INTERNSHIP REPORT (FINAL)
-
Upload
sindhuja-balaji -
Category
Documents
-
view
316 -
download
19
Transcript of INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORTAT ELECTRICAL AND MECHANICAL DEPARTMENT OF
POWER TRANSMISSION AND DISTRIBUTION IC
LARSEN & TOUBRO LIMITED
SUBMITTED BY
B.SINDHUJA
M.G.VISHALI
Electrical and Electronics Engineering
RMD Engineering College
During the period09-06-2014 to 20-06-2014
CONTENTS
Acknowledgement
Introduction – BMRCL Project
BMRCL Specifications
Electrification of metro rail stations
Earthing philosophy
Assignment- vendor offer review report
Diesel Generator sizing
Load details and Switchgear sizing
L.V Feeder cable sizing
Distribution Transformer sizing
Electrical calculations -Lighting calculations
Cable schedule
ACKNOWLEDGEMENT
The industrial exposure that we have experienced as trainees in
Industrial Electrification Business Unit of Power transmission and
Distribution Independent Company (PT&D IC) of L&T Construction
has helped us a lot not only in improving our theoretical knowledge but
also to understand the working of a large industry and Practical
engineering.
We are sincerely grateful to the management of PT & D IC and
Mr. D. Maheswaran, GM & Head Engineering (IE&SS)- PT&D IC, for
giving us an opportunity to undergo a ten days Internship program in
their organization.
We would like to express our deepest gratitude towards Mr. Krishnan
C. Menon for associating us in this training. We also express our sincere
gratitude & thanks to Ms. Priyanka Dharamshi and Mrs. R.Sandhiya
for the guidance and encouragement at various stages during our
internship.
Last but not the least; we would like to thank L&T Construction for
providing us this opportunity and exposure to the real Industry.
BANGALORE METRO RAIL PROJECT
What is METRO Rail?
• An urban electric passenger transport system
• High capacity & high frequency of service
• Totally independent from other traffic road or pedestrianRevolution in traction systems
Electric trains came to existence with DC over headlines of 1.5kV & 3kV DC in late 19th Century.
Usage of high voltage DC would lead to electrocution and considered unsafe. Hence was restricted to low speed to overcome the same
AC traction system came to existence in mid 20th century with 15kV system feeding the DC Series motors through AC-DC rectifiers.
Due to the technical difficulty in rectifier technology 25kV AC Induction motor traction system came to existence in late 20th century.
There was revolution in DC traction system as it was more appealing for metro due to its aesthetic aspects. Due to high demand of Metro 750V DC Third rail traction system came to existence. “Third rail” Terms the rail other than two running rails which feeds power to the traction motors
Advantages & Disadvantages of 25kV over 750V DC Traction system
• 25kV AC Traction system is safer. • Used for high speed trains for longer distances• Cost effective compared to DC third rail• But causes imbalance in 3-phase supply
Delhi Metro
(Line -1, Line 2, Line 3, Line
4, Line 5 & Line 6)
Kolkata Metro(Line -1)
Bangalore Metro(Reach-1, Reach- 2,
Reach – 3 & Reach -4)
Jaipur Metro
Chennai Metro
Hyderabad Metro
Total No. of Stations
142 24 42 11 40 64
Line Length 189 kms 28kms 42 kms 9.25 kms 42 kms 72 kms
Traction System 25 kV AC 750 VDC 750 VDC 25 kV AC 25 kV AC 25 kV AC
Type of Station
Both U/G & Elevated
Both U/G & Elevated
Both U/G & Elevated
Both U/G &
Elevated
Both U/G &
ElevatedElevated
Project Status Completed** Completed Completed** Under
ExecutionUnder
ExecutionUnder
Execution
Comparison between various metro rails in India
** These projects are executed in different phases and some phases are handed over and are under commercial operation.
Characteristics of railway electrification
Two forms in which Power is supplied to moving trains:
1. Overhead line or catenary wire suspended from poles or towers along the track or from structure or tunnel ceilings
2. Third rail mounted at track level and contacted by a sliding "pickup shoe“ usually use the running rails as the return conductor but some systems use a separate fourth rail for this purpose.
Third rail : A third rail is a method of providing Electric power to a railway train, through a semi-continuous rigid conductor placed alongside or between the rails of a railway track.
The conductor rail is supported on ceramic insulators (known as "pots") or insulated brackets, typically at intervals of around 10 feet (3 metres).
Usually use the running rails act as the return conductor but some systems use a separate fourth rail for this purpose.
Benefits of Third Rail system:
• Eradicates Electromagnetic interference on electrical components
• Reduces maintenance costs.
• Offers high efficiency - a 750V dc system gives efficiency of 92-94%.
• More Rugged than an overhead contact wire
• Longer life expectancy.
• High reliability because it is fed on both sides by rectifiers from adjacent substations
• Lower comparative initial costs than an AC system.
• Cheaper Rolling stock
• Since no transformers are installed on board– Reduced Weight of the vehicles and Increased Passenger Capacity
METRO TERMINOLOGIES RELEVANT TO POWER DISTRBUTION
• RSS (Receiving Sub-Station)
• TSS (Traction Sub-Station)
• ASS (Auxiliary Sub-Station)
• Depot
• Viaduct
• Chainage
Key Features of BMRCL
Owner Bangalore Metro Rail Corporation Limited
Number of lines2 (Now)2 (Phase I Target- March 2015)4 (Phase II Target - December 2019)
Number of stations16 (Now)41 (Phase I Target - March 2015)102 (Phase II Target- December 2019)
Chief executive Pradeep Singh Kharola, MD
Operation
Began operation 20 October 2011 (2011-10-20)
Train length 3 coaches
Headway 10 – 15 minutes
Technical
System length 42.3 km (Phase I)114.39 km (Phase II)
Track gauge 1,435 mm standard gauge
Electrification 750V DC Third rail
Speed 40 km/h (Average) , 80 km/h (Top)
Other features of BMRCL
• Tunnel air conditioning
• Uses Composite DC Third rail
• Air conditioned coaches
• Automatic Train Protection System
• Derailment protection guards
• Wi-Fi enabled (the first metro in India to have this feature)
• Emergency voice communication
• Powerheart Automated external defibrillator to protect its commuters against death from sudden cardiac arrest
• Earthquake proof & rainwater harvesting
• The minimum fare is 10 and maximum fare of 15 for Reach-1
Levels of Underground station:
1. Concourse – level below the ground, that has escalators, ,ticket counters, DG rooms etc2. Platform - level below concourse that has tracks for commutation3. Undercroft- bottom most level , it consists of cable trays .
L&T’s scope of work
Electrical and Mechanical( E&M) works including Hydraulic, Fire safety systems, UPS, DG Sets for Seven Underground stations and associated tunnel sections of North-South and East-West Corridors of Bangalore Metro Rail Project-Phase-1
The seven underground stations under L&T ‘s scope are
1. City Railway, 2. Sir M Vishveshwaraya,3. VidhanaSoudha, 4. Cubbon Park, 5. Chickpete, 6. KR Market and 7. Kempegowda
I. ELECTRICAL WORKS: -- E&M Package
• Design, Preparation of Working or shop drawings
• Provision of :
1. Power & control cables
2. Main, sub main LV switchboards & rest other distribution boards
3. Interlocks & protection schemes for power distribution
4. Normal & emergency lighting arrangement
5. Plug & sockets for lighting in tunnel & station areas
6. Earthing system –Main Earth bus in ASS, Clean Earth system & Clean Earth Bus
7. Lightning protection system
• Interface & coordination with BMS contractor for development of suitable control schemes
• Ascertain power supply feeding arrangements for ECS, TVS, Lifts & Escalators ets
• Supply & Lying of GI conduits with accessories for PA, communication, Signaling systems.
II. HYDRAULIC WORKS:
• Provision of:
1. Pumping arrangements
2. Automatic control & monitoring of operation of pumps
3. Feeding arrangement of various pumps
4. Pipeline network with control valves, water treatment to suit ECS requirements
III. FIRE FIGHTING & PROTECTION WORKS
1. Complete Fire suppression system in UG stations and associated tunnel sections & ancillary buildings including hydrants, hose reels, sprinkler system, fire hose cabinets, portable extinguishers, gas based flooding system etc
2. Fire Detection & Alarm system including monitoring & control through SCADA.
Designated contractors
General Consultants: RITES-OC-PBI-SYSTRA Detail Design consultants: Mott MacDonald Civil works: CEC & SOMA Traction : ABB Telecom: Thales Signaling: Alstom HVAC: Bluestar Tunnel fans: ETA Elevators, Lifts, Escalators: Johnson
Other interfaces excluding E&M
Lifts and escalators Railways electrification( DC Traction)
Auxiliary substation( up to the provision of bus ducts from transformer to LV main switch board)
SCADA and UPS Track work and Rolling stock Signaling and telecommunication
EARTHING PHILOSOPHYEarthing:
To understand the earthing codes and practices, we have been provided with the Indian Standard 3043 (Code of Practice for Earthing). We understand various earthingphilosophies followed in industries and are briefly described here.
In electricity supply systems, an earthing system or grounding system is circuitry which connects parts of the electric circuit with the ground, thus defining the electric potential of the conductors relative to the Earth's conductive surface. The choice of earthing system can affect the safety and electromagnetic compatibility of the power supply. In particular, it affects the magnitude and distribution of short circuit currents through the system, and the effects it creates on equipment and people in the proximity of the circuit. If a fault within an electrical device connects a live supply conductor to an exposed conductive surface, anyone touching it while electrically connected to the earth will complete a circuit back to the earthed supply conductor and receive an electric shock.
Earthing methods
The choice of these methods governs the measures necessary for protection against indirect-contact hazards.
The earthing system qualifies three originally independent choices made by the designer of an electrical distribution system or installation:
The type of connection of the electrical system (that is generally of the neutral conductor) and of the exposed parts to earth electrodes.
A separate protective conductor or protective conductor and neutral conductor being a single conductor
The use of earth fault protection of overcurrent protective switchgear which clear only relatively high fault currents or the use of additional relays able to detect and clear small insulation fault currents to earth
In practice, these choices have been grouped and standardised as explained below.Each of these choices provides standardisedearthing systems with three advantages and drawbacks:
Connection of the exposed conductive parts of the equipment and of the neutral conductor to the PE conductor results in equipotentiality and lower overvoltages but increases earth fault currents
A separate protective conductor is costly even if it has a small cross-sectional area but it is much more unlikely to be polluted by voltage drops and harmonics, etc. than a neutral conductor is. Leakage currents are also avoided in extraneous conductive parts
Installation of residual current protective relays or insulation monitoring devices are much more sensitive and permits in many circumstances to clear faults before heavy damage occurs (motors, fires, electrocution). The protection offered is in addition independent with respect to changes in an existing installation
Classification OfEarthing Based On System Earthing
TT system (earthed neutral) TN systems (exposed conductive parts connected to the neutral) IT system (isolated or impedance-earthed neutral)
TT system (earthed neutral)
One point at the supply source is connected directly to earth. All exposed- and extraneous-conductive-parts are connected to a separate earth electrode at the installation. This electrode may or may not be electrically independent of the source electrode. The two zones of influence may overlap without affecting the operation of protective devices.
TN systems (exposed conductive parts connected to the neutral)
The source is earthed as for the TT system (above). In the installation, all exposed- and extraneous-conductive-parts are connected to the neutral conductor. The several versions of TN systems are shown below.
TN-C system The neutral conductor is also used as a protective conductor and is referred to as a PEN (Protective Earth and Neutral) conductor. This system is not permitted for conductors of less than 10 mm2 or for portable equipment.The TN-C system requires an effective equipotential environment within the installation with
dispersed earth electrodes spaced as regularly as possible since the PEN conductor is both the neutral conductor and at the same time carries phase unbalance currents as well as 3rd order harmonic currents (and their multiples).The PEN conductor must therefore be connected to a number of earth electrodes in the installation. Caution: In the TN-C system, the “protective conductor” function has priority over the “neutral function”. In particular, a PEN conductor must always be connected to the earthing terminal of a load and a jumper is used to connect this terminal to the neutral terminal.
Fig.: TN-C system
TN-S system The TN-S system (5 wires) is obligatory for circuits with cross-sectional areas less than 10 mm2 for portable equipment.The protective conductor and the neutral conductor are separate. On underground cable systems where lead-sheathed cables exist, the protective conductor is generally the lead sheath. The use of separate PE and N conductors (5 wires) is obligatory for circuits with cross-sectional areas less than 10 mm2 for portable equipment.
Fig.: TN-S system
TN-C-S system The TN-C and TN-S systems can be used in the same installation. In the TN-C-S system, the TN-C (4 wires) system must never be used downstream of the TN-S (5 wires) system, since any accidental interruption in the neutral on the upstream part would lead to an interruption in the protective conductor in the downstream part and therefore a danger.
Fig: TN-C-S system
Fig.: Connection of the PEN conductor in the TN-C system
IT system (isolated or impedance-earthed neutral)
IT system (isolated neutral)No intentional connection is made between the neutral point of the supply source and earth
Fig: IT system (isolated neutral)
Exposed- and extraneous-conductive-parts of the installation are connected to an earth electrode.In practice all circuits have a leakage impedance to earth, since no insulation is perfect. In
parallel with this (distributed) resistive leakage path, there is the distributed capacitive current path, the two paths together constituting the normal leakage impedance to earth .
Fig: IT system (isolated neutral)
In a LV 3-phase 3-wire system, 1 km of cable will have a leakage impedance due to C1, C2, C3 and R1, R2 and R3 equivalent to a neutral earth impedance Zct of 3,000 to 4,000 Ω, without counting the filtering capacitances of electronic devices.
Fig: Impedance equivalent to leakage impedances in an IT system
IT system (impedance-earthed neutral)An impedance Zs (in the order of 1,000 to 2,000 Ω) is connected permanently between the neutral point of the transformer LV winding and earth (see Fig. E11). All exposed- and extraneous-conductive-parts are connected to an earth electrode. The reasons for this form of power-source earthing are to fix the potential of a small network with respect to earth (Zs is small compared to the leakage impedance) and to reduce the level of overvoltages, such as transmitted surges from the MV windings, static charges, etc. with respect to earth. It has, however, the effect of slightly increasing the first-fault current level.
Step Potential
Step potential is the step voltage between the feet of a person standing near an energized grounded object. It is equal to the difference in voltage, given by the voltage distribution curve, between two points at different distances from the electrode. A person could be at risk of injury during a fault simply by standing near the grounding point.
Touch Potential
Touch potential is the touch voltage between the energized object and the feet of a person in contact with the object. It is equal to the difference in voltage between the object and a point some distance away. The touch potential or touch voltage could be nearly the full voltage across the grounded object if that object is grounded at a point remote from the place where the person is in contact with it. For example, a crane that was grounded to the system neutral and that contacted an energized line would expose any person in contact with the crane or its uninsulated load line to a touch potential nearly equal to the full fault voltage.
Reducing Step and Touch Potential Hazards
One of the simplest methods of reducing Step and Touch Potential hazards is to wear Electric Hazard Shoes. When dry, properly rated electric hazard shoes have millions of ohms of resistance in the soles and are an excellent tool for personnel safety. On the other hand, when these boots are wet and dirty, current may bypass the soles of the boots in the film of material that has accumulated on the sides of the boot. A wet leather boot can have a resistance on the order of 100 ohms. Furthermore, it cannot be assumed that the general public, who may have access to the outside perimeter of some sites, will wear such protective gear.
Another technique used in mitigating Step and Touch Potential hazards is the addition of more resistive surface layers. Often a layer of crushed rock is added to a tower or substation to provide a layer of insulation between personnel and the earth. This layer reduces the amount of current that can flow through a given person and into the earth. Weed control is another important factor, as plants become energized during a fault and can conduct hazardous voltages into a person. Asphalt is an excellent alternative, as it is far more resistive than crushed rock, and weed growth is not a problem. The addition of resistive surface layers always improves personnel safety during a GPR event.
Also it is the industrial practice to have underground earthmat which is properly designed to bring touch and step potential to tolerable limits. There are provided in switchyards, Power generation stations, Metro rail stations, etc.
BMRCL Equipment DetailsI. DG SETS
It has Diesel engine integrated with alternator, engine mounted radiator, battery, battery charger and day service tank.
Piping with fuel handling system, lube oil system, air filters, exhaust piping and residential silencer.
Power and Control cabling system
Contains steel base frame, integral sound proof enclosure (acoustic enclosure) and anti vibrating mounting pads.
Satisfies the requirements of NFPA110.
Rating
750 & 1010 kVA, 415V DG Sets.
Power Factor-0.9 lagging (average) but at rated condition, load power factor is 0.8 lagging or better.
Operating mode –Used only for standby purposes supplying the rated loads for 8 hours with the rest period not less than 30 minutes.
Overload capacity-Reserve capacity-10% for one hour in twelve hours.
Ambient conditions-Maximum temperature 45º,Maximum Humidity-75%RH attitude:1000m(Above mean sea level)
Service Interval-running full load-less than 300 hours without maintenance adjustments and for 10,000 hours between major overhauls.
Shaft Speed-Not more than 1500 rev/min
Motor Starting-Largest motor set is require to start-18KW-Star-Delta starter
Loads-Operating in conjunction with non-linear and harmonics generating electronic loads in UPS Systems.
Cold Conditions
Start automatically-full rated loads (30sec) on failure of supply.
Jacketed water heating facility before starting pre-lubrication array.
Housing
Sound proof enclosure reduces the noise level of 75 dB at one meter distance from DG set enclosure.
Diesel Engine
Four stroke, multi cylinder –dynamically balanced with electronic fuel injection systems, turbo charged and intercooled suitable for heavy duty emergency operations.
Critical speed-Crankshaft-15% rated speed.
Engine-10% over load for one hour in 12 hour running period.
Engine fitted with heavy dynamically balanced flywheel for constant speed generator-BS649 requirements.
Engine Speed maintained-BS 5514
DG set parallel to another DG set-installation of an auto synchronizing panel suitable for PCC operation.
DG set provides continuous operation at ambient temperature for 8 hours.
Basic Engine
Connecting rod-heavy duty-forged special steel for handling power tariff.
Pistons are provided with piston rings and forced lubrication is employed to avoid any hotspot development.
Cylinder-lubrication-inner side with close tolerance-efficient output.
Air Intake System
Intake-air-force from engine room.
Ventilation system-DG sound proof enclosure.
Twin heavy duty air intake-BS72266
Turbo Charger
Driven by exhaust gas from cylinder.
Intercooled System
Compressed air-turbo charger-after cooled air heat exchange.
Enhance engine performance level and pre mature requirements of maintenance.
Exhaust System
High noise reduction muffler-correct position-exhaust pipeline.
Two silencers in series, one is located inside and other one is fitted on the roof of the generator building.
Minimum wall thickness of pipes and silencers-3mm.
Installation thickness-checked in tender-Max temperature is 50ºC on outside of pipe and supporting should be provided o withstand back pressure.
Silencer reduces sound level of 25dB by one meter form DG set.
Engine Cooling System
Engine cooled-water jacket-heavy duty air blast radiator.
Separate oil cooling is provided by cooling engine oil.
Lubricating System
Engine lubrication-closed circuit-wet sump, forced feed system
Forced lubrication uses lubrication filter with a minimum time period of 300 hours or more.
Lubricating oil pressure is monitored and on any fall below the recommended value, alarm is used and engine is safely shut down.
Fuel System
High speed diesel oil-IS 1460.
2 stage fuel filtration. The Fuel system-engine speed governor of electronic type.
Governor
Governor control- isochronous type –constant speed of engine at different load-maximum rating of machine.
Requirements
Steady state speed - + 1% of nominal speed.
Transient frequency change on application-rejection of 60% of load.
Max speed drop : 8%
Performance of governor under all load conditions – class A in BS5514:part 4(ISO 3040)
Starting System and Battery Charging
Starting system compromise-24V heavy duty sealed maintenance free, has lead acid battery and electric starting motor.
Provision to start engine from remote locations-from control panel or control room.
Automatic change over-battery charging-engine driven alternator at all times-generator set is running.
Automatic changer with automatic selection unit.
Alternator
Four pole, three phase, salient pole, self excited, revolving field, brushless type, self regulating and manufactured –IEC 60034.
Screen protected, fan ventilated, Neutral dip proof-IP23.
Capable of maintaining short circuit I, three times full load for a period of 3 seconds.
Alternator winding-insulation-Class H.
Transient performance-Clause 13.18.7.
Three neutral sides CT for differential protection.
Test temperature rise test of winding-100% of rated current.
Mounting and Package Generator
Fully painted anti corrosive plate.
Noise level restricted to 70dB at 1m from canopy.
Anti vibrationmounting is spring type between bedplate and floor prevents the vibration from being transmitted.
Metering
Parameter monitoring
Electrical-system DC voltages, AC voltages, AC current, frequency, real power, reactive power, power factor.
Engine-Lubricating oil pressure, exhaust temperature, RPM
Protections
Alarms.
Over speed, alternator winding temperature, start failed alarm, low oil pressure.
Engine protection/shut off parameters.
Over speed, low oil pressure, over ranking.
Electrical protection.
Loss of excitation, over and under frequency, over current, over and under voltages.
OPERATIONS
Manual start/stop-generator set.
Local and remote selection for the operation of generator set.
Engine speed/voltage control.
Fuel transfer control.
Provisions for PLC I/Ps &O/Ps
DG Battery voltage
DG Output voltage
Generator Control Unit
Manual start/stop of generators from LPGCP
Metering & alarm
Auto start/stop of generator for generator switch gears
Performance data transmission
Load management/load based auto start/stop/paralleling
Protection of generator sets
Active and reactive load sharing for generator sets
Automatic paralleling /Synchronizing of generator sets
Control Unit: - Electrical and System Protection
Features
Over current, earth fault and under voltage
Under frequency, reverse power and standby earth fault
Differential, alternator bearing/winding temperature high
Protection Of Operations
High water/oil temperature, low lubrication oil and high pressure.
High and low speed, alternator over pressure.
Fuel Tanks
Integral fuel day tank-capacity to run for 8 hours.
Tank constructed with mild steel BS 2594.
Fuel Filters
Supply line fuel filter-BS 4552
Fuel Pipe Work and Valves
Not limited to service filling pipe.
Bulk fuel tank to service tank pipes
Service tank vent pipe.
Generate fuel supply and return pipes.
Fire Protection
Multi sensor detectors
Ventilator in generator building.
II. LIGHTING
Operate at power factor not less than 0.95 lagging.
Conduit terminations with aluminum fittings and special accessories to prevent corrosion action.
All wiring within light fitting –heat resisting low smoke, zero halogen wires for normal luminaries and fire survival wires for emergency luminaries.
All light fittings-BS 4533
Specification for general requirements and tests-BS 4533
Photometric data for luminaries-BS 5225
Requirements for electrical installations, IEE wiring regulations 17th edition-BS 7671.
Fluorescent Luminaries
Supplied with HF, electronic ballasts.
Diffuses light subjected polycarbonate/glass, injection moulded, glass-not combustion-self extinguishing.
High intensity discharge luminaries
Installation of interior luminaries.
After installation remove dirt and debris from enclosures
Clean photometric control surfaces
Exterior Luminaries
Poles shall be set in the ground to a depth of 1030 m or one fifth of length.
Pole internal copper conductor, PVC installed IS 694.
Control gear-galvanized steel case mounted on or inside pole.
Emergency Lighting
Emergency lighting installation-NFPA 101 and NEPA 130, BS 5266,BS 4553,part 101 and part 102.22.
Emergency Luminaries
Clearly marked with labels visible to persons standing on floor beneath them.
Lamp Parameters
Linear fluorescent lamp
Metal ballide
High pressure sodium
Compact fluorescent
LED
Light Emitting Diode (Led) Based Fitting
LED based luminaries, in addition to LED module, provision for heat transfer-control gear, optical conditioning, mechanical support and protection as well as aesthetic switch elements.
III. SWITCHGEARS
Standards
BS 1432, specification for copper for electrical purposes: high conductivity copper rectangular conductors with rolled edges.
IEC 60439-1/EN 60439-1: Specifications for low voltage switch gear.
Switch Boards
Low Voltage Main Switch Boards(LVBs)
IEC 60255/EN 60255:Electrical protection relays
BS 381 C/BS 4800: Colours for identification, coding and special purposes.
BS 921 :Rubber mats
BS 1432: Copper for electrical purposes.
BS 7211-Thermosetting insulating cable
BS 5685 –Electricity meters
General Requirements
Totally Type Tested Assemblies (TTTA).
All type tests-IEC 60439-1 or EN 60439-1
LV main switch boards-fault containment tests-IEC 11641
Protecting earthing configuration TN-S
Service life-30years
Separate current transformer for each device.
Quality Control
Work man ship
All suitable items of LVSBs-completely interchangeable.
Tropicalisation
Encloses required degree of protection,`
Current transformer winding are epoxy resin capsulated against ingress of mixture.
LVSB Construction
LVSB is constructed by using 2mm CRCA thick sheet steel.
LVSB front and back access has maximum height of 2.3m
Degree of IP for LVSB –IP54.
Equipment is arranged within each component
It requires normal maintenance
SB-Rated sort time with stand current of 65KA for 1 second.
BS 951 & BS7430- the component parts of SB.
Busbars
Bus bars and bus connections – not exceed 90ºC.
Short time withstand current rating is 65KA for 1sec at 415V
Bus bar and bus bar connections-IEC 60439-1 or EN 60439-1
Separate insulating covers-BS EN 60216,IEC 60085 &IEC 60216-1
Polarity
2 pole, phase pole and neutral pole reacting top to bottom/left to right.
3 Pole, Red, Yellow, Blue And Neutral/Phase.
Internal and Control Wiring
All internal and control wiring-low smoke halogen(LSZH)-BS 7211
Control wiring-single core with min of 1.5mm2.
Bus wires are fully insulated.
Control Wires Are Protected By Msb.
Instrumentation
Instruments-similar in appearance throughout LVSB
Direct reading electrical meters -1S 13779/IEC 1036,687,1286
Meter is in continuous operation - 0ºC and 50ºC
Meters operation with CT/PT-RS 485/RS 232.
Relays
All control, interlock and alarm relays –EN60255 or IEC60255.
The relays are microprocessor based with auxiliary contacts – RS232/485.
The relays are provided with dust proof cases and flush mounting.
The relays are not affected by mechanical shock or vibration or by external magnetic fields.
Operating Coils
The fine wire operating coils with wire wound resistors are vacuum impregnated with insulating varnish.
Air Circuit Breakers (ACB)
All ACBs are from IEC-609472 or EN-60947-2
Frequency-50hz
Ambient temperature-45 ºC.
All ACBs are withdrawable type.
ACB mechanically robust construction.
Overload and short circuit characteristics are front adjustable.
Safety Shutters
Shutters cover each 3 phase group of stationary isolating restarts.
Transformer Incomers
Four pole horizontal draw out automatic ACB with normal current rating are present.
Two way tripping relays are provided.
Circuit breakers close/trip control switch is of piston grid type.
Control relay and wiring for automatic changeover interlocking/voltage sensing relay for automatic changeover are present.
Moulded Case Circuit Breakers (MCCB)
MCCB comply with and be type tested-IEC 60947-2 or EN 60947-2.
Each MCCB are fixed or withdrawable type.
The trip units are easily replaceable in same MCCB without changing MCCB.
All MCCBs arrange padlocking in OFF positions with locks provided.
The degree of protection is IP3X to IEC 60529 or EN 60529.
They have an electrical endurance of 1000 operating cycles.
The MCCB in low voltage main switch board store energy motorized and suitable for remote closing by BMS.
Contractors
They comply with IEC 60947-4-1 or EN 60947-4-1.
They are electro magnetically controlled, double air-break type. they are silver or silver faced.
They are modular in design and mechanically interlocked.
The making and braking capacity of contractors IEC 947-4
They are capable of being integrated into automated system without interposing components in minimum operating condition.
IV. UNINTERRUPTIBLE POWER SUPPLY (UPS)
UPS maintain continuous AC power supply to loads-emergency category loads.
Noise from UPS during operation should not exceed 55 dB at a distance from enclosure, over load range of 10% to 100% of rated full load ISO 3756/BS 4196:Part 6.
The design life is about 20 years.
They are modular in construction to facilitate unit replacement and all electronic cards shall permit plug in type replacement.
They are dust and vermiform proof with IP-33 to IEC 60529.
The UPS are provided with RS 232 & 485 for remote monitoring to extend alarm and status indications, communications and metering to BMS system located in station control room.
The system has operating efficiency, front access and self diagnosing features.
The heat producing devices are mounted on ample heat sinks.
The UPS as a whole are mounted on heavy duty fabricated steel base frame.
The UPS has low impedance with less than 50V, touch voltage and ripple content.
The UPS output voltage is in synchronization with main supply voltage feeding the static bypass switch.
The UPS are equipped with interlocking system to prevent parallel operation.
The UPS are capable of supplying non linear types of loads.
The UPS interface for remote monitoring of status and alarms.
The surge protective devices are used for protection.
Modes
Normal mode (mains up)
Stored energy mode (mains down)
Battery recharge(mains restored)
Automatic bypass mode (static bypass switch)
Built in/manual bypass (maintenance)
The UPS on taking unbalanced load shall be provided with H class insulation.
ELECTRIFICATION OF METRO RAIL STATIONSchematic layout diagram
The SLD is the single line schematic layout that gives the plan and layout of every equipment electrification, its cable layout, earthing layout etc.
The SLD for the city railway station was studied.
The Schematic layout diagram includes the following.
General schematics Panel wise schematic- with distribution boards Circuit Breaker Interlocking Lighting layout for concourse, platform and undercroft Ancillary building layout
Chiller pump room – basement Refuse,toilet, mess ,DG room – ground floor
Power socket layout Cable tray layout Lighting layout Protection layout Earth strip layout Main earth distribution Clean earth distribution Main earth mat location Clean earth pit location Earth details
There are two substations ASS I and ASS II that powers the main distribution board. Diesel generators are used as backup during power failure. UPS system is used for powering up the emergency loads.The various Distribution boards used are
DB 100 , DB 200 ------- main supply
DB 110, DB 210 -------- small power
DB 120, DB 220 -------- lighting
DB 150, DB 250 -------- B classified loads (Essential loads)
DB 151, DB 251 --------- escalator
DB 180, DB 280 --------- UPS
DB 130, DB 230 --------- Air handling unit
DB 140, DB 240 --------- Ventilation loads
DB 290, DB 390 --------- DG set
Classification of supply
All power supply equipment will have feeds from two auxiliary substations (ASS) so that failure of any ASS or single component will not result in a supply disconnection. Certain loads will have back up supply from the diesel generator and/or from the UPS.
‘A’ Classification (Emergency)
Derived from the station UPS, with 30 minutes standby. The station UPS is provided with dual incoming supplies from ASS and backed up from the diesel generator set with auto changeover. The devices under this class are
Station And Tunnel Emergency Lights Fire Alarm Panel Supply Control Circuits Station Control Room Signage Points All Over Station SCADA System Signaling And Telecom Equipments
‘B’ Classification (Essential)
Supply from both sub stations (with automatic changeover at substation level) and backed up with diesel generator set. The devices under this class are
ECS And TVS Equipments Fire Fighting Pumps Seepage Pumps Lifts Automatic Fare Collection Escalators Sewage Pumps Cross Passage Pumps Ramp Sump Pumps
‘C’ Classification (Semi Essential)
Supply from substation with automatic changeover at substation level. No generator back-up is provided. The devices under this class are
Chiller Plant Room Equipments AHU’s And Associated Filters Water Treatment Pumps
‘D1’ Classification (Normal)
Dual supply from both sub stations at distribution board level (no generator back-up), manual changeover is provided in the event of failure of any substation. Manual transfer switches are provided. The devices under this class are
Normal Lighting Small Power Sockets Advertisement Points Storm Water Pumps
‘D2’ Classification (Normal)
Supply from any one substation only, no generator back-up and no manual changeover. The devices under this class are
GSM/CDMA Room
Cables used in metro electrification:
The type of cable used for normal supply is generally XLPE with NO SMOKE & ZERO HALOGEN characteristics. Fire resistant cables are used for UPS supplies and they power up the emergency loads .
Fire resistant and fire retardant cable sheaths are design to resist combustion and limit the propagation of flames. Low smokes cables have a sheath designed to limit the amount of smoke and toxic halogen gases given off during fire situations.
Flame Retardant - designed for use in fire situations where the spread of flames along a cable route needs to be retarded
Fire Resistant (FR) - cables are designed to maintain circuit integrity of those vital emergency services during the fire
Low Smoke and Fume (LSF) - burns with very little smoke and fumes compared to standard PVC, fumes may contain halogens
Low Smoke Zero Halogen (LSZH) - when burns there is very little smoke and fumes (compared to standard PVC the fumes contain no halogens
Alternative names for LSZH - LSZO (Low Smoke Zero Halogen), 0HLS (Zero Halogen Low Smoke), LSHF (Low Smoke Halogen Free)
Fire Survival (FS) cables - Fire survival cables are used to maintain circuit integrity for designated period of time (3 hrs. in general) under fire. Same is used for all emergency feeders in a Metro station.
A comparison of common insulating materials is as follows:
Material Advantages Disadvantages
PVC Cheap
Durable Widely available
Highest dielectric losses Melts at high temperatures
Contains halogens Not suitable for MV / HV cables
PE Lowest dielectric losses High initial dielectric
strength
Highly sensitive to water treeing Material breaks down at high temperatures
XLPE
Low dielectric losses Improved material
properties at high temperatures
Does not melt but thermal expansion occurs
Medium sensitivity to water treeing (although some XLPE polymers are water-tree resistant)
EPR
Increased flexibility Reduced thermal expansion
(relative to XLPE) Low sensitivity to water
treeing
Medium-High dielectric losses Requires inorganic filler / additive
Paper / Oil
Low-Medium dielectric losses
Not harmed by DC testing Known history of reliability
High weight High cost
Requires hydraulic pressure / pumps for insulating fluid
Difficult to repair Degrades with moisture
VENDOR OFFER REVIEW REPORT
S.no SPECIFICATIONS Powerica - DG 750 KVA REMARKS
Generator Control Unit
1. Auto/manual selection Manual push botton In Compliance
2. Separate selection facility (key operated) - Details required
3. Auto mode – controlled by SG room Remote control In compliance
4. Manual mode-lockable selector switch - Details required
5. Starting with cranking cranking 3 attempts In compliance
6. Fail to start alarm Overcrank shutdown In compliance
7. Stopping when CB is open Alarm provided In compliance
8. Cool down time cycle
(0 – 300 ms) prior to starting(0-600 ms) prior to stopping
In compliance
9. Isochronous paralleling Available in PCU In compliance
10. Auto control of V,F, phase angle and sequence
within ±1.0% for any load between no load and full load
In compliance
11. Paralleling based on microprocessor Sensor based In compliance
12. Load sharing and managementIntegrated load sharing control system
In compliance
Protection against over voltage, earth fault, under voltage, over AmpSentry protective
Metering
1, Digital type display320*240 pixels LEd with LCD backlight In Compliance
2,
Electrical parameter mounting for System DC voltage Ac voltage AC current Frequency KW KVAR PF
Digital genset metering system In Compliance
3,
Engine monitoring for RPM Oil pressure Running hours
Service hours
SAE-J1939CANEngine controller In Compliance
4, Engine monitoring for Jacket water temperature Not specified Not applicable in India
5, Engine monitoring for Exhaust temperature - Details required
Protection
6, Alarm Start failure
Overcrank shutdown with warning In Compliance
7, Winding temperature shut down alarm - Details required
8, Over speed alarm Data available Details required
9, Service tank level( high & low) alarm - Details required
10, Low oil pressureHigh coolant temperature Data available Details required
11,
Electrical Protection Over current Under voltage Over voltage Under and over frequency Reverse power
Loss of excitation
present With shut down mechanism In compliance
12, Single phase protection - Details required
Operation
13, Remote selection of operation In PCC not in GCU In compliance
14, Engine speed control Within +/- 0.25% In compliance
15, Alt. voltage control Within +/- 1.0% In compliance
16, No load and manual test facility Clock interfaced test facility In Compliance
17, Volt free contacts for remote signaling of alarm - Details required
18, Signal isolators for remote signaling - Details required
19, Anti condensation heater control -Not required for Indian climate. Details required
20, Fuel transfer pump control -Level is sensed, no control, Details required
GENERAL REQUIREMENT
1. Steel base frame ISMC-300 In Compliance
2. Integral sound proof enclosure Composite type,75 db at 1m length In Compliance
3. Power factor Avg 0.80.9 at rated load In Compliance
4. Continuous operation for 8 hours, with rest not more than 30 mins Not specified Details required
5. Ambient conditions Temp 40 deg C No mention about humidity
6. Service interval Not specified Details required
7. RPM 1500 RPM In Compliance
8. Wake up time 30 seconds Not specified Details required
9. Pre lubrication arrangement Not specified Details required
Engine Details
10. Strokes 4 In Compliance
11. Multi cylinder 12 In Compliance
12. Turbo charged Not specified Details required
13. Critical crank shaft speed within 15% of rated
15010% of rated In Compliance
14. Sustain 10% overload in 12 hour running Not specified Details required
15. lubricating oil filters 4 paper element filters of 30 microns size In Compliance
16. air cleaner
2 air cleaners with filtering capacity of 15 microns with an efficiency of 99.7%
In Compliance
17. starter 2 starters of 24 volts ,9 KW In Compliance
18. battery charger
Battery charging alternator of 35 amps with 2.33/3500 drive ratio
In Compliance
19. Flywheel SAC 14 ( dimensions = 589,89,142 mm) In Compliance
20. Bearings Replaceable Ball bearings In Compliance
21. Air filter type Paper element In Compliance
22. Twin heavy duty air intake filters Not specified Details required
23. Silencer
2 silencer of 562 mm dia.
Muffler, 3mm thick
Details required about material used, ( galvanized steel is required)
about dBA at 1 m length
about insulation and thickness
24. Radiator Air blast Oil cooled In Compliance
25. Lubricating system Min. life 300 hrs. In Compliance
26. Fuel system P/T typeDetails required about 2 stage fuel filtration
27.
Governor
Isochronous type
Steady state band of +/- 0.25%
Class A1
Details required about frequency change on load rejection.
28. Starting system
Maintainable Battery
charging with 24V lead acid battery
Automatic changeover
With stop push button
Details required about starting time off engine from the receipt of command
No mention about trickle boost facility
ALETERNATOR
29. General requirement 4 POLE, 3 PHASE, 750 KVA Stamford make
30.Short circuit current bearing must be thrice of full load current in 3 seconds
Not specified Details required
31. Voltage regulation +/- 0.5% In Compliance
32. Ingress protection IP-23 In Compliance
33. Insulation Class H In Compliance
34.Transmission voltage deviation folowin step load of, must be55% is +/- 8% and 60% is +/- 10%
- Details required
35.
Mounting and packaging
With steel base plate and anti corrosive paint
In Compliance No mention about anti vibration mounting
36. Fuel tank
Integral fuel tank -8 hours , 990 lit
Drain at lowest point ,inlet at top
Direct level indicator
In Compliance
37. Fuel filter Element type In Compliance No mention
about firesensor
Diesel Generator SizingA 415V, 3phase 50Hz, Diesel Generator sets are been provided at each underground Metro stations for the back-up electrical power supply to essential and emergency services in the event of failure of regular electrical power supply. There are three modes of operation:
Normal mode - TVF is off Congested mode - TVF is on Fire mode - TVF running in reverse ,up going escalators on
Normal mode is when the train is freely travelling between the stations, the tunnel ventilation fans are off during normal mode.
Congested mode of operation is when there is no fire in the station but the train is struck in the tunnel area between two stations and the tunnel ventilation fans and the tunnel booster fans are required to work due to sudden congestion of the tunnel area.
During the fire mode, both the tunnel ventilation fans and the fire fighting pumps are on. The tunnel ventilation fans are operated in reverse mode to extract the smoke during fire.
Among the three modes of operation the maximum demand load on the station is during congested operation mode, hence the same is considered to arrive at the DG rating.
Steps for calculating the DG size:
Step 1: Decide the maximum load. It is known from the modes that the congested mode will have the maximum load as the tunnel fans will have to work.
Step 2: Estimate the engine size in KW. The factors to be considered here is the specification given by the client and the cost.
Step 3: Estimate the alternator size in KVA.
Step 4: Check the criteria for the Transient voltage dip (TVD).
TVD < 15 % at the starting of the Tunnel ventilation fan motor.
TVD = Xd
'
Xd' +C
X d' = Transmissionreactance of the alternator (given)
C = rated KVA (to be calculated) = Totalratingof 2 DG∈¿
Starting KVA load wen TVF is started
Starting KVA when TVF is started = (starting KVA of 180 KW motor) + (base KVA load when motor is started)
Base KVA = Max. load KVA – motor load in KVA (0.86 pf TVF motor)
Step 5:
Downstream load calculation.
The downstream load distribution is calculated and tabulated in the below format.
The individual board load for every distribution board is considered.
Distribution board start
Board load
Loads connectedIn KW
Working status
Supply class
Power factor
Load frequency
Diversity factor
MD factor
Total connected load in KW
Full load current in amps
KVAR
Total connected load in KVA
Later the loads have been summarized at main board level as shown below.
Switch board
Load dissipation
Connected load in KW
Total CLKW
Connected load in KVA
Total CLKVA
Overall DF
Total MD in KW
Total MD KVA remarks
ASS I ASS II ASS I ASS II
The distribution board column indicates the various DB’s like DB 100, DB 200 etc, and their respective individual loads are considered.
Status basically specifies the mode.S = standby
W = working
Supply class gives the classification of the supply
‘A’ Classification (Emergency)
‘B’ Classification (Essential)
‘C’ Classification (Semi Essential)
‘D1’ Classification (Normal)
‘D2’ Classification (Normal)
Power factor points to that of the systems.
Total connected load refers to every load that is powered by the system.
Load Factor =Maximum demand
aperiod
Peak load∈t h at period
Diversity Factor = Individual maximum demands of variousdivisions of a system
Maximum demand of t h ew h ole system
Diversity factor on working mode will be 1 and on standby mode will be 0.
Maximum demand Factor = MaximumdemandConnected load
LOAD DETAILS AND SWITCHGEAR SIZING
Basis of Calculations-
1. Lighting and small power loads are considered as per the actual loads based on the layout drawings and distribution board details.
2. Equipment data (i.e.) the preliminary data for ECS and TVS system are provided by the GC.3. Advertisement and Commercial loads are to be received from the designer. These loads are usually assumed.4. The references are taken from National Building Code of India, Outline Design criteria (ODC).
Load calculations-
1. The sizing of LT panels is done in terms of switchgear rating and number of feeders.2. Feeder quantity and sizing is based on grouping of loads according to classification of supply.
The downstream calculations and the upstream calculations are done for ASS I and ASS II under the following conditions: Load details for ASS I:
When both ASS I and ASS II are working, feeding their respective loads.
Load details for ASS II When both ASS I and ASS II are working, feeding their respective loads.
The load details are calculated panel wise when
ASS I is working ,ASS II is failed ASS II is working , ASS I is failed
Downstream load tabulations
Distribution
board start
Board
load
Loads
connecte
d
In KW
Workin
g status
Supply
class
Power
factor
Load
frequency
Diversity
factor
MD
factor
Total
connected
load in
KW
Full load
current in
amps
KVAR
Total
connected
load in
KVA
Later the loads have been summarized at main board level as shown below.
DB Name Power factor CL load in KW CL load in KVACL load in
KVAR
Full load current
in amps
Fault Level calculations of switchgearWhen a short circuit occurs in an electric system, heavy current flows through all the sections of the system which are in the
path between the power source and the equipment. The short circuit current is limited only by the impedance of the system.
This heavy current can damage the components of the electric system if they are not properly rated. If circuit breakers are not able to interrupt the high short circuit currents in a system, arcing and explosions may occur
The Rating of the components is done based on the maximum short circuit current.The short circuit current is calculated from the fault level KVA of the System. The Fault Level in a distribution system is a very important parameter. The kVA at the instant of a Fault should be correctly calculated and the components of the distribution system such as bus bars, circuit breakers, isolators, etc should be properly sized
Short Circuit Current (kA) for switchgear will be selected based on the 3 phase fault level (kA) of the board. Which can be arrived based on short circuit analysis of the system.
Distribution board start
Board load
Loads connectedIn KW
Working status
Supply class
Power factor
Load freq.HZ
DFMD factor
Total connected load in KW
Full load current in amps
KVAR
Total connected load in KVA
design current
Appr,Breaker rating
3 phFault level KA
Tabulation for the same is as follows.
LV Feeder cable sizingReference standards
IS 5819-(1970) recommended Short circuit rating of high voltage PVC cables
Assumptions
Voltage drop due to source during the steady state-compensated by OLTC power transformer and 100% voltage is maintained at source.
Design inputs
Load details
Load dissipation Voltage drop at above source during steady state (%)
System Inputs
System voltage (v) Frequency (f) Short circuit current withstand capacity at switchboard (I f ) Duration of fault withstand capacity (t) Apparent power of load (s) Load power factor (cos φ) Length of the cable (L) Efficiency (η) Maximum allowable steady state voltage drop at load terminals (V da) Source reactance (X s)
Environmental details
Ambient temperature (T)
Cable data
Voltage grade (V c) Number of cores Cross sectional area (A) Conductor material (copper/aluminum) Insulation Current carrying capacity
I cair I cgnd
Resistance of the conductor (Rc) Reactance of the conductor (X s) Short circuit current withstanding capacity of conductor (I sc) Number of runs selected (n)
Checking thermal ampacity
Calculation of derating factor for laying in ground
Derating factor for variation in ground temperature = G1
Derating factor for thermal resistivity of soil = G2
Derating of depth of laying = G3
Touching or spacing or trefoil spacing = G4
Overall derating factor = K-Gnd = G1*G2*G3*G4
Calculations of Derating factor for laying in air
Derating factor for air temperature = A1
Derating factor grouping = A2
Overall derating factor = K-Air = A1*A2
Calculations
The derated current carrying capacity of cable in air
I CDRA=I c Air∗K−Air (A)
The derated current carrying capacity of cable in ground
I CDRG=I C Gnd∗K−Gnd (A)
Derating capacity of the cable selected
ICDRA∗Runs
The current carrying capacity required for full load current
I L =S
√3 . V
Checking short circuit withstand capability
Short circuit withstand capability of selected size of cable = I SC∗n√ t
Resistance of cable for length selected R= RC∗L
1000∗n
Reactance for length of the cable X= XC∗L
1000∗n
3 phase fault current at load terminal = V
√3¿¿
Checking for steady state voltage drop
From phasor diagram,
V Ph= V L+ IRcosQ+ IXcos ( 90−Q )
Steady state voltage drop V d=I ( RcosQ+XsinQ )
% V d for this length = V d∗100∗√3
1000∗V
Total voltage drop = % V d+voltage drop at source during steady state ( give n )
RESULT
The cable is selected based on the calculated values
Thermal ampacity (derated current) Short circuit withstand capacity Steady state voltage drop
DISTRIBUTION TRANSFORMER SIZINGPurpose
To select the optimum sizing of the distribution transformer
Reference
IS 2026 – part I – gives the specification of power transformer IS 325 – gives the specifications of 3 phase induction motor
I
Q
V Ph
IXsin(90-Q)IX
IXcos(90-Q)
VIR
Assumptions
Voltage drop due to source during the steady state-compensated by OLTC power transformer and 100% voltage is maintained at source.
Design inputs
HV side voltage (V H¿ LV side voltage (V L¿ Frequency (f) Total maximum demand (MD) Total connected load (TCL) Design margin (DM) System power factor LV side phase voltage (V Ph¿
Largest rating motor data
Power rating Type of motor and starter Full load power factor and Starting power factor Ratio of starting current to full load current Full load efficiency Motor cable details ( dimensions, type and material used) Number of runs Length of cable (Lm¿ Resistance of cable (R¿¿m)¿ Reactance of cable (X m¿ Source parameters (KVA) and source fault (MVA)
Steady State capacity calculations
Transformer capacity required = MD
1−DM
Based on this the size of the transformer is selected.
Checking on capacity for transient conditions
Base load
BL= MD – P*MD/TCL/Cos φ
Base load current
I m1=BL∗1000
√3 V
Full load current of motor
I fl=P∗1000
√3 V L∗cosφ∗η
Starting current of motor
I st=1.2∗K∗I fl
Total starting KVA required = STLM + BL = transformer overload withstanding capacity (200%)
Overload withstand capacity of transformer = transformer overload withstanding capacity (200%) + selected size
Checking for voltage drop during largest motor starting
Base impedance at 1 MVA and given KV (Ω ) Source fault MVA Source reactance (X s¿
Transformer parameters
% impedance (Z) Transformer reactance (XT ¿ Net source reactance (XT +X s=X s 0¿
Phasor diagram
Calculations
From phasor diagram
V ph¿(V m cosQ+ I s Rm)2+(V m sinQ+ I S Xm+ I s X so+X so ( I m2−I m1 ))2
motor starting current
I s=I st V m
V Ph
bus voltage
V m cosQ
V ph
V b
V m
V m sinQ
I X X0
I s Xm
I s
V b ¿(V mcosQ+ I s Rm)2+(V m sinQ+ I S X t)2
So far from these equations
V ph2=(V m cosQ+
I st Rm V m
V Ph)
2
+¿¿
RESULT:
Using the rating of transformer KVA thermal loading on transformer during motor starting , voltage available at motor during motor starting, voltage available at bus during motor starting, the transformer size is selected.
Electrical Calculations – Lighting CalculationsThe lighting calculations has been carried out based on the outline design requirements from BMRCL, Design basis reports and design review discussions with general consultants. DIALUX software has been used for lighting calculations. The lighting fixtures have been selected to suit the architectural ceiling plan.
General inputs:
Height of the room in m Mounted height m Maintenance factor
We determine the following
The minimum lux in the corners Emin[lx] The maximum lux which is the concentrated intensity of light Emax[lx] The average lux in the room Eavg[lx] Reflection factor ρ [% ]
Utilization factor u0
For the surfaces: work plane, floor, ceiling and walls
From the determined parameters we decide the luminaries’ parts list.
CABLE SCHEDULEThe majestic interchange station was considered for cable scheduling during the internship period. Cable scheduling was done for power cables, normal earth and clean earth. The routing sequence of the cables was found out from the schematic layout diagram using true view software and the length of the cables are measured by using ZWCad software.
The routing sequence is tabulated as follows.
FromFrom(code) To To
(code) Cable ID Length in km
Insulation type Core Area
No of core and size
No of runs
Routing sequence
The beginning and ending points of the cable connecting every equipment in the station is considered and their ‘from’ and ‘to’ codes are generated. The cable ID is thus generated using the ‘from’ and ‘to’ codes to distinctly identify every cable, to ease the cable laying process during construction. The details of the cables namely, their length, insulation type (XLPE), Core type, Area , Number of cores, core sizes and the number of runs are tabulated as shown above.
The Routing Sequence is done by comparing the earthing layout with the combined service layout and according to the client inputs regarding the selection of trays for the respective cables in their route.
From the routing sequence the cable scheduling is done for calculating the free space available and proposing new sizes when there is contradiction. The cable schedule tabulation is shown below.
Route tag
SpaceReq.
Spec.Free space%
TotalSpaceReq.
Tray SizeProvided
No of trays
Space Avail.
Excess space avail.
Free Space %
Proposed TraySize
No of TraysProps.
Space avail.props
Free space avail.Props.
Type
Route tag: This gives the distinct tag given to every tray route.
Space required: Space required is calculated from the routing sequence and the size of that cable.
Specified free space %: This is given by the client with the idea of future expansion.
Total space required: It is the sum of the space required and the free space specified.
Tray size provided: This gives the size of the trays provided by the client.
Number of trays: It gives the number of trays provided.
Space available: This is given by the product of tray size and the number of cables. This gives the area available for placing the cables.
Excess space available: This is difference between the total space required and the space available.
Free space % : It gives the percentage of free space that is available.
Number of trays proposed and their area:If the free space % is in negative then new tray size or a new number of trays is proposed. If the free space available is too large, the proposed tray number or size can be reduced.
Type : this specifies the type of the tray that is given. It can be perforated or ladder .
Ladder cable trays Perforated
Thus cable scheduling is a very important work when laying cables. This is done to avoid overcrowding of cables in any tray and to avoid increased free space.
“There is NO Substitute for Hard Work.”Thomas Edison (1847-1931);
Inventor, Businessman
THANKYOU
B. SINDHUJA
M.G.VISHALI