Steel SymphonySteel Symphony!!All about
And more …
The Story behind ISPAT’s Successful SAP Implementation!
Contents
What is Steel Symphony?
How was it accomplished ?
Functionality Implemented
Training (Strategy & Statistics)
User Satisfaction Survey (Samples)
Help Desk (Strategy & Statistics)
Benefits (After Steel Symphony)
The Road Ahead
Project Vision
“Leverage the SAP Enterprise System across all functional & executive areas of ISPAT Group”
Project Mission
“The future SAP R/3 system shall become the backbone of initiatives in SCM, CRM, HR, ESS, BIW etc. across ISPAT Group ”
Guiding Statements
Our Goal
To bring all the functional areas into SAP R/3 SystemTo have a single system which can serve all reporting requirements of ISPATTo enable current and future Management Initiatives
Target
ISPAT - As Owners of the SystemCoconut – As Implementation PartnersE & Y – As Quality Assurance Partners
Participants
Geographical SpreadReporting RequirementsInfrastructure RequirementsOther Management Initiatives
Considerations
Legal EntitiesIspat Industries Limited Ispat Metallic LimitedIspat Energy Limited
Geographical Spread
DolviKalmeshwarAll depots / Consignment Agents (approximately 23 in number)Service CentersRaw Material Storage Locations (like Visakhapatnam, Paradeep etc.)
Scope of the Project
TIMELINES
Project Kick Off Project Kick Off
31st Aug Project PreparationProject Preparation
26th Sep
System AcceptanceSystem Acceptance12th April
User TrainingUser Training25th Apr
2002
CPI
All Dates are Sign-Off Dates
Achieved
18th Mar
BBP RealizationBBP Realization31st Dec
As-Is To-Be Gaps
1st Apr
Go-Live PreparationGo-Live Preparation
2nd MayPI SupportPI Support
Go-LiveGo-Live2nd Apr
M I L E S T O N E S
2003
Planned at the Start of the Project
Project Implementation Time Lines
To be Achieved
Key User and Consultant Roles & InteractionISPAT Key Users Coconut App. Cons.
Guide Key Users in As-Is Doc.Prepare & Implement Testing StrategyPrepare & Implement Training StrategyPrepare and implement Go-live strategy
Guide Key Users in As-Is Doc.Prepare & Implement Testing StrategyPrepare & Implement Training StrategyPrepare and implement Go-live strategy
To-Be Business Processes & Gaps To-Be Business
Processes & Gaps
As – Is Business Processes
As – Is Business Processes
Collecting Work Profiles & Master DataGet end user buy-inEnd User DocumentationTraining End UsersGo-Live Support
Collecting Work Profiles & Master DataGet end user buy-inEnd User DocumentationTraining End UsersGo-Live Support
Business Requirements
Business Requirements
Reporting Requirements
Reporting Requirements
• As-Is and Business requirement Doc.
• Review of To-be • Business Processes
& Gaps• Review Realization Realization
on System Realization on System
Key User Training Key User Training
• As-Is review• To-Be process &
Gaps Documentation• Realization on the
System• Key User Training
System Testing & Acceptance
System Testing & Acceptance
Go-Live Go-Live
Owner
Inputs Received from Other Initiatives like ...
Performance Management SystemBy Hewitt Associates
Performance Management SystemBy Hewitt Associates
SCM
FI CO AMPP PM QM PS MM SDTR
SAP
CRM
TPM
PMS
Six Sigma
HR CIN
Supply Chain StrategyBy Price Water Coopers
Supply Chain StrategyBy Price Water Coopers
Customer Relations By National Institute of Sales
Customer Relations By National Institute of Sales
Six Sigma Process ImplementationBy WIPRO
Six Sigma Process ImplementationBy WIPRO
Total Productivity ManagementBy Freelance Consultant
Total Productivity ManagementBy Freelance Consultant
SAP ImplementationBy Coconut
SAP ImplementationBy Coconut
Responsibilities of Coconut – Implementation Partner
ManagerialProject Charter PreparationProject Management along with other partnersInfrastructure Planning and Procurement RecommendationsChange ManagementIssue Resolution & Escalation
TechnicalSynchronization of Development and Production environmentInstallation of SAP R/3 4.6C/ CIN4.0A/ IS-MP BBP Realization on the SAP R/3 systemConnecting business partners with SAP R/3 systemGo-Live Post Implementation SupportEnhancements, Interfaces, Reports, Layouts Development
ManagerialProject Charter PreparationProject Management along with other partnersInfrastructure Planning and Procurement RecommendationsChange ManagementIssue Resolution & Escalation
TechnicalSynchronization of Development and Production environmentInstallation of SAP R/3 4.6C/ CIN4.0A/ IS-MP BBP Realization on the SAP R/3 systemConnecting business partners with SAP R/3 systemGo-Live Post Implementation SupportEnhancements, Interfaces, Reports, Layouts Development
Responsibilities of Coconut – Implementation Partner
TrainingTraining PlanProject Team Training (in various Documentation Standards etc.)User Training using “Train the Trainer” concept
DocumentationConfiguration Requirement DocumentBusiness Blueprint Documentation (As-Is, To-be, Gap Analysis)User Manual (along with Key Users)Other Project documents mentioned in Project charter
Project ReportingProject Status Reports – Weekly, Fortnight, Issue reporting (to Steering Committee)Delay-Reports
TrainingTraining PlanProject Team Training (in various Documentation Standards etc.)User Training using “Train the Trainer” concept
DocumentationConfiguration Requirement DocumentBusiness Blueprint Documentation (As-Is, To-be, Gap Analysis)User Manual (along with Key Users)Other Project documents mentioned in Project charter
Project ReportingProject Status Reports – Weekly, Fortnight, Issue reporting (to Steering Committee)Delay-Reports
Project Charter - Highlights
Formation of Project Organization
Finalized Project Plan
Finalized Project Schedules
Defined Project Management Standards
Finalization of Project Scope
Finalization of Testing Strategy
Finalization of Training Strategy
Project Charter
Project Organization – Roles & Responsibilities
Steering Committee
Committing the required resources to the project Monitoring the progress and the organizational impacts of the project Empowering the core project team to make decisions Resolve escalated issues Generating timely decisions & sign-offsSupporting the project management team to accomplish the project goals Resolve issues regarding achievement of milestonesEnsure that Divisional heads sign-off Business Blue Print Documentation.Provide guidance in the Monthly Steering Committee Meetings
Time commitment: 3 hours per month+ as and when necessary
Project Organization – Roles & Responsibilities
Project Sponsor
Is the ultimate owner of the project and has decision-making power in the fulfillment of the primary responsibilities, as outlined for the steering committee members Maintains the final authority to set priorities, approve scope, and settle company-wide issues Promotes the SAP project throughout the organization. Where conflicts exist in the completion of these responsibilities, the sponsor is empowered to negotiate and promote a solution. Has final budget authority
Time commitment: Minimum 8 hours per week
Project Organization – Roles & Responsibilities
Project Manager
Ensure contractual obligations are met with all project vendors Ensure good communication between teams within the project Ensure timely issue resolution or appropriate escalation of issues Ensure timely availability of all resources required for the project as per the project plan (like key users, hardware, software, network required for the project)Report project status to the Steering Committee on a regular basisApprove significant changes to project plansReview and signoff on project plans and deliverables
Time commitment: Full Time
Project Organization – Roles & Responsibilities
Key User
Prepare As-Is DocumentPrepare Business RequirementsReview and Sign-Off To-Be Process & GapsValidate the R/3 design Validate the Configuration of the system Test and document the R/3 implementation Manage the validation of R/3 System unit testing and integration testingWorking with the project team to identify mission critical business process scenarios Identifying transactions and data to be tested; managing expected results versus actual results, and reasons for differences Assigning follow up tasks to reconfigure and retest Train End Users
Time commitment: Full Time
Timelines
Project Kick Off Project Kick Off
31st Aug Project PreparationProject Preparation
26th Sep
System AcceptanceSystem Acceptance12th April
User TrainingUser Training25th Apr
CPI
All Dates are Sign-Off Dates
Achieved
To be Achieved
18th Mar
BBP RealizationBBP Realization31st Dec
As-Is To-Be Gaps
1st May
Go-Live PreparationGo-Live Preparation
2nd Jun
PI SupportPI Support
Go-LiveGo-Live2nd May
M i l e s t o n e s
Project Implementation Time Lines (Revised after VAT)
2002
2003
Actual Go Live against target time of 11 PM on 2nd May ‘03
Actual Go Live Time# Module
Dolvi Kalmeshwar1 Financial Accounting 5:00 PM on 3rd May 5:00 PM on 3rd May
2 Asset Management 1:00 PM 12th May 1:00 PM on 12th May
3 Treasury 5:00 PM on 3rd May 5:00 PM on 3rd May
4 Controlling Partial Partial
5 Material Management 9:00 AM on 7th May 2:00 AM on 6th May
6 Sales & Distribution 9:25 PM on 2nd May 6:00 AM on 3rd May
7 Production Planning 07:00 AM on 13th May 06:00 AM on 9th May
8 Quality Management 07:00 AM on 13th May 06:00 AM on 9th May
9 Project system 11:00 AM on 3rd May 11:00 AM on 3rd May
10 Human Resources 2:00 PM on 3rd May 2:00 PM on 3rd May
11 Country India Version 9:25 PM on 2nd May 6:00 AM on 3rd May
12 Plant maintenance 11:00 PM on 2nd May 11:00 PM on 2nd May
Implementation of Best Business Practices Post Go-Live(Examples)
Elimination of Hard Copy Document• No internal circulation of hard copies of PO, GR, PA, RGP/NGP• All transactions to be done on the system, at the point of transaction and the time of transaction• A pre-requisite to make this success is ‘documents should be prepared free of errors’
Simplifying Cash Purchase Process
Practice on 3.1H system• All Functional Heads/ Divisional Heads have been authorized to make cash purchase up to a limit of Rs.5000/-.• Gate Entry of the material purchased is done by Security.• Then stores verifies the purchases.• Then a cash voucher is created by Accounts in the system and then payment is made
Practice on 4.6C system• The Divisional / department Heads shall advise their subordinates to get the cash/purchase bill/receipt entered in
the SAP R/3 system at main gate.• Each Cash Purchase Bill/receipt shall be authorized by concerned Functional/Divisional Head and forward the
same to the Accounts Department for payment.
# Business Scenario - Accounts ReceivableRevenue Determination
Direct Factory Sales
Export Sales
Depot Sales
Sales from Service Center
Inter Unit Sale
Home / Captive Consumption
Sales Return
Accrual of following Liabilities for Sale & Distribution Expenses
Rebate & Discount
Agency Commission
Dealers Commission
Outward Freight Expenditure
Export Related Expenses
Customer Receipt
Down Payment
Incoming Payment
Security Deposit / Earnest Money Deposit
Bill of Exchange Receivable with link to the Letter of Credit Component
3
2
1
FIFunctionality Implemented
# Business Scenario - Accounts Receivable4 Interest Calculation on Customer Outstanding
5 Customer Credit Management
6 Customer Balance & Debtors Ageing Reports
FIFunctionality Implemented
# Business Scenario - Accounts PayableMaterial Accounting at Plants and Material Revaluation
Liability generation
Consumption Booking
Service Entry Accounting
Project Contractors / Equipment Suppliers Accounting
Material Issued on Loan
Material Issued to Contractors
Plant to Plant material Transfer
Chargeable Issue to Contractors
Port Material Accounting
Stock updating
Physical verification
Generation of Fines
Stock Transfer
Invoice Verification Elements
Material Cost
Planned & Unplanned Delivery Cost
Subsequent Debits / Credits
Cenvat Entry for Raw Materials & Capital Goods
Extended Withholding Tax
3
2
1
FIFunctionality Implemented
# Business Scenario - Accounts PayableTDS Processing
At the time of Invoice Verification
At the time of Down Payment
Certificate Printing
Return Filing
Payment Process
Automatic Payment Proposal
Outgoing Payment
Down Payment
Bill of Exchange Payable with link to Letter of Credit Component
Cash Payment
6 Accounting in Foreign Currency
Month End Closing Operations
Liability Statement
Netting Statement
Grossing Up of Balances
GR/ IR Clearing
Vendor Account Clearing
7
5
4
FIFunctionality Implemented
# Business Scenario - General LedgerMonth End and Year End Closing Operations
Business Area Adjustments
Valuation of Exchange Fluctuation
Vendors and Customers - Regrouping of Balances
Carry Forward of Balances
Internal Transaction
Inter unit Transaction
Intra office Transaction
Cross Company Transaction
House Bank
Bulk cheques
Bank Reconciliation
Cash Journal Transaction
Assets & CWIP Accounting 4
Pre-operative Expenses Accounting
3
2
1
FIFunctionality Implemented
# Business Scenario - Materials Management A Purchasing System
1 Purchase Requisition, Quotations. Purchase Order for Stock transfer, Subcontracting and Services
2 Contracts & Scheduling agreements.
3 Release Strategy for Purchase Documents for hierarchical E-Approval
4 Rebate Agreement.
B Inventory Management System
1 Returnable Gate Pass and Non Returnable Gate Pass.
2 Creation of Gate Entry for normal Purchase, Cash Purchase and Emergency Materials.
3 Capturing weighment of weight on weigh bridge for incoming materials.
4 Goods receipts, Goods issue, Reservations and Transfer posting.
5 Sale of Scrap / Disposable materials using SD functionality.
6 Batch Managed Inventory
C Material Requirements Planning
D Physical Inventory
E Invoice Verification for Vendor Payment
1 Parking of Invoice, Block Payment for various reasons (when deviation occurs), etc
2 Evaluated Receipt Settlement, Consignment and Pipeline Settlement
3 Invoicing Plan
MMFunctionality Implemented
# Business Scenarios – Production Planning1 Creation of Plans – Monthly, Weekly and Daily.
2 Creation of Process Orders – Monthly and Daily basis as per business plan.
3 Make to Order (MTO) and Make to Stock (MTS) production and on-line inventory details.
4 Integrated Raw material planning, material availability check and material quality recording.
5 On-line Daily Process data recording including Log-Sheets, in-house production transfer or consumption details.
6 Sales Order-Costing, Process Order / Heat wise Costing. Reason wise NCO generation Recording
7 On-line stock of Saleable / Non-saleable, Finished / Semi-Finished, By-products & Scrap in the customizable formats.
8 Co-Products and By-Products generation and Recording.
9 Capacity Planning & Scheduling
10 Work Roll and Backup Roll Management and related reports.
11 Simplified Transfer posting – e.g. Plant to Plant, Order to NCO, NCO to Order, etc.
12 NCO Stocks allocation to Orders – Automatic Coil Determination / Allocation by Marketing
13 Sequence Planner
14 Plant Control Reports
PPFunctionality Implemented
QM
# Business Scenarios – Quality Management
1QM in Procurement, QM in Process and QM during Dispatches are the major QM activities. QM available in all the areas, viz. Sponge Iron, Lime, Oxygen, Hot Metal, Pig Iron, HR, CR, GC, CC and all WIP. This functionality is extended to by-products where ever applicable.
2 Master Data of Quality Assurance Division is available.
3 Result Recording & Usage Decision of Raw Materials of HSM, SIP & BF maintained.
4 Chemical Analysis & Mechanical properties Entry data available as per requirement.
5 Automatic transfer of Heat Chemistry & Mechanical/Metallurgical details to the respective coils of the heat thereby reducing manual job duplication.
6 Taloja QM requirements are configured.
7 Customer Enquiries and Complaints handling system.
8 New TDC Creation & automatic requirement transfers from SD to QM.
Functionality Implemented
PM
# Business Scenario – Plant Maintenance1 Online capturing of equipment history.
2 Equipment/ functional location wise maintenance cost booking.
3 Equipment/ functional location wise service cost booking.
4 Scheduling of maintenance plans through system.
5 On line Preventive maintenance.
Functionality Implemented
CIN
# Business Scenario – Country India Version1 Generation of excise invoices – for CENVAT
2 Rejection returns to vendor through system
3 Sales invoices
4 Sales return
5 Depot procedure for Delhi and Calcutta
6 VAT Scenario
7 Imports - Bill of Entry through system
8 Exports – Complete Automated Documentation
9 Sales Tax Registers
10 All Export and Customs Benefits
11 Sale of scrap / disposable materials using SD functionality inclusive of all statutory compliance.
Functionality Implemented
TR
# Business Scenario - Treasury1 Bank Reconciliation
2 Cheque Deposit
3 LC Established by Customer
4 LC Established by ISPAT
5 Clean Bills Monitoring
6 Bank Guarantee
7 Limits Monitoring (LC, BG, Discounting & Others -CC)
8 Bank Position
9 Cash Flow
10 Liquidity Forecast
Functionality Implemented
PS
# Business Scenario – Project Systems1 CAPITAL / MODIFICATION Project
2 Project budgeting with “error” block for budget overflow
3 Comprehensive network for entire project with different user departments
4 Payment details against purchase orders.
5 Effect of delay of any activity on final date
6 GANTT Chart & Critical Path of the network with project progress
7 Settlement of WBS Elements to “Asset Under Construction” thus transferring the Project cost to “AUC”
9 Identification of purchase orders with respect to Projects
10 Budget supplement, transfer, return in the project
11 Different type of relationships with lead/lag time
Functionality Implemented
# Business Scenario – Assets Management1 Maintenance of Master Data like Assets
2 Asset Acquisition / Addition / Deletion etc.
3 Creation of assets links with assets class.
4 Depreciation as per Company’s Act.
5 Depreciation as per Income Tax Act.
6 Transfer of assets.
7 Blocking of assets.
8 Retirement of assets.
9 Revaluation of assets.
10 Asset Tracking against a Cost Center / Employee etc.
AMFunctionality Implemented
HR
# Business Scenario – Human Resources1 Organizational Management - Creation of Organization Units, Jobs, Positions, Maintaining vacancy
2 Recruitment – Process Applicant, Offer applicant contract, Prepare for Hiring
3 Integration between Recruitment - Personnel Administration – Organizational Management (Direct data transfer of applicant)
4 Personnel Administration – Hiring, Maintaining Basic pay, Confirmation, Transfer, Promotion, Change in pay, Separation, Resignation
5 Time Management – Leave balances, Booking of attendance, Leave, creation of Master shift schedule
6 Training & Event Management – Creation of Business Event group, Event type, Booking, Pre booking of attendance, Creation of External Instructors profile and company details
7 General Services – Maintaining service order and service entries
8 Correspondence – Generation of letters pertaining to applicant and employees such Interview call letter, Confirmation Letter, Relieving Letter, Appointment letter etc.
Functionality Implemented
User rating# Business Process
Excellent Very Good Good Average Bad Worse
1 Normal Factory Sale of HR, Sponge Iron & Pig Iron Products
2 Complete Export Sales Cycle
3 Sales under CT2 Certificate
4 Inter company and captive consumption sales Cycle
5 Sale of Lime , Coke Products & raw material
6 Sale under Letter of Credit
7 Customer Complaints Tracking
8 Sales Visit plans , Follow up and Recording
9 Credit Management
10 Sale of MTS & Narrow Slit
11 Sales Returns
User Satisfaction Survey - Configuration
Sample – For Sales ‘n’ Distribution - DOLVI
User Satisfaction Survey - Configuration
User rating# Reports
Excellent Very Good Good Average Bad Worse
1 Sales Order Balance
2 SO Balance from
3 Work Order Balance
4 Scheduling Agreement Status
5 Billing Details
6 Dispatch Details (Bill Wise)
7 Dispatch Details (Mat Doc Wise)
8 Transporter's Performance
9 Customer Stock & Sales & Collection
10 Condition Types
11 Dispatch Plan Delivery Due List
12 Delivery Performance
13 Visit Compliance Report
14 Customer Complaint Status Summary
… …………………..
…. …………………..
Sample – For Sales ‘n’ Distribution - DOLVI
Helpdesk - Post Implementation Strategy
Central Help Desk Features
Monitored and Coordinated by ISPAT IT Personnel at DolviIssue Tracker - A tool developed on Lotus Notes, used by the Project Team to track and resolve open issuesFirst Level Issue Resolution by ISPAT Key Users for each moduleEscalation to Coconut SAP On-Site SAP Team at Dolvi, Casablanca and KalmeshwarFirst Six Months Support – Full Project Team On siteNext 6 months:
On-Site Support – Abap/4, PP/QM and SD TeamOn-Call Support – Other Modules
Optimization of Several Functions done and under process during PI Support
Helpdesk - Post Implementation Strategy
Dolvi + Casablanca Kalmeshwar Total
Issues Reported
Issues Resolved
Issues Reported
Issues Resolved
Issues Reported
Issues Resolved
Basis 17 15 5 4 22 19
CIN 18 10 4 3 22 13
FI 25 22 10 3 35 25
Hardware + Software 127 126 145 139 272 265
HR 2 2 0 0 2 2
MM 121 119 8 5 129 124
PM 23 20 3 0 26 20
PP 60 43 40 38 100 81
PS 1 1 0 0 1 1
QM 9 8 9 9 18 17
SD 33 32 52 50 85 82
TR 2 2 0 0 2 2
Total 438 400 276 251 714 651
Module
Issue Resolution – First Month after Go-Live
Helpdesk - Statistics
Dolvi Kalmeshwar TotalReported Resolved Pending Reported Resolved Pending Reported Resolved Pending
May 299 299 0 128 126 2 427 425 2
June 135 133 2 130 125 5 265 258 7
July 13 12 1 87 87 100 99 1
August 38 36 2 28 28 66 64 2
September 9 3 6 29 27 2 38 30 8Total 494 483 11 402 393 9 896 876 20
Period
Five Months – From May ’03 to September ‘03
After Steel Symphony
FMSPB (Payroll)System
SAP 4.6C/ CIN 4.0A / SAP MP
IT Systems – Status After the Project
# Additional Features Business Impact
1Single Company Code (1000) for Ispat Industries Limited at Dolvi & Kalmeshwar Locations
Standardization & Consolidated of Dolvi & Kalmeshwar Accounts.
2
Separate Number Range & Clear Identification of Vendors & Customers Codes, based on nature of Supplies / Services
One to One linkage with reconciliation accounts and better presentation in MIS
To facilitate the automatic posting through integration with various modules 3 Complete restructuring of Chart of Accounts
Clear Identification of Account Groups
Major Business Activities are covered in one system 4 Online Accounting of Kolkata Office
Transactions Elimination of Duplicate Accounting
Complete integration & generation of Automatic posting transactions for :
Direct Factory Sales – Domestic & Export
Depot Sales
Sales from Service Center
Inter Unit Sale
Home / Captive Consumption
Sales Return
Generation of liabilities for selling & distribution related expenses at the time of sales invoicing
Capturing of Vendor Code in Freight Liability
5 Integration of SD with FI
FIKey Benefits from Financial Accounting
# Additional Features Business ImpactAutomatic posting of entries in FI at the time of :
Delivery Cost GR auto clearing
Goods Receipt , Issue and Stock Transfer
Business Area capture in CENVAT Liability on Invoice Verification
MM Stock Reconciliation with FI Ledgers
Letter of Credit Management Component 7 Integration of TR with FI
Automated Bank Reconciliation Statement
Automatic posting of Excise related Transaction: 8 Integration of CIN with FI
PLA & CENVAT, CENVAT on HOLD
Actual online booking of major raw materials
Auto creation of Finished Goods Stock
Valuation of WIP & FG at MAP, based on COP thru production order confirmation in PP & actualization of Cost
Input / Output Standardization and Control
Proper Planning & Control on Inventory of Raw Materials as per JIT
Capturing of Equipment Maintenance History Records & Service Entry thru Maintenance Order 10 Integration of PM with FIBooking of Maintenance Cost thru Service Entry
9 Integration of PP with FI
6 Integration of MM with FI
FIKey Benefits from Financial Accounting
# Additional Features Business ImpactCapturing CWIP & Project Cost thru WBS element
11 Integration of PS with FI Project Cost Monitoring and Budgeting
Automatic Depreciation Calculation & Entries posting
Maintenance of detailed Assets Register
Accounting of Assets acquisition and its discarding thru system
Cost Center Wise details of Overheads
Budget Versus Actual variance analysis
Tally of Accounts with Gain / Loss Report
Corporate Plan Preparing and Monitoring
Automatic calculation of TDS
Payment of TDS with Clearing
Challan Updating, TDS Certificate and Filing of Return
Income Tax Range wise MIS Report
Auto Control of Exemption Certificates of concessional TDS rates thru vendor master
Cash Journal function with system check on Negative Balance
Daily, Weekly, Monthly Status of Cash Transaction with facility to view Total Cash Receipts and Payments
Record Maintenance of Cheques in Hand
16 One Time Vendor Time Saving for small value purchases and job work payments
17 Line Item Display with ALV Viewing / Printing of Accounts Line Items with facility to add / remove fields
15 Cash Journal
14 Extended Withholding Tax (TDS)
13 Integration of CO with FI
12 Integration of AM with FI
FIKey Benefits from Financial Accounting
# Key Features Impact on ISPAT Business
1 Enjoy transaction Features in 4.6 C (MIGO,MIRO,PO etc) All material transactions are done in single screen and thus time saving
2 ALV in reporting Every one can access data and prepare the report themselves.
3 Hold and Check features In hold feature documents can be kept saved even if they are incomplete and in Check feature we can know the reasons for incompleteness of the document.
4Screen can be customized by the user as per his requirement i.e. personnel setting in desktop is allowed in SAP 4.6 c
Time saving and user friendly screen
5 SAP 4.6 c is compatible to handle web enabled transactions Conventional process of working in excel and word is being reduced
6
Field for identifying material based on Strategic, bottleneck, leverage and routine etc provided in line with suggestions with SCM initiative
Analysis of material based on consumption can be done .
7 Various components developed like LC request, gate entry, RGP/NRGP etc.
All documents can be traced from a single system and hence transparency and better analysis can be done.
MMKey Benefits from Materials Management
PP
# Key Features Business Impact
1 On-line data availability for decision making and controlling.
Presently multiple departments are maintaining Heat wise / Shift wise Consumption data. After Go-Live, data will be available centrally, thereby reducing the work duplication.
2 Correct and on-line Product costing and valuation analysis.
Existing practice of analyzing the process data and leaving room for manipulation can be minimized.
3On-line Inventory Monitoring is possible at all Plants, Depots and service centers for better control.
On-line business related data will provide better opportunities in international market. On-line trading, auction, sale, purchase, stock and inventory control. This will create a better edge for ISPAT in this highly competitive environment.
4
To record and monitor process data on shift / heat basis will provide sufficient guideline for enhancing benchmark by producing improved quality.
Process Log-Sheets shall be maintained in SAP. Present trend of manual Log-Sheets will be discontinued and the data will be available centrally.
5
Standard SAP PP Transactions are time consuming and Process Staff may not have sufficient time to maintain the online data in the system. To cater to this requirement, a component has been developed which is simplified up-to the extent possible.
The Process related data can be maintained through user friendly screens. Data entry time has reduced drastically, thereby ensuring the system acceptance.
Key Benefits from Production Planning
QM
# Key Features Business Impact
1 Single Specification for HSM Raw Materials. Better control over the Quality of Raw Materials.
2Automatic transfer of Heat Chemistry & Mechanical/Metallurgical details to the respective coils of the heat.
Reduction of Man Hours for data entry of each coil. Resulting faster Quality Clearance.
3 All reports (HSM, SIP & BF) are generated through SAP.
Reduction of excel usage, Man hours for reports preparation, Better control of outputs, Minimize the usage of Lotus Notes.
4 Customer Enquiries & Customer Handling System.
Facilitates faster reply on Customer enquiry. Required details covered in Customer complaint Handling System.
5 TDC as a Master Document This is a single master document wherein all details are maintained against a grade. This has reduced the manual maintenance of TDC.
Key Benefits from Quality Management
PM
# Key Features Business Impact1 On Line Shift Log Viewing. Easy Communication & Transparency
2 On-line data availability for maintenance decision making and controlling.
Appropriate Maintenance strategies can be formulated without any delay leading to better availability of equipments for production.
3 Capturing Maintenance Cost Equipment Wise. Maintenance Cost History will be available at one place .
4 Capturing Maintenance History of Each Equipment.
Equipment Maintenance History will be available at one place and access will be open to all.
5 On line Preventive maintenance scheduling & Job History Automatic scheduler
6 Person wise aggregation of maintenance activities. Enhanced way of work distribution and performance review.
Functionality ImplementedKey Benefits from Plant Maintenance
CIN
# Key Features Business Impact
1All Statutory Compliances relating to Excise documentation have been incorporated in the system
Generation and printing of all Excise Documents through the system minimizing manual efforts and thereby reducing errors
2 Export – Import documentation Generation and printing of all Export Documents through the system minimizing manual efforts and thereby reducing errors.
3 Enjoy transaction Features in 4.0 Release (J1IEX) All material transactions are done in single screen and thus time is saved
4 Tight Integration As all the modules are tightly integrated, lot of job duplication is avoided resulting in saving time and efforts.
5 ALV in reporting Easy way to create and maintain report formats by end users.
6Screen can be customized by the user as per his requirement i.e. personal setting in desktop is allowed in SAP 4.6 C
Time saving and user friendly screen
7 New Configuration as per VAT requirements System is readily configured for new taxation policies.
Key Benefits from Country India Version
TR
# Key Features Business Impact
1 Cash Flow Cash Flow which was prepared manually is now available online on a day to day basis in the required format
2 LC Management (Customer)
The whole cycle right from creation of LC, to BOE collection/ discounting & contingent liability reversal along with all required outputs & reports along with the integration of the same with the SD & FI modules will help ISPAT in getting accurate information online
3 LC Management (Vendor)The whole cycle right from LC request to creation of BOE to subsequent payment along with all required outputs & reports plus the integration of the same with the MM & FI module will help ISPAT in getting accurate information online
4 BG Tracking Details of all BG given to customers (performance) and to vendors will be available online along with the due dates and the bank through which the same will be given.
5 Limits monitoring All types of limits – LC, BG, Discounting & others (CC, etc.) are maintained for eachbank. The details of utilization and availability of these limits are available on line.
Key Benefits from Treasury
PS
# Key Features Business Impact1 Reports with ALV features Availability of status of the project online with different Variants
2 Critical path of the network Can be concentrated for effective execution of the project
3 Online service entry details Balance work of the external execution agency will be available online
4 Online budget & expenditure details Availability of details of the consumption of budget Project / WBS element wise
5 Reservation of various stocks Special project stock and stocks with contractors will be maintained against the project
Key Benefits from Project Systems
# Key Features Business Impact
1 Direct capitalization through MM Module and AUC settlement through PS Module Due to integration with other modules accuracy has increased and lot of time is saved.
2 Schedule V Manual preparation time and efforts have been saved.
3 Income Tax Depreciation Manual preparation time and efforts have been saved.
4 Automatic Depreciation Run Due to incorporation of additional checks and customization manual depreciation computation has been discontinued thereby saving time and efforts.
5 Automatic Profit / Loss entry on sale / Discard of assets No need to track the Asset retirement manually.
AMKey Benefits from Assets Management
HR
# Key Features Business Impact
1 Direct data transfer of applicant from Recruitment to Personnel Administration.
Elimination of filling up of MIS form by applicant and personal details by personnel department
2 On line generation of Appointment letter, Confirmation letter, Interview call letter etc.
Elimination of manual generation of letters. Duplicity of job and error during MIS will not be there.
3 Complete structure of position and employee can be viewed
Updating of Organization chart as when employee relieves or joined is carried out automatically.
4 Employee history can be viewed like job profile, salary details, training details etc.
This will help us how the events have been takes place in respect of an individual such as Hiring, promotion etc
5 Easy access to employee data across the company irrespective of location. Manual data creation and report generation will be minimal with maximum accuracy.
Key Benefits from Human Resources
# Functionality Benefit
1 Online processing of orders Orders booked in marketing are available immediately to production planning thereby saving time (sometimes weeks) and money
2 Control on unplanned production Material cannot be produced without proper documentation. In case it is done in emergency it is possible to trace
3 Systematic Flow Indirectly problem areas are being highlighted e.g. need to change weight at the time of dispatch etc.
4Online availability of information at Kalmeshwar, Dolvi, Casablanca, Delhi and Kolkata
No need to send information from plant (dispatch report/stocks) to Marketing office and vice versa (work orders). E.g. HR Skelp sold from Kalmeshwar, under instruction from Dolvi can be better monitored
5 Depot stock availability Even though only two depots are online, coil/packet wise stocks of all depots are available in system
6 Online MTS Material allocation while creating Scheduling Agreement Better Stock Monitoring and enabling Faster Dispatch of Material.
7 LC Tracking Better control of outstanding / Overdue of Customers. Control of Dispatches to the extent of LC Value, information on BOE made against LC.
8 Scrap Sales Cycle Online availability of scrap stocks leading to transparency in operations
9 Visit Plan Compliance Sales activities of marketing personnel can be monitored
10 Auto pricing in Scheduling Agreements Reduction in Pricing Errors.
11 Online and Flexible Reporting Reduction in MIS & Reports preparation time on account of up-to-date information and user control on choice of fields to be displayed
12 Complaints recording and settlementDefined procedure and Reduction in Settlement Time. Identifying areas of improvement in terms of defects. History of Complaints from Customer Order, Visit Reports to Settlement.
Key Benefits from Sales n Distribution - Kalmeshwar
# Functionality Benefit13 Credit Note issuance through sales module Online Issuance of Credit Note resulting in lower processing time.
14 Gate Entry of Vehicles Proper monitoring of truck movement
15 Online liability creation for Discounts, Rebates Online Liability Provision during Invoicing.
16 Automatic freight provision Creates exact liability against transporter
17 Material Receipt acknowledgement Delivery Performance Analysis can be done to improve order to cash cycle time
18 Variant and Batch Classification Provision for recording differences between ordered and supplied specifications.
19 Export Documentation Component Reduction in Preparation Time of Export Documents
20 Export related data copying into various output documents
More accuracy in export documentation & hence reduction in realization time of export proceeds.
21 Export Procedure (replicates physical goods movement) Online Stock Status of Stock lying at Port /Stock in Transit.
22 Export Liability/Benefit posting in accounts On line provision of liability for shipping freight, export commission, port charges & other export expenses.
23 Online Profitability analysis Better analysis and control
24 Document Change Analysis Changes made to order specifications, quantities etc can be traced upto exact time and use preventing misuse and confusion
25 Stock assignment Stocks (Coil/Packets) can be segregated into assigned and not assigned in Delivery Order giving a clear picture of the balance stock
Key Benefits from Sales n Distribution - Kalmeshwar
# Functionality Benefit
1 Production process against customer orderProduction is planned only for the orders booked. Information is available to planning as and when the order is booked. No separate intimation is required from marketing dept. Customer requirements is available in more details.
2 Stage wise material requirementRequirement of each intermediate stages of material is planned (Quantity & required date) at the time of customer order creation. Availability date is also known in system for on time delivery
3 Load on each production line Load on each line is available from the system for the order booked. This will help to schedule the production plan and plan the shut downs.
4 Raw material requirement for the order booked Requirement of raw materials & HR coils from Dolvi are known in the system as and when orders are booked.
5 Process order wise production planning & tracking
Better control over production process and better monitoring.As material produced at every stage is identified with customer order, hence online order tracking possible.
6 Production cost control & process controlInformation of all cost inputs (consumables, power etc) & output (prime & arising) to a process order are easily available in the system.Product costing is available.
7 Inventory Management
• Better inventory control• Information regarding quantity produced with out customer order, for Home
consumptions, Non conformance production, diversions etc are easily available in the system
• Material cannot be produced without proper documentation.
8 Control on unplanned production Material cannot be produced without proper documentation. Production with out customer order can be easily tracked.
9 Scrap generation & disposal cycle Online availability of scrap stocks leading to transparency in operations
Key Benefits from Production Planning - Kalmeshwar
# Functionality Benefit
10 Production process & Recording Actual consumption against planned consumption is available.Equipment utilization available .
11 Variant and Batch Classification Provision for recording differences between ordered and supplied specifications.
12 Online production cost analysis Better analysis and control
13 Online and Flexible Reporting Reduction in MIS & Reports preparation time on account of up-to-date information and user control on choice of fields to be displayed
14 Document Change Analysis Changes made to process order ,Batch specifications, quantities etc can be traced upto exact time and use preventing misuse and confusion
15 Online availability of information at plant and marketing offices.
No need to send information from plant (dispatch report/stocks) to Marketing office and vice versa (work orders).Planning is possible based on the HR coil dispatched from Dolvi and in transit.
Key Benefits from Production Planning - Kalmeshwar
Never do server sizing before the BBP finalization
Never go productive without SAP Early Watch Check
Never tread beyond the scope of the project
Never make “manpower reduction” as the sole motive or one of the motives of implementation
Training should never be done on a Development Server
Never change Project Plan in the midst of the Project
Never include unplanned activities in the Project
Never try to re-build the legacy system on SAP
Lastly …..Never force the Implementation partner to over-commit unplanned deliverables during the project
Lessons learnt during & after Steel Symphony
Don'ts!
Always freeze the business requirements – as per schedule – before the start of configuration on system
Freeze customization requirements before start of configuration
Training should always be done on a Training Server
Project team and End Users should be identified in the Preparatory Phase of the Project
Connectivity should be available to remote locations before the start of the training and testing
Have alternate integration (data-transfer) plan with remote locations in case of non-availability of connectivity.
Always, finalize the quantum of ABAP/4 development per module at the start of the Project
Last, but not least, utilize the services of a third party auditor for milestone auditing
Always plan sufficient cut-over time during transition to SAP
Ensure timely availability of accurate Open Item data during transition
Always, finalize the scope of training before commencing the Implementation
Lessons learnt during & after Steel Symphony
Do’s!
2007
mySAPSCM
mySAP PLM
Implement MySAP Business Suite with in 3 yearsMySAP Business Suite includes:
1. SAP Enterprise
2. mySAP Customer Relationship
Management
3. mySAP Human Resources
4. mySAP Financials
5. mySAP Enterprise Portals
6. mySAP Supply Chain Management
7. mySAP Product Lifecycle Management
8. mySAP Supplier Relationship
Management
9. mySAP Business Warehousing
2005
My SAP BIW, mySAP
CRM, PPMS Integration
2006
mySAPHR, mySAPSRM mySAP EP, mySAP FI
Road-Map for Future
Contacts
PROJECT SPONSORMr. Banwari Lal [email protected]
PROJECT MANAGEMENT TEAMMr. Kishore BannerjeeGeneral Manager, IT - [email protected]+91 98208 01533
Mr. Amit KumarGeneral Manager, IT - [email protected]+91 98200 01588
Mr. Alok KumarA.G.M, IT - [email protected]+91 98200 01588
PROJECT MANAGEMENT TEAMMr. Anil NimbargiProject Manager, [email protected]+91 98200 26138
Mr. Sabahat KaziProject Manager, KALMESHWARsabahat,[email protected]+91 98206 45885
Mr. Gopal KrishnaProgram [email protected]+91 98214 34991