INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss

Transcript of INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta...

Page 1: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

INTERNATIONAL COMMERCIAL LAW

THE WORK ON A COMMON CONTRACT LAW

University of Oslo

Ass.Prof. Giuditta Cordero Moss

Page 2: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

A Common Contract Law?

• Globalisation, Regionalisation• Common regulation of sectors• Contract law not harmonised• Mechansims that permit cross-border contracts• Vision: a common contract law• EU action plan• Does vision solve the percieved problems?

Page 3: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Contract law is not harmonised -I

• Tender for construction in Italy

• Norwegian contractor makes a bid

• Bid based on local sub-contractors’ prices

• Contractor is awarded the contract

• Tender for construction in England

• Norwegian contractor makes a bid

• Bid based on local sub-contractors’ prices

• Contractor is awarded the contract

Page 4: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

The subcontractors’ offer

• ”This offer is binding on the offeror and cannot be revoked before 30 days have elapsed from the date hereof”

• Subcontractor revokes the offer before the term (but after the the contract was awarded)

Page 5: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Consequences

• Italian law:

– Firm offer cannot be revoked before the term

– Subcontractor is legally bound

• English law:

– Firm offer is not binding unless there is consideration

– Subcontractor is not bound

Page 6: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Contract law is not harmonised -II

• Norwegian producer purchases components from Italian supplier

• Force Majeure circumstance reduces supplier’s capacity

• Supplier has delivery obligations towards plurality of creditors

• At reduced capacity supplier can meet obligations towards only one creditor

• Norwegian producer purchases components from Italian supplier

• Force Majeure circumstance reduces supplier’s capacity

• Supplier has delivery obligations towards plurality of creditors

• At reduced capacity supplier can meet obligations towards only one creditor

Page 7: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Force majeure clause

• ”Non performance by a party hereto of its obligations hereunder is excused if such party was prevented from fulfilling its obligations by an event beyond such party’s control, that was not foreseeable and that could not be prevented or overcome by the prevented party using reasonable efforts.”

Page 8: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Consequences

• Italian law– Supplier’s obligations

are reduced pro rata with the capacity reduction

– Purchasers can demand delivery pro rata with the other creditors

• English law– ”Frustration kills the

contract”– Impossibility to deliver

is deemed to be a consequence of supplier’s own fact

– Purchasers can demand whole delivery

Page 9: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Mechanisms for cross-border contracts

• Conflict rules determine the law of what country governs

• Conflict rules are part of each country’s own law

• EU has harmonised conflict rules

• Norway has own conflict rules

Page 10: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Mechanisms for cross-border contracts, cont.

• Judge applies his own conflict rules

• First step: identify forum

• Then: apply conflict rule

• So: conflict rule determines what country’s substantive law governs the contract

Page 11: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Application of conflict rules

FIRM OFFER

• Forum: Lugano convention, art. 2 or 5.1

• Governing Law:– Italian subcontractor:

Italian law– English subcontractor:

English law

FORCE MAJEURE

• Forum: Lugano convention, art. 2 or 5.1

• Governing Law:– Italian supplier: Italian

law– English supplier:

English law

Page 12: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Vision: A common (European) contract law• Assumption:

– Plurality of systems is confusing– Conflict rules are complicated– Domestic legal system are meant for domestic

transactions

• Vision:– An international system deriving from the

parties’ own practice

Page 13: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

From lex mercatoria to general contract principles

• ”Principles rooted in the good sense and common practice of the generality of civilised nations”

• Contractual practice

• Model laws, conventions

• Standard contracts

• Private codifications

• Restatements

Page 14: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Restatements

• To improve lex mercatoria’s weaknesses:– Difficult to determine– Not systematic– Too vague

• 1994, UNIDROIT Principles of International Commercial Contracts– Not a codification of existing principles– Systematic set of principles based on consensus

among international academics

Page 16: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Commission’s Communication

• Communication from the Commission to the Council and the European Parliament on European Contract Law – COM (2001) 398 final, 11.7.2001

• Requests comments on four alternatives:– Leave it to market forces– Through research establish general European

principles– Improve coherence of existing European law– Enact a European code

Page 17: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

The answers to the Communication

• 181 answers• Each alternative has been supported and

criticised• Working groups established to develop each

alternative (especially 2 and 4)• In some academic circles focus on answer from:

– Commission on European Contract Law and Study Group on a European Civil Code (PECL)

Page 18: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

The Commission’s Action Plan

• A more coherent European contract law – An action plan – COM (2003) 68 final, 12.2.2003:– Continue sector-based approach– Increase coherence of existing European law

(CFR)– Support development of European standard

contracts (webpage)– Examine possibility of general measures,

such as “an optional instrument”

Page 19: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Action plan’s effect

• Common Frame of Reference for Acquis Comunitaire– Does not cover general contract law

• EU Standard contracts– Must be referred to– Do not solve interpretation problems

• Optional Instrument– Must be referred to– Does not help if vacuum– Does not totally exclude application of national law

Page 20: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

PECL and firm offer

• Italian Law:– Offer is binding until term

expires

• English law:– Offer is not binding until it

has been accepted (or there is a consideration)

• PECL, art. 2:202:– Offer is not binding until it

has been accepted, but cannot be revoked if it contains a term

• PECL, art. 1:103:– PECL can derogate from

mandatory rules, if governing law allows it

– PECL cannot derogate from internationally mandatory rules

– Consideration?

Page 21: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

PECL and Force Majeure

• Italian law:– Purchasers are

entitled to delivery pro rata with each other

• English law:– Purchasers are

entitled to whole delivery

• PECL, art. 8:108:– No specific regulation

• PECL, art. 1:106 (2):– If regulation lacks,

underlying principles shall be applied. If this is not possible, governing law shall be applied

Page 22: INTERNATIONAL COMMERCIAL LAW THE WORK ON A COMMON CONTRACT LAW University of Oslo Ass.Prof. Giuditta Cordero Moss.

Conclusion

• Comparative law as a tool towards unification?– Unification is not exhaustive– Even unified wording is interpreted in light of

interpreter’s own legal background

• Different legal systems will continue to survive long after unification (if any)