Introduction to Panel Caving

52
An Introduction to Block and Panel Caving Allan Moss, General manager Rio Tinto Copper Projects

Transcript of Introduction to Panel Caving

  • An Introduction to Block and Panel CavingAllan Moss, General manager Rio Tinto Copper Projects

  • Context why the interest in caving

    How block caving works and key technical considerations

    Risks

    Value drivers

    Agenda

    2BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Greater Depths of Mining

    3BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Trends in Mining ~ to 2013

    4BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Trends in Mining ~ after 2013

    5BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Why Caving?

    Use of gravity to break the rock (instead of explosives), thus low operating cost compared with other underground methods

    High production rates can be achieved allowing economies of scale

    Allows high degree of mechanization

    Safe

    However

    High initial capital costs

    Conceptually simple let gravity do the work - but technically very challenging

    Requires large design effort; high quality construction; and rigorously managed operations

    6BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • 7BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    Cave Mining ~ When is it Applicable?

    Orebodies with a substantial vertical dimension; massive or pipe like

    Rock strength not a limitation but need sufficient orebody dimensions

    Primarily used in copper mining but also molybdenum and diamonds,

  • 020000

    40000

    60000

    80000

    100000

    120000

    140000

    160000

    1880 1900 1920 1940 1960 1980 2000 2020 2040YEAR

    T

    O

    N

    N

    E

    S

    P

    E

    R

    D

    A

    Y

    Climax

    Salvador

    Kiruna

    Mount Isa

    San Manuel

    MiamiRidgeway

    Olympic DamAndina

    Freeport IOZ/DOZ

    Henderson

    MalmbergetPalabora

    PremierKidd Creek

    1000m

    2000m

    3000m

    4000m

    Pala

    bora

    Hen

    ders

    on

    Kid

    d C

    reek

    Wes

    tern

    Dee

    ps

    Hom

    esta

    ke -

    S D

    akot

    a

    Mag

    ma

    Evolution of daily production rates

    (after Brown 2004a)

    New generation Caves; under construction

    Conventional underground

    Open pits Super caves

    8BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Modernisation of an Old Method

    Grizzley Block CaveLHD Block Cave

    9BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • With Increasing Production comes need for Size

    HendersonDOZ

    San Manuel PalaboraParkes PremierPerseveranceQuesta

    Oyu Tolgoi Resolution

    10BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    Note: size is for illustrative purpose only and has been sourced from published informationExploited resource

    Unexploited resource

    Waste

    Caved waste

  • Major block and panel cave mines

    Rio TintoPlannedCurrently operatingClosed mines

    11BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Rio Tinto a leader in cave mining

    Involved in 5 block caves in operation or development

    Applying experience from operating mines to developing next generation block cave mines

    Advancing technology and innovation in block cave mining

    Building an Underground Technology Centre to ensure objectives are met, particularly with regard to people

    12BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Context why the interest in caving

    How block caving works and key technical considerations

    Risks

    Value drivers

    Agenda

    13BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Where Does Caving fit in the Spectrum of Underground?

    Method T / Manshift Avg. T / Day Relative Operating Cost per tonne

    Resuing 0.2 - 0.5 50 - 100+ 70+

    Cut and Fill 12 - 48 500 1,500 20 to 70

    Shrinkage 20 - 28 200 - 800 20 to 50

    Room and Pillar 15 - 150 1,500 10,000 7 to 20

    Open Stoping 20 - 115 1,500 25,000 7 to 25

    Sub-level Caving 65 - 180 1,500 50,000 7 to 17

    Block Caving 300 - 2000 10,000 100,000 1 to 2.5

    Underground mining methods modified from Brown, 2003

    14BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Five Key Components of a Cave Mine

    Orebody access Shafts Tunnels

    Undercutting The level where caving is initiated

    Extraction Where ore is removed from the broken rock

    Ore flow Sizing and transfer of ore to surface

    Infrastructure Support systems, ventilation, power, water, supplies, men

    15BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    Haulage Level

    Exhaust Level

    Ore PassVent Raise

    OrebodyExtraction Level

    Undercut Level

  • Block Cave Concept

    Production tunnels

    Haulagesystem

    Crushed Ore

    ShaftOre body

    Plant

    Draw bells

    16BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • 1. Develop undercut level2. Develop production tunnels

    3. Drill and blast undercut rings4. Open troughs

    Progressive spalling

    Caving Process

    45

    20

    25 35

    Block cave mining is based on the principle that, once a sufficiently large area of a block has been undercut by drilling and blasting, the overlying block of ore will start to cave under the influence of gravity.

    The process will continue until caving propagates through the entire block to surface or to the open pit above

    17BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Extraction

    Undercut

    Caved Ground

    LHDLoading

    What are we trying to achieve?

    18BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • CAPITAL INVESTMENT

    Block Caving Concept

    VALUE REALIZATION

    100%

    V

    y

    a

    z

    m

    e

    n

    s

    k

    y

    2

    0

    0

    7

    $

    TIME

    CAVEDYNAMICSSOURCESOFUNCERTAINTY

    CAVEMANAGEMENT19BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Section Through Cave

    20BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Key Technical Issues

    21BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    cave propagation

    cave fragmentation

    cave flow

  • Critical dimensions to initiate caving

    22BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Geometry of drawbells

    DRAWBELLS

    23BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Fragmentation: the key to a successful operation

    24BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Impacts of Fragmentation

    IMPLICATIONS ON RESOURCE RECOVERY

    PRODUCTIVITY

    VALUE AT RISK

    SECONDARY BLASTING

    25BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Caving the block

    Secondary Fragmentation

    Primary Fragmentation

    FlowInterruptionIndex(events/tonsx1000)

    Initialsecondaryfragmentation

    Blastingeffect

    Secondaryfragmentation

    Blastedundercutmaterial

    HoD

    Index of Interruptions Frequency (Salvador mine, draw point 04W20)

    26BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Rock Structure and fragmentation

    27BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • zone of loosening

    expansion void

    f

    (

    f

    r

    a

    g

    m

    e

    n

    t

    s

    i

    z

    e

    )

    fragment sizeevolution with draw

    higher mobility of finerfragments within a draw column

    IDZ

    Primary fragmentation

    Secondary fragmentation

    Fragmentation is complex: risks!!!

    Fine material

    Coarse material

    28BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Cave Flow

    W

    a

    s

    t

    e

    E

    n

    t

    r

    y

    H

    o

    D

    waste

    ore

    IDZ ~ Ellipsoid of Motion (extracted blocks)

    Zone of Loosening (blocks that were displaced vertically at least once)

    oreore

    o

    r

    e

    w

    a

    s

    t

    e

    w

    a

    s

    t

    e

    29BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Flow dictates Revenue Stream

    CAVED OREUNCAVED

    ORE

    EXTRACTED ORE

    WASTE ENTRY

    RILLING and MASS FLOW PREDOMINATLY MASS FLOW

    elliptical or frustumshaped IEZ;height equivalent to~100-200 mean fragment size

    cylindrical IEZ

    WASTE ROCK

    30BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • WASTE ROCK WASTE ROCK

    ORE BODY

    Vyazmensky 2008Vyazmensky 2008

    DilutionentryHighgradeore

    TIME

    $

    What do we draw?- the recovery issue

    31BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    REPEAT

  • WASTE ROCK WASTE ROCK

    ORE BODY

    Vyazmensky 2008Vyazmensky 2008

    Dilutionentry

    TIME

    $

    32BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    Highgradeore

    What do we draw?- the recovery issue

  • Rings to be blasted

    Blasted undercut rings

    CAVED ORE

    UNCAVED ORE

    Undercutting

    33BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Purpose of the Extraction Level

    ACCESS TO ORE ABOVEALLOW DEVELOPMENT OF DRAWBELLS

    34BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Light at the End of the Tunnel

    35BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    A video of some of the concepts outlined can be found http://www.argylediamonds.com.au/video_block_cave.html

  • Context why the interest in caving

    How block caving works and key technical considerations

    Risks

    Value drivers

    Agenda

    36BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Cant define risk - Cant define value

    Complete knowledge of the future is an impossibility The question then becomes how representative is

    the information we have on hand?

    This information is used to develop a robust enough plan to cater for the inherent uncertainty.

    Uncertainty translates to risk (Flexibility costs money)

    Block caving is not for marginal projects

    37BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Differences in Knowledgetherefore differences in Uncertainty

    Initiation point close to surface Substantial informationNo geotechnical constraints

    Initiation point remote from surface Limited information Substantial geotechnical constraints

    Ore drilled and typically sampled as part of mining process detailed knowledge for short term planning

    Limited knowledge of ore- sampling after the fact

    38BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Scale

    39BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • GBT Area I & II

    IOZ

    DOZ

    GBT Area I & II

    IOZ

    DOZ

    Access and Extraction Complexity

    Escondida, Chile

    DOZ Mine Freeport, Indonesia

    40BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    Courtesy of PTFI

  • Control

    OPENPITMINING CAVEMINING

    goodcontrol

    morecertainty

    limitedcontrol

    uncertainty

    reducedknowledge

    wellestablishedmethod

    BETTERTECHNOLOGYISAKEYTOBETTERVALUE

    41BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Risk

    42BMO Capital Markets 2011 Global Metals & Mining Conference

    Characterisation the resource; understanding the size of the prize

    Design resource to reserve; time for imagination

    Construction the big spend and first taste of reality

    Operation recovery and payback

    CONCRETEDAMAGE

    CONCRETEDAMAGE

    1,5 m

    Paper (Design) Value vs. Actual Value

    1 March 2011

  • Mine

    infrastructure

    Surface subsidence

    Lesson learned at Palabora

    dilution of the ore reserve andsubsequent reduction in life of mine

    43BMO Capital Markets 2011 Global Metals & Mining Conference

    Palaborasuccessfully transitioned from an open pit to a 30,000 tpd underground block cave but.

    1 March 2011

  • Context why the interest in caving

    How block caving works and key technical considerations

    Risks

    Value drivers

    Agenda

    1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference 44

  • BMO Capital Markets 2011 Global Metals & Mining Conference 45

    Ore grade and value

    Value is a function of Run of Mine (ROM) grade which is an

    outcome of three inter-related factors

    1. The resource grade; a measure of the metal that is in the ground

    2. The reserve grade, a measure of the effectiveness of the design

    3. The recovered grade, a measure of how the cave is managed and cave dynamics

    1 March 2011

  • Indicative Costs

    46BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    The capital and operating costs shown are relative and provide an indication of the spread. Both green field and brown field projects are included as are operations where access is via shaft or by decline. They were developed simply by normalising to lowest cost producers in terms of capital and operating cost.

    Capital

    Operating

  • How Soon do you Get your Money Back?

    47BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Realising Value

    New generation of Cave Mines

    represent a step change in the size of operations require investment levels of $2 to 10 billion and require significant time to achieve operating targets

    There are value drivers common to any mining project:1. Costs (capital and operating)2. Revenue3. Time

    48BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Cave dynamics Block caving is inflexible and value

    locked in at the design phase Important to understand cave

    behaviour and reliably forecast metal production (tons and grade)

    Intelligent Mining Autonomous equipment Block cave operations well suited to

    concept of intelligent mining; real time information

    Operating efficiencies

    Mine of the Future

    Investment in technology and innovation to drive value

    49BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • Investment in technology and innovation to drive value

    Rapid development Tunnelling concepts that are more

    productive and cost effective than traditional methods

    Integrated shaft boring machinery with the potentialto dramatically improve safety while reducing construction time

    Optimised design and management Building on ability to predict cave

    behaviour Improved planning techniques and

    software to improve grade sequencing

    50BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

  • The Vision an Ore Factory

    RequiredFragmentator

    ReliableOre Flow

    Predictable Fragmentation(+ grade)

    The Rock Factory

    Ore Transportand Sizing

    FragmentSize

    Energy(Distance Traveled)

    In Situ

    Crushing and Grinding

    51BMO Capital Markets 2011 Global Metals & Mining Conference1 March 2011

    The Ore Factory

  • Thank You

    Allan Moss, General manager Rio Tinto Copper Projects