Introduction & Up-date 20 th August 2012

Transcript of Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The...

Page 1: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

Introduction & Up-date20th August 2012

Page 2: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

Contents• The Background• The Teams• The Facilities• Location & Layout• The Planning• Communications• Your Input

Page 3: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

The Background• Current Campus Designed for Max Capacity of 1200 students

We are now c.1150 & growing

• Campus Master Plan - completed 2008Find it on InsideASH>Search “Campus Master Plan”

Historically 5 small locations in & around The HagueNew Campus 20 years agoMS “temporary” wing added 15 years agoNew ES Wing in 2003

• Purchased Land from Municiapality of Wassenaar for ECC Boerderij (farm) Ter Weer (area name)Located on small Deijlerweg, 5/7 minutes walkConstruction commenced early 2102

3

Page 4: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

The BackgroundThe key parties in the negotiations:• Municapality of Wassenaar – owned the

land & farmhouse “Boerderij Ter Weer”

• SJW Youth Club had clubhouse in the Farmhouse - were already being re-located by Gemeente

• Olympia ‘72 Handball Club will share sports facilities

• ASH – now own land & buildings

4

Page 5: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

Location & Layout

5

Page 6: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

Location & Layout

6

Page 7: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

7

• Ground cleared & prepared late 2011/ early 2012• Groundbreaking Ceremony took place 16th

February 2012• Handball fields complete (for new handball season)• Construction drawings & foundation work

completed over the summer - passed a key risk phase

• Sport complex and Gym due for completionend of December 2012

• Main ECC instructional areas doe for completion July 2013.

• Currently on schedule – weather permitting• Now: Fixtures & Fittings & Landcaping

The Planning

Page 8: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

The TeamsASH

ECC Project TeamTim Messick, Ton Ravensbergen, Rick Spradling, Hans

Carmiggelt, Lesley Murphy, Project Managers (External) ECC Design Team

Tim Messick, Fereshteh Dastani, Matthew Steuer, Ann Pleij, Carla Bruzual, Hans Carmiggelt, Project Managers

External Project Manager – Themelion

Arjen Brandon, Marije Bierenbroodspot

Architect – Kraaijvanger UrbisHans Goverde

Landscape Architect – recently selected Design Studio Van Ginneken

8

Page 9: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

Communications

9

Page 10: Introduction & Up-date 20 th August 2012. Contents • The Background • The Teams • The Facilities • Location & Layout • The Planning • Communications •

Your InputThank you for you valuable input to date. We welcome your ideas about any aspect of the project:

Contact a member of The Design Team or The Project Team

Watch out for up-dates on the website, InsideASH & PTO Bulletin

Check out the model in the main entrance

Get students involved

Direct non-staff members with inquiries to email: [email protected]

Let us know in advance when you would like to visit – we’ll pick time slots per week - hard hats must be worn at all times on the construction site.