Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

22
Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

Transcript of Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

Page 1: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

Investment Project

Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

Page 2: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua2

About project

Limited Liability Company “MMCT “Galitsyno” was established in 2007. The company owns incomplete construction projects and other assets of “MMCT “Galitsyno”, and also accomplishes functions of a customer in project development, fulfills licensing procedures and implementation of the project “MMCT “Galitsyno”. In future LLC “MMCT “Galitsyno” will accomplish functions of a port and cargo-carrying operator.Two Ukrainian companies own 50% each of equity rights of LLC “MMCT “Galitsyno”.

Page 3: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua3

Structure of platforms of MMCT

SEA PORT9 specialized terminals for cargo

handling

RAILWAY STATION32 railroads for receiving and

sending of railroad trains

LOGISTICS CENTERWarehouses for storage,

assortment and other types of handling of goods

TECHNOLOGICAL COMPLEXPlants for для mid handling, sub

assembly etc., types of cargo handling

Page 4: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua4

Port characteristics

Number of landing places 32

Total length of landing places 5 945 m

Maximum depth close to landing places 15 m

Width of access board (from a landing place into the depth of a terminal)

650 – 850 m

Number of located warehouses (stacks) From 5 to 8

Capacity 1-2 steps: 35 mln. t per year

3 step: up to 100 mln. t per year

Page 5: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua5

Location peculiarity

Nikolayev has access to important European and international directions

Page 6: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua6

Location peculiaritySea and land ways of Eurasia lay through Nikolayev

Page 7: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua7

Location peculiarity

Number of water and land routes, going through three main sea regions of Ukraine

Illichevsk Odessa Nikolayev

Railway direction ++ ++ ++++

Auto direction +++ +++ ++++

Inner river routes +++

Intransit river routes ++

River – sea + + ++

Oversea shipment + + +

Air transportation + + +

Page 8: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua8

Location peculiarity

Crossing of 4 transport directions through Nikolayev region and amount of operating railway stations

Page 9: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua9

Location peculiarity

MMCT “Galitsyno” will be located within 8 km from Nikolayev and 36 km from the Black Sea between operating sea ports “Oktyabrsk” and “Dnieper-Bug”.

Page 10: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua10

Location peculiarity

The platform where the port is located was formed in the result of sand recultivation after dredging works

Page 11: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua11

A map from the satellite

Page 12: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua12

Major premises, business provisions and risks

Legislative warranties of private ownership of port objects Prospective market in the basin of the Black Sea –14 countries, ~ 250 mln. people Lack of port capacities in the northern part of the Black Sea Deficiency of a big port with logistical and technological terminals in the basin of the Black Sea Deficiency of opportunities to enlarge operating ports in countries of the Black Sea basin MMCT is located along an elongation vector of the VII Danube alley way towards water way

along the river Dnieper MMCT is located along the logistical route of a ring road around the Black Sea Availability of areas for leveed platforms and water area of the port on the water area of the

Dnieper-Bug basin Availability of areas for composition of port objects (railway stations, logistical warehouses and

plants) Legislative opportunity to grant the status of free trade zone to these territories Application of new approaches and technologies in complex handling of goods

Page 13: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua13

General layout on the map from the satellite

Page 14: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua14

Implementation plan

General layout: The 1st phase of the project – red color, the 2nd – green, the 3rd – yellow

Page 15: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua15

Implementation plan

Approved scheme of zoning of the plot for construction of the port and logistics terminal, railway and auto entry on the 1st and the 2nd phases of the project

Page 16: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua16

Photofixation

View overlooking a coastal zone and prospective MMCT from a roof

of a five-storied administrative building of LLC “MMCT “Galitsyno”

Page 17: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua17

Photofixation

Coastline of the territory of “MMCT “Galitsyno”

Page 18: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua18

Photofixation

Warehouse equipment and technologies

Page 19: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua19

Photofixation

Administrative building

Page 20: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua20

Financial indexation

Overall costs – 2,7 bln. $ Cost of the 1st step – 0,55 bln.$ Total construction period – 4,5 years Payback period – from 5 to 10 years

Page 21: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua21

Plan of investor entry into the project

1. Memorandum ratification between Investor and Owner of LLC “MMCT “Galitsyno” on entry into the Project.

2. Purchase of not less than 76 % of equity rights and effective assets of LLC “MMCT “Galitsyno” by the Investor on contractual terms of the contract of purchase and sale.

3. Establishment of An Asset Management Company (out of the territory of Ukraine), where Investor will own 76% of equity rights.

Page 22: Investment Project Construction of Multi-purpose Marine Complex of Terminals (MMCT) “Galitsyno”

www.titul.net.ua22

INVESTMENT- REAL ESTATE DEVELOPMENT COMPANY “TITUL”

CONTACTS:

President of the company: Telman AbbasovTel.: +38 0487155551, +38 0674899222Email: [email protected], [email protected]: www.titul.net.ua