INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity...

17
INTRA STATE ABT Necessity Issues Implementation

Transcript of INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity...

Page 1: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

• INTRA STATE ABT

Necessity

Issues

Implementation

Page 2: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Some of the features of New National Some of the features of New National

Electricity Policy – Feb.’05Electricity Policy – Feb.’05

• Appropriate Commissions to undertake development of power market

• SERCs to notify GRID CODE by September 2005, if not yet notified

• State Commissions to ensure upgradation of SLDCs by June 2006

• SERCs are advised to introduce ABT regime at the State level within one year i.e. by February 2006.

Page 3: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Need for intra-State ABTNeed for intra-State ABT

• Accountability of utilities after reforms• Passing on UI payment

– Intra State ABT to identify agencies responsible for overdrawal/underdrawal, overgeneration/ undergeneration, resulting in UI payment to regional pool.

• Proper Demand forecast and load management by DISCOMs

• To establish a framework for bilateral trading at intra-State level

• To achieve overall merit order operation.

Page 4: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

ISGS-1 ISGS-2 ISGS-3

CTU / ISTS SYSTEM RLDC CORDINATES

INTER-STATE

INTRA STATE

STU/INTRA STATE SYSTEM

SGS-1 SGS-2 SGS-3

DISCOM-1 DISCOM-2 DISCOM-3

SLDC CO-ORDINATES

OPEN ACCESS CUSTOMER

~ ~ ~

~ ~ ~

•ISGS: Inter State Generating Stations•SGS: State Generating Stations•CTU: Central Transmission Utility•STU: State Transmission Utility

Inter-State ABT

Intra-State ABT

•Distribution Control Centre – One for each Discom

IPPs CPPs

Non-conventional source of energy e.g., wind energy

Page 5: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Intra state ABT Intra state ABT

• Pre – requisites• Unbundling of Vertically Integrated State Utilities• Allocations from ISGS/ other state owned generators to

various Discoms by State Govt• Control centres in each Discom• RTUs at required locations

– Generating stations– Drawal points from STU to DISCOMS on

various tie-lines, ICTs– various other critical lines

• SCADA information to Discom Control Centres• SEMs at required locations • Processing of SEMs data/Settlement system

Page 6: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Intra-state ABT Intra-state ABT ..what it achieves ?what it achieves ?

Harness surplus generating capacity available in state with CPPs / IPPs

• Operation of grid on economic principles –Merit Order Despatch

• Open Access in Intra-state Transmission and Distribution.

• Generate signals for efficient grid operation at the intra-state level.

Page 7: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Intra-state ABT Intra-state ABT ––what it achieves ?what it achieves ?

• Overdrawals at low frequency by Discoms duly priced.

• Encourage serving of higher consumer demand • Encourage maximisation of generation during

deficit conditions.• Each Discom and state generating station

responsible for its actions – a profit centre• Commercial signals available to large

consumers capable of regulating drawal

Page 8: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

……Intra-state ABT Intra-state ABT – what it – what it achieves ?achieves ?

• UI mechanism at the intra-state level• UI to be applied on the deviations from the schedules

of the DISCOMS/State generators/IPPs/CPPs.• State Utilities to be collectively liable for the States’

liabilities with the regional UI pool account. • Achieves merit order operation for all the entities

under ABT• Commercial viability of running Pumped Storage

Stations.

Page 9: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Issues needs to be addressed for Issues needs to be addressed for intra-State ABTintra-State ABT

• Restructured SEBs• Identification of entities for intra-State ABT• Scheduling Principles & Procedures• Commercial Principle

– Metering Philosophy• Treatment of existing Agreements• Organisational Development• Regulatory Issues

Page 10: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

The main steps involved to implement intra-State ABT are:

• Listing of entities on which ABT/UI mechanism to be applied

• Listing of Metering locations and assess the requirement of meters and accessories

• Finalize the specifications for meters and accessories

• Presentation of the mechanism to all concerned

• Finalisation of the tariff for all generating stations in ABT format.

Implementation of intra-State Implementation of intra-State ABTABT

Page 11: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Implementation of intra-State ABTImplementation of intra-State ABT

• Finalisation of shares of each distribution zones and other commercial arrangements

• Organize installation & commissioning of meters and accessories.

• Organising meter reading, data transfer and computation at SLDC

• Establishment of the scheduling process along with scheduling software

• Presentation/training to all concerned

Page 12: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Implementation PlanImplementation Plan• 1st Phase Activities

– Finalisation of listing of entities– Listing of Metering locations– Finalisation of technical specifications &

quantities of SEMs, DCDs/MTEs– Initiate tendering process for procurement

of meters & RTUs

Page 13: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

• 2nd Phase Activities – Finsalisation of Tariff of State Generating

Stations as per ABT parameters/norms– Finalisation of Reactive Charge scheme– Finalisation of commercial mechanism for

CPPs, Wind farms, Wheeling and banking, Open Access Customers etc.

– Determination of Allocations of different Discoms in State Genco/ ISGS/ IPPs.

Implementation PlanImplementation Plan

Page 14: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

• 3rd Phase Activities – Supply and commissioning of meters at

different locations– Installation of software for data processing – Installation of software for scheduling /

energy accounting– Training– Estimate time for implementation – 12 to

18 months

Implementation PlanImplementation Plan

Page 15: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

Status on intra-State ABTStatus on intra-State ABT• Many SEBs restructured, others in process• State Utilities looking for benefits of intra-

State ABT• took lead for intra-State ABT• Punjab took lead in Northern Region• Road-map for Maharashtra is ready• POWERGRID assisting these States by

providing consultancy• Other States like MPSEB & Haryana to

follow.

Page 16: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.

1616

INTRA-STATE ABT

METERING

Page 17: INTRA STATE ABT Necessity Issues Implementation. Some of the features of New National Electricity Policy – Feb.’05 Appropriate Commissions to undertake.