Islanding Scheme Uttar Pradesh - NRPCnrpc.gov.in/Reports/Other/Islanding_Up.pdfISLANDING SCHEME...
Transcript of Islanding Scheme Uttar Pradesh - NRPCnrpc.gov.in/Reports/Other/Islanding_Up.pdfISLANDING SCHEME...
ISLANDING SCHEME
UTTAR PRADESH
(February, 2013)
Uttar Pradesh Power Transmission Corporation Limited
Shakti Bhawan, 14 Ashok Marg, Lucknow
2
INDEX
CHAPTER NAME Page No.
1. Introduction
3-4
2. Overview of Uttar Pradesh Transmission System 5-6
3. General Philosophy on formation of Islands 7-10
4. Islanding Scheme for 5x210 MW Unchahar
Generating Station
11-14
5. Average Generation and dedicated load details of
proposed Island Scheme for Unchahar
15-18
6.0 Major Challenges And Way Forward
19-20
APPENDIX
I Minutes of 1st Meeting of Islanding Scheme Group held on 7-Aug-2012
II Transmission Map of U.P. Transmission Network (132 KV and above voltage)
III Single Line Diagrams
3
CHAPTER-1.0
1.0 Introduction
1.1. Twin grid failures on 30th & 31st July 2012 affecting the Northern Region (NR),
Eastern (ER) & North- Eastern (NER) regions stirred up the entire power sector in
the country and specially the Northern region. Considering the colossal impact of
these grid disturbances on the economy as well as on the daily life of the society,
Ministry of Power (MoP), Govt. of India (GoI), immediately constituted an enquiry
committee to investigate the reasons of these grid failures and to make suitable
recommendations to prevent its recurrence in future. The above committee
submitted its report on 16.08.2012. While deliberating on the reasons of grid
failure, the Committee, in its report, among various other recommendations also
recommended implementation of islanding schemes from grid security point of
view and its early restoration in case of any failure in future. The recommendations
of the committee in this regard are as quoted below:
"Effort should be made to design islanding scheme based on frequency sensing
relays so that in case of imminent grid failure, electrical islands can be formed.
These electrical islands can not only help in maintaining supply to essential
services but would also help in faster restoration of grid .
Action: CEA, RPCs, POWERGRID, STUs, SLDCs and Generators
Time Frame: 6 months"
1.2. The Expert Committee further formed five groups to look into various aspects
related to grid disturbances. One of the groups, headed by Member
Secretary, NRPC, was formed for exploring the possibilities and
4
implementing the islanding scheme in Northern Region. First meeting of the
islanding scheme group was held at NRPC office at New Delhi on
07.08.2012. Representatives from all the constituents from the Northern
Region attended the above meeting. The group agreed on various aspects &
modalities for implementation of the islanding scheme. The Minutes of above
meeting are enclosed as Appendix I.
1.4 In order to further identify & work out the modalities for taking up design &
implementation of islanding schemes in line with the recommendations of the
enquiry committee, provisions of Electricity Grid Code, guidelines of CEA,
NRPC, PGCIL etc., UPPTCL constituted a study-cum-implementation group
consisting of officers from Transmission Planning & Power System Study
Group, SLDC and field units. Further, a meeting of officers from UPPTCL,
SLDC, Uttar Pradesh RajyaVidyutUtpadan Nigam and representatives from
the Power Grid (Operation Services Group), was organized at the head
quarter level, wherein deliberations were held on the tentative islanding
schemes prepared by Power System Study group of UPPTCL.
1.5 Based on the inputs provided by NRPC/ Power Grid and in house
deliberations, UPPTCL has finalized the islanding scheme for 5 x 210 MW
Unchahar Generating Station of NTPC.
5
CHAPTER 2.0
2.0 OVERVIEW OF TRANSMISSION SYSTEM OF UTTAR PRADESH
2.1 The Transmission function in the state of Uttar Pradesh is being looked after
by U.P. Power Transmission Corporation Limited (UPPTCL), which is a State
Government owned company. UPPTCL maintains a very robust intra-State
Transmission System, which is part of the integrated “NEW” grid network. It
consists of 1 no. 765KV, 14 Nos. 400KV, 69 Nos. 220KV & 271 Nos. 132KV
substations with total transformation capacity of around 56844 MVA.
UPPTCL further has total line length of 411 ckms 765KV, 4260 ckms 400KV,
8099 ckms 220KV and 13800 ckms of 132KV lines. Transmission map of
Uttar Pradesh (132 KV & above voltages) is attached at Appendix II.
2.2 The total demand met by the transmission system of UPPTCL in the range of
8000 MW to 11500 MW. Out of this total demand, approximately 2500 MW is
met through State Government owned generating stations and balance 5500
to 8500 MW through IPP’s & co-generators in the State, allocations from the
centre sector generating stations, bilateral agreement and purchases through
power exchange.
2.3 To develop evacuation system for such large quantum of power, considering
dearth of funds with UPPTCL, the Government of U.P. has planned to
augment the State Transmission system through participation of private
players. Accordingly, contracts have been awarded to two private companies
to create additional transmission capacity of around 8000 MVA including 3
6
nos. 765 kV sub-stations with capacity of 9630 MVA, 9 nos. of 400 kV sub-
stations with capacity of 8320 MVA 1485 ckt. kms of 765 kV lines and 1780
ckt. kms of 400 kV lines.
2.4 As the State of Uttar Pradesh is also planning to procure additional power
through IPPs and ultra Mega Power Projects situated in other States, it is
also planning major intra-State network expansion linked to the development
of inter-State transmission network for evacuating power from these IPPs
and Ultra Mega Power Projects.
7
CHAPTER 3.0
3.0 GENERAL PHILOSOPHY FOR FORMATION OF ISLANDS
3.1 The Ministry of Power constituted a Committee to enquire into recent grid
disturbances on 30th& 31st July 2012. This committee in turn formed five
groups to look into various aspects related to grid disturbances. One of the
groups formed (headed by Member Secretary, NRPC) was to look into all
aspects of Islanding Scheme and explore the possibilities of its
implementation in the Northern Region.
3.2 The initial discussions of the above group were centered on the criteria for
formation of islands. In this regard some members suggested that the size of
the islands should be big as the chances its survival will be more due to high
inertia and stability. However, there was also an opinion that in order to form
bigger islands, more number of switching operations would be required, which
would considerable reduce the chances of success of Islanding. After detailed
discussion, it was agreed that criteria for formation of islands should not be
the geographical or electrical size but reliability of load-generation balance in
the islands.
3.3 The group agreed on following issues:
i. All control areas should endeavor to operationalize under frequency
based load shedding scheme as the first line of defense. Only when
8
this defense mechanism fails and frequency continues to fall further,
formation of islands should be initiated.
ii. The probability of survival of islands will be realistic only when all the
generating units are on free governor or on restricted governor mode of
operation in accordance with provisions of Indian Electricity Grid Code.
iii. Islanding scheme should be a two-tier scheme. At frequency level of
say 47.9 Hz, trigger for formation of islands comprising of more than
one generating stations along with pre-identified load should be
initiated. However, if frequency continues to fall further to say to 47.7
Hz, possibilities of forming smaller islands with pre-identified loads
should be explored.
iv. Islands should be created in such a manner that possibility of
generation exceeding load is more.
v. In case of hydro generators, islanding should be considered keeping
peak generation in mind. This is because, in low hydro season,
generation may be practically nil during off-peak hours and hence
forming of island may not be feasible.
vi. As the load-generation balance in pre-identified islands may change
due to seasonality of load, there would be need to review the scheme
9
on seasonal basis. Such review would also capture network changes
taking place in the interim period.
vii. As far as possible, major hospitals and other essential loads should be
incorporated in the islands. However, if this is not possible due to some
reasons, efforts should be made to extend supply from these islands to
essential loads on priority basis.
3.4 Based on the recommendations of the enquiry committee constituted by
MOP, Govt. of India, to investigate the reasons of Grid failure on 30th and 31st
July 2012, and minutes of Islanding Group dated 07.08.2012, UPPTCL on its
own constituted a study-cum-implementation group consisting of officers from
Transmission Planning & Power System Study Group, SLDC and field units
of transmission. Further, a meeting of officers from UPPTCL, SLDC, Uttar
Pradesh Rajya Vidyut Utpadan Nigam and representatives from the Power
Grid was organized at the head quarter level, wherein deliberations were held
on the tentative islanding schemes prepared by Power System Study group
of UPPTCL. During the above meeting successful models of Islanding
Schemes were discussed and deliberations were held on the following main
issues:
a. Size of Island
b. Frequency level at which Islanding should take place.
c. Possibilities of formation of smaller island in case of failure of bigger
island and the frequency for the same.
d. Identification of dedicated load for the purposes of forming an island.
10
e. Selection and monitoring of UFR.
f. Segregation of feeder and loads for different Schemes
g. Monitoring of Islanding Schemes for the purposes of load–Generation
balance.
h. House-load for survival of Island in case of extreme contingencies.
In the above meeting while deliberating on the above issues, it was suggested
that while Delhi may plan to implement a comprehensive Islanding Scheme
covering many generating stations the same may not be feasible for a State
like Uttar Pradesh, which has large geographical area and longer length of
lines with many inter-connections and loops. Accordingly, it was initially
decided that separate Islanding Schemes, for generating stations of
Unchhahar, Tanda, Roza&Parichha, as prepared by Power System Study
group of UPPTCL, only may be considered for its implementation. To make
the Islanding scheme fool proof it was further decided that two sets of under
frequency relays of different make and with different algorithm should be
utilized to isolate the island from the rest of the system.
Subsequently, in view of large demand supply gap in the State wherein large
quantum of load has to be shed on rotational basis to meet the load
generation balance, it was discussed that it may not be possible to provide
dedicated load for all the four generating stations, and accordingly, it was
finally decided that in the first go islanding scheme for only 5x210 MW
Unchahar generating station may be considered.
11
CHAPTER-4.0
4.0 ISLANDING SCHEME FOR 5 X 210 MW UNCHAHAR THERMAL POWER
STATION
4.1 In the state of Uttar Pradesh, islanding scheme at the Narora Atomic Power
Station of NPC is in operation. This generating station was able to
successfully island itself during the grid disturbances of 30th July 2012 and
31st July 2012. Islanding for this generating station has been planned in two
stages at frequencies of 47.7Hz and 47.5Hz. At frequency of 47.7Hz the bulk
load is disconnected by sending tripping command to 220kV feeders of
Moradabad, Khurja and Atrauli from NAPS and only the 220kV Simbholi
feeder is kept in-service.
Similar methodology has been adopted for islanding of 5x210 MW Unchahar
generating station of NTPC in Uttar Pradesh. The first stage of islanding is
targeted at a frequency of 47.9 Hz with dedicated load of 610 MW and if
frequency still continues to fall the second stage of islanding is targeted at a
frequency of 47.7Hz with dedicated load of only 180-200 MW (i.e. house load
+ load of Rai Bareilly), with only one generator unit considered under
operation. For the second stage of Islanding suitable scheme would be
required for tripping of generator units and to prevent over-speeding of
balance unit due to reduced load.
12
4.2 With respect of Islanding Scheme in general following philosophy was
agreed:
i) It was agreed that islanding would be initiated as a step of last resort
should the frequency continue to fall to lower levels even after the
operation of Under Frequency Relays (UFRs) under automatic load
shedding schemes in the UP system.
ii) With respect to UFR’s to be utilized for Islanding purposes it was
decided that:
a. Two sets of Under Frequency Relays of different make and
different algorithm (like the Main – 1&2 protection relays) shall be
utilized to make the islanding scheme fool proof.
b. Remote monitoring facility of the under frequency relays for its
operational readiness shall be built in the scheme in phased
manner.
c. Development of communication system to enable the UFR data
communication to SLDC so that the load relief obtained through
UFR operations is available at the central location.
iii) The islanding scheme would be devised in two stages. In the first
stage of islanding at 47.9 Hz larger island of operation would be
enabled. In case the 1st islanding attempt at 47.9 Hz does not survive
the 2nd stage islanding at 47.7Hz would be initiated with only one
generating unit running with house load of the generating station and
some local load so as to maintain load generation balance at
13
frequency of 47.7Hz. Further, considering the time of relay operation
and opening of breaker a time delay 3500 mili second shall be
provided between first stage of islanding and second stage of islanding
to prevent false initiation of second stage of islanding and to provide
time for first stage islanding to stabilize.
iv) As a general philosophy it was also agreed that in case of second
stage of Islanding no traction load shall be included as it may give rise
to harmonics and lead to instability of the system.
v) For the survival of island it shall be ensured that Island always remains
slightly on generation plus side. Possibility of automatic load
reconnection/management for maintaining load-generation balance
within the island on real time basis may also be explored.
vi) For effective control of frequency Generator units will run in free
governor mode of operation.
vii) The seasonal changes shall be reviewed periodically with the real time
data at the UP - SLDC.
viii) The assessment of committed generation and connected loads in the
island shall be discussed with the representative of generating stations
also.
14
ix) The major essential loads shall be identified including hospitals,
Railway Station, traction supply points, important government offices,
defence installation, cantonment etc. To the extent possible efforts
would be made to extend supply from these islands on priority to the
essential load supply stations.
x) The identified loads of the island shall not be included in the automatic
load shedding schemes through UFRs, Scheduled Rostering
Schemes, and the SPS schemes. However, rotational schemes, as
may be approved by the management, may be incorporated to provide
alternative dedicated load.
xi) The State load dispatch center (SLDC) shall be nodal control room
responsible for the island control; however, it may involve concerned
generating station and ALDS, for effective management of the Island.
xii) Islanding load to be identified shall exclude the anticipated impact of
scheduled load shedding, automatic load shedding through existing
UFR &df/dt relays when frequency starts dipping below the pre set
level of 49.7 Hz as per the norms set by NRPC and the SPS schemes
etc..
15
CHAPTER-5.0
5.0 AVERAGE GENERATION AND DEDICATED LOAD DETAILS OF
PROPOSED ISLANDING SCHEME FOR UNCHAHAR:
5.1 The Unchahar (NTPC) generating station has five units of 210 MW capacities
each. Considering that one machine or load equivalent to one machine may
be not be available all the time, the average available ex-bus generation from
this generating station, after deducting auxiliary consumption, has been
considered as 760 MW. Further, to maintain the island in a generation
surplus state the dedicated load for this Island scheme has been considered
as 600 MW, i.e. approximately 80% of the average available generation from
this generating station.
5.2 Through Islanding of Unchahar Generating Station almost 50% of total load
requirement of Lucknow (i.e 380 MW ) and almost entire load of Raibareilly &
Fatehpur would be fed.
5.3 Further, through this Islanding supply to following essential loads shall be
provided:
a. State Assembly and nearby VIP areas.
b. Raj Bhawan
c. Cantonment
d. Hospitals like Sanjay Gandhi Post Graduate Institute of Medical
Sciences, Sahara, Metro, Mayo, etc.
e. Railway Station
16
f. Traction load through Sarojini Nagar &SGPGI in Lucknow, Malwaon &
Bachrawan in Fatehpur,
5.2 The details of feeders and ICTs that will remain connected during first stage
of Islanding at frequency of 47.9 Hz are provided in the tables given below:
Feeders to remain connected for Intentional Islanding of 5x210 MW Unchahar TPS Power
S.
No. Details of Sub-station No of
Circuits Load (MW) at Originating S/s
From To
1 2 3 4 5 A Generating Stn. end 1 220 kV Unchahar Gen Stn. 220 kV Raibareilly PG 3 510 2 220 kV Unchahar Gen Stn. 220 kV Fatehpur 2 150 Total 660
B 220 kV Rai Bareilly PG Details
520
1 220 kV Rai Bareilly PG 220 kV Chinhat 1
2 220 kV Rai Bareilly PG 220 kV Sarojini Nagar (Lko) 1
3 220 kV Chinhat 220 kV Gomti Nagar 1
4 220 kV Gomti Nagar 220 kV Sarojini Nagar (Lko) 1 40
5 132 kV Sarojini Nagar (Lko) 132 kV SGPGI 3 150
6 132 kV Chinhat 132 kV Gomti Nagar 1 120 (50 MW Martin purwah) 7 132 kV Chinhat 132 kV Martinpurwa 1
8 132 kV Gomti Nagar 132 kV SGPGI 1 70 9 132 kV Martinpurwa 132 kV SGPGI 1
10 132 kV Rai Bareilly PG 132 kV Rai Bareilly New 105 (10 MW Rai Bareilly New +25 MW Bachrawan)
11 132 kV Rai Bareilly New 132 kV Rai Bareilly Old 2
12 132 kV Rai Bareilly New 132 kV Bachrawan 1
14 132 kV Rai Bareilly Old 132 kV Dalmau 25 (15 MW Dalmau)
15 132 kV Fatehpur 132 kV Malwa 2 150 (60 MW Fatehpur + 60 MW Malwa + 20 MW Jahanabad+ 10
16 132 kV Fatehpur 132 kV Khaga 1
17
S. No.
Details of Sub-station No of Circuits
Load (MW) at Originating S/s
From To
MW Khaga)
17 132 kV Malwa 132 kV Jahanabad
Total 670
ICTs to remain connected during first stage of Islanding of Unchahar
S. NO.
Name of the Sub-station ICTs to remain connected (Capacity /Voltage Ratio)
1 220 kV Rai Bareilly PG 2x 100 MVA, 220/132 kV 2 220 kV Fatehpur (U.P.) 1x160 MVA, 1x100 MVA, 220/132 kV
3 220 kVSarojini Nagar 2x100 MVA, 1x160 MVA, 220/132 kV
4 220 kVChinhat 2x160 MVA, 220/132 kV
5.3 Similarly, for the second stage of the islanding at 47.7Hz (i.e. with only one
generating unit of 210 MW running) feeders with dedicated load of say 180-
200 MW have been identified and tabulated in the table given below:
5.4 Further, for isolation of island from rest of the grid following lines and Inter-
connecting transformers would be required to be opened through operation of
UFRs:
S. No.
Details of Sub-station No of Circuits
Load (MW) at Originating S/s From To
1 2 3 4 5
1 Self Load Unchahar - - 60
2 220 kV Rai Bareilly (PG) 132 kV Raibareilly New 1 20
3 132 kV Raibareilly (New) 132 kV Raibareilly (Old) 2 60
4 132 kV Raibareilly (Old) 132 kV Dalmau 1 15
5 132 kV Raibareilly (New) 132 kV Bachrawa 1 25
Total 180
18
Lines to Remain open on Islanding of Unchahar
1 Unchahar (NTPC) Generating Stn. Switchyard i 4x220 Kanpur PG 2 220 kV Chinhat S/S UP i Lucknow UP (Chinhat) - Lucknow PG ii 220 kV Hardoi Rd. UP S/S iii 132 kV Barabanki iv 132 kV NKN v 132 kV Khuramnagar 3 400/220/132 kV Sarojini Nagar S/S i 220 kV Hardoi Road ii 2x220 kV Unnao iii 2x132 kV TRT iv 1x132 kV Sandila v 1x132 kV Kundan Rd. 4 132 kV Raibareilly S/S (New) (Amawan) i 1x132 kV GauriGanj ii 1x132 kV Jagdishpur 5 220 kV Fatehpur S/S i 220 kV Rewa Rd. ii 220 kV Allahabad Cantt. iii 2x220 kV Fatehpur PG iv 220 Banda 6 132 kV Malwa S/S i 2x132 kV Naubasta 7 132 kV Jahanabad S/S i 132 kV BharwaSumerpur
ICT to remain open on Islanding of Unchahar
S. NO. Name of the Sub-stationICT to remain Open (Voltage Ratio/ Capacity)
400 kV
1 Sarojini Nagar S/S 400/220 kV , 2x240 MVA ICTs
19
CHAPTER-6
6.0 MAJOR CHALLENGES AND WAY FORWARD
6.1 Maintaining load Generation balance for the island throughout the year in
view of changing demand during different seasons. This shall require regular
review and re-adjustments.
6.2 Availability of dedicated load for the success of Islanding Scheme in view of
massive demand supply gap and large scale scheduled and unscheduled
rostering.
6.3 Day today system contingencies.
6.4 Commitment of the generators for Free Governor Mode Operation of
Generating Stations to effectively control frequency on real time basis.
6.5 Monitoring of healthiness of Under Frequency Relays for their operation at
the set frequency.
6.6 Availability of dedicated trained staff at SLDC to monitor the scheme on daily
basis and make necessary adjustments.
6.7 Training and Mock Drills at SLDC and Generating Stations to familiarize for
handling real time situation during grid disturbance.
20
6.8 To suitably plan and implement islanding schemes for other generating
stations considering the availability of dedicated load.
Single Line Diagram of First Stage of Islanding Scheme of 5x210 MW Unchahar Generating Station at Frequency of 47.9 Hz
UNCHAHAR (5x210 MW) Ex Bus Avg. Generation 760 MW with 4 unit in operation
G‐1, 2, 3, 4, 5
220 kV Rai Bareilly PG S/S
220 kV LKN – UP Sarojini Nagar 220 kV Chinhat S/S
Hardoi Road Gomti Ngr
SGPGI
Unnao
220 kV Kanpur (PG) S/S
Kundan Rd.
Sandila
TRT
132 kV Raibareilly (New) S/S
Fatehpur (PG)
Banda
220 kV Fatehpur S/S
Allhd. Cant
Rewa Rd
400/220 kv ICT
400/220 kv ICT2x 160 MVA 220/132 kv ICT
220/132 kV ICT
G. Nagar
220 KV BUS Unchahar Generating Station
To be disconnected for Islanding
132 kV Raibareilly (Old) S/S
Bachrawan
Dalmau
Malwa
Jahanabad
Gauriganj
Khaga
Bharwah Sumerpur
Martinpurwa
220/132 kv ICT
Khurram Nagar
NKN
Barabanki
132 kV LKN‐UP
Jagdishpur
132 kV Chinhat
Single Line Diagram of Second Stage of Islanding Scheme of 5x210 MW Unchahar Generating Station at Frequency of 47.7 Hz
UNCHAHAR (5x210 MW) Ex Bus Avg. Generation 180 MW with 1 unit in operation
G‐1, 2, 3, 4, 5
Rai Bareilly PG
LKN ‐ UP Chinhat
Hardoi Road Gomti
Ngr
To Chibra Mau
Unnao
Open
BithoorRPH
Panki
Rai Bareilly (New)
Fatehpur(PG)
To Shahjahanpur
Kanpur (South)
Banda
220 kV Fatehpur S/S
Allhd. Cant
Rewa Rd
To Allahabad To Obra 400/220 kv ICT 400/220
kv ICT
400/220 kv ICT
400/220 kv ICT
LKN (PG)
Sitapur
220 KV BUS
To be disconnected for Islanding
Rai Bareilly (Old)
Bachrawan
Dalmau
Malwan
Jahanabad
Gauriganj
Khaga
Bharwah Sumerpu
2x 160 MVA 220/132 kv ICT