ISPA Measure 2002 BG 16 P PE 009 WWTP Bourgas – Meden Rudnik

12
ISPA Measure 2002 BG 16 P PE 009 WWTP Bourgas – Meden Rudnik

description

ISPA Measure 2002 BG 16 P PE 009 WWTP Bourgas – Meden Rudnik. Works Contract. Commencement Date:15 th May 2007 Completion Date:31 st Dec. 2009 Physical Execution:100 % Financial Execution:100 % WWTP became operational on 21 st Dec. 2009 1 year DNP expired on 27 th Dec. 2010 - PowerPoint PPT Presentation

Transcript of ISPA Measure 2002 BG 16 P PE 009 WWTP Bourgas – Meden Rudnik

ISPA Measure 2002 BG 16 P PE 009

WWTP Bourgas – Meden Rudnik

Works Contract

• Commencement Date: 15th May 2007

• Completion Date: 31st Dec. 2009

• Physical Execution: 100 %

• Financial Execution: 100 %

• WWTP became operational on 21st Dec. 2009

• 1 year DNP expired on 27th Dec. 2010

• Performance Certificate was issued on 27th Dec. 2010

• Final Payment was made on 27th Dec. 2010

WWTP Meden Rudnik - Completed

WWTP Meden Rudnik (during DNP and operation)

WWTP Meden Rudnik(during DNP and operation)

Reconstruction of the Main Collector(implemented by Final Beneficiary)

Reconstruction of effluent channel(implemented by ViK Bourgas)

Site visit by reporters of TV France 3

WWTP Meden RudnikPublicity

Supervision Contract

• Commencement Date: 24th April 2007

• Completion Date: 31st March 2011

• Time elapsed: 100 %

• Financial Execution: 100 %

Compliance with Article 8of the Financing Memorandum

All other conditions under Article 8 of the FM are considered fulfilled.