CHECKLIST FOR PILING WORKS (BORED PILE)
Location:
S/No Description of Works Checked by Confirmed by
Contractor QP(S)
1 Check setting out
2 Check pegged position of individual pile
3 Check services plan
4 Locate services with cable detector and digging trial trench
5 Check soil sample at pile base and confirm by contractor's
Professional Engineer
6 Check certificate of fitness of bored piling machine and service crane
7 Check certificate of crane operator
8 Check piling frame and crane located on firm bases
9 Check cover blocks/spacers
10 Check steel cage reinforcement
11 Check provision of couplers
12 Check galvanising (if applicable)
13 Ensure cleanliness of bored hole
14 Provision of tremie pipe
15 Ensure concrete is placed 1000mm above cut-off level
16 Quantity of ready-mix concrete : m3
--------------17 Check concrete grade Grade:
-------------------
18 Take slump test Desired slump: mm
-------------------
19 Take cube samples
No of sets: Reference:
20 Check verticality of piles
21 Check calculated depth of penetration
22 Check eccentricity of piles
23 Check cut-off level of piles
24 Check sufficient temporary traffic devices if lane
closure is required
25 Others
No.
Date/Time: chainage: