INTEROP WP10: Training activities by e-learning Raúl Poler.

31
INTEROP WP10: Training activities by e- learning Raúl Poler

Transcript of INTEROP WP10: Training activities by e-learning Raúl Poler.

Page 1: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROPWP10: Training activities by e-learning

Raúl Poler

Page 2: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 2Kick-Off Bordeaux: Jan-2004

Contents

• WP10 Working Plan

• Task Assignment

• Workpackage Monitoring

• Connection with other WPs

• Next meetings

Page 3: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 3Kick-Off Bordeaux: Jan-2004

WP10 Overview

WP10WP10

GlossaryGlossary Document Document RepositorRepositor

yy

TutorialsTutorials

Web Web coursescourses

PhD PhD ProgramProgram

Master Master ProgramProgram SynergySynergy

Page 4: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 4Kick-Off Bordeaux: Jan-2004

Tasks

Task 10.1Task 10.1. Preparation and dissemination of a Glossary on Enterprise Modelling, Architecture & Platform and Ontologies.

Task 10.2Task 10.2. To create a virtual Library of papers about interoperability (Interoperability Explicit Knowledge Repository-IEKR)

Task 10.3Task 10.3. Creation of Tutorials (interactive courses on CDROM) on Interoperability.

Task 10.4Task 10.4. Creation of web courses about interoperability.

Task 10.5Task 10.5. Coordination of the creation of a European Master on Interoperability.

Task 10.6Task 10.6. Coordination of the creation of a European PhD Program on Interoperability.

Page 5: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 5Kick-Off Bordeaux: Jan-2004

Participants

Polytechnic University of Valencia (Leader) GRAISOFT Université Henri Poincaré – Nancy 1 Consiglio Nazionale delle Ricerche (CNR - IASI) Stiftelsen for Industriell log Teknisk Forskning ved NTH - SINTEF AIDIMA Ecole Centrale de Lille University degli Studi di Roma “La Sapienza” Tilburg University Kungl Tekniska Högskolan University of Geneva Free University of Bolzano-Bozen Institute for Information Systems at the German

Page 6: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 6Kick-Off Bordeaux: Jan-2004

Participants

Page 7: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 7Kick-Off Bordeaux: Jan-2004

Deliverables & Milestones

DeliverablesDeliverables: D 10.1 Interoperability Glossary (Month 12) D 10.2 Interoperability Explicit Knowledge Repository-

IEKR (Month 18) MilestonesMilestones:

M6 To define web sites and responsible for IEKR and courses about interoperability (Month 6)

M18 List of Universities and Institutions participating in Master and PhD Program on Interoperability (Month 18)

M18 Tutorials and web-courses on Interoperability (1st version)

M24 Creation of a European Master on Interoperability M36 Tutorials and web-courses on Interoperability

(2nd version)

INTEROP portal

Page 8: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 8Kick-Off Bordeaux: Jan-2004

Task 10.1. Preparation and dissemination of a GlossaryTask 10.1. Preparation and dissemination of a Glossary

Duration: One year (M1-M12) Based on a Web interface:

The glossary will be made up of two main parts: Public zone: consultation of the Glossary by any external user

(with search engine). Private zone: insertion of terms in the Glossary by the

partners, sending of revision requests and term approval & publication.

Classified in: Modelling Architectures & Platforms Ontologies

Term fields: Term: text Modelling: checkbox Arq&Plat: checkbox Ontology: checkbox Definition: text Author: text Language: text

Date: date Partner: text SendToRev: checkbox Revised: checkbox Validated: checkbox Score: integer

Done by WP2

newnew

Page 9: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 9Kick-Off Bordeaux: Jan-2004

Task 10.1. Preparation and dissemination of a GlossaryTask 10.1. Preparation and dissemination of a Glossary

Working method: WP2 will develop the Web environment supporting the glossary. WP10 will develop a manual of the Web environment in order to

avoid problems with the insertion process. INTEROP members will be the providers of terms and definitions. Each term will be able to have more than one definition and will be

assigned to a WP10 participant as reviewer. Finally, the revised terms (after all needed modifications done in

the portal) will be checked as valid in order to be published in the Public web space.

D10.1 will include all gathered terms.

Develop Web Environment

M1-M6Term

InsertionTerm

RevisionTerm

Approval & Publication

Web Environment

M7-M11

M12

Develop D10.1

Page 10: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 10Kick-Off Bordeaux: Jan-2004

Divided in seven formal subtasks:

Task 10.1. Preparation and dissemination of a GlossaryTask 10.1. Preparation and dissemination of a Glossary

Weight (%)

in WP10

TASK 10.1 - PREPARATION AND DISSEMINATION OF A GLOSSARY 9

1 Develop the Web environment to support the glossary 4

2Elaborate manual about the Glossary introduction process and Web

interface0,5

3 Request the insertion of terms in the glossary to all INTEROP partners 0,25

4Drive the revision process (assign and send terms to be revised by WP10

Partners)0,75

5 Revise terms 2

6 Revision approval and term validation 0,5

7 Develop Deliverable 10.1 - "Interoperability Glossary" 1

Page 11: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 11Kick-Off Bordeaux: Jan-2004

Task 10.1. Preparation and dissemination of a GlossaryTask 10.1. Preparation and dissemination of a Glossary

• Task 1 PlanningTask 1 Planning

Page 12: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 12Kick-Off Bordeaux: Jan-2004

Task 10.2. Create a virtual Library of papers Task 10.2. Create a virtual Library of papers (IEKR)(IEKR)

Duration: One year and a half (M1-M18) Based on a Web interface (similar to the glossary):

The IEKR will be made up of two main parts: Public zone: consultation of documents by any external user

(with search engine). Private zone: insertion of documents in the IEKR by the

partners, sending of revision requests and document approval & publication.

Classified too in: Modelling Architectures & Platforms Ontologies

Term fields: DocTitle: text Modelling: checkbox Arq&Plat: checkbox Ontology: checkbox Abstract: memo Author: text Date: date

Partner: text State: (full text, abstract only) Link: hypertext SendToRev: checkbox Revised: checkbox Validated: checkbox Language: text

Done by WP2

newnew

Page 13: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 13Kick-Off Bordeaux: Jan-2004

Task 10.2. Create a virtual Library of papers (IEKR)Task 10.2. Create a virtual Library of papers (IEKR)

Working method: WP2 will develop the Web environment supporting the IEKR. WP10 will develop a manual of the Web environment in order to

avoid problems with the insertion process. INTEROP members will be the providers of papers and links. The IEKR will support documents in different languages. Finally, the revised papers (after all needed modifications done in

the portal) will be checked as valid in order to be published in the Public web space.

All external documents hosted or linked, must have the permission of the author.

Moreover, it should have a Search Engine to locate the desired documents.

Develop Web Environment

M1-M6Paper

InsertionPaper

RevisionPaper

Approval & Publication

Web Environment

M7-M17

M18

Develop D10.2

Page 14: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 14Kick-Off Bordeaux: Jan-2004

Divided in seven formal subtasks:

Task 10.2. Create a virtual Library of papers (IEKR)Task 10.2. Create a virtual Library of papers (IEKR)

Weight (%)

In WP10

Task 10.2 - CREATION OF A VIRTUAL REPOSITORY OF PAPERS 9

1 Develop the Web environment to support the Virtual repository 4

2 Elaborate manual about the papers introduction process and Web interface 0,5

3Request quarterly the insertion of papers in the repository to all INTEROP

partners0,25

4Drive the revision process (assign and send papers to be revised by WP10

Partners)0,75

5 Revise papers 2

6 Revision approval and papers validation 0,5

7Develop Deliverable 10.2 - "Interoperability Explicit Knowledge Repository

- IEKR"1

Page 15: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 15Kick-Off Bordeaux: Jan-2004

Task 10.2. Create a virtual Library of papers Task 10.2. Create a virtual Library of papers (IEKR)(IEKR)

• TaskTask 2 Planning 2 Planning

Page 16: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 16Kick-Off Bordeaux: Jan-2004

Task 10.3. Creation of Tutorials (interactive courses Task 10.3. Creation of Tutorials (interactive courses on CD)on CD)

Duration: 36 months (M1 - M36). Working plan:

To define: In Kick-off will be defined the e-learning platform accordingly

to the global requirements of the project. Tutorials types:

Generic, Specific, Trainer, Best Practices, etc. (to be defined) Tasks:

INTEROP members will provide tutorials or courses already developed.

WP10 members will develop the contents of the required courses.

WP10 members will build the tutorials on CD.

Define tutorials

framework (types and

topics)

Gather existing tutorials or

courses

Check tutorials to

be developed

Develop contents

Build tutorials

on CD

Done by WP2

Page 17: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 17Kick-Off Bordeaux: Jan-2004

Divided in seven formal subtasks:

Task 10.3. Creation of Tutorials (interactive courses on Task 10.3. Creation of Tutorials (interactive courses on CD)CD)

Weight (%)

In WP10

Task 10.3 - CREATION OF TUTORIALS (INTERACTIVE COURSES ON CD) 21

1 Define types of tutorials (generic, specific, trainer, etc.) and structure 0,5

2Decide the tutorials to be developed. Topics and main contents (proposals

by WP10 members)1

3Drive the gathering process of existing tutorials and courses on

interoperability (EM, A&P, ONTO) within INTEROP members1

4 Select suitable courses 1

5 Check the tutorials with contents to be developed 0,5

6 Develop contents of new tutorials 9

7 Build tutorials based on the information gathered and developed 8

Page 18: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 18Kick-Off Bordeaux: Jan-2004

Task 10.3. Creation of Tutorials (interactive courses Task 10.3. Creation of Tutorials (interactive courses on CD)on CD)

• TaskTask 3 Planning 3 Planning

Page 19: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 19Kick-Off Bordeaux: Jan-2004

Task 10.4. Creation of web courses about Task 10.4. Creation of web courses about interoperabilityinteroperability

This task can be done This task can be done jointlyjointly with Task 10.3. with Task 10.3. Duration: 36 months (M1 - M36). Working plan:

The same that Task 10.3. Web courses types:

Generic, Specific, Trainer, Best Practices, etc. (to be defined) Tasks:

INTEROP members will provide courses already developed. WP10 members will develop the contents of the required courses. WP10 members will build the Web courses on the e-learning

Platform.

Define Web courses

framework (types and

topics)

Gather existing tutorials or

courses

Check web courses to be

developed

Develop contents

Build Web courses on e-learning platform

Page 20: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 20Kick-Off Bordeaux: Jan-2004

Divided in seven formal subtasks:

Task 10.4. Creation of web courses about Task 10.4. Creation of web courses about interoperabilityinteroperability

Weight (%)

In WP10

Task 10.4 - CREATION OF WEB COURSES ABOUT INTEROPERABILITY 19

1 Define types of web courses (generic, specific, trainer, etc.) and structure 0,5

2Decide the web courses to be developed. Topics and main contents

(proposals by WP10 members)1

3Drive the gathering process of existing tutorials and courses on

interoperability (EM, A&P, ONTO) within INTEROP members1

4 Select suitable courses 1

5 Check the web courses with contents to be developed 0,5

6 Develop contents of new web courses 9

7 Build web courses based on the information gathered and developed 6

Page 21: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 21Kick-Off Bordeaux: Jan-2004

Task 10.4. Creation of web courses about Task 10.4. Creation of web courses about interoperabilityinteroperability

• TaskTask 4 Planning 4 Planning

Page 22: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 22Kick-Off Bordeaux: Jan-2004

Task 10.5 & Task 10.6. Coordination of the Task 10.5 & Task 10.6. Coordination of the creation of a European Master and European Phd creation of a European Master and European Phd on Interoperabilityon Interoperability

Working plan: Duration: 36 months (M1 - M36).

M24 Creation of a European Master on Interoperability

Program basis: The participant Universities in the Master and PhD

program will be only from within INTEROP Project.

European Master and PhD contents production: Those tasks will search the maximum synergy with

Task 10.4 (development of Web Courses). All the INTEROP Universities and Research Institutions

interested should provide subjects and contents. Each WP10 participant should coordinate the

production of contents of some parts of the courses.

Participant Un.StructureKernel subjects

Page 23: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 23Kick-Off Bordeaux: Jan-2004

Task 10.5 divided in seven formal subtasks:

Task 10.5 & Task 10.6. Coordination of the creation of a Task 10.5 & Task 10.6. Coordination of the creation of a European Master and European Phd on InteroperabilityEuropean Master and European Phd on Interoperability

Weight (%)

In WP10

Task 10.5 - COORDINATION OF THE CREATION OF A EUROPEAN MASTER 21

1 Analyze existing experiences on European Masters 0,75

2 Methodology and strategic framework for Master Program and e-learning 1,5

3Search universities and research institutions interested in the

development and teaching of the Master within INTEROP members0,5

4 Collect proposals of contents of the Master 1

5 Define subjects of the Master and responsibles 2,5

6Develop contents for each subject of the Master (theoretical and

practical contents)8

7 Put contents in the INTEROP e-learning environment 3

8Develop a teaching plan to be carried out in the next years (included

presence and virtual dedication and locations)2

9 Develop a university professor's mobility plan for the Master 1

10 Analyze legal aspects on European Masters 0,75

newnew

Page 24: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 24Kick-Off Bordeaux: Jan-2004

Task 10.5 & Task 10.6. Coordination of the creation Task 10.5 & Task 10.6. Coordination of the creation of a European Master and European Phd on of a European Master and European Phd on InteroperabilityInteroperability

• TaskTask 5 Planning 5 Planning newnew

Page 25: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 25Kick-Off Bordeaux: Jan-2004

Task 10.6 divided in seven formal subtasks:

Task 10.5 & Task 10.6. Coordination of the creation of a Task 10.5 & Task 10.6. Coordination of the creation of a European Master and European Phd on InteroperabilityEuropean Master and European Phd on Interoperability

Weight (%)

In WP10

Task 10.6 - COORDINATION OF THE CREATION OF A EUROPEAN PhD PROGRAM 21

1 Analyze existing experiences on European PhDs 0,75

2 Methodology and strategic framework for PhD Program and e-learning 1,5

3Search universities and research institutions interested in the

development and teaching of the PhD Program within INTEROP members

0,5

4 Collect proposals of contents of the PhD Program 1

5 Define subjects of the PhD Program and responsibles 2,5

6Develop contents for each subject of the PhD Program (theoretical and

practical contents)8

7 Put contents in the INTEROP e-learning environment 3

8Develop a teaching plan to be carried out in the next years (included

presence and virtual dedication and locations)2

9 Develop a university professor's mobility plan for the PhD Program 1

10Analyze legal aspects on European PhDs 0,75

newnew

Page 26: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 26Kick-Off Bordeaux: Jan-2004

Task 10.5 & Task 10.6. Coordination of the creation Task 10.5 & Task 10.6. Coordination of the creation of a European Master and European Phd on of a European Master and European Phd on InteroperabilityInteroperability

• TaskTask 6 Planning 6 Planning newnew

Page 27: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 27Kick-Off Bordeaux: Jan-2004

Task Assignment

Page 28: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 28Kick-Off Bordeaux: Jan-2004

Workpackage Monitoring

UPV will make the “Macro-Monitoring” of the Workpackage based on dates.

Each member with assigned supervising tasks, will be responsible of the monitoring of the development of those tasks by other partners.

Page 29: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 29Kick-Off Bordeaux: Jan-2004

Connection with other WPs

WP10

Roadmap for researchers mobility

WP3WP3

WP12WP12

Services

Ontology based integration WP8WP8

RepositoryTutorialsWeb courses

Glossary

Master&PhD

WP9WP9

Architectures

WP7WP7Generation of customized

Enterprise Software

WP6WP6

Design principles for interoperability

WP5WP5

Common Enterprise Modelling Framework

K Map

WP1WP1

Technical support WP2WP2

Dissemination & Communication

WP11WP11

Page 30: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 30Kick-Off Bordeaux: Jan-2004

Connection with other WPs

 

AIDIM

A

CNR-IA

SI

EC-LILLE

FUB

GRAISOFT

DFKI

KTH

SINTEF

UNITILB

UPV

UHP-CRAN

UNIROMA

UNIGE

WP1                          

WP2                          

WP3                          

WP4                          

WP5                          

WP6                          

WP7                          

WP8                          

WP9                          

WP10                          

WP11                          

WP12                          

WP Input Contact Point

WP Member

Assignment Criteria:

1. To be WPi Leader

2. Effort in WPi

Assignment Criteria:

1. To be WPi Leader

2. Effort in WPi

WP Output Contact Point

“Contact Point” means an interlocutor of any WP10

participant with the WPi. It will be the responsible to notify to the “WP10 Task responsibles”

the appearance of some relation between the Wpi and WP10. A “Contact Point” is not a document provider

“Contact Point” means an interlocutor of any WP10

participant with the WPi. It will be the responsible to notify to the “WP10 Task responsibles”

the appearance of some relation between the Wpi and WP10. A “Contact Point” is not a document provider

newnew

newnew

Page 31: INTEROP WP10: Training activities by e-learning Raúl Poler.

INTEROP - WP10 31Kick-Off Bordeaux: Jan-2004

Next Meetings

2 WP10 meetings between now and next General Assembly (Nov 2004) Dates: May 2004, Sept 2004 Location: tbd Should be linked with other WPs meetings