Apr 2017 FTTN 5300

South Yarra 3SYR H1 2017 Planned Jan-Jun 2019 HFC 26700

Southbank Planned Jan-Jun 2019

Tatura 3TAT H2 2017 Planned Jan-Jun 2018 FTTC FTTN 1800

Blind Bight 3TDI Q4 2016 Build comm Apr 2017 FTTN 2500

Cannons Creek Build comm Apr 2017

Koo Wee Rup Build comm Apr 2017

Tooradin Build comm Apr 2017

Warneet Build comm Apr 2017

Terang 3TER H1 2017 Planned Oct-Dec 2017 FTTN 1000

Timboon 3TIM H1 2017 Flipped FW available FTTN 500

Tallangatta 3TLT H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 600

Preston 3TNB H2 2017 Planned Jul-Dec 2018 HFC 14300

Thornbury Planned Jul-Dec 2018

Preston 3TNB H1 2018 Planned Jul-Dec 2018 FTTN 500

Hoppers Crossing 3TNI H1 2016 Planned Mar 2017 HFC 15200

Tarneit 3TNI Q1 2017 Planned July-Sep 2017 FTTN 10700

Lalor 3TOM H1 2017 Planned Jan-Jun 2019 FTTC HFC 14800

Thomastown Planned Jan-Jun 2019 FTTC

Lalor 3TOM H1 2018 Planned Jan-Jun 2019 FTTC FTTN 1200

Blue Mountain 3TRE Q1 2017 Planned FW 710

Byers Unclear

Trentham Build comm

Burwood East 3TYH H2 2017 Planned Apr-Jun 2017 HFC 20400

Glen Waverley Planned Apr-Jun 2017

Mount Waverley Planned Jan-Mar 2-18

Vermont South Planned Jan-Jun 2018

Venus Bay 3VEN Q4 2016 Build comm Feb 2017 FTTN 2200

Seville 3WAD H2 2017 Planned Jan-Jun 2018 FTTN 1600

iTnews’ reconstructed NBN three-year plan 65

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 66: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

64

Wandin North Planned Jan-Jun 2018

Allansford 3WBO Mar 2016 Build comm Mar 2017 FTTN 14800

Dennington Build comm Mar 2017

Warrnambool Build comm Mar 2017

Bandiana 3WDG Q2 2016 Build comm No date FTTN 21400

Baranduda Available

Barnawartha North Flipped? FW available

Leneva Flipped? FW available

West Wodonga Available

Wodonga Available

Kangaroo Ground 3WDT Q1 2017 Planned FW 930

Panton Hill Planned

Warrandyte East Planned

Wonga Park North Planned

North Warrandyte 3WDT H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 4100

Warrandyte Planned Jan-Jun 2018 FTTC

Wonga Park Planned Jan-Jun 2018 FTTC/N

Lake Gardens 3WEN H2 2017 Planned Jul-Dec 2018 FTTN 8600

Lake Wendouree Planned Jul-Dec 2018

Miners Rest Planned Jul-Dec 2018

Mitchell Park Planned Jul-Dec 2018

Wendouree Planned Jul-Dec 2018

Werribee 3WER H1 2016 Build comm Oct 2017 HFC 5100

Werribee 3WER H1 2018 Build comm May 2017 FTTN 4200

Wyndham Vale Buid comm Jan-Jun 2018

Darnum 3WGU Dec 2015 Build comm Sep 2017 FTTN 13800

Drouin Build comm Sep 2017

Drouin East Unclear

Nilma Build comm Sep 2017

Warragul Build comm Sep 2017

Yarragon Build comm Sep 2017

Glen Waverley 3WHL H1 2016 Planned Apr-Jun 2017 HFC 15600

iTnews’ reconstructed NBN three-year plan 66

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 67: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

65

Notting Hill Planned Jan-Jun 2019

Wheelers Hill Available

Mulgrave 3WHL H1 2018 Planned Jan-Mar 2018 FTTN 1200

Notting Hill Planned Jan-Jun 2019

Wheelers Hill Unclear

Glen Waverley Planned Jan-Jun 2018

Winchelsea 3WIN H1 2017 Planned FW 260

Prahran 3WIR H1 2018 Planned Jan-Jun 2019 HFC 29900

South Yarra Planned Jan-Jun 2019

Toorak Planned Jan-Jun 2019

Windsor Planned Jan-Jun 2019

Warracknabeal 3WKB H1 2017 Flipped Jan-Jun 2018 FTTC/N FTTN 1400

Heathcote Junction 3WLN Nov 2015 Build prep Oct-Dec 2017 FTTN 4700

Wallan Available

Wandong Build prep Oct-Dec 2017

Beveridge East 3WLN Q1 2017 Planned FW 1210

Darraweit Guim Build comm

Kalkallo Build comm

Upper Plenty South Planned

Whittlesea North Planned

Yan Yean North Planned

Cape Paterson 3WON Mar 2016 Available FTTN 7000

Dalyston Available

North Wonthaggi Available

South Dudley Available

Wonthaggi Available

Launching Place 3WOR Q3 2016 Build comm Mar 2017 FTTN 1800

Seville East Build comm Mar 2017

Woori Yallock Build comm Mar 2017

Yea 3YEA H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 800

Yarram 3YRA Q1 2017 Planned Jul-Sep 2017 FTTN 1100

Mulwala 3YWG H1 2017 Planned Jan-Jun 2018 FTTC/N FTTN 5900

iTnews’ reconstructed NBN three-year plan 67

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 68: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

66

Yarrawonga Planned Jan-Jun 2018 FTTC/N

Coopers Plains 4AAR H2 2016 Planned Jan-Jun 2018 HFC 11900

Robertson Planned Jan-Jun 2018

Stretton Build comm Mar 2017

Sunnybank Planned Jan-Jun 2018

Sunnybank Hills Planned Jan-Jun 2018

Algester 4AAR H2 2017 Available FTTN 3300

Calamvale Available

Drewvale Planned Jul-Sep 2017

Parkinson Build comm Sep 2017

Runcorn Available

Sunnybank Hills Available

Willawong Build comm Jun 2017

Albany Creek 4ABC H1 2016 Planned Jan-Jun 2018 HFC 5600

Eatons Hill Build comm Jan 2018

Clear Mountain 4ABC H1 2017 Unclear FTTN 3300

Eatons Hill Planned Jan-Jun 2018

Albion 4ABO H2 2016 Planned Jan-Jun 2019 HFC 30700

Alderley Planned Jul-Dec 2018

Clayfield Planned Jan-Jun 2019

Gordon Park Planned Jan-Jun 2019

Grange Planned Jul-Dec 2018

Kedron Planned Jan-Mar 2018

Lutwyche Planned Jan-Jun 2019

Newmarket Planned Jul-Dec 2018

Stafford Planned Jul-Dec 2018

Wilston Planned Jul-Dec 2018

Windsor Planned Jan-Jun 2019

Wooloowin Planned Jan-Jun 2019

Clayfield 4ABO H2 2017 Planned Jan-Jun 2019 FTTN 2600

Ashgrove 4AGV H1 2016 Planned Jan-Jun 2018 HFC 14400

Bardon Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 68

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 69: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

67

Mount Coot-tha Build comm Mar 2017

The Gap Planned Jan-Mar 2018

Agnes Water H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 1200

Cannon Valley 4AIR Q3 2016 Build comm FW 610

Woodwark East Avail / Build comm

Alice River 4ALC Q2 2016 Planned Oct-Dec 2017 FTTN 1100

Rangewood Planned Oct-Dec 2017

Allora 4ALL H2 2017 Planned Jan-Jun 2018 FTTC FTTN 500

Alexandra Hills 4ALX H1 2017 Planned Jan-Jun 2019 HFC 19700

Birkdale Planned Jan-Jun 2019

Cleveland Planned Jul-Dec 2019

Ormiston Planned Jul-Dec 2019

Thorneside Planned Jan-Jun 2019

Wellington Point Planned Jan-Jun 2019

Thornlands 4ALX H2 2017 Build comm Jul-Dec 2019 FTTN 5100

Wellington Point Planned Jan-Jun 2019

Carseldine 4APL H2 2016 Planned Jan-Mar 2018 HFC 3100

Geebung Planned Jan-Jun 2019

Arundel 4ARU H2 2016 Unclear HFC 9200

Parkwood Planned Jul-Dec 2018

Arundel 4ARU H2 2017 Planned Jul-Dec 2018 FTTN 3800

Ashmore 4ASH H1 2017 Build comm Feb 2017

Benowa Build comm Mar 2017 HFC 16500

Bundall Planned Jan-Jun 2018

Molendinar Build comm Mar 2017

Nerang Build comm Sep 2017

Bundall 4ASH H2 2017 Planned Jul-Dec 2018 FTTN 6000

Gaven Planned Jan-Jun 2018

Molendinar Planned Jan-Jun 2018

Avoca 4AVO H1 2018 Planned Jul-Dec 2018 FTTC/N FTTN 3900

Branyan Planned Jul-Dec 2018 FTTC/N

Millbank Planned Jul-Dec 2018 FTTC/N

iTnews’ reconstructed NBN three-year plan 69

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 70: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

68

Barcaldine 4BAR H2 2017 Planned Jan-Jun 2018 FTTN 1000

Blackstone 4BDB H2 2016 Planned Jul-Dec 2018 FTTC HFC 6200

Booval Planned Jul-Dec 2018 FTTC

Collingwood Park Planned Jul-Dec 2018 FTTC

North Booval Unclear

Silkstone Planned Jul-Dec 2018 FTTC

Bundamba 4BDB H1 2018 Unclear FTTN 900

Collingwood Park Unclear

Dinmore Unclear

Ebbw Vale Unclear

New Chum Unclear

North Booval Unclear

Riverview Unclear

Barney View South 4BDS Q1 2017 Build comm FW 730

Boyland Build comm

Cainbable Build comm

Canungra Build comm

Canungra South Build comm

Lamington North Build comm

Mount Tamborine Build comm

Bahrs Scrub 4BEE Q4 2016 Flipped? FW Build comm FTTN 5700

Bannockburn Build comm Jun 2017

Belivah Build comm Jun 2017

Holmview Build prep / comm Jul-Sep 2017

Stapylton Planned Jul-Sep 2017

Windaroo Build comm Jun 2017

Yatala Planned Jul-Sep 2017

Beenleigh 4BEE H1 2018 Planned Jul-Dec 2018 HFC 10400

Eagleby Planned Jul-Dec 2018

Mount Warren Park BC / Planned Jul-Dec 2018

Biloela 4BIL H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 2700

Brookfield 4BKI Q4 2016 Build comm May 2017 FTTN 1800

iTnews’ reconstructed NBN three-year plan 70

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 71: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

69

Kenmore Hills Build comm Mar 2017

Pullenvale Build comm May 2017

Blackwater 4BKW Q4 2016 Build comm Apr 2017 FTTN 2500

Blackbutt 4BLB H2 2018 Planned Jan-Jun 2019 FTTN 500

Blackall 4BLC H2 2017 Planned Jan-Jun 2018 FTTN 900

Bracken Ridge 4BLH H2 2017 Planned Jul-Dec 2018 FTTN 1400

Brighton Unclear

Deagon Unclear

Sandgate Planned Jan-Jun 2018

Shorncliffe Planned

Bald Hills Planned

Bald Hills 4BLH H2 2017 Planned Jul-Dec 2018 HFC 15900

Bracken Ridge Planned Apr-Jun 2017

Brighton Planned Oct-Dec 2017

Deagon Planned Oct-Dec 2017

Sandgate Planned Oct-Dec 2017

Shorncliffe Planned Oct-Dec 2017

Bli Bli 4BLI H1 2017 Planned Jan-Jun 2018 FTTN 7800

Diddillibah Planned Jan-Jun 2018

Kiels Mountain Planned Jan-Jun 2018

Marcoola Unclear

Mudjimba Planned Jan-Jun 2018

Pacific Paradise Planned Jan-Jun 2018

Twin Waters Planned Jan-Jun 2018

Drewvale 4BNP Q1 2017 Planned Apr-Jun 2017 FTTN 3800

Forestdale Build comm Sep 2017

Larapinta Build comm Sep 2017

Boronia Heights 4BNP H1 2017 Planned Apr-Jun 2017 HFC 10200

Browns Plains Planned Apr-Jun 2017

Forestdale Planned Apr-Jun 2017

Hillcrest Planned Apr-Jun 2017

Regents Park Planned Apr-Jun 2017

iTnews’ reconstructed NBN three-year plan 71

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 72: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

70

Boonah 4BOO H1 2018 Planned Jan-Jun 2018 FTTC/N FTTN 1400

Dugandan Planned Jan-Jun 2018

Benaraby 4BOY H1 2017 Planned Jul-Dec 2018 FTTN 4100

Boyne Island 4BRA H2 2016 Planned Jul-Dec 2018 FTTC HFC 4200

Tannum Sands Planned Jul-Dec 2018 FTTC

Wurdong Heights Planned Jul-Dec 2018 FTTC

Moores Pocket Planned Jul-Dec 2018 FTTC

North Ipswich Planned Jul-Dec 2018 FTTC

Tivoli Planned Jul-Dec 2018 FTTC

Borallon 4BRA Q1 2017 Build comm FW 1510

Chuwar West Build comm

Harrisville Build comm

Ironbark East Build comm

Karrabin Planned

Kholo South Build comm

Limestone Ridges Planned

Peak Crossing Build commPeak Crossing North Build comm

Purga Build comm

Brassall 4BRA Q1 2017 Planned Jul-Dec 2018 FTTC FTTN 2500

Pine Mountain UnclearBeerwah and surrounds 4BRW Mar 2016 Planned FW 1940

Beerwah 4BRW H2 2017 Planned Jul-Dec 2018 FTTC FTTN 3700Glass House Mountains Planned Jul-Dec 2018

Beaconsfield 4BUC Q3 2016 Build comm May 2017 FTTN 8400

Blacks Beach Build comm Mar 2017

Bucasia Build comm Feb 2017

Dolphin Heads Build comm Mar 2017

Eimeo Build comm Feb 2017

Richmond Unclear

Rural View Build comm Mar 2017

iTnews’ reconstructed NBN three-year plan 72

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 73: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

71

Shoal Point Available

Buderim 4BUD Q2 2016 Build comm Apr 2017 FTTN 18700

Forest Glen Build comm May 2017

Kuluin Available

Kunda Park Build comm Additional work required

Mons Build comm May 2017

Palmwoods Available

Sippy Downs Build comm Jul 2017

Tanawha Build comm May 2017

Burrum Heads 4BUM H1 2018 Planned Jul-Dec 2018 FTTN 1200

Burleigh Heads 4BUR H2 2016 Planned Oct-Dec 2017 HFC 19300

Burleigh Waters Planned Oct-Dec 2017

Miami Build comm Mar 2017

Palm Beach Planned May 2017

Burleigh Waters 4BUR H2 2017 Build comm Aug 2017 FTTN 3800

Miami Unclear

Palm Beach Unclear

Varsity Lakes Planned Jan-Mar 2018

Burleigh Heads Build comm Aug 2017

Aroona 4CAL H1 2018 Planned Jan-Jun 2019 FTTN 24800

Battery Hill Planned Jan-Jun 2019

Bells Creek Planned Jan-Jun 2019

Caloundra Planned Jan-Jun 2019

Caloundra West Planned Jan-Jun 2019

Currimundi Planned Jan-Jun 2019

Dicky Beach Planned Jan-Jun 2019

Golden Beach Planned Jan-Jun 2019

Kings Beach Planned Jan-Jun 2019

Little Mountain Planned Jan-Jun 2019

Meridan Plains Planned Jan-Jun 2019

Moffat Beach Planned Jan-Jun 2019

Pelican Waters Planned Jan-Jun 2019

iTnews’ reconstructed NBN three-year plan 73

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 74: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

72

Shelly Beach Planned Jan-Jun 2019

Cambooya 4CAM Q4 2016 Build comm Apr 2017 FTTN 1000

Wyreema Build comm Apr 2017

Boyland 4CAN H2 2017 Flipped? FW FTTN 800

Canungra Flipped? FW

Wonglepong Planned Jan-Jun 2018

Cardwell 4CDW Q4 2016 Build comm Apr 2017 FTTN 1200

Chermside 4CHD H1 2017 Planned Jan-Mar 2018 HFC 16700

Chermside West Planned Jan-Mar 2018

Everton Hills Planned Jan-Mar 2018

Kedron Planned Jan-Mar 2018

McDowall Planned Jan-Mar 2018

Stafford Heights Planned Jan-Mar 2018

Chermside West 4CHD H2 2017 Planned Jan-Jun 2018 FTTN 3600

McDowall Planned Jan-Jun 2018

Chinchilla 4CHI H1 2017 Planned Oct-Dec 2017 FTTN 3000

Brisbane City 4CHL H1 2016 Unclear HFC 19600

Herston Planned Jul-Dec 2019

Kelvin Grove Planned Jul-Dec 2018

Milton Planned Jul-Dec 2018

Paddington Planned Jan-Jun 2019

Petrie Terrace Planned Jul-Dec 2018

Red Hill Planned Jul-Dec 2018

Spring Hill Planned Jul-Dec 2019

Brisbane City 4CHL H2 2018 Planned Jul-Dec 2019 FTTN 14000

Milton Unclear

Chapel Hill 4CHP H1 2017 Build comm Mar 2017 HFC 13100

Fig Tree Pocket Build comm Mar 2017

Indooroopilly Planned Jul-Sep 2017

Kenmore Build comm Mar 2017

Kenmore Hills Build comm Mar 2017

Pinjarra Hills 4CHP H2 2017 Build comm Jun 2017 FTTN 500

iTnews’ reconstructed NBN three-year plan 74

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 75: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

73

Pullenvale Build comm Jul 2017

Childers 4CHR H1 2018 Flipped? BC FW FTTN 900

Charleville 4CHV Q1 2017 Build comm Oct 2017 FTTN 1800

Cooktown 4CKT Q3 2016 Available / Build comm No date FTTN 1000

Cooktown 4CKT Q3 2016 Planned FW 290

Cooktown West Planned

Clermont 4CLE Q4 2016 Build comm May 2017 FTTN 1200

Clifton 4CLI H2 2017 Planned Jan-Jun 2018 FTTN 800

Coolum Beach 4CLM Q3 2016 Build comm Feb 2017 FTTN 15000

Marcoola Unclear

Marcus Beach Build comm May 2017

Mount Coolum Build comm Mar 2017

Peregian Build comm Mar 2017

Peregian Springs Build comm Mar 2017

Point Arkwright Build comm Feb 2017

Yandina Creek Build comm May 2017

Yaroomba Build comm Feb 2017

Cloncurry 4CLO Q1 2017 Build comm Jul 2017 FTTN 1400

Builyan 4CLP Q2 2016 Unclear FW 460

Elizabeth Peak Build comm

Hellens Unclear

River Ranch Unclear

Taragoola Planned

Calliope 4CLP H1 2017 Planned Jul-Dec 2018 FTTN 1300

Crows Nest 4CNS H2 2017 Planned Jan-Jun 2018 FTTN 800

Burbank 4CPB H1 2018 Build comm Jan 2017 FTTN 3500

Capalaba Available

Chandler Build comm Aug 2017

Gumdale Build comm Jun 2017

Ransome Build comm Jun 2017

Carindale 4CPH H1 2018 Unclear FTTN 600

Camp Hill 4CPH H1 2018 Planned Jul-Sep 2017 HFC 16100

iTnews’ reconstructed NBN three-year plan 75

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 76: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

74

Carina Planned Jul-Sep 2017

Carina Heights Planned Apr-Jun 2017

Carindale Planned Apr-Jun 2017

Seven Hills Planned Jan-Jun 2019

Alabama Hill 4CTR Q2 2016 Available FTTN 3700

Grand Secret Available

Lissner Unclear

Millchester Build comm Jan 2017

Mosman Park Build comm Jan 2017

Queenton Build comm Jan 2017

Richmond Hill Available

Toll Available

Towers Hill Build comm Jan 2017

Currumbin Waters 4CUR H1 2017 Build comm Jul 2017 FTTN 1700

Bonogin South 4CUR H1 2018 Planned FW 590

Gwinganna South Planned

Piggabeen Planned

Bilinga 4CUR H1 2018 Planned Jan-Jun 2018 HFC 11300

Currumbin Planned Jan-Jun 2018

Currumbin Waters Planned Jan-Jun 2018

Elanora Planned Jul-Dec 2018

Palm Beach Build comm May 2017

Tugun Planned Jan-Jun 2018

Darra 4DRR Q4 2016 Planned Jul-Sep 2017 FTTN 8100

Oxley Planned Oct-Dec 2017

Richlands Planned Oct-Dec 2017

Riverhills AvailableSeventeen Mile Rocks Planned Oct-Dec 2017

Sinnamon Park Available

Sumner Planned Oct-Dec 2017

Dayboro 4DYB Dec 2015 Available FTTN 1000

King Scrub Available

iTnews’ reconstructed NBN three-year plan 76

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 77: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

75

Dayboro Central 4DYB Q1 2017 Planned FW 760

Kobble Creek West Planned

Mount Mee Planned

Ocean View Planned

Ocean View North Planned

Samsonvale Planned

Dysart 4DYS Q4 2016 Build comm Apr 2017 FTTN 1500

Mackenzie River Unclear

Emerald 4EME Q1 2017 Build comm Oct 2017 FTTN 6200

Eight Mile Plains 4EMP H1 2017 Build comm Apr 2017 HFC 12400

Kuraby Build comm Mar 2017

Rochedale South Available

Underwood Available

Burbank 4EMP H1 2017 Build comm Jan 2017 FTTN 4600

Kuraby Planned Oct-Dec 2017

Priestdale Planned Oct 2017

Rochedale Planned Jun 2017

Underwood Build comm Aug 2017

Emu Park 4EPK Q4 2016 Planned Jan-Jun 2018 FTTN 3100

Kinka Beach Planned Jan-Jun 2018

Mulambin Planned Jan-Jun 2018

Zilzie Planned Jan-Jun 2018

Esk 4ESK H1 2018 Planned Jan-Jun 2018 FTTC FTTN 700

Arana Hills 4FHL H1 2016 Available HFC 21800

Enoggera Planned Jul-Dec 2018

Everton Hills Planned Jan-Mar 2018

Everton Park Planned Jul-Dec 2018

Ferny Grove Available

Ferny Hills Build comm Mar 2017

Gaythorne Planned Jul-Dec 2018

Keperra Build comm Apr 2017

Mitchelton Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 77

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 78: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

76

Upper Kedron Build comm Apr 2017

Bunya 4FHL H2 2017 Unclear FTTN 2200

Everton Hills Planned Jul-Dec 2018

Upper Kedron Unclear

Flaxton 4FLA H1 2018 Planned Jul-Dec 2018 FTTN 1100

Mapleton Planned Jul-Dec 2018

Brinsmead 4FRE Q3 2016 Available Now FTTN 8000

Freshwater Build comm Feb 2017

Holloways Bay Build comm

Kamerunga Build comm Feb 2017

Machans Beach Available

Redlynch Available

Stratford Build comm Feb 2017

Berserker 4FRV Mar 2016 Build comm Jan 2017 FTTN 14900

Frenchville Available

Kawana Build comm Apr 2017

Koongal Available

Lakes Creek Available

Limestone Creek Unclear

Nerimbera Available

Norman Gardens Available

Park Avenue Build comm Apr 2017

Fernvale 4FVL Q2 2016 Available FTTN 2800

Lowood Available

Churchable 4FVL Q1 2017 Available FW 1370

Coominya Planned

Fairney View West Planned

Lockyer Waters Build comm

Lowood Build comm

Mt Tarampa Build comm

Wivenhoe Pocket Planned

Brightview 4GAT Q2 2016 Build comm Mar 2017 FTTN 6400

iTnews’ reconstructed NBN three-year plan 78

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 79: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

77

Forest Hill Build comm Mar 2017

Glenore Grove Build comm Mar 2017

Hatton Vale Build comm Jan 2017

Kensington Grove Build comm Jan 2017

Laidley Build comm Mar 2017

Laidley Heights Build comm Feb 2017

Lockrose Build comm Mar 2017

Plainland Build comm Mar 2017

Regency Downs Build comm Mar 2017

Summerholm Build comm Jan 2017

Gayndah 4GAY H1 2018 Planned Jul-Dec 2018 FTTN 900

Beecher 4GLS Nov 2015 Build comm FW 1230

Benaraby Available

Bororen Available

Burua Build comm

Iveragh Unclear

Miriam Vale Available

Mount Larcom Build comm

Mount Maurice Build comm

Turkey Beach Available

West Gladstone Unclear

Barney Point 4GLS H2 2017 Planned Jul-Dec 2018 FTTN 16400

Byellee Flipped? FW Planned

Callemondah Planned Jul-Dec 2018 FTTC/N

Clinton Planned Jul-Dec 2018 FTTC/N

Gladstone Central Planned Jul-Dec 2018 FTTC

Glen Eden Planned Jul-Dec 2018

Kin Kora Planned Jul-Dec 2018

Kirkwood Planned Jul-Dec 2018

New Auckland Planned Jul-Dec 2018 FTTC/N

South Gladstone Planned Jul-Dec 2018

Sun Valley Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 79

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 80: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

78

Telina Planned Jul-Dec 2018

Toolooa Planned Jul-Dec 2018 FTTC/N

West Gladstone Planned Jul-Dec 2018

Goomeri 4GMR H2 2018 Planned Jan-Jun 2019 FTTN 500

Goldsborough 4GNV Q2 2016 Planned Oct-Dec 2017 FTTN 2800

Gordonvale Planned Oct-Dec 2017

Goondiwindi 4GOO H1 2017 Planned Jul-Dec 2018 FTTC/N FTTN 2800

Gracemere 4GRA Q4 2016 Planned Jan-Jun 2018 FTTN 3900

Greenbank 4GRB Q1 2017 Unclear FTTN 5200

Munruben Build comm Sep 2017

New Beith Build comm Oct 2017

North Maclean Build comm No date

Park Ridge South Build comm Sep 2017

Gatton 4GTW Q4 2016 Planned Jan-Jun 2018 FTTN 3300

Placid Hills Planned Jul-Sep 2017

Grantham 4HEL Q1 2017 Build comm Jul 2017 FTTN 600

Helidon Build comm Jul 2017Blue Mountain Heights 4HFD Q1 2017 Planned Jan-Jun 2018 FTTN 4200

Highfields Planned Jan-Jun 2018

Kleinton Planned Jan-Jun 2018

Meringandan Planned Jan-Jun 2018

Meringandan West Planned Jan-Jun 2018

Herberton 4HRB Q3 2016 Planned 2020 FW 310

Herberton South Planned 2020

Wondecla Planned 2020

Hughenden 4HUG Q1 2017 Planned Oct 2017 FTTN 900

Howard 4HWR H1 2018 Planned Jul-Dec 2018 FTTN 800

Doolandella 4IAL Q3 2016 Build comm Jun 2017 FTTN 9100

Ellen Grove Build comm May 2017

Forest Lake Unclear

Heathwood Build comm Jun 2017

Pallara Build comm Jun 2017

iTnews’ reconstructed NBN three-year plan 80

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 81: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

79

Richlands Build comm May 2017

Willawong Build comm Jun 2017

Durack 4IAL H1 2018 Build comm May 2017 HFC 10200

Forest Lake Planned Oct-Dec 2017

Inala Build comm May 2017

Inglewood 4ING H1 2017 Planned Jan-Jun 2018 FTTN 500

Belvedere 4INN Q3 2016 Build comm Mar 2017 FTTN 5400

Coconuts Build comm Feb 2017

Cullinane Build comm Feb 2017

East Innisfail Build comm Mar 2017

Flying Fish Point Build comm Feb 2017

Goondi Bend Build comm Mar 2017

Goondi Hill Build comm Mar 2017

Hudson Build comm Mar 2017

Innisfail Build comm Feb 2017

Innisfail Estate Build comm Feb 2017

Mighell Build comm Mar 2017

Mourilyan Build comm Mar 2017

South Innisfail Build comm Mar 2017

South Johnstone Flipped FW

Wangan Build comm Mar 2017

Webb Build comm Mar 2017

Basin Pocket 4IPS H2 2016 Planned Jul-Dec 2018 FTTC HFC 8000

East Ipswich Planned Jul-Dec 2018 FTTC

Eastern Heights Planned Jul-Dec 2018 FTTC

Leichhardt Planned Jul-Dec 2018 FTTC

Newtown Planned Jul-Dec 2018

Wulkuraka Planned Jul-Dec 2018 FTTC

Amberley 4IPS H1 2018 Planned Jul-Dec 2018 FTTC FTTN 3100

Churchill Unclear

Coalfalls Unclear

Deebing Heights Unclear

iTnews’ reconstructed NBN three-year plan 81

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 82: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

80

Flinders View Planned Jul-Dec 2018 FTTC/N

Ipswich Planned Jul-Dec 2018 FTTC

One Mile Planned Jul-Dec 2018 FTTC

Sadliers Crossing Unclear

South Ripley Unclear

West Ipswich Unclear

Willowbank Planned Jul-Dec 2018

Woodend Build comm Jul 2017

Yamanto Unclear

Allenview 4JBB Q1 2017 Planned FW 2290

Cedar Vale Build comm

Jimboomba Build comm

Jimboomba East Build comm

Jimboomba North Build comm

Jimboomba South Build comm

Jimboomba West Build comm

Maclean Build comm

Maclean East Build comm

Mundoolun Build comm

South Maclean Build comm

Stockleigh South Planned

West Maclean Build comm

Yarrabilba North Build comm

Bohle Plains 4KIR Q3 2016 Build comm Feb 2017 FTTN 14100

Condon Build comm Mar 2017

Kelso Build comm Feb 2017

Kirwan Build comm Mar 2017

Rasmussen Build comm Jan 2017

Kilcoy 4KLC H1 2018 Planned Jan-Jun 2018 FTTC/N FTTN 1000

Dakabin 4KLG Q3 2016 Build comm Aug 2017 FTTN 13700

Griffin Build comm Jun 2017

Kallangur Available

iTnews’ reconstructed NBN three-year plan 82

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 83: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

81

Kurwongbah Build comm May 2017

Mango Hill Build comm Mar 2017

Murrumba Downs Build comm Jun 2017

North Lakes Build comm Apr 2017

Petrie Available

Whiteside Build comm May 2017

Kooralbyn 4KOO H1 2018 Planned Jan-Jun 2018 FTTN 1100

Kuranda 4KRA Q3 2016 Build comm Feb 2017 FTTN 1000

Bell 4KRO Q3 2016 Build comm FW 180

Mount Mowbullan Unclear

Kingaroy 4KRO H2 2018 Planned Jan-Jun 2019 FTTC FTTN 5100

Kingsthorpe 4KTP Q4 2016 Build comm Mar 2017 FTTN 700

Barlows Hill 4LAM Q2 2016 Build comm Mar 2017 FTTN 8000

Barmaryee Build comm Mar 2017

Cooee Bay Build comm Feb 2017

Hidden Valley Build comm Mar 2017

Inverness Build comm Mar 2017

Lammermoor Build comm Feb 2017

Meikleville Hill Build comm Mar 2017

Pacific Heights Build comm Mar 2017

Rosslyn Build comm Feb 2017

Taranganba Build comm Feb 2017

Taroomball Planned 2020

Yeppoon Build comm Mar 2017

Landsborough 4LND H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 1500

Cornubia 4LNH H2 2016 Planned Jul-Dec 2018 HFC 700

Carbrook 4LNH H2 2017 Build comm No date FTTN 2200

Cornubia Planned Jan-Jun 2018

Loganholme Planned Jan-Jun 2018

Bahrs Scrub 4LOG Q1 2017 Planned FW 2270

Buccan Build comm

Cedar Creek North Planned

iTnews’ reconstructed NBN three-year plan 83

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 84: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

82

Chambers Flat Build comm

Crestmead Unclear

Logan Reserve Build commLogan Reserve North Build comm

Logan Village Build comm

Park Ridge East Planned

Stockleigh Planned

Stockleigh North Planned

Tamborine East Build comm

Tamborine North Build comm

Tamborine South Build comm

Yarrabilba South Build comm

Longreach 4LRC H2 2017 Planned Jan-Jun 2018 FTTN 1600

Arcadia 4MAG H1 2017 Planned Jul-Dec 2019 FTTN 2300

Horseshoe Bay Planned Jul-Dec 2019

Nelly Bay Planned Jul-Dec 2019

Picnic Bay Planned Jul-Dec 2019Maleny and surrounds 4MAL Q2 2016 Available FW 2080

Maleny 4MAL H2 2017 Planned Jul-Dec 2018 FTTC FTTN 1900

Aldershot 4MBO Sep 2015 Build comm FW 1740

Bauple Available

Boonooroo Build comm

Maaroom Unclear

Oakhurst Build comm

Poona Planned

Tiaro Available

Granville 4MBO H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 10400

Maryborough Planned Jul-Dec 2018 FTTC/N

Tinana Planned Jul-Dec 2018 FTTC/N

Mundubbera 4MBR Q1 2017 Build comm FW 120

Mundubbera 4MBR H1 2018 Planned Jul-Dec 2018 FTTC FTTN 600

Brookfield 4MCH Q1 2017 Planned FW 1990

iTnews’ reconstructed NBN three-year plan 84

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 85: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

83

Brookfield North Planned

Bunya Planned

Camp Mountain Planned

Closeburn Planned

Draper Planned

Herron Park Planned

Highvale Planned

Mount Coot-tha PlannedMount Samson West Planned

Upper Brookfield Planned

Wights Mountain Planned

Highvale 4MCH H1 2017 Planned Jan-Jun 2018 FTTC/N FTTN 1500

Samford Valley Planned Jan-Jun 2018 FTTC/N

Samford Bridge Planned Jan-Jun 2018 FTTC/N

Malanda 4MDA Q1 2017 Build comm Jul 2017 FTTN 600

Mareeba 4MEB H1 2017 Planned Jul-Dec 2018 FTTN 4100

Holland Park 4MGA H2 2016 Planned Jan-Jun 2018 HFC 22500

Holland Park West Planned Jan-Jun 2018

Macgregor Planned Apr-Jun 2017

Mansfield Planned Apr-Jun 2017

Mount Gravatt Planned Apr-Jun 2017

Mount Gravatt East Planned Apr-Jun 2017Upper Mount Gravatt Planned Jan-Mar 2018

Wishart Planned Oct-Dec 2017

Burbank 4MGA H1 2018 Build comm Oct 2017 FTTN 1700

Carindale Unclear

Mackenzie Unclear

Gilston 4MGB H1 2017 Build comm / Planned Sep 2017 / Jan-Jun 2019 FTTN 8200

Highland Park Build comm Sep 2017

Merrimac Unclear

Tallai Planned Jul-Dec 2018

Worongary Unclear

iTnews’ reconstructed NBN three-year plan 85

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 86: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

84

Highland Park 4MGB H2 2018 Build comm Sep 2017 HFC 4000

Nerang Build comm Sep 2017

Bingil Bay 4MIB Q3 2016 Build comm Mar 2017 FTTN 2400

Mission Beach Build comm Mar 2017South Mission Beach Build comm Mar 2017

Wongaling Beach Build comm Mar 2017

Middlemount 4MIM Q4 2016 Build comm Jun 2017 FTTN 1000

Mitchell 4MIT Q1 2017 Build comm Aug 2017 FTTN 600

Miles 4MLE H1 2017 Flipped Jul-Dec 2018 FTTC FTTN 900

Clagiraba 4MLS Sep 2015 Available FW 700

Guanaba Build comm

Guanaba North Build comm

Mount Nathan 4MLS Dec 2015 Available FTTN 600

Millmerran 4MMR Q1 2017 Flipped FW BC FTTN 600

Moranbah 4MNB Q3 2016 Build comm Apr 2017 FTTN 4200

Carborough Range 4MNB Q1 2017 Unclear FW 1300

Elphinstone North Unclear

Glenden Planned

Moranbah Planned

Nebo Planned

Smith Hill Unclear

Cannindah 4MNT Nov 2015 Available FW 0

Monto 4MNT H1 2018 Planned Jul-Dec 2018 FTTN 700

Anstead 4MOG Q3 2016 Build comm May 2017 FTTN 4800

Bellbowrie Build comm Jun 2017

Moggill Build comm Jun 2017

Pinjara Hills Build comm May 2017

Glenview 4MOO H1 2018 Planned Jul-Dec 2020 FTTN 1700

Mooloolah Valley Planned Jul-Dec 2020

Palmview Plannedf Jul-Dec 2020

Mowbray 4MOS Q3 2016 Available FW 120

Bonnie Doon 4MOS H1 2017 Flipped? FW available FTTN 1500

iTnews’ reconstructed NBN three-year plan 86

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 87: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

85

Cooya Beach Planned Jan-Jun 2018

Mossman Planned Jan-Jun 2018

Moura 4MOU H2 2017 Planned Jan-Jun 2018 FTTN 1100

Broadbeach Waters 4MRA H2 2016 Planned Jan-Jun 2018 HFC 15100

Clear Island Waters Available

Mermaid Beach Planned Oct-Dec 2017

Mermaid Waters Available

Miami Planned / BC Apr-Jun 2017 / Jul 2017

Marburg 4MRB Q3 2016 Planned Oct-Dec 2017 FTTN 800

Minden Planned Oct-Dec 2017Glenore Grove North 4MRB Q1 2017 Build comm FW 1090

Haigslea Build comm

Minden South Build comm

Mt England Unclear

Prenzlau Build comm

Tallegalla Build comm

Burpengary East 4MRF H2 2017 Build comm / Pl Mar 2018 / Jan-Jun 2018 FTTN 7400

Morayfield Planned Jan-Jun 2018

Dalrymple Heights 4MRN Q3 2016 Unclear FW 530

Finch Hatton Build comm

Mirani Available

Pinnacle Build comm

Chuwar 4MTC Q1 2017 Planned Oct-Dec 2017 FTTN 4400

Karalee Planned Oct-Dec 2017

Karana Downs Planned Oct-Dec 2017

Mount Crosby Planned Oct-Dec 2017

Fisher 4MTI Q1 2017 Unclear FTTN 8900

Happy Valley Planned Jul-Sep 2017

Healy Planned Oct-Dec 2017

Menzies Planned Jan-Jun 2018

Mica Creek Planned Jul-Sep 2017

Miles End Planned Oct-Dec 2017

iTnews’ reconstructed NBN three-year plan 87

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 88: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

86

Mornington Planned Oct-Dec 2017

Mount Isa Planned Jan-Jun 2018

Mount Isa City Planned Jan-Jun 2018

Parkside Planned Jul-Sep 2017

Pioneer Planned Jan-Jun 2018

Soldiers Hill Planned Oct-Dec 2017

Sunset Planned Jan-Jun 2018

The Gap Unclear

Townview Planned Oct-Dec 2017

Winston Planned Jan-Jun 2018

Mount Morgan 4MTM Q3 2016 Planned FW 400

Mount Morgan 4MTM Q1 2017 Build comm Aug 2017 FTTN 1200

Murgon 4MUR H2 2018 Planned Jan-Jun 2019 FTTC/N FTTN 1300

Nanango 4NAN H2 2018 Planned Jan-Jun 2019 FTTC/N FTTN 1500Sunshine Coast Hinterland and surrounds 4NBR Mar 2016 Available FW 2430

Burnside 4NBR Q3 2016 Build comm Feb 2017 FTTN 9800

Coes Creek Build comm Feb 2017

Highworth Build comm Feb 2017

Image Flat Build comm Jan 2017

Kiels Mountain Build comm Apr 2017

Nambour Build comm Jan 2017

Parklands Build comm Jan 2017

Perwillowen Build comm Feb 2017

Rosemount Build comm Mar 2017

Towen Mountain Build comm Feb 2017

West Woombye Build comm Apr 2017

Woombye Build comm Apr 2017

Northgate 4NDG H1 2018 Planned Jul-Dec 2018 HFC 9100

Nundah Planned Jul-Dec 2018

Virginia Planned Jul-Dec 2018

Wavell Heights Planned Jul-Dec 2018

Moore Park Beach 4NGO H1 2018 Planned Jul-Dec 2018 FTTC/N FTTN 1100

iTnews’ reconstructed NBN three-year plan 88

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 89: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

87

Beachmere North 4NIN H1 2017 Planned FW 1670

Beachmere West Planned

Bellmere West Planned

Donnybrook West Planned

Meldale Planned

Moorina Planned

Narangba Planned

Narangba West Planned

Toorbul Planned

Wamuran Planned

Andergrove 4NMK Q1 2017 Planned Jul-Sep 2017 FTTN 12500

Beaconsfield Build comm May 2017

Cremorne Planned Jul-Sep 2017

Glenella Planned Jul-Sep 2017

Mackay Harbour Planned Jul-Sep 2017

Mount Pleasant Planned Jul-Sep 2017

North Mackay Planned Jul-Sep 2017

Slade Point Planned Jul-Sep 2017

Castaways Beach 4NOO Q1 2017 Build comm Aug 2017 FTTN 23300

Cooroibah Planned Oct-Dec 2017

Doonan Planned Oct-Dec 2017

Noosa Heads Build comm Sep 2017

Noosaville Build comm Oct-Dec 2017

Sunrise Beach Build comm Aug 2017

Sunshine Beach Build comm Aug 2017

Tewantin Planned Oct-Dec 2017

Tinbeerwah Planned Oct-Dec 2017

Verrierdale Flipped? FW planned

Burpengary 4NRB Q3 2016 Build comm May 2017 FTTN 12700

Burpengary East Build comm May 2017

Narangba Build comm Aug 2017 / Dec 2017

New Farm 4NWF H2 2017 Planned Jul-Sep 2017 FTTN 1400

iTnews’ reconstructed NBN three-year plan 89

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 90: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

88

Oakey 4OKE Q4 2016 Build comm Mar 2017 FTTN 2000

Coomera 4ORM Q4 2016 Build comm Nov 2017 FTTN 15000

Luscombe Flipped? FW planned

Ormeau Build comm Aug 2017

Ormeau Hills Build comm Mar 2018

Pimpama Build comm Aug 2017

Upper Coomera Build comm Aug 2017

Gilberton 4ORM Q1 2017 Build comm FW 1170

Jacobs Well Planned

Kingsholme Planned

Stapylton Build comm

Willow Vale Planned

Wolffdene South Planned

Woongoolba Build comm

Helensvale 4OXE Q1 2017 Build comm / Pl Aug 2017 FTTN 12100

Maudsland Build comm Jul 2017

Oxenford Build comm Aug 2017

Pacific Pines Build comm May 2017

Biggera Waters 4PDP H1 2017 Planned Jan-Jun 2019 HFC 16800

Coombabah Planned Jul-Dec 2018

Hollywell Planned Jul-Dec 2018

Paradise Point Planned Jul-Dec 2018

Runaway Bay Planned Jan-Jun 2019

Hope Island 4PDP H2 2017 Planned Jul-Dec 2018 FTTN 6100

Craiglie 4PDS Q1 2017 Planned Jul-Sep 2017 FTTN 5400

Port Douglas Planned Jul-Sep 2017

Pittsworth 4PWT Q1 2017 Build comm Jun 2017 FTTN 1400

Bonogin 4RBN Q1 2017 Planned 2020 FTTN 7100

Robina Planned Jan-Jun 2018

Beechmont 4RBN H1 2018 Planned FW 1990

Beechmont North Planned

Bonogin Central Planned

iTnews’ reconstructed NBN three-year plan 90

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 91: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

89

Bonogin West Planned

Gilston Planned

Hellfire Pass Planned

Mudgeeraba Planned

Neranwood South Planned

Springbrook North Planned

Springbrook South Planned

Newport 4RDC H2 2017 Planned Jan-Jun 2018 FTTN 1800

Carbrook 4RED Nov 2015 Build comm No date FTTN 2200

Mount Cotton Available

Redland Bay Available

Ravenshoe East 4RHO Q3 2016 Planned FW 190

Tully Gorge Available

Ravenshoe 4RHO Q4 2016 Build comm Jun 2017 FTTN 500

Balgal Beach 4RLS Q3 2016 Build comm Feb 2017 FTTN 700

Roma 4ROM Q4 2016 Build comm Aug-Sep 2017 FTTN 3300

Walloon Available

Calvert 4RSW Q1 2017 Build comm FW 960

Ebenezer South Build comm

Grandchester Build comm

Mount Forbes Build comm

Mount Walker Build comm

Rosewood Build comm

Walloon North Build comm

Willowbank Build comm

Rothwell 4RTW H1 2016 Unclear HFC 600

Deception Bay 4RTW H2 2017 Planned Jan-Jun 2018 FTTN 10600

Mango Hill Planned Jan-Jun 2018

Rothwell Planned Jan-Jun 2018

Karragarra Island 4RUS H1 2017 Planned Jul-Dec 2019 FTTC FTTN 15700

Lamb Island Planned Jul-Dec 2019 FTTC

Macleay Island Planned Jul-Dec 2019 FTTC

iTnews’ reconstructed NBN three-year plan 91

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 92: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

90

Russell Island Planned Jul-Dec 2019 FTTC

Booral 4RVH H1 2018 Planned Jan-Jun 2019 FTTN 7400

River Heads Planned Jan-Jun 2019

Urangan Planned Jul-Dec 2018

Augustine Heights 4SGI Q3 2016 Build comm Feb 2017 FTTN 6600

Brookwater Build comm Feb 2017

Camira Build comm No date

Springfield Build comm No date

Springfield Lakes Available

Camira 4SGI H2 2018 Planned Jan-Jun 2019 HFC 2600

Springfield Planned Jan-Jun 2019

Berrinba 4SLA H2 2016 Build comm Apr-Jun 2017 HFC 22900

Daisy Hill Build comm Jun 2017

Karawatha Build comm Mar 2017

Kingston Planned Jul-Sep 2017

Logan Central Planned Oct-Dec 2017

Slacks Creek Build comm / Planned Jun 2017 / Jul-Sep 2017

Springwood Planned Jul-Sep 2017

Woodridge Planned Oct-Dec 2017

Slacks Creek 4SLA H2 2017 Build comm/ Planned Jun 2017 / Jul-Sep 2017 FTTN 900

Labrador 4SOP H1 2017 Planned Jan-Mar 2018 HFC 26000

Main Beach Planned Oct-Dec 2017

Southport Planned Oct-Dec 2017

Southport 4SOP H2 2017 Planned Jul-Dec 2018 FTTC/B FTTN 1400

Currumbin Valley 4SPH Q4 2016 Build comm July 2017 FTTN 6800

Currumbin Waters Build comm July 2017

Reedy Creek Build comm Apr 2018

Tallebudgera Build comm May 2018

Tallebudgera Valley Flipped? FW planned

Elanora 4SPH H1 2018 Planned Jul-Dec 2018 HFC 3600

Annerley 4SRW H2 2017 Planned Jan-Jun 2018 HFC 26200

Chelmer Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 92

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 93: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

91

Corinda Planned Jan-Jun 2018

Fairfield Planned Jan-Jun 2018

Graceville Planned Jul-Dec 2018

Moorooka Planned Jan-Jun 2018

Oxley Planned Jan-Jun 2018

Sherwood Planned Jul-Dec 2018

Tarragindi Planned Jan-Jun 2018

Tennyson Planned Jul-Dec 2018

Yeerongpilly Planned Jul-Dec 2018

Yeronga Planned Jan-Jun 2018

Acacia Ridge 4SSB H1 2017 Planned Jan-Jun 2018 HFC 9500

Archerfield Planned Jan-Jun 2018

Coopers Plains Planned Jul-Dec 2018

Nathan Planned Jan-Jun 2018

Rocklea Planned Jul-Dec 2018

Salisbury Planned Jan-Jun 2018

Archerfield 4SSB H2 2017 Planned Jul-Dec 2018 FTTC FTTN 1700

Rocklea Planned Jul-Dec 2018 FTTC

St George 4STG H1 2017 Planned Jul-Dec 2018 FTTN 1300

Stanthorpe 4STP H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 2700

Surfers Paradise 4SUR H2 2017 Planned Jan-Jun 2018 FTTC/B FTTN 2000

Broadbeach Waters 4SUR H2 2018 Planned 2020 HFC 2000

Tamborine 4TBE H2 2017 Planned Jan-Jun 2018 FTTN 400Tamborine Mountain 4TBN H2 2017 Planned Jul-Dec 2018 FTTN 4000

Belmont 4TGP H1 2017 Planned Jul-Dec 2018 HFC 24100

Hemmant Planned Jul-Dec 2018

Lota Planned Jul-Dec 2018

Lytton Planned Jul-Dec 2018

Manly Planned Jul-Dec 2018

Manly West Planned Jul-Dec 2018

Murrarie Planned Jul-Dec 2018

Tingalpa Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 93

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 94: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

92

Wynnum Planned Jul-Dec 2018

Wynnum West Planned Jul-Dec 2018

Gumdale 4TGP H1 2018 Build comm Aug 2017 FTTN 6700

Hemmant Planned Jul-Dec 2018

Tingalpa Planned Jul-Dec 2018

Wakerley Build comm Jun 2017

Tieri 4TIE Q1 2017 Build comm Jul 2017 FTTN 600

Toogoolawah 4TOG H1 2018 Flipped? FW FTTN 600

Craignish 4TQA H1 2017 Planned Jul-Dec 2018 FTTN 20600

Dundowran Planned Jul-Dec 2018

Dundowan Beach Planned Jul-Dec 2018

Eli Waters Planned Jul-Dec 2018 FTTC/N

Kawungan Planned Jul-Dec 2018

Nikenbah Planned Jul-Dec 2018

Pialba Planned Jul-Dec 2018 FTTC/N

Point Vernon Planned Jul-Dec 2018

Scarness Planned Jul-Dec 2018 FTTC/N

Toogoom Planned Jul-Dec 2018

Torquay Planned Jul-Dec 2018 FTTC/N

Urraween Planned Jul-Dec 2018 FTTC/N

Wondunna Planned Jul-Dec 2018 FTTC/N

Tully 4TUL Q4 2016 Build comm May 2017 FTTN 1200

Auchenflower 4TWO H1 2018 Planned Jul-Sep 2017 HFC 20900

Indooroopilly Planned Jan-Jun 2019

St Lucia Planned Jan-Jun 2019

Taringa Planned Jan-Jun 2019

Toowong Planned Jan-Jun 2019Coochiemudlo Island 4VAP H1 2018 Planned Jan-Jun 2019 FTTC/N FTTN 9600

Sheldon Planned Jan-Jun 2019 FTTC/N

Thornlands Planned Jul-Dec 2019

Victoria Point Planned Jan-Jun 2019 FTTC/N

Wondai 4WDA H2 2018 Planned Jan-Jun 2019 FTTN 800

iTnews’ reconstructed NBN three-year plan 94

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 95: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

93

Beerburrum 4WDF H2 2017 Planned FW 1120

D'Aguilar Planned

D'Aguilar South Planned

Elimbah Planned

Wamuran North Planned

Woodford Planned

D'Aguilar 4WDF H2 2017 Planned Jul-Dec 2020 FTTN 1000

Delaneys Creek Planned Jul-Dec 2020

Woodford Planned Jul-Dec 2020

Nanum 4WEP Q3 2016 Planned Jul-Sep 2017 FTTN 700

Rocky Point Planned Jul-Sep 2017

Trunding Planned Jul-Sep 2017

Annandale 4WLG Q4 2016 Planned Jan-Jun 2018 FTTN 9800

Cluden Planned Jan-Jun 2018

Douglas Planned Jan-Jun 2018

Idalia Planned Jan-Jun 2018

Mount Stuart Planned Jan-Jun 2018

Murray Planned Jan-Jun 2018

Nome Planned Jan-Jun 2018

Oonoonba Planned Jan-Jun 2018

Stuart Planned Jan-Jun 2018

Wulguru Planned Jan-Jun 2018

Walkerston 4WLK Q3 2016 Build comm Jul 2017 FTTN 1300

East Brisbane 4WOB H2 2017 Planned Jan-Jun 2019 HFC 3100

Kangaroo Point Planned Jan-Jun 2019

Woolloongabba Planned Jan-Jun 2019

Annerley Planned Jan-Jun 2018

Bargara 4WON H1 2018 Planned Jan-Jun 2019 FTTN 7600

Burnett Heads Planned Jan-Jun 2019

Coral Cove Planned Jan-Jun 2019

Elliott Heads Planned Jan-Jun 2019

Innes Park Planned Jan-Jun 2019

iTnews’ reconstructed NBN three-year plan 95

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 96: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

94

Woodgate 4WOT H1 2018 Planned Jul-Dec 2018 FTTN 1100

Bray Park 4WRN H1 2018 Planned Oct-Dec 2017 HFC 6100

Strathpine Planned Oct-Dec 2017

Rosenthal Heights 4WRW H1 2017 Planned Jul-Dec 2018 FTTN 5800

Warwick Planned Jul-Dec 2018 FTTC

Bethania 4WTF H2 2017 Planned Jan-Jun 2019 FTTN 5900

Buccan Flipped? FW

Crestmead Planned Jan-Jun 2019

Heritage Park Planned Jan-Jun 2019

Meadowbrook Planned Jan-Jun 2019

Waterford Planned Jan-Jun 2019

Bethania 4WTF H1 2018 Planned Jan-Jun 2018 HFC 14700

Crestmead Planned Jan-Jun 2018

Edens Landing Planned Jan-Jun 2019

Heritage Park Planned Jan-Mar 2018

Logan Reserve Unclear

Loganlea Planned Jan-Jun 2018

Marsden Planned Jan-Jun 2019

Meadowbrook Planned Jan-Jun 2019

Waterford West Planned Jan-Jun 2019

Winton 4WTN H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 600

Jacobs Well 4WWL Q4 2016 Build comm Sep 2017 FTTN 1100

Steiglitz Build comm Sep 2017

Maroochy River 4YIN H1 2017 Flipped? FW FTTN 1700

Ninderry Planned Jul-Dec 2018

Yandina Flipped Jul-Dec 2018 FTTC/N

Birdwood 5BDW Q2 2016 Build comm Apr 2017 FTTN 900

Gumeracha Build comm Apr 2017

Kersbrook Build comm Apr 2017

Beachport 5BPT Q2 2016 Build comm Jan 2017 FTTN 500

Brighton 5BRI H1 2017 Planned Oct-Dec 2017 HFC 18800

Darlington Planned Oct-Dec 2017

iTnews’ reconstructed NBN three-year plan 96

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 97: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

95

Dover Gardens Planned Jan-Jun 2018

Hove Planned Jan-Jun 2018

Kingston Park Planned Oct-Dec 2017

Marino Build comm Jun 2017

Marion Planned Jan-Jun 2018

North Brighton Planned Jan-Jun 2018

Oaklands Park Planned Jan-Jun 2018

Seacliff Planned Oct-Dec 2017

Seacliff Park Planned Jul-Sep 2017

Seacombe Gardens Planned Oct-Dec 2017

Seacombe Heights Planned Jul-Sep 2017

Seaview Downs Planned Jul-Sep 2017

South Brighton Planned Jan-Jun 2018

Sturt Planned Oct-Dec 2017

Warradale Planned Jan-Jun 2018

Darlington 5BRI H1 2018 Planned Jul-Dec 2018 FTTN 900

Flagstaff Hill Build comm Apr 2017

Berri 5BRR Q2 2016 Build comm Apr 2017 FTTN 2100

Burra 5BUR Q2 2016 Build comm Mar 2017 FTTN 700

Ceduna 5CDN H1 2017 Planned Jan-Jun 2018 FTTN 1300

Thevenard Planned Jan-Jun 2018

Clare North 5CLR Q1 2017 Planned FW 320

Sevenhill Build comm

Aberfoyle Park 5CMD Q4 2016 Build comm May 2017 FTTN 9000

Chandlers Hill Build comm Mar 2017

Coromandel Valley Build comm May 2017

Flagstaff Hill Build comm May 2017

Cowell 5COW Q4 2016 Build comm Jun 2017 FTTN 700

Coober Pedy 5CRP Q4 2016 Planned Jun 2017 FTTN 1100

Angle Park 5CRY H2 2017 Planned Jul-Dec 2018 FTTC FTTN 17600

Athol Park Planned Jul-Dec 2018 FTTC

Beverley Planned Jul-Dec 2018 FTTC

iTnews’ reconstructed NBN three-year plan 97

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 98: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

96

Bowden Planned Jul-Dec 2018 FTTP

Devon Park Planned Jul-Dec 2018 FTTC

Ferryden Park Planned Jul-Dec 2018 FTTC

Findon Planned Jul-Dec 2018 FTTC/N

Hindmarsh Planned Jul-Dec 2018 FTTC

Kilkenny Planned Jul-Dec 2018

Mansfield Park Planned Jul-Dec 2018 FTTC

Pennington Planned Jul-Dec 2018

Regency Park Planned Jul-Dec 2018 FTTC

Woodville Planned Jul-Dec 2018 FTTC

Woodville Gardens Planned Jul-Dec 2018 FTTC

Woodville North Planned Jul-Dec 2018 FTTC

Woodville Park Planned Jul-Dec 2018 FTTC

Woodville South Planned Jul-Dec 2018 FTTC

Woodville West Planned Jul-Dec 2018 FTTC

Allenby Gardens 5CRY H2 2017 Planned Jan-Jun 2019 HFC 8200

Bowden Planned Jan-Jun 2019

Brompton Planned Jan-Jun 2019

Croydon Planned Jan-Jun 2019

Croydon Park Planned Jan-Jun 2019

Devon Park Unclear

Regency Park Unclear

Renown Park Planned Jan-Jun 2019

Ridleyton Planned Jan-Jun 2019

Welland Planned Jan-Jun 2019

West Croydon Planned Jan-Jun 2019

West Hindmarsh Planned Jan-Jun 2019

Ashford 5EDW H2 2017 Planned Oct-Dec 2017 HFC 18200

Black Forest Planned Aor-Jun 2017

Clarence Gardens Planned Apr-Jun 2017

Clarence Park Planned Apr-Jun 2017

Cumberland Park Planned Apr-Jun 2017

iTnews’ reconstructed NBN three-year plan 98

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 99: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

97

Edwardstown Planned Apr-Jun 2017

Everard Park Planned Oct-Dec 2017

Forestville Planned Oct-Dec 2017

Glandore Planned Apr-Jun 2017

Keswick Planned Oct-Dec 2017

Kurralta Park Planned Apr-Jun 2017

Marleston Planned Apr-Jun 2017

Netley Planned Apr-Jun 2017

North Plympton Planned Apr-Jun 2017

Plympton Planned Apr-Jun 2017

Plympton Park Planned Apr-Jun 2017

Plympton South Planned Apr-Jun 2017

Paralowie 5EZB H2 2016 Planned Apr-Jun 2017 HFC 9100

Salisbury North Available

Burton 5EZB H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 17200

Craigmore Planned Jul-Dec 2018 FTTC

Edinburgh Planned Jul-Dec 2018 FTTC

Elizabeth Planned Jul-Dec 2018 FTTC/N

Elizabeth Downs Planned Jul-Dec 2018 FTTC/N

Elizabeth East Planned Jul-Dec 2018 FTTC/N

Elizabeth Grove Planned Jul-Dec 2018 FTTC/N

Elizabeth Park Planned Jul-Dec 2018 FTTC/N

Elizabeth South Planned Jul-Dec 2018 FTTC/N

Elizabeth Vale Planned Jul-Dec 2018 FTTC/N

Elizabeth West Planned Jul-Dec 2018 FTTC/N

Hillbank Planned Jul-Dec 2018 FTTC/N

North Adelaide 5FLN H1 2016 Build comm Oct-Dec 2017 HFC 4700

Adelaide 5FLN Q1 2017 Planned Jan-Jun 2019 FTTC FTTN 17500

Freeling 5FRL Q4 2016 Planned Jul-Sep 2017 FTTN 700

Novar Gardens 5GLL H1 2018 Unclear FTTN 1500

Camden Park 5GLL H2 2018 Planned Jul-Dec 2018 HFC 8900

Glenelg East Planned Jul-Sep 2017

iTnews’ reconstructed NBN three-year plan 99

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 100: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

98

Glenelg North Planned Jul-Sep 2017

Glengowrie Planned Jul-Sep 2017

Morphettville Planned Apr-Jun 2017

Novar Gardens Planned Jul-Dec 2018

Goolwa 5GLW Q3 2016 Build comm Apr 2017 FTTN 7100

Goolwa Beach Build comm Mar 2017

Goolwa North Build comm Apr 2017

Goolwa South Build comm Mar 2017

Hindmarsh Island Build comm Apr 2017

Middleton Build comm Mar 2017

Golden Grove 5GNG H2 2017 Unclear FTTN 3400

Greenwith Build comm

Yatala Vale Planned Jul-Sep 2017

Fairview Park 5GNG H1 2018 Planned Jul-Sep 2017 HFC 9300

Golden Grove Planned Apr-Jun 2017

Greenwith Build comm Sep 2017

Surrey Downs Planned Jul-Sep 2017

Wynn Vale Planned Jul-Sep 2017

Yatala Vale Planned Jul-Sep 2017

Mawson Lakes 5GPC H1 2018 Build comm Aug 2017 HFC 800

Clarence Park 5GUG H1 2016 Planned Apr-Jun 2017 HFC 12300

Cumberland Park Planned Apr-Jun 2017

Goodwood Available

Highgate Available

Hyde Park Available

Kings Park Available

Kingswood Available

Millswood Available

Mitcham Available

Netherby Available

Parkside Available

Torrens Park Available

iTnews’ reconstructed NBN three-year plan 100

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 101: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

99

Unley Available

Unley Park Available

Wayville Available

Beaumont 5GUG H2 2017 Planned Jan-Jun 2018 FTTN 15800

Eastwood Planned Jul-Dec 2018

Frewville Planned Jul-Dec 2018 FTTC/N

Fullarton Planned Jul-Dec 2018 FTTC

Glen Osmond Planned Jul-Dec 2018 FTTC

Glenside Planned Jan-Jun 2018 FTTC

Glenunga Planned Jul-Dec 2018 FTTC

Hawthorn Planned Jan-Jun 2018 FTTC/N

Hazelwood Park Planned Jan-Jun 2018

Hyde Park Planned Jan-Jun 2018

Linden Park Planned Jan-Jun 2018 FTTC/N

Malvern Planned Jan-Jun 2018

Mount Osmond Planned Jul-Dec 2018 FTTC

Myrtle Bank Planned Jul-Dec 2018 FTTC

Netherby Planned Jul-Dec 2018 FTTC

Springfield Planned Jul-Dec 2018 FTTC

St Georges Planned Jul-Dec 2018 FTTC

Unley Park Planned Jan-Jun 2018

Urrbrae Planned Jul-Dec 2018 FTTC

Westbourne Park Planned Jan-Jun 2018 FTTC

Fulham 5HNL H2 2017 Planned Oct-Dec 2017 HFC 15200

Fulham Gardens Planned Oct-Dec 2017

Grange Planned Apr-Jun 2017

Henley Beach Planned Apr-Jun 2017Henley Beach South Planned Oct-Dec 2017

Kidman Park Planned Oct-Dec 2017

Seaton Planned Oct-Dec 2017

West Beach Planned Oct-Dec 2017

Grange 5HNL H2 2017 Planned Jan-Jun 2018 FTTN 4600

iTnews’ reconstructed NBN three-year plan 101

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 102: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

100

Seaton Planned Jul-Dec 2018

Tennyson Planned Jan-Jun 2018

West Lakes Build comm Apr 2017

Broadview 5HPS H1 2017 Planned Jan-Jun 2019 HFC 11600

Dernancourt Planned Jan-Jun 2019

Gilles Plains Planned Jan-Jun 2019

Greenacres Planned Jan-Jun 2019Hampstead Gardens Planned Jan-Jun 2019

Holden Hill Planned Jan-Jun 2019

Klemzig Planned Jan-Jun 2019

Manningham Planned Jan-Jun 2019

Vale Park Planned Jan-Jun 2019

Windsor Gardens Planned Jan-Jun 2019

Gilles Plains 5HPS H2 2017 Planned Jan-Jun 2019 FTTN 6600

Hillcrest Planned Jan-Jun 2019

Holden Hill Planned Jan-Jun 2019

Manningham Planned Jan-Jun 2019

Northgate Planned Jan-Jun 2019

Oakden Planned Jan-Jun 2019

Vale Park Planned Jan-Jun 2019

Kapunda 5KAP Q3 2016 Build comm Apr 2017 FTTN 1400

Anstey Hill 5LEN Q1 2017 Unclear FW 2230

Ashton Build comm

Carey Gully Build comm

Cromer Build comm

Inglewood Build comm

Kersbrook East Build comm

Lenswood Build comm

Mount Pleasant Build comm

Mount Torrens Build comm

Woodside East Build comm

Charleston 5LEN H1 2018 Planned Jul-Dec 2018 FTTN 2100

iTnews’ reconstructed NBN three-year plan 102

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 103: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

101

Lobethal Planned Jul-Dec 2018

Woodside Planned Jul-Dec 2018

Christie Downs 5LSD Q1 2017 Planned Jul-Sep 2017 FTTN 24600

Christies Beach Planned Jul-Sep 2017

Hackham Build comm Aug 2017

Hackham West Build comm Aug 2017

Huntfield Heights Build comm Aug 2017

Lonsdale Build comm Sep 2017

Morphett Vale Build comm Sep 2017

Noarlunga Centre Planned Jul-Sep 2017

Noarlunga Downs Planned Jul-Sep 2017

O'Sullivan Beach Planned Jul-Sep 2017

Onkaparinga Hills Build comm Jul 2017

Port Noarlunga Planned Jul-Sep 2017

Altona 5LYD Q1 2017 Build comm FW 1310

Cockatoo Valley Build comm

Humbug Scrub Build comm

One Tree Hill Build comm

Sandy Creek Build comm

Uleybury Build comm

Warpoo Unclear

Williamstown Build comm

Williamstown North Build comm

Yattalunga Build comm

Bugle Ranges 5MCF Q1 2017 Build comm FW 1860

Callington Build comm

Echunga North Build comm

Echunga South Build comm

Kanmantoo Build comm

Littlehampton Build comm

Macclesfield South Build comm

Mount Barker Build comm

iTnews’ reconstructed NBN three-year plan 103

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 104: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

102

Oakbank Build comm

Paris Creek West Build comm

Millicent 5MIC Q2 2016 Build comm Mar 2017 FTTN 2400

Minlaton 5MNL Q1 2017 Build comm Jul 2017 FTTN 500

Mannum 5MNN Mar 2016 Build comm Feb 2017 FTTN 1500

Port Mannum Build comm Feb 2017

Banksia Park 5MOD H1 2018 Planned Jul-Sep 2017 FTTN 5000

Highbury Build comm Jun 2017

Hope Valley Planned Apr-Jun 2017

Ingle Farm Available

Modbury Available

Modbury Heights Available

Modbury North Available

Para Hills Available

Para Vista Available

Redwood Park Available

Ridgehaven Available

St Agnes Available

Tea Tree Gully Available

Valley View Planned Jan-Jun 2019

Vista Build comm Jun 2017

Mount Gambier 5MTG Q3 2016 Build comm May 2017 FTTN 13400

Worrolong Build comm Jun 2017

Teal Flat 5MYB Q1 2017 Planned 2020 FW 180

Naracoorte 5NAR Q2 2016 Build comm Jan 2017 FTTN 2700

Auldana 5NRW H2 2016 Planned Jan-Jun 2018 HFC 21400

Beulah Park Planned Jan-Jun 2018

Burnside Planned Jan-Jun 2018

Dulwich Planned Jan-Jun 2018

Erindale Planned Jan-Jun 2018

Firle Planned Oct-Dec 2017

Hazelwood Park Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 104

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 105: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

103

Heathpool Planned Jan-Jun 2018

Kensington Planned Jan-Jun 2018Kensington Gardens Planned Jan-Jun 2018

Kensington Park Planned Jan-Jun 2018

Leabrook Planned Jan-Jun 2018

Magill Planned Jan-Jun 2018

Marryatville Planned Jan-Jun 2018

Norwood Planned Jan-Jun 2018

Payneham South Planned Oct-Dec 2017

Rose Park Planned Jan-Jun 2018

Rosslyn Park Planned Jan-Jun 2018

Skye Planned Jan-Jun 2018

St Morris Planned Oct-Dec 2017

Stonyfell Planned Jan-Jun 2018

Teringie Planned Jan-Jun 2018

Toorak Gardens Planned Jan-Jun 2018

Tranmere Planned Jan-Jun 2018

Trinity Gardens Planned Oct-Dec 2017

Tusmore Planned Jan-Jun 2018

Wattle Park Planned Jan-Jun 2018

College Park 5NRW H2 2017 Planned Jul-Dec 2018 FTTN 9500

Evandale Planned Jul-Dec 2018

Hackney Planned Jul-Dec 2018

Joslin Planned Jul-Dec 2018

Kent Town Planned Jul-Dec 2018

Marden Planned Jul-Dec 2018

Maylands Planned Jul-Dec 2018

Norwood Planned Jul-Dec 2018

Payneham Planned Jul-Dec 2018

Royston Park Planned Jul-Dec 2018

St Peters Planned Jul-Dec 2018

Stepney Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 105

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 106: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

104

Eudunda 5NUR Feb 2016 Planned FW 1250

Eudunda West Planned

Kapunda Planned

Mallala Build comm

Springton Build comm

Tanunda Available

Angaston 5NUR Q2 2016 Build comm Feb 2017 FTTN 6600

Greenock Build comm Mar 2017

Nooriootpa Build comm Feb 2017

Penrice Build comm Feb 2017

Stockwell Build comm Feb 2017

Tanunda Build comm Mar 2017

McLaren Flat 5ONK Q4 2016 Build comm FW 1000

McLaren Vale North Build comm

Sellicks Hill Build comm

Tatachilla Planned

The Range Build comm

Willunga Build comm

Birkenhead 5OSB Q4 2016 Build comm Mar 2017 FTTN 18400

Ethelton Build comm Apr 2017

Exeter Build comm Apr 2017

Glanville Build comm Apr 2017

Largs Bay Build comm Apr 2017

Largs North Build comm Apr 2017

New Port Build comm Apr 2017

North Haven Build comm Apr 2017

Osborne Build comm Apr 2017

Outer Harbor Build comm Apr 2017

Peterhead Build comm Mar 2017

Semaphore Build comm Apr 2017

Semaphore Park Build comm Apr 2017

Semaphore South Build comm Apr 2017

iTnews’ reconstructed NBN three-year plan 106

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 107: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

105

Taperoo Build comm Mar 2017

West Lakes Build comm Apr 2017

West Lakes Shore Build comm Apr 2017

Albert Park 5PAD H1 2017 Build comm Jan 2018 FTTN 15600

Alberton Planned Jan-Jun 2018

Athol Park Planned Jul-Dec 2018

Cheltenham Planned Oct-Dec 2017

Garden Island Planned Oct-Dec 2017

Hendon Planned Jan 2018

Ottoway Planned Oct-Dec 2017

Pennington Planned Oct-Dec 2017

Port Adelaide Planned Oct-Dec 2017

Queenstown Planned Oct-Dec 2017

Rosewater Planned Jul-Sep 2017

Royal Park Planned Jan-Jun 2018

Seaton Planned Jul-Dec 2018

West Lakes Build comm Apr 2017

Wingfield Planned Oct-Dec 2017

Port Pirie 5PIR Q3 2016 Build comm Apr 2017 FTTN 7500

Port Pirie South Build comm Apr 2017

Port Pirie West Build comm Apr 2017

Risdon Park Build comm Apr 2017

Risdon Park South Build comm Apr 2017

Solomontown Build comm Mar 2017

Athelstone 5PRD H1 2018 Planned Jan-Jun 2019 HFC 19900

Campbelltown Planned Jan-Jun 2019

Dernancourt Planned Jan-Jun 2019

Felixstow Planned Jan-Jun 2019

Glynde Planned Jan-Jun 2019

Hectorville Planned Jan-Jun 2019

Newtown Planned Jan-Jun 2019

Paradise Planned Jan-Jun 2019

iTnews’ reconstructed NBN three-year plan 107

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 108: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

106

Payneham Planned Jan-Jun 2019

Rostrevor Planned Jan-Jun 2019

Tranmere Planned Jan-Jun 2019

Woodforde Planned Jan-Jun 2019

Athelstone 5PRD H1 2018 Planned Jul-Dec 2018 FTTC FTTN 3000

Glynde Planned Jul-Dec 2018

Orroroo 5PTG Feb 2016 Build comm FW 310

Port Lincoln 5PTL Q1 2017 Planned Jul-Sep 2017 FTTN 8000

Quorn 5QUR Q1 2017 Planned Jul-Sep 2017 FTTN 700

Roxby Downs 5RBY Q3 2016 Build comm Jun 2017 FTTN 1800

Trott Park 5REL H1 2017 Planned Jan-Jun 2019 HFC 3100

Paringa 5RNK Q3 2016 Build comm Apr 2017 FTTN 3000

Renmark Build comm Apr 2017

Brahma Lodge 5SAL H2 2016 Build comm Mar 2017 HFC 19800

Gulfview Heights Unclear

Para Hills West Planned Apr-Jun 2017

Parafield Gardens Build comm May 2017

Salisbury Available / Planned Now / Jul-Dec 2018

Salisbury Downs Planned Jul-Sep 2017

Salisbury East Planned Jan-Mar 2017

Salisbury Heights Build comm Sep 2017

Salisbury Park Planned Jan-Mar 2017

Salisbury Plain Available

Globe Derby Park 5SAL H1 2018 Planned Jul-Dec 2018 FTTN 4700

Green Fields Planned Jul-Dec 2018 FTTC

Gulfview Heights Planned Jul-Dec 2018

Mawson Lakes Planned Jul-Dec 2018 FTTC

Parafield Unclear

Salisbury South Unclear

Andrews Farm 5SMF Q1 2017 Planned Oct-Dec 2017 FTTN 17100

Angle Vale Planned Oct-Dec 2017

Blakeview Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 108

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 109: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

107

Craigmore Planned Jul-Dec 2018

Davoren Park Planned Jan-Jun 2018

Elizabeth North Planned Jan-Jun 2018

Munno Para Planned Jan-Jun 2018

Munno Para Downs Flipped? FW planned

Munno Para West Planned Oct-Dec 2017

Penfield Planned Jan-Jun 2018

Smithfield Planned Oct-Dec 2017

Smithfield Plains Planned Jan-Jun 2018

Cherry Gardens 5STI Q1 2017 Build comm FW 1890

Clarendon Build comm

Compass Heights Unclear

Crafers West Build comm

Hope Forest Build comm

Kangarilla Build comm

Longwood North Build comm

Meadows Build comm

Mylor Build comm

Myponga Planned

Scott Creek Build comm

Tailem Bend 5TMB Q2 2016 Available FTTN 1100

Wellington East Planned 2020

Wellington East 5TMB Q1 2017 Planned 2020 FW 130

Two Wells 5TWO Feb 2016 Available FTTN 800

Virginia Available

Angle Vale 5TWO Q1 2017 Build comm FW 3350

Edinburgh Unclear

Evanston South Build comm

Gawler West Build comm

Hillier Build comm

Lewiston East Build comm

Port Gawler Planned

iTnews’ reconstructed NBN three-year plan 109

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 110: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

108

Roseworthy Build comm

Two Wells Planned

Virginia Planned

Wasleys Build comm

Waterloo Corner Planned

Tumby Bay 5TYB H1 2017 Planned Jan-Jun 2018 FTTN 1100

Brookyln Park 5WES H1 2017 Planned Jan-Jun 2018 HFC 14000

Cowandilla Planned Oct-Dec 2017

Flinders Park Build comm Dec 2017

Hilton Build comm Dec 2017

Lockleys Build comm Dec 2017

Mile End Build comm Dec 2017

Richmond Build comm Dec 2017

Thebarton Planned Oct-Dec 2017

Torrensville Build comm Dec 2017

Underdale Planned Jan-Jun 2018

West Richmond Build comm Dec 2017

Mile End South 5WES H2 2017 Planned Jan-Jun 2019 FTTN 1600

Thebarton Build comm Dec 2017

Whyalla 5WHL Mar 2016 Build comm Apr 2017 FTTN 11000

Whyalla Jenkins Build comm Apr 2017

Whyalla Norrie Build comm Apr 2017

Whyalla Playford Build comm Apr 2017

Whyalla Stuart Build comm Apr 2017

Edithburgh 5YOW Feb 2016 Build comm FW 370

Yorketown 5YOW Q1 2017 Build comm Jun 2017 FTTN 500

Albany 6ALN Mar 2016 Build comm FW 290

Albany 6ALN Q1 2017 Planned Oct-Dec 2017 FTTN 16500

Bayonet Head Planned Oct-Dec 2017

Big Grove Planned Oct-Dec 2017

Centennial Park Planned Oct-Dec 2017Collingwood Heights Planned Oct-Dec 2017

iTnews’ reconstructed NBN three-year plan 110

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 111: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

109

Collingwood Park Planned Oct-Dec 2017

Emu Point Planned Oct-Dec 2017

Gledhow Build comm No date

Lange Planned

Little Grove Planned Oct-Dec 2017

Lockyer Planned Jan-Jun 2018

Lower King Planned Oct-Dec 2017

McKail Planned Oct-Dec 2017

Middleton Beach Planned Jan-Jun 2018

Milpara Planned Oct-Dec 2017

Mira Mar Planned Jan-Jun 2018

Mount Clarence Planned Jan-Jun 2018

Mount Melville Planned Oct-Dec 2017

Orana Planned Jan-Jun 2018

Robinson Planned Oct-Dec 2017

Spencer Park Planned Jan-Jun 2018

Torndirrup Planned Oct-Dec 2017

Walmsley Unclear

Warrenup Planned Oct-Dec 2017

Yakamia Planned Jan-Jun 2018

Bateman 6APP H1 2016 Available HFC 11100

Bull Creek Available

Leeming Available

Murdoch Available

North Lake Build comm Mar 2017

Winthrop Available

Armadale 6ARM Q2 2016 Build comm Jun 2017 FTTP, FTTN 22000

Bedfordale Build comm Jun 2017

Brookdale Build comm Apr 2017

Byford Build comm Apr 2017

Darling Downs Build comm Apr 2017

Forrestdale Build comm Apr 2017

iTnews’ reconstructed NBN three-year plan 111

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 112: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

110

Harrisdale Available

Haynes Build comm Apr 2017

Hilbert Build comm Apr 2017

Mount Nasura Available / Build comm Now / Apr 2017

Mount Richon Build comm Jun 2017

Piara Waters Available

Seville Grove Build comm Apr 2017

Darling Downs 6ARM Q1 2017 Planned FW 1180

Forrestdale Planned

Hilbert Planned

Oakford Build comm

Wandi Build comm

Wandi North Planned

Ascot 6ASO Q1 2017 Planned Jan-Jun 2018 FTTN 15500

Belmont Planned Jan-Jun 2018

Cloverdale Planned Jan-Jun 2018

Kewdale Planned Jan-Jun 2018

Perth Airport Planned Jan-Jun 2018

Redcliffe Planned Jan-Jun 2018

Rivervale Planned Jan-Jun 2018

Australind 6AUS Q4 2016 Build comm May 2017 FTTN 6800

Leschenault Build comm Apr 2017

Roelands Build comm Aug 2017

Augusta 6AUU Q3 2016 Available FTTN 1200

Baldivis 6BAL H1 2018 Planned Jan-Jun 2019 FTTC FTTN 7300

Rolling Green 6BKH Q1 2017 Not on map FW 740

Rolling Green North Not on map

Wooroloo East Planned

Wooroloo West Build comm

Wundowie West Planned

Brookton 6BKT Q4 2016 Build comm FW 130

Bilingurr 6BRM Q3 2016 Unclear FTTN 7000

iTnews’ reconstructed NBN three-year plan 112

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 113: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

111

Broome Planned Oct-Dec 2017

Cable Beach Planned Oct-Dec 2017

Djugun Planned Oct-Dec 2017

Minyirr Planned Oct-Dec 2017

Ashfield 6BSD Q4 2016 Planned Oct-Dec 2017 FTTN 21600

Bassendean Build comm / Planned Aug 2017 / Oct-Dec 2017

Beechboro Build comm Oct 2017

Caversham Build comm Oct 2017

Eden Hill Build comm Oct 2017

Guildford Build comm Nov 2017

Kiara Build comm Oct 2017

Lockridge Build comm Oct 2017

Morley Build comm Oct 2017

South Guildford Build comm Nov 2017

Yallingup East 6BUS Jan 2016 Build comm FW 260

Abbey 6BUS Mar 2016 Build comm Feb 2017 FTTN 11500

Bovell Available

Broadwater Build comm Feb 2017

Busselton Available

Geographe Available

Marybrook Build comm Feb 2017

Vasse Additional work No date

West Busselton Build comm Feb 2017

Yalyalup Available

Bertram 6CGE Q2 2016 Build comm Feb 2017 FTTN 13600

Calista Build comm Jul 2017

Casuarina Build comm Feb 2017

Hope Valley Build comm May 2017Kwinana Town Centre Build comm Jul 2017

Leda Build comm Apr 2017

Medina Build comm May 2017

Naval Base Build comm May 2017

iTnews’ reconstructed NBN three-year plan 113

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 114: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

112

Orelia Build comm May 2017

Parmelia Build comm Jul 2017

The Spectacles Build comm Feb 2017

Wattleup Build comm May 2017

Wellard Build comm Feb 2017

Cunderdin 6CND Q4 2016 Build comm Aug 2017 FTTN 500

Canning Vale 6CNV H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 27600

Gosnells Planned Jul-Dec 2018 FTTC/N

Huntingdale Planned Jul-Dec 2018 FTTC/N

Martin Planned Jul-Dec 2018 FTTC/N

Southern River Planned Jul-Dec 2018 FTTC/N

Capel 6CPL Q2 2016 Build comm Apr 2017 FTTN 1500Peppermint Grove Beach Build comm Apr 2017

Claremont 6CTO H2 2016 Build comm Mar 2017 HFC 13700

Cottesloe Planned Jan-Mar 2017

Karrakatta Unclear

Mosman Park Planned Apr-Jun 2017

Mount Claremont Planned Jan-Mar 2017

Peppermint Grove Planned Apr-Jun 2017

Swanbourne Planned Jan-Mar 2017

Claremont 6CTO H2 2018 Planned Jan-Jun 2018 FTTN 1500

Brockman 6CVN H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 2400

Brown Range Planned Jan-Jun 2018 FTTC/N

Carnarvon Planned Jan-Jun 2018

East Carnarvon Planned Jan-Jun 2018 FTTC/N

Greys Plain Planned Jan-Jun 2018

Kingsford Planned Jan-Jun 2018 FTTC/N

Morgantown Planned Jan-Jun 2018

South Carnarvon Planned Jan-Jun 2018

Dunsborough North 6DBG Sep 2015 Build comm FW 800

Dunsborough South Build comm

Yallingup Available

iTnews’ reconstructed NBN three-year plan 114

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 115: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

113

Yallingup Siding Available

Dunsborough 6DBG Q2 2016 Build comm Aug 2017 FTTN 4700

Eagle Bay Build comm Aug 2017

Quindalup Build comm Jun 2017

Dampier 6DMP H1 2017 Planned Jan-Jun 2018 FTTN 500

Dongara 6DNG Jan 2016 Build comm Apr 2017 FTTN 2400

Port Denison Build comm Apr 2017

Dongara 6DNG H1 2018 Planned FW 520

Milo Planned

Mingenew Planned

Denham 6DNH H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 700

Hazelvale 6DNK Q3 2016 Available FW 230

Peaceful Bay Build comm

Denmark 6DNK Q3 2016 Build comm Aug 2017 FTTN 2000

Ocean Beach Build comm Aug 2017

Donnybrook 6DNY Q2 2016 Available FTTN 1400

Yabberup 6DNY Q4 2016 Build comm FW 100

Derby 6DRB Q4 2016 Planned Oct-Dec 2017 FTTN 1900

Bullsbrook 6ELB Q1 2017 Build comm FW 2810

Bullsbrook East Build comm

Bullsbrook North Build comm

Bullsbrook West Build comm

Dayton Planned

East Baskerville Build comm

Hazelmere Planned

Herne Hill Planned

Lower Chittering Build comm

Millendon Hill South Build comm

South Chittering Planned

Upper Swan Build comm

Ellenbrook 6ELB H2 2017 Planned Jan-Jun 2019 HFC 5400

Aveley 6ELB H1 2018 Planned Jan-Jun 2019 FTTN 3100

iTnews’ reconstructed NBN three-year plan 115

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 116: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

114

Belhus Planned Jan-Jun 2019

The Vines Planned Jan-Jun 2019

Upper Swan Planned Jan-Jun 2019

Castletown 6ESP Q3 2016 Planned Oct-Dec 2017 FTTN 5600

Chadwick Planned Oct-Dec 2017

Esperance Planned Oct-Dec 2017

Nulsen Planned Oct-Dec 2017

Sinclair Planned Oct-Dec 2017

West Beach Planned Oct-Dec 2017

Exmouth 6EXM H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 1800

Alexander Heights 6GIR H1 2017 Planned Jan-Mar 2018 HFC 14700

Ballajura Planned Jul-Sep 2017

Greenwood Planned Jul-Dec 2018

Marangaroo Planned Oct-Dec 2017

Mirrabooka Planned Jul-Sep 2017

Balga 6GIR H2 2017 Planned Jan-Jun 2018 FTTN 11700

Girrawheen Planned Jan-Jun 2018

Koondoola Planned Jan-Jun 2018

Malaga Unclear

Carine 6HAM H2 2017 Planned Jul-Dec 2018 HFC 7800

Duncraig Planned Jul-Dec 2018

Sorrento Planned Jul-Dec 2018

Watermans Bay Planned Jul-Dec 2018

Carine 6HAM H1 2018 Planned Jul-Dec 2018 FTTN 13900

Duncraig Planned Jul-Dec 2018

Greenwood Planned Jul-Dec 2018

Hamersley Planned Jul-Dec 2018

Karrinyup Planned Jul-Dec 2018

Marmion Planned Jul-Dec 2018

North Beach Planned Jul-Dec 2018

Sorrento Planned Jul-Dec 2018

Trigg Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 116

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 117: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

115

Warwick Planned Jul-Dec 2018

Bouvard 6HER Q2 2016 Build comm No date FTTN 14400

Dawesville Available

Erskine Build comm Feb 2017

Falcon Build comm Feb 2017

Halls Head Available

Wannanup Build comm Feb 2017

Beaconsfield 6HIL Q3 2016 Build comm Jul 2017 FTTN 29200

Coolbellup Build comm Mar 2017

Fremantle Build comm / Planned May 2017 / Jul-Sep 2017

Hamilton Hill Build comm Aug 2017

Hilton Build comm Jun 2017

Kardinya Build comm Mar 2017

North Coogee Build comm Jul 2017

North Fremantle Build comm Jul 2017

North Lake Build comm Mar 2017

O'Connor Build comm Mar 2017

Samson Build comm Jun 2017

South Fremantle Build comm Jul 2017

White Gum Valley Build comm Jun 2017

Willagee Build comm Mar 2017

Hopetoun 6HOP Q3 2016 Build comm Mar 2017 FTTN 1000

Harvey 6HRV Q2 2016 Build comm No date FTTN 1400

Connolly 6JDL H1 2016 Available HFC 5300

Joondalup Build comm Jul 2017

Ocean Reef Available

Burns Beach 6JDL H1 2017 Planned Jan-Jun 2018 FTTN 9900

Currambine Planned Jan-Jun 2018

Iluka Planned Jan-Jun 2018

Joondalup Planned Jul-Dec 2018

Kinross Planned Jan-Jun 2018

Atwell 6JTS H1 2017 Planned Jan-Jun 2018 FTTN 16900

iTnews’ reconstructed NBN three-year plan 117

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 118: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

116

Aubin Grove Planned Jan-Jun 2018

Banjup Planned Jan-Jun 2018

Beeliar Planned Jan-Jun 2018

Cockburn Central Planned Jan-Jun 2018

Hammond Park Planned Jan-Jun 2018

Henderson Planned Jan-Jun 2018

Jandakot Planned Jan-Jun 2018

Munster Planned Jan-Jun 2018

Success Planned Jan-Jun 2018

Wandi Planned Jan-Jun 2018

Jurien Bay 6JUR Mar 2016 Build comm FW 130

Baynton 6KAH Q4 2016 Planned Jan-Jun 2018 FTTN 7200

Bulgarra Planned Oct-Dec 2017

Gap Ridge Planned Jan-Jun 2018

Karratha Planned Jan-Jun 2018Karratha Industrial Estate Planned Jan-Jun 2018

Millars Well Planned Jan-Jun 2018

Mulataga Planned Oct-Dec 2017

Nickol Planned Jan-Jun 2018

Pegs Creek Planned Jan-Jun 2018

Stove Hill Unclear

Bickley 6KAL Q1 2017 Build comm FW 330

Pickering Brook Planned

Bickley 6KAL H1 2018 Planned Jan-Jun 2018 FTTN 8000

Carmel Planned Jan-Jun 2018

Gooseberry Hill Planned Jan-Jun 2018

Kalamunda Planned Jan-Jun 2018

Lesmurdie Planned Jan-Jun 2018

Piesse Brook Planned Jan-Jun 2018

Walliston Planned Jan-Jun 2018

Kambalda East 6KAM H1 2017 Planned Jul-Dec 2018 FTTN 1300

Kambalda West Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 118

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 119: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

117

Katanning 6KAT Q4 2016 Build comm Apr 2017 FTTN 2100

Kellerberrin 6KBR H2 2017 Planned Jul-Dec 2018 FTTN 600

Camillo 6KEL Q3 2016 Build comm Apr 2017 FTTN 10400

Champion Lakes Build comm Aug 2017

Kelmscott Build comm May 2017

Mount Nasura Build comm Apr 2017

Roleystone Build comm Apr 2017

Seville Grove Build comm Apr 2017

Boulder 6KGL Q4 2016 Planned Jan-Jun 2018 FTTN 14100

Broadwood Planned Jan-Jun 2018

Hannans Planned Jan-Jun 2018

Kalgoorlie Planned Jan-Jun 2018

Karlkurla Planned Jan-Jun 2018

Lamington Planned Jan-Jun 2018

Mullingar Planned Jan-Jun 2018

Piccadilly Planned Jan-Jun 2018

Somerville Planned Jan-Jun 2018

South Boulder Planned Jan-Jun 2018

South Kalgoorlie Planned Jan-Jun 2018

Victory Heights Planned Jan-Jun 2018

West Lamington Planned Jan-Jun 2018

Williamstown Planned Jan-Jun 2018

Kununurra 6KNR Q4 2016 Planned Jan-Jun 2018 FTTN 2100

Kojonup 6KOJ Q4 2016 Build comm May 2017 FTTN 500

Darch 6KSL Q2 2016 Available FTTN 9900

Edgewater Planned Jul-Dec 2018

Landsdale Build comm Apr 2017

Madeley Build comm Apr 2017

Kingsley 6KSL H1 2017 Planned Jul-Sep 2017 HFC 7500

Woodvale Planned Jul-Dec 2020

Green Head 6LEA Q3 2016 Build comm Apr 2017 FTTN 900

Leeman Build comm Apr 2017

iTnews’ reconstructed NBN three-year plan 119

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 120: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

118

Lancelin 6LNC Q3 2016 Build comm May 2017 FTTN 1500

Ledge Point Build comm May 2017

Bullsbrook 6LWC H1 2018 Planned Jan-Jun 2018 FTTN 1100

Muchea Flipped Planned FW

Frankland River 6MBA Q3 2016 Planned FW 270

Kendenup East Available

Tenterden East Available

Mount Barker 6MBA Q4 2016 Build comm Nov 2017 FTTN 1000

Jane Brook 6MDD H2 2018 Planned Jul-Dec 2018 FTTC FTTN 6400

Middle Swan Unclear

Red Hill Flipped? FW planned

Stratton Planned Jul-Dec 2018

Swan View Build comm Oct 2017

Merredin 6MDI Sep 2015 Available FW 120

Merredin 6MDI H1 2017 Planned Jan-Jun 2018 FTTN 1800

Baldivis 6MDJ Q1 2017 Build comm FW 1860

Baldivis South Build comm

Cardup Build comm

Karnum South Unclear

Mardella South Build comm

Mundijong Build comm

Wellard Planned

Cardup 6MDJ H2 2017 Build comm Apr 2017 FTTN 1200

Jarrahdale Planned Jan-Jun 2018

Mundijong Planned Jan-Jun 2018 FTTC/N

Serpentine Planned Jan-Jun 2018 FTTC/N

Bellevue 6MDL Q4 2016 Build comm Jul 2017 FTTN 20300

Boya Build comm Nov 2017

Darlington Build comm Nov 2017

Gooseberry Hill Build comm Jul 2017

Greenmount Build comm Oct 2017

Hazelmere Build comm Jul 2017

iTnews’ reconstructed NBN three-year plan 120

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 121: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

119

Helena Valley Build comm Oct 2017

High Wycombe Build comm Oct 2017

Koongamia Build comm Oct 2017

Maida Vale Build comm Oct 2017

Midland Build comm Jul 2017

Midvale Build comm Jul 2017

Swan View Build comm Oct 2017

Viveash Planned Oct-Dec 2017

Woodbridge Planned Oct-Dec 2017

Bailup 6MDN Q1 2017 Planned FW 1890

Chidlow East Build comm

Chidlow North Build comm

Gidgegannup Planned

Glen Forrest Planned

Parkerville North Planned

Sawyers Valley Planned

South Stoneville Planned

Chidlow 6MDN H2 2018 Planned Jan-Jun 2019 FTTC FTTN 5500

Glen Forrest Planned Jan-Jun 2019 FTTC

Mahogany Creek Planned Jan-Jun 2019 FTTC

Mount Helena Planned Jan-Jun 2019 FTTC

Mundaring Planned Jan-Jun 2019 FTTC/N

Parkerville Planned Jan-Jun 2019 FTTC

Sawyers Valley Flipped? Planned FW

Stoneville Planned Jan-Jun 2019 FTTC

Beldon 6MLO H1 2017 Planned Apr-Jun 2017 HFC 19300

Craigie Planned Apr-Jun 2017

Heathridge Planned Apr-Jun 2017

Hillarys Planned Jul-Sep 2017

Kallaroo Planned Apr-Jun 2017

Mullaloo Planned Apr-Jun 2017

Ocean Reef Planned Apr-Jun 2017

iTnews’ reconstructed NBN three-year plan 121

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 122: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

120

Padbury Planned Jul-Sep 2017

Moora 6MRA Q4 2016 Build prep Jul-Sep 2017 FTTN 900

Margaret River 6MRG Q4 2016 Build comm Oct 2017 FTTN 3700

Witchcliffe Build comm Oct 2017

Nannup 6NNU Q3 2016 Planned FW 180

Narrogin 6NRG Q3 2016 Build comm Feb 2017 FTTN 2400

Norseman 6NSM Q4 2016 Build comm Jul 2017 FTTN 900

Northam 6NTM Q3 2016 Build comm Mar 2017 FTTN 3900

Newman 6NWM H2 2017 Planned Jan-Jun 2018 FTTN 2600

Paraburdoo 6PDO H2 2017 Planned Jan-Jun 2018 FTTN 700

Port Hedland 6PHE Q1 2017 Planned Jan-Jun 2018 FTTN 7200

South Hedland Planned Jan-Jun 2018

Wedgefield Planned Jan-Jun 2018

East Perth 6PIE Q4 2016 Flipped Jul-Dec 2018 FTTC/B FTTN 23600

Highgate Build comm / Planned Jun 2017 / Jul-Dec 2018 FTTC/N

Mount Lawley Build comm / Planned Jun 2017 / Jul-Dec 2018 FTTC/N

North Perth Build comm / Planned Jun 2017 / Jul-Dec 2018 FTTC/N

Northbridge Planned Jan-Jun 2019 FTTC

Perth Planned Jul-Dec 2018 FTTC

Perth West Planned Jul-Dec 2018

Pemberton 6PMB H1 2018 Planned FW 150

Alfred Cove 6PMY H1 2017 Planned Jan-Mar 2018 FTTC FTTN 18600

Attadale Planned Jan-Mar 2018

Bicton Planned Jan-Mar 2018

Booragoon Planned Jan-Mar 2018 FTTC

East Fremantle Planned Jan-Mar 2018

Melville Planned Jul-Dec 2018

Myaree Planned Jan-Mar 2018 FTTC

Palmyra Planned Jan-Mar 2018

Dwellingup 6PNJ Jan 2016 Build comm FW 520

Lakelands Build comm

Parklands Build comm

iTnews’ reconstructed NBN three-year plan 122

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 123: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

121

Pinjarra East Build comm

Preston Beach 6PRE H1 2018 Build comm FW 380

Carabooda 6QIN Q1 2017 Planned FW 230

Neerabup West Planned

Roebourne 6RBR H1 2017 Planned Jan-Jun 2018 FTTN 600

Ferndale 6RIV H2 2017 Planned Jan-Jun 2018 FTTN 16500

Lynwood Planned Jan-Jun 2018

Parkwood Planned Jan-Jun 2018

Riverton Planned Jan-Jun 2018

Rossmoyne Planned Jan-Jun 2018

Shelley Planned Jan-Jun 2018

Willetton Planned Jan-Jun 2018

Cooloongup 6RKH Feb 2016 Build comm Feb 2017 FTTN 22600

East Rockingham Build comm Jul 2017

Hillman Build comm Feb 2017

Peron Available

Rockingham Available

Safety Bay Build comm Apr 2017

Shoalwater Available

Waikiki Available

Scarborough 6SCB H2 2018 Planned Jan-Jun 2018 FTTN 6600

Wembley Downs Planned Jul-Dec 2018

Southern Cross 6SCR H2 2017 Planned Jan-Jun 2018 FTTC/N FTTN 600

Karnup 6SEC H2 2018 Unclear FTTN 14700

Lakelands Planned Jul-Dec 2018 FTTC/B/N

Port Kennedy Planned Jul-Dec 2018 FTTC/N

Secret Harbour Planned Jul-Dec 2018 FTTC/N

Warnbro Planned Jul-Dec 2018 FTTC/N

Bibra Lake 6SPR Q1 2017 Planned Oct-Dec 2017 FTTN 11200

Coogee Planned Oct-Dec 2017

Hamilton Hill Build comm Jun 2017

Munster Planned Jan-Jun 2018

iTnews’ reconstructed NBN three-year plan 123

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 124: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

122

North Coogee Build comm Jul 2017

Spearwood Planned Oct-Dec 2017

Como 6SPT H2 2016 Unclear HFC 2500

Crawley 6SUB H2 2016 Planned Apr-Jun 2017 HFC 15500

Daglish Planned Apr-Jun 2017

Dalkeith Planned Jul-Sep 2017

Jolimont Planned Jan-Jun 2018

Nedlands Planned Jul-Sep 2017

Shenton Park Planned Apr-Jun 2017

Subiaco Planned Oct-Dec 2017

West Leederville Planned Jan-Jun 2018

Dumbarton 6TOO Q4 2016 Flipped? FW planned FTTN 800

Toodyay Build comm Jul 2017

Tom Price 6TPC H2 2017 Planned Jan-Jun 2018 FTTN 1300

Balcatta 6TUT H2 2018 Planned Jan-Jun 2018 FTTN 22700

Balga Planned Jan-Jun 2018

Nollamara Planned Jan-Jun 2018

Stirling Planned Jan-Jun 2018

Tuart Hill Planned Jan-Jun 2018

Westminster Planned Jan-Jun 2018

Yokine Planned Jan-Jun 2018

Ashby 6WAN H2 2017 Planned Jul-Dec 2018 FTTC/N FTTN 21400

Banksia Grove Planned Jul-Dec 2018 FTTC/N

Carramar Planned Jul-Dec 2018 FTTC/N

Gnangara Planned Jul-Dec 2018

Hocking Planned Jul-Dec 2018

Jandabup Planned Jul-Dec 2018 FTTC/N

Mariginiup Planned Jul-Dec 2018

Neerabup Planned No date

Pearsall Planned Jul-Dec 2018 FTTC/N

Sinagra Planned Jul-Dec 2018 FTTC/N

Tapping Planned Jul-Dec 2018

iTnews’ reconstructed NBN three-year plan 124

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 125: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

123

Wangara Planned Jul-Dec 2018 FTTC/N

Wanneroo Planned Jul-Dec 2018 FTTC/N

Gabbadah 6WDE Q3 2016 Build comm Aug 2017 FTTN 1100

Guilderton Build comm Aug 2017

Seabird Build comm Aug 2017

Woodridge Build comm Aug 2017

Wagin 6WGI Q3 2016 Build comm Mar 2017 FTTN 900

Point Samson 6WIK H1 2017 Planned Jan-Jun 2018 FTTN 1200

Wickham Planned Jan-Jun 2018

Churchlands 6WMB H2 2017 Planned Jan-Jun 2018 HFC 7900

Floreat Planned Jan-Jun 2018

Herdsman Planned Jan-Jun 2018

Jolimont Planned Jan-Jun 2018

Wembley Planned Jan-Jun 2018

Wongan Hills 6WNG Q4 2016 Build comm May 2017 FTTN 600

Waroona 6WRN Q2 2016 Available FTTN 1300

Two Rocks 6YAN H2 2017 Planned Jan-Jun 2018 FTTN 3600

Yanchep Planned Jan-Jun 2018

North Yunderup 6YND H2 2018 Planned Jan-Jun 2018 FTTC/N FTTN 1900

South Yunderup Planned Jan-Jun 2018

York 6YOR Q4 2016 Planned Oct-Dec 2017 FTTN 1700

Bridport 7BDP Q3 2016 Build comm Jun 2017 FTTN 1100

Beaconsfield 7BEL Q3 2016 Build comm Jun 2017 FTTN 1500

Beauty Point Build comm Jun 2017

Acton 7BUI Mar 2016 Build comm Jun 2017 FTTN 14500

Brooklyn Build comm Jun 2017

Burnie Build comm Mar 2017

Cooee Build comm May 2017

Downlands Build comm Jun 2017

East Cam Build comm May 2017

Emu Heights Build comm Feb 2017

Havenview Build comm Feb 2017

iTnews’ reconstructed NBN three-year plan 125

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 126: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

124

Hillcrest Build comm Mar 2017

Montello Build comm Mar 2017

Ocean Vista Build comm May 2017

Park Grove Build comm May 2017

Parklands Build comm May 2017

Romaine Build comm Jun 2017

Shorewell Park Build comm May 2017

South Burnie Build comm Feb 2017

Upper Burnie Build comm Jun 2017

Wivenhoe Build comm Feb 2017

Clifton Beach 7CRE Q3 2016 Build comm Aug 2017 FTTN 1200

Cremorne Build comm Aug 2017

Sandford Build comm Aug 2017

Dover 7CYE Nov 2015 Build comm FW 1340

Geeveston Available

Lune River Build comm

Southport Build comm

Surveyors Bay Available

Tylers Hill Build comm

Cygnet 7CYE Q2 2016 Build comm Mar 2017 FTTN 500

Aberdeen 7DER Dec 2015 Available FTTN 10000

Devonport Available

Don Available

Miandetta Build comm May 2017

Quoiba Build comm May 2017

Spreyton Build comm May 2017

Stony Rise Build comm May 2017

Tugrah Build comm May 2017

Carlton 7DSF Jan 2016 Build comm Feb 2017 FTTN 4000

Dodges Ferry Build comm Feb 2017

Forcett Build comm Feb 2017

Lewisham Build comm Feb 2017

iTnews’ reconstructed NBN three-year plan 126

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 127: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

125

Primrose Sands Build comm Feb 2017

Ambleside 7ETD Q2 2016 Build comm Feb 2017 FTTN 4200

East Devonport Build comm Feb 2017

Latrobe Build comm Mar 2017

West Hobart Available

Catos Hill 7HUL Feb 2016 Build comm FW 380

Chimney Pot Build comm

Franklin 7HUL Q2 2016 Build comm May 2017 FTTN 1800

Huonville Build comm May 2017

Ranelagh Build comm May 2017

Grindelwald 7LEG Jan 2016 Available FTTN 1900

Legana Available

Swan Bay North 7LEG H1 2018 Available FW 140

Longford 7LGF Q2 2016 Mar 2017 FTTN 1700

Coningham 7MGT Q2 2016 Build comm Mar 2017 FTTN 1700

Electrona Build comm Mar 2017

Lower Snug Build comm Mar 2017

Margate Build comm Mar 2017

Snug Build comm Mar 2017

Margate West 7MGT Q3 2016 Build comm FW 500

Tinderbox Build comm

Orford 7ORF Q2 2016 Build comm Jun 2017 FTTN 1200

Spring Beach Build comm Jun 2017

Heybridge 7PEI Q2 2016 Build comm May 2017 FTTN 2200

Penguin Build comm May 2017

Sulphur Creek Build comm May 2017

Devon Hills 7PER Q3 2016 Build comm Jul 2017 FTTN 1500

Perth Build comm Jul 2017

Brighton 7PON Q2 2016 Build comm Mar 2017 FTTN 6000

Honeywood Build comm Mar 2017

Old Beach Build comm May 2017

Pontville Build comm Mar 2017

iTnews’ reconstructed NBN three-year plan 127

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 128: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

126

Hawley Beach 7PTS Q3 2016 Build comm Jul 2017 FTTN 2400

Port Sorell Build comm Jul 2017

Shearwater Build comm Jul 2017

Railton 7RAO Q3 2016 Flipped? FW FTTN 900

Sheffield Flipped? FW

Richmond 7RIC Q3 2016 Build comm Mar 2017 FTTN 500

Scamander 7SCA Q3 2016 Build comm Jun 2017 FTTN 500

Beechford 7SCE Sep 2015 Planned FW 870

Branxholm Build comm

Derby Village Build comm

Knockup Planned

Mount Horror Planned

Ringarooma North Build comm

Springfield Available

Winnaleah Available

Opossum Bay 7SHR Q3 2016 Build comm May 2017 FTTN 800

South Arm Build comm May 2017

St Helens 7STH H2 2017 Planned FW 130

Beaumaris 7STM H2 2017 Build comm FW 900

Falmouth Planned

Fingal Planned

North Cornwall Planned

St Marys Planned

Coles Bay East 7SWA Jan 2016 Available FW 220

Swansea 7SWA Q3 2016 Build comm May 2017 FTTN 700

Taroona 7TAR Q3 2016 Build comm Apr 2017 FTTN 1500

Forth 7ULN Q2 2016 Build comm Jun 2017 FTTN 6300

Leith Build comm Jun 2017

Turners Beach Build comm Jun 2017

Ulverstone Build comm Jun 2017

West Ulverstone Build comm May 2017

Hagley 7WST Feb 2016 Available FTTN 1000

iTnews’ reconstructed NBN three-year plan 128

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 129: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

127

Westbury Build comm No date

Wynyard 7WYN Q3 2016 Build comm Jun 2017 FTTN 2700Bonner, Casey, Forde, Hall 9BON H2 2017 Build comm Apr 2017 800

Acton 9CVI Q4 2016 Available / Build prep Jul-Sept 2017 FTTN 16900

Ainsle Planned Oct-Dec 2017

Braddon Planned/Built Oct-Dec 2017

Campbell Planned Oct-Dec 2017

City Available

Dickson Planned Oct-Dec 2017

Downer Build comm / Planned 01/05/2017 or Oct-Dec

Hackett Build comm May 2017

Lyneham Planned Jul-Dec 2018 FTTC

O'Connor Build prep/ Planned Jul-Sept 2017 / Jul-Dec 2018

Reid Planned Oct-Dec 2017

Turner Build comm Jul-Sept 2017

Watson Build comm May 2017

Chapman 9DKI H2 2018 Planned Jan-Jun 2019 FTTN-FTTP 18600

Chifley Planned Jan-Jun 2019

Curtin Planned Jan-Jun 2019

Deakin Planned Jan-Jun 2019

Duffy Planned Jan-Jun 2019

Fisher Planned Jan-Jun 2019

Garran Planned Jan-Jun 2019

Holder Planned Jan-Jun 2019

Hughes Planned Jan-Jun 2019

Lyons Planned Jan-Jun 2019

Phillip Planned Jan-Jun 2019

Rivett Planned Jan-Jun 2019

Stirling Planned Jan-Jun 2019

Tharwa Satellite

Waramanga Planned Jan-Jun 2019

Weston Available

iTnews’ reconstructed NBN three-year plan 129

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 130: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

128

Yarralumla Planned Jan-Jun 2019

Farrer 9KBA Q4 2016 Planned Jul-Dec 2017 FTTN 16800

Isaacs Planned Oct-Dec 2017

Kambah Build prep / Planned Jul-Sept 2017 / Oct-Dec 2017

Mawson Planned Oct-Dec 2017

O'Malley Planned Oct-Dec 2017

Oxley Planned Oct-Dec 2017

Pearce Planned Jul-Dec 2017

Torrens Planned Jul-Dec 2017

Wanniassa Planned Jul-Dec 2017

Acton 9SCU Q4 2016 Build prep Jul-Sept 2017 FTTN 23300

Charnwood Planned Jan-Jun 2018 FTTC/N

Dunlop Planned Jan-Jun 2018 FTTC/N

Evatt Planned Jan-Jun 2018

Florey Planned Jan-Jun 2018

Flynn Planned Jan-Jun 2018

Fraser Planned Jan-Jun 2018

Hawker Planned Jan-Jun 2018

Higgins Planned Jan-Jun 2018

Holt Planned Jan-Jun 2018

Latham Planned Jan-Jun 2018

Macgregor Planned Jan-Jun 2018

McKellar Planned Jan-Jun 2018

Melba Planned Jan-Jun 2018 FTTC/N

Page Planned Jan-Jun 2018

Scullin Planned Jan-Jun 2018 FTTC/N

Spence Planned Jan-Jun 2018

New rollout areas

NSW

Barden Ridge Planned Apr-Jun 2017 HFC

Burraneer Planned Jan-Jun 2019 FTTC HFC

iTnews’ reconstructed NBN three-year plan 130

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 131: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

129

Cronulla Planned Jan-Jun 2019 FTTC HFC

Woolooware Planned Jan-Jun 2019 FTTC HFC

East Hills Planned Jan-Jun 2019 FTTC HFC

Panania Planned Jan-Jun 2019 FTTC HFC

Picnic Point Planned Jan-Jun 2019 FTTC HFC

Revesby Planned Jan-Jun 2019 FTTC HFC

Revesby Heights Planned Jan-Jun 2019 FTTC HFC

Holsworthy Planned Jan-Jun 2018 HFC

Sandy Point Planned Jan-Jun 2018 FTTN

Pleasure Point Planned Jan-Jun 2018 FTTN

Hammondville Planned Jan-Jun 2018 HFC

Wattle Grove Planned Jan-Jun 2018 HFC

Padstow Planned Jan-Jun 2019 FTTC HFC

Campsie Planned Jul-Dec 2018 FTTP

Belfield Planned Jul-Dec 2020 FTTC

Enfield Planned Jul-Dec 2018 HFC

Burwood Planned Jul-Dec 2018 HFC

Burwood Heights Planned Jul-Dec 2018 HFC

Croydon Park Planned Apr-Jun 2017 HFC

Canada Bay Planned Jul-Dec 2018 HFC

Concord Planned Jan-Jun 2019 HFC

Cabarita Planned Jan-Jun 2019 HFC

Northmead Planned Jan-Jun 2019 HFC

Baulkham Hills Planned Jan-Jun 2019 HFC

North Parramatta Planned Jan-Jun 2019 HFC

Parramatta Planned Jan-Jun 2019 HFC

Westmead Planned Jul-Dec 2018 HFC

Oatlands Planned Jan-Jun 2019 HFC

Camellia Planned Jul-Dec 2018 FTTP

Rosehill Planned Jul-Dec 2018 HFC

Harris Park Planned Jul-Dec 2018 HFC

Marsden Park Planned Jul-Dec 2018 FTTC

iTnews’ reconstructed NBN three-year plan 131

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 132: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

130

Chatswood Planned Jul-Dec 2018 HFC

Chatswood West Planned Jan-Jun 2018 HFC

Northbridge Planned Jan-Jun 2019 HFC

Cammeray Planned Apr-Jun 2017 HFC

Killarney Heights Planned Apr-Jun 2017 HFC

Frenchs Forest Planned Apr-Jun 2017 HFC

Forestville Planned Apr-Jun 2017 HFC

Beacon Hill Planned Oct-Dec 2017 HFC

Narraweena Planned Jan-Jun 2019 HFC

Dee Why Planned Jan-Jun 2019 HFC

Cromer Planned Jan-Jun 2019 HFC

Collaroy Planned Jan-Jun 2019 HFC

Wheeler Heights Planned Jan-Jun 2019 HFC

Collaroy Plateau Planned Jan-Jun 2019 HFC

Terrey Hills Planned Jan-Mar 2018 FTTC

Duffys Forest Planned Jan-Mar 2018 FTTC

Kogarah Planned Jan-Jun 2019 FTTC

Carlton Planned Jan-Jun 2019 FTTC

Bronte Planned Apr-Jun 2017 HFC

Redfern Planned Jan-Jun 2019 HFC

Bogan Gate Build comm FW

Trundle Build comm FW

Geurie Build comm FW

Maryvale Build comm FW

Terrabella Build comm FW

Wongarbon Build comm FW

Benolong Build comm FW

Menah Build comm FW

Milroy Build comm FW

Burrundulla Build comm FW

Wilbetree Build comm FW

Victoria

iTnews’ reconstructed NBN three-year plan 132

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 133: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

131

North Essendon Planned Jan-Jun 2019 FTTC

Dallas Planned Jan-Jun 2019 FTTC

St Kilda Planned Jan-Jun 2019 HFC

St Kilda West Planned Jan-Jun 2019 HFC

Elwood Planned Jan-Jun 2019 HFC

Yellingbo Planned FW

Warranwood Planned Jan-Jun 2019 HFC

Park Orchards Planned Jan-Jun 2019 HFC

Bena Build comm FW

Krowera Build comm FW

Moyarra Build comm FW

Korumburra Build comm FW

Corinella Planned FW

Newhaven Build comm FW

Lang Lang East Build comm FW

Yannathan Build comm FW

Lang Lang Build comm FW

Caldermeade Build comm FW

Monomeith Build comm FW

Bayles Build comm FW

Catani Build comm FW

Nar Nar Goon Build comm FW

Pakenham South Build comm FW

Koo Wee Rup Build comm FW

Pakenham Build comm FW

Garfield Build comm FW

Vervale Build comm FW

Iona Build comm FW

Tynong Build comm FW

Tynong North Build comm FW

Garfield North Build comm FW

Bunyip North Build comm FW

130

Chatswood Planned Jul-Dec 2018 HFC

Chatswood West Planned Jan-Jun 2018 HFC

Northbridge Planned Jan-Jun 2019 HFC

Cammeray Planned Apr-Jun 2017 HFC

Killarney Heights Planned Apr-Jun 2017 HFC

Frenchs Forest Planned Apr-Jun 2017 HFC

Forestville Planned Apr-Jun 2017 HFC

Beacon Hill Planned Oct-Dec 2017 HFC

Narraweena Planned Jan-Jun 2019 HFC

Dee Why Planned Jan-Jun 2019 HFC

Cromer Planned Jan-Jun 2019 HFC

Collaroy Planned Jan-Jun 2019 HFC

Wheeler Heights Planned Jan-Jun 2019 HFC

Collaroy Plateau Planned Jan-Jun 2019 HFC

Terrey Hills Planned Jan-Mar 2018 FTTC

Duffys Forest Planned Jan-Mar 2018 FTTC

Kogarah Planned Jan-Jun 2019 FTTC

Carlton Planned Jan-Jun 2019 FTTC

Bronte Planned Apr-Jun 2017 HFC

Redfern Planned Jan-Jun 2019 HFC

Bogan Gate Build comm FW

Trundle Build comm FW

Geurie Build comm FW

Maryvale Build comm FW

Terrabella Build comm FW

Wongarbon Build comm FW

Benolong Build comm FW

Menah Build comm FW

Milroy Build comm FW

Burrundulla Build comm FW

Wilbetree Build comm FW

Victoria

iTnews’ reconstructed NBN three-year plan 133

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 134: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

132

Maryknoll Build comm FW

Nar Nar Goon North Build comm FW

Merrimu Build comm FW

Maddingley Build comm FW

Pentland Hills Build comm FW

Ingliston Build comm FW

Greendale Build comm FW

Ballan Build comm FW

Colbrook Build comm FW

Vite Vite Build comm FW

Lismore Build comm FW

Derrinallum Build comm FW

Larralea Build comm FW

Tyrendarra Build comm FW

Homerton Build comm FW

Taggerty Build comm FW

Buxton Build comm FW

QLD

Coorparoo Planned Jan-Jun 2018 HFC

Greenslopes Planned Jul-Dec 2018 HFC

Cannon Hill Planned Jan-Jun 2019 HFC

Teneriffe Planned Jul-Dec 2019 HFC

Fortitude Valley Planned Jul-Dec 2019 HFC

Fortitude Valley Planned Jan-Mar 2018 FTTC/B

Newstead Planned Jul-Dec 2019 HFC

Bowen Hills Planned Jul-Sep 2017 FTTN

Wacol Planned Oct-Dec 2017 FTTN

Shailer Park Planned Jul-Dec 2018 FTTN

Tanah Merah Planned Jul-Dec 2018 HFC

Glamorgan Vale Planned FW

Vernor Planned FW

Fairney View Planned FW

iTnews’ reconstructed NBN three-year plan 134

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 135: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

133

Wanora Planned FW

Marburg Planned FW

Glenrae Build comm FW

Boynewood Build comm FW

Riverleigh Build comm FW

Baffle Creek Build comm FW

Rules Beach Build comm FW

Deepwater Build comm FW

Berajondo Build comm FW

Rosedale Build comm FW

Yarwun Build comm FW

Lake Mary Build comm FW

SA

North Adelaide Planned Jan-Jun 2019 FTTC

Stirling North Build comm FW

Port Paterson Build comm FW

Winnienowie Build comm FW

Blanche Harbor Build comm FW

Commissariat Point Build comm FW

Port Augusta West Build comm FW

Lincoln Gap Build comm FW

Carriewerloo Build comm FW

Emeroo Build comm FW

Wami Kata Build comm FW

Quorn Build comm FW

Wilmington Build comm FW

Jamestown Build comm FW

Bundaleer North Build comm FW

Georgetown Build comm FW

Spalding Build comm FW

Mintaro Build comm FW

Farrell Flat Build comm FW

iTnews’ reconstructed NBN three-year plan 135

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 136: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

134

Hill River Build comm FW

Polish Hill River Build comm FW

Hoyleton Build comm FW

Halbury Build comm FW

Woolshed Flat Build comm FW

Stockport Build comm FW

Linwood Build comm FW

Freeling Build comm FW

Redbanks Build comm FW

Kangaroo Flat Build comm FW

Ward Belt Build comm FW

Gawler River Build comm FW

Coromandel East Build comm FW

Ironbark Build comm FW

Chapel Hill Build comm FW

Biggs Flat Build comm FW

Highland Valley Build comm FW

Woodchester Build comm FW

Hartley Build comm FW

Rockleigh Build comm FW

Harrogate Build comm FW

Woodside Build comm FW

Brukunga Build comm FW

Dawesley Build comm FW

Mount Barker Summit Build comm FW

Petwood Build comm FW

St Ives Build comm FW

Red Creek Build comm FW

Hay Valley Build comm FW

Saunderston Build comm FW

Cambrai Build comm FW

Murbko Build comm FW

iTnews’ reconstructed NBN three-year plan 136

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 137: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

135

Morgan Build comm FW

Kalangadoo Build comm FW

Trihi Build comm FW

Koorine Build comm FW

Glencoe Build comm FW

Kelly Build comm FW

Kimba Build comm FW

Paskeville Build comm FW

Kulpara Build comm FW

Sunnyvale Build comm FW

Weetulta Build comm FW

Arthurton Build comm FW

Maitland Build comm FW

Dowlingville Build comm FW

Sandilands Build comm FW

Stansbury Build comm FW

Port Vincent Build comm FW

Tickera Build comm FW

Alford Build comm FW

Wallaroo Plain Build comm FW

Ward Hill Build comm FW

WA

Thornlie Planned Jul-Dec 2018 FTTC

City Beach Planned Jan-Jun 2019 FTTC

Pemberton Planned Jul-Dec 2018 FTTN

Stake Hill Build comm FW

Keralup Build comm FW

North Dandalup Build comm FW

Karragullen Planned FW

ACT

Belconnen Planned Jul-Dec 2018 FTTC/N

Bruce Planned Jul-Dec 2018 FTTN, FTTP

iTnews’ reconstructed NBN three-year plan 137

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA

Page 138: iTnews’ reconstructed NBN three-year plan · Ry Crozier, iTnews journalist Guide to interpreting the document Suburbs are grouped by fibre or wireless serving area (FSA and WSA);

136

Lawson Planned Jul-Dec 2018 FTTB, FTTN

Kaleen Planned Jul-Dec 2018 FTTN

Giralang Planned Jul-Dec 2018 FTTC/N

Aranda Planned Jul-Dec 2018 FTTC/N

Cook Planned Jul-Dec 2018 FTTC/N

Macquarie Planned Jul-Dec 2018 FTTC/N

Weetangera Planned Jul-Dec 2018 FTTC/N

Kingston Planned Jan-Jun 2019 FTTC/B

Narrabundah Planned Jan-Jun 2019 FTTC/N

Fyshwick Planned Jan-Jun 2019 FTTC

Red Hill Planned Jan-Jun 2019 FTTC/P

Forrest Planned Jan-Jun 2019 FTTC/B

Gowrie Planned Jan-Jun 2019 FTTN

Monash Planned Jan-Jun 2019 FTTC

Isabella Plains Planned Jul-Dec 2018 FTTN

Bonython Planned Jul-Dec 2018 FTTN

Greenway Planned Jul-Dec 2018 FTTC/B

Richardson Planned Jul-Dec 2018 FTTC/N

Calwell Planned Jul-Dec 2018 FTTC/N

Theodore Planned Jul-Dec 2018 FTTC/N

Chisholm Planned Jul-Dec 2018 FTTN

Gilmore Planned Jul-Dec 2018 FTTN

MacArthur Planned Jul-Dec 2018 FTTN

Fadden Planned Jul-Dec 2018 FTTN

Gordon Planned Jul-Dec 2018 FTTC/N

Conder Planned Jul-Dec 2018 FTTN

Banks Planned Jul-Dec 2018 FTTC/N

iTnews’ reconstructed NBN three-year plan 138

Suburb FSA / WSA

3 year plan(Commenceconstruction) Rollout Map New map (Availability) FTTC/x change Service

Premises inFSA / WSA