Isolation Valve Installation Readiness

Trevor Smith/Mark Nichols 11 May 2010

MC 252 Incident Response

Page 2: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

2

Problem Statement

Capping of the well with the dual ram or isolation valve assembly will require:

•stabbing into a flange opening which may be obstructed by debris and flowing oil and gas

•aligning and bolting up a flange connection which is designed for make-up on the drill floor

•and performing this for the first time at 5000ft water depth, suspended from a drill rigProposal: perform onshore and/or onshore trials to

maximize probability of success

Page 3: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

MC 252 Site Overview

Page 4: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

Top of BOP Stack

Page 5: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

Mule Shoe Detail

Page 6: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

Readiness Summary

Flex Joint Capping Method - Readiness Status DRAFT

Item Comment Status Item Comment Status

Equipment Valve Assembly Issued to D&C at Berwick Ram Assembly Assembly by D&C at BerwickRunning Assembly Being assembed Running Assembly Being assembed

Pressure Cap Status unknown Pressure Cap Status unknownROV Tools Available - location to be confirmed ROV Tools Available - location to be confirmed

Vessels ROV Vessel Vessel TBD - briefing required ROV Vessel Vessel TBDMODU DDII Briefing required MODU DDII

Procedures Riser Removal Being updated by BP to Rev1 Riser Removal Being updated by BPFlange Removal Being developed by BP Eng. Flange Removal Being developed by BP Eng.Valve Running Developed by BP D&C Valve Running Developed by BP D&CFlange Make-up Being developed by BP Eng. Flange Make-up Being developed by BP Eng.

Trials Onshore Not in plan Onshore Not in planSite to be selected - BP Fourchon? Site to be selected - BP Fourchon?

Subsea Not in plan Subsea Not in planTest Stump/Mat: build & deploy Test Stump/Mat: build & deploy

Readiness Review Peer Review Peer Review

Legend Ready for useIn progress - on track

Potential risk 11-May-2010

Isolation Valve Dual Ram BOP

Page 7: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

Trial Objectives & Site Suitability

Issue to be checked or tested Onshore Test Suitability

Subsea Test Suitability

Alignment pin & plug make-up risks Risk of seal damage Befit or risk from pins & plug use Mule shoe engagement with pipe debris Flange rotation & bolt release ROV tool access & function/speed ROV crew familiarization & training Rig crew familiarization &training Ability to stab with rig X Ability to keep flange alignment during make-up

X

Flow effect on seals X XStabbing under flow X X

Page 8: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

Schedule

DRAFTActivities

Draft objectives

Establish plan

Fabricate Test Stump

Onshore Trial

Develop Trial Procedures

Approve Trial Procedures

Set-up Trial Site

Perform Onshore Trials

Modify Valve/Ram Assemblies

Ship Assemblies to DD-II

Offshore Trial

Ship Test Stump & Install on Seabed

Run DD-II Riser with Cap Assembly

Perform Trial

Modify Procedure

Go/No-Go Decision

Well Capping

Riser Cutting

Cap Well

22 23 24 2518 19 20 21Sun Mon Tue

11 12 13 14 15 16 17Wed Thu Fri SatSat Sun Mon TueTue Wed Thu Fri

Page 9: Isolation Valve Installation Readiness Trevor Smith/Mark Nichols 11 May 2010 MC 252 Incident Response.

Other Issues

• Decide if trials are necessary, if so which & when

• Define Accountabilities

• Confirm ROV vessel for flange unbolting

• Confirm ROVs for flange make-up (DD2 or other support vessel)