    CHECKLIST FOR PILING WORKS (BORED PILE)

    Location:

    S/No Description of Works Checked by Confirmed by

    Contractor QP(S)

    1 Check setting out

    2 Check pegged position of individual pile

    3 Check services plan

    4 Locate services with cable detector and digging trial trench

    5 Check soil sample at pile base and confirm by contractor's

    Professional Engineer

    6 Check certificate of fitness of bored piling machine and service crane

    7 Check certificate of crane operator

    8 Check piling frame and crane located on firm bases

    9 Check cover blocks/spacers

    10 Check steel cage reinforcement

    11 Check provision of couplers

    12 Check galvanising (if applicable)

    13 Ensure cleanliness of bored hole

    14 Provision of tremie pipe

    15 Ensure concrete is placed 1000mm above cut-off level

    16 Quantity of ready-mix concrete : m3

    --------------17 Check concrete grade Grade:

    -------------------

    18 Take slump test Desired slump: mm

    -------------------

    19 Take cube samples

    No of sets: Reference:

    20 Check verticality of piles

    21 Check calculated depth of penetration

    22 Check eccentricity of piles

    23 Check cut-off level of piles

    24 Check sufficient temporary traffic devices if lane

    closure is required

    25 Others

    No.