Mislukking of succes?
Stand van zaken
Jan Devos• ELIT-Lab & Industrial Management
• Faculty of Engineering• Ghent University
• Graaf Karel De Goedelaan 5• BE-8500 KORTRIJK - BELGIUM
• T: +32 56 24 12 72• F: +32 56 24 12 24
• e-mail: [email protected]• e-mail: [email protected]
• linkedIn: www.linkedin.com/in/jangdevos• website: http://ela.howest.be/jdevos
Projectbeheer: kan het beter?
![Page 2: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/2.jpg)
IS Failures
© Jan Devos - 2
•Recent paper (18 May 2010)
•Project failure en masse: a study of loose budgetary control in ISD projects
• K. Conboy (NUI Galway, Ireland)
• This paper represents a case of extreme information systems development (ISD) failure en masse, where all but two of the 22 projects in a business unit went over budget, causing senior executives to refocus their strategic priorities and cancel all current and potential projects that followed. This study focuses specifically on the two best performing (12 and 4% under budget) and worst performing (223 and 320% over budget) of these projects.
• European Journal of Information Systems (2010) 19, 273-287. doi:10.1057/ejis.2010.7; published online 18 May 2010
![Page 3: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/3.jpg)
© Jan Devos - 3
![Page 4: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/4.jpg)
Project/Company Damage Year
London Ambulance Service (LASCAD) £1,1 - £1,5 mio 1992
Denver International Airport $2.000.000.000 1995
Sydney Water AU$61.000.000 2000
Feniks (Belgium) €12.000.000 2007
Hershey’s $112.000.000 2000
Fox-Meyer Drug Company $18.000.000 1994
Confirm (Hilton, Mariott, Rent-A-Car) $125.000.000 1988
TAURUS (UK Stock Exchange) £75 - £300 mio 1993
Accounting System at Cambridge University £10.000.000 2001
Royal Melbourne Institute of Technology (RMIT) AU$47.300.000 2001
Cambridge University (accounting system) £10.000.000 2001
Hit Parade of IS Failures
![Page 5: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/5.jpg)
• Best kept (public) secret worldwide ?
• A lot of research for almost 45 years • 1967, Management misinformation systems, (Ackoff)• 2010, Project failure en masse: a study of loose budgetary control in
ISD projects (Conboy)
• Much is known - less is done !• 1975 / 1995, The mythical Man-Month (Brooks)
• Failure to learn ? CIOs - IS-Researchers• 1999, Learning failure in information systems development (Lyytinen
& Robey)• MISQ, EJIS, ISR, JAIS, …
IS Failures
© Jan Devos - 5
![Page 6: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/6.jpg)
What are IS Failures ?
© Jan Devos - 6
Engineering Failures?
![Page 7: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/7.jpg)
What are IS Failures ?
© Jan Devos - 7
An IS Failure is an outcome of a human process
![Page 8: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/8.jpg)
1994 1996 1998 2000 2004
Failed projects 31% 40% 28% 23% 18%
Challenged projects 53% 33% 46% 49% 53%
Succeeded projects 16% 27% 26% 28% 29%
Standish Group
![Page 9: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/9.jpg)
Research on IS failures
What is an IS Failure ?
What is an IS Success ? Does the ‘iron triangle’ BTS measures success ? Does it prevent from failure ?
Failure ≠ NOT(Success)
How do we measure failures & successes ?
How do we prevent from failure ? Or how do we conduct successful IT projects ?
![Page 10: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/10.jpg)
Research on IS failures – WHAT ?
Expectation failures (Lyytinen & Hirschheim) = the inability of an IS to meet a specific stakeholder group’s expectations
Termination failures (Sauer) versus Perpetual beta (calculation of ∏ ?)
Project Runaways (Ewusi-Mensah, Keil) & Project Abandonment• IS Project Runaways = Escalation of commitment• IS project abandonment is defined as a phenomenon that
concerned with the anticipated failure of the project prior to its full implementation
Outsourcing failures (Devos)• Moral Hazard: lost of trust • Adverse Selection: Lemon Markets
Engineering failures ? MTBF ?
![Page 11: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/11.jpg)
Research on IS failures – WHAT ?
Expectation failures (Lyytinen & Hirschheim) = the inability of an IS to meet a specific stakeholder group’s expectations
• Correspondence failures
• Process failures
• Interaction failures
![Page 12: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/12.jpg)
•de patiënt:
• wordt snel afgeleid• schenkt weinig aandacht aan zijn omgeving• kan niet goed zijn aandacht bij één zaak houden
(concentratiegebrek)• geeft onvoldoende aandacht aan details• lijkt vaak niet te luisteren als hij/zij direct wordt
aangesproken• antwoordt vaak al uit voordat de vragen afgemaakt• verstoort vaak bezigheden van anderen of dringt
zich op (bijvoorbeeld mengt zich zomaar in gesprekken)
Managerial Attention Deficit & Disorder (MADD)
© Jan Devos - 12
![Page 13: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/13.jpg)
Research on IS failures
Cover-UpOrganization
Deaf, Dumb and BlindOrganization
Healthy Organization
Ostrich Organization
Mum Effect
Deaf Effect
high
high
low
low
Blowing the whistle on troubled software projects (Keil, 2001)
bad news is transmitted less frequently than good news
reluctance to hear bad news
![Page 14: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/14.jpg)
•Moral Hazard (Opportunistic behavior)▫Trust versus Control
•Adverse Selection (Lemon Markets)
• 2009, IT Governance in SMEs: Trust or Control? (Devos et al.)• 2011, The Theory of the Lemon Markets in IS Research (Devos
et al.)
Outsourced IS Failures
© Jan Devos - 14
![Page 15: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/15.jpg)
Lemon Market
© Jan Devos - 15
= €1
= €0.1
ICT
![Page 16: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/16.jpg)
Lemon Market
© Jan Devos - 16
€1
€0.1?
![Page 17: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/17.jpg)
Lemon Market
© Jan Devos - 17
€0.55
€0.55 - €1 = -€45
€0.55 - €0.1 =
€0.45
![Page 18: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/18.jpg)
Lemon Market
© Jan Devos - 18
€0.55
€0.55 - €0.1 = €0.45
€0.55 - €0.1 = €0.45
€0.55 - €0.1 = €0.45
![Page 19: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/19.jpg)
Lemon Market
© Jan Devos - 19
€0.23
€0.23- €0.1 = €0.13
€0.23 - €0.1 = €0.13
€0.23 - €0.1 = €0.13
![Page 20: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/20.jpg)
Research on IS failures - HOW?
• Resistance against change
• 1983• Power, Politics and MIS implementation (Markus)
• 20 years later:• - 2003, "Computers can land people on Mars, why can't
they get them to work in a hospital?" - Implementation of an Electronic Patient Record System in a UK Hospital (Jones)
• - 2004, Informating the Clan: Controlling Physicians' Costs and Outcomes (Kohli & Kettinger)
© Jan Devos - 20
![Page 21: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/21.jpg)
Organizational Change
Nov. 2010
© Jan Devos - 21
![Page 22: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/22.jpg)
Organizational Change
![Page 23: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/23.jpg)
Research on IS failures - better ?
- Maturing the discipline of PM
- Alternative approaches to PM
- Real Options
- HRO
© Jan Devos - 23
![Page 24: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/24.jpg)
Alternative approaches to PM
• PM does not guaranteed success nor eliminates failures• PM too much focused on ‘how-to-do’
• Management of meaning iso management of control ? • Critical perspective on projects: focus on values (technology is
not neutral), ethics and morality equally important than efficiency & effectiveness ?
• Research on SMEs: Trust vs Control ? (Devos, 2009)
• “Political” PLC
2003, The chimpanzees’ tea party: a new metaphor for project manager (Drummond & Hodgson)
2006, New Possibilities for Project Management Theory: A Critical Engagement (Cicmil & Hodgson)
© Jan Devos - 24
![Page 25: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/25.jpg)
PLC and the ‘Political’ PLC
© Jan Devos - 25
InceptionConception
Requi
rem
ents
Design & Dev.
Implem
entat
ion
Term
inat
io
n
PLC Wild enthusiasm
Disillusionme
nt
Tota
l
conf
usio
n
Search for the guilty
Punishment of
the innocent
Prom
otio
n of
non-
particip
ants
“P”PLC
![Page 26: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/26.jpg)
Alternative measures: real options
Real Options Pricing Models (ROPMs)
• Suitable for large IT infrastructure investments• Future revenue streams are unclear (unsuccessful ?)• Invest now – harvest later• An initial expenditure on IT creates the right, but not the
obligation to obtain the benefits associated with further development
• Management has the freedom to cancel, defer, restart, or expand the project
Benaroch, M. and R.J. Kauffman, “A Case for Using Real Options Pricing Analysis to Evaluate Information Technology Project Investments,” Information Systems Research, 10 (1), 1999, pp. 70-86.
John A. Campbell, Real options analysis of the timing of IS investment decisions, Information and Management, v.39 n.5, p.337-344, March 2002
© Jan Devos - 26
![Page 27: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/27.jpg)
HRO concept
• High Reliability Organizations
© Jan Devos - 27
![Page 28: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/28.jpg)
HRO concept
• Organizing for High Reliability: Processes of Collective Mindfulness (Weick, 1999)
• Preoccupation with failure (“Failure is not an option”)
• Reluctance to simplify interpretation (beware of ‘frameworks’, ‘models’, ‘mindsets’, …)
• Sensitivity to operations (“situational awareness”)
• Commitment to resilience (“continuous management of fluctuations”)
© Jan Devos - 28
![Page 29: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/29.jpg)
HRO concept
• Lessons from HROs
• The expectation of surprise is an organizational resource because it promotes attentiveness and discovery
• Anomalous events should be treated as outcomes rather than as accidents, to encourage search for sources and causes
• Errors should be made as conspicuous as possible to undermine self-deception and concealment
• Reliability requires diversity, duplication, overlap, and a varied response repertoire, whereas efficiency requires homogeneity, specialization, non-redundancy and standardisation
• Interpersonal skills are just as important in HROs as are technical skills
© Jan Devos - 29
![Page 30: IS Failures - state of the art ?](https://reader035.fdocuments.net/reader035/viewer/2022070318/5578f08cd8b42a5c5c8b50c4/html5/thumbnails/30.jpg)
End
Questions ?
© Jan Devos - 30