Introduction to Process Plant Design
-
Upload
enrico-samaritani -
Category
Documents
-
view
224 -
download
0
Transcript of Introduction to Process Plant Design
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 1/8
1
Introduction to
Process Plant
Design
Copyright ©, 2012
William G. Beazley, PhD
All Rights ReservedPhoto:Air Products
Process Plants
• Characterized by Chemical Processes
– Different from power (including nuclear), propulsion,
etc. – Hazards from both energy and substance release
– Substances and their temperature and pressure, etc.,usually drives the selection of piping materials anddesign ratings
• Petrochemical Plants have their own:
– Design standards
– Terminology
– Practices and
– Constraints
Basic Components of a
Typical Chemical Process(R. K. SINNOTT)
Tanks,
Warehouses,
Hoppers,
Piles, etc.
Pumps,Compressors,
Exchangers,
Heaters,
Crushers,
Mixers, etc.
Reactors,
Furnaces,
etc.
Drums,
Towers,
Filters,
Dryers, etc.
Reflux,
Strippers,
Treaters,
etc.
Tanks,
Warehouses,
Baggers,
etc.
Raw Material Storage
• Tanks, Hoppers, Piles, etc.
Feed Preparation
(US Navy, Nasa, Transportation,• Pumps, Compressors, Exchangers, Heaters,
Crushers, Mixers, etc.
http://www.npt.nuwc.navy.mil/facilities/QuietWater/default.htm
http://www.tfhrc.gov///pubrds/05jan/02.htm
http://www.ih.navy.mil/Departments/ord/che-ext-tec-div/index.asp
Reaction
(US Army, DOE, )• Reactors, Furnaces, CSTRs, etc.
http://www.pmcd.apgea.army.mil/multimediaviewer.aspx?id=585
http://www.netl.doe.gov/technologies/coalpower/cctc/summaries/tampa/tampaedemo.html
CSTR – Continuously Stirred
Tank Reactor
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 2/8
2
Product Separation(US DOE)
• Drums, Towers, Filters,
Extraction, Dryers, etc.
http://www.nrel.gov/data/pix/searchpix.cgi?
http://www.greensboro-nc.gov/departments/Water/watersystem/treatment.htm
Product Purification(US OSHA, DOT)
• Reflux, Strippers,
Treaters, Sorters, etc.
http://iforms.osha-slc.gov/dts/osta/otm/otm_iv/otm_iv_2.html
Product Storage
• Tanks, Warehouses,
Baggers, Drums, etc.
Waste Capture and Storage(DOE, EPA, USGS)
http://www.fedcenter.gov/_storage/Photos/176.jpg
http://www.tobyhanna.army.mil/about/certifications/environmental/rcra%20cleanup.htm
http://pubs.usgs.gov/gip/gw_ruralhomeowner/gw_ruralhomeowner_new.html
• Incinerators, Sequestration, Ash
Precipitators, Chemical Sewers,
etc.
Sales
• Pipelines, Tanker Trucks,Metered OBL Flows, etc.
http://www.msc.navy.mil/sealift/2005/September/katrina.htm
Portland Process for Cement Manufacture(US CDC)
http://www.cdc.gov/elcosh/docs/d0200/d000279/ilochap93.html
Limestone,
Clay, etc.
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 3/8
3
What a Barrel
of Crude Oil
Makes
(Texas Oil &
Gas Association)
Product Gallons per barrel
Gasoline 19.5
distillate fuel oil(Includes home heating oil & diesel fuel)
9.2
kerosene-type jet fuel 4.1
residual fuel oil(Heavy oils used as fuels in industry,marine transportation and forelectric power generation)
2.3
lique fied re finery gasses 1.9
still gas 1.9
coke 1.8
asphalt and road oil 1.3
pe trochemical fe edst ocks 1.2
lubricants 0.5
kerosene 0.2
other 0.3
Figures are based on 1995
average yields for U.S.
refineries. One barrel
contains 42 gallons of
crude oil. The total
volume of products made
is 2.2 gallons greaterthan
the original 42 gallons of
crude oil. This represents
"processing gain."
http://www.txoga.org/articles/308/1/WHAT-A-BARREL-OF-CRUDE-OIL-MAKES
Crack Spread(Wikipedia)
• Hedge against adverse price movements by buying
oil futures and selling futures for its primaryrefined products according to the proportions of its
optimal mix.
• Crack Ratio X:Y:Z and X=Y+Z. Hedging by
buying X barrels of crude oil and selling Y barrels
of gasoline and Z barrels of distillate in the futures
market.
• As the 3:2:1 crack spread is the most popular, i.e.,
the "Gulf Coast 3:2:1" and the "Chicago 3:2:1"
http://en.wikipedia.org/wiki/Crack_spread
CAPEX vs OPEX
• Capital Expenditures (CAPEX)’
– First Costs
– Ends with Production (Commissioning)
– Amortized over the “life” of the plant
• Operational Expenditures (OPEX)
– Ongoing expenditures resulting in revenue (sales)
– Starts with Production – Current expense, matched with revenue
• Main Point: EPC is generally CAPEX
– EPC guys are temporary “rented experts”
– Save your money for rainy days
Life-Cycle Sustainable Development(Sandia)
http://www.sandia.gov/archsur/C33.htm
Parties to Plant
Design(The 'PIPING GUIDE')
• Client wants a finished
plant
– Business Cas e Primary
Concern
– Everyone Else is
Temporary
• Design Engineers
produce highly quality
assured product
definition data
• Construction Realizes
DesignSource:
The 'PIPINGGUIDE'
http://www.pipingguide.com
Process Plant Client
• Funds the engineering and construction of the plant• Generally supplies or approves the processes to be used
• Accepts the work performed
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 4/8
4
The Project Engineer
• Formal point of contact with the client
– Voice of the client insi de the engineering organization
– Usually “seals” design as professional engineer
• Responsible for completeness and correctness of work http://www.nps.gov/hfc/products/imi/imi-ser-class.htm
The Project Engineer
• Reviews the Design
Basis of Plant
• Enforces Client
Requirements
http://www.osha.gov/dcsp/partnerships/regional/region2/453_signing.html
The Project Engineer
• Plans and Schedules
Work http://www.osha.gov/dcsp/partnerships/regional/region2/459_signing.html
Procured Materials and Services
• Items that has been obtained from vendor or
supplier
• Assistance or advice provided by a vendor
or supplier
• Obtained through a procurement process• Result in a list of vendors and
subcontractors
Project Organization
Source: The 'PIPING GUIDE'
http://www.pipingguide.com
Project
Design
Groups and
Information
Flow(Source: The
'PIPING GUIDE')
http://www.pipingguide.com
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 5/8
5
Design Organizational Roles
Design
Supervisor
Designer
Designer
Designer
Designer
Checker
Project
Data
Design Supervisor/Group Leader
• Manages the documentation of in process
and approved engineering data
• Contacts the Project Engineer for any
approvals required
• Assigns work to designers at the appropriate
time
• Assures all data needed for work is
available to designers
The Piping Designer
• Responsible for correctness of his
work
• Inform supervisor if questions arise
• Recognize need for data required to
complete work
• Never contact the client directly
Engineering Design Specifications
• Established basis for final plant design
• Includes:
– start-up procedures,
– initial site selection information,
– general pre-commissioning guidelines,
– equipment testing procedures and acceptancemethods
– final process topology,
– material and energy balance information
Functional Equipment Characteristics
• Describe or specify:
–Functional requirements for the
equipment
–Service provided to the process by
the equipment
–What equipment is supposed to do
Vendor-Proprietary Equipment
• Equipment whose performance is
guaranteed by the vendor.
• Specified by equipment datasheet in
process design specifications
package.
• Usually designed by first selecting a
vendor who performs testing and
sizing of the item
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 6/8
6
Documentation
• All project management, design,
contractual, regulatory, and disposal
documents produced during the life
cycle of a process plant.
• Has versions and releases that must
be managed.
• Includes all documentation retained
past the end of the plant life cycle
Operations Documents
• Covers all the many different phases and
aspects of plant operation
• Documentation necessary to run the
plant safely:
– Procedure to start up and shut down the
plant
– Parameters and settings for process
equipment and controls
Handover
• Transfer of responsibility for the plant
– Construction team to commissioning team
– Commissioning team to operating team
• Involves transfer of all supporting
documentation
Common Status Terms
• As-built: Process plant's actual physical
and functional aspects at a specific point
in time
As-approved: Product data provide to
and approved by client
As-specified: Approved data provide to
engineer by client
As-released: Product data officially
provided to anyone
Construction Release
• All data needed to realize the plant
– Build,
– Commission,
– Train to operate, maintain
• Approved for release by engineering for
construction
• Stamped by a registered professional
engineer
Finalized Construction Documents
• All documentation related to theerection, commissioning and operation
• Includes:
– As-built reports,
– Equipment certification,
– Operating manuals,
– Testing procedures,
– Field changes,
– Nameplate information of installedequipment , and
– Photos of as-built units, modules and plant
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 7/8
7
Plant Commissioning• Required before
client handover
• Proven operational
through specific
procedures
– Confirm Staff
Skills
– Verify product
data
– Test equipment
• Equipment
Commissioning
Procedures - Step-
by-step expla nation
of start-up actions
required to
commission
equipment in the
planthttp://www.usaid.gov/iraq/photogallery/gallery_8/capconstr1_06.html
Maintenance
http://flickr.com/photos/coolnewspics/244371213/in/dateposted/
Maintenance
http://www.eere.energy.gov/industry/bestpractices/energymatters/full_issue.cfm/volume=37
http://www.srs.gov/general/busiops/tech-transfer/plant.htm
http://www1.usaid.gov/iraq/photogallery/gallery_39/photo18.html
http://splash.metrokc.gov/wtd/southplant/index.htm
Shutdown/Decommissioning• Shutdown: Ceasing
Operations
• Decommissioning:
– Remove from
active status
– Shutdown &
preserving for later
commissioning or
demolition
– May not include
site remediation
http://www-als.lbl.gov/als/als_news/news_archive/vol.240_042804.html
http://www.lm.doe.gov/land/sites/oh/fernald_orig/VImages/PhotoTour/1998/Dec98/Plt6c.htm
http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html
Project Schedule• Duration
• Start Date
• Critical Path
– Sequence of Tasks
such that if any is late
the project is late.
– Can be more than one
http://www.coconino.az.gov/cji.aspx?id=383
Questions
8/13/2019 Introduction to Process Plant Design
http://slidepdf.com/reader/full/introduction-to-process-plant-design 8/8
8
Production Output• Materials or energy to be sold or
traded
• Result of processing raw material(s)
(Production Input)
• Produced according to a scheduled
delivery time, grade, and quantity of
product to be producedSource: EPISTLE Process Industries Data Handover Guide - Part 1
http://www.uspi.nl/projects/Joint_Projects/fr_joint_projects.html
PISTEP Process Plant Engineering Processes
Course Outline
• Part 1 Pipe Lifecycle
• Part 2 Pipe Fluid Flow & Control
• Part 3 Plant Equipment
• Part 4 Pipe Structural Design
• Part 5 Project Practices & Management• Part 6 Project
Activity Model of the Oil and Gas
Production Facility Life-cycle(ISO 15926)
Produce Conceptual
Process Design
Produce Detailed
Process Design
Produce Conceptual
Engineering Design
(Front End)
Produce Detailed
Engineering Design
Commission
Plant
Construct Plant
Pre-Commission
Operate Plant Decommission
Plant
MaintainPlant
and Equipment
Demolish Plant
and Restore Site
Procure and Control Equipment,Material and ServicesSuppliers and
Fabricators
http://www.tc184-sc4.org/About_TC184-SC4/About_SC4_Standards/
Supplier/Vendor Relationship
• Request the required information only
• Disclosing only necessary information to
get the right data
• Avoid:
– Disclosing competition
– Telling vendor he’ll get the order
– Gratuities and never demand them (lunch)
– Ordering to get information then cancel