INTERNATIONAL CAPITAL CORPORATION CASE PRESENTATION
-
Upload
jyoti-punj-prakash -
Category
Business
-
view
1.242 -
download
1
description
Transcript of INTERNATIONAL CAPITAL CORPORATION CASE PRESENTATION
INTERNATIONAL CAPITAL CORPORATION
Presented By:Amit KumarVarsa Avtar
Rohitash GhaiDebasree Saha
Jyoti Punj PrakashSwapnil Nishant Minz
Prashant Kumar Sharma
0 A small investment banking0 Specializes in securing funds for small to medium
sized firms.0 Use a standardized project format for each
management0 Have a policy of passing their plan through a project
review committee of colleagues
ABOUT CASE
0 Programme Evaluation Review Techniques0 Critical Path Method
PROJECT TIME MANAGEMENT
0 Pert was developed by a consulting firm in 19580 Pert Uses Three time estimates for each activity0 Each activity duration can range from an optimistic
time to a pessimistic time0 Weighted average can be calculated for each activity0 Weightage average activity time = a + 4m + b 6
PROGRAMME EVALUATION REVIEW TECHNIQUES
Where, a = Optimisticm = Most Likely b = Pessimistic
0 Then we calculate the standard deviation for the activity which represents the standard deviation for the project.
0 This is also called variance0The equation below is used to compute the “ Z
(Number of standard deviation from the mean) ” 0 Z = Ts - Te √ (sum of variance)^2 [The sum includes only activities on the critical path(s) or path being reviewed]
Contd……
0 Developed in 1957 by Dupont Company, Remington Rand and Mauchy Associates in an industrial setting.
0Systematic approach0Greatest reduction in project duration0Least cost0CPM assumes that the time to perform any project
activity depends on the efforts or resources
CRITICAL PATH METHOD
0 Completion time for a project can be shortened by additional resources
0 Cost is dependent on time.0 Cost slope= Cc-Cn Tc-Tn
Using the formula the shortest possible completion time for the activity can be calculated.
Contd….
Where, Cc= Crash costsCn= Normal costsTc= Crash time Tn= Normal time
0 Probabilistic0Pert considers optimistic,
likely and pessimistic time for any task.
0 Based on probability0PERT is more suitable for
R & D related projects.
0 Deterministic0CPM takes only a single
time for any task.0 don’t consider probability0 CPM is best suited for
routine projetcs
DIFFERENCE BETWEEN CPM & PERT
Securing Funds
Project Planning
●Research Client Firm● Rough Draft● Coordinate needs proposal with Clients
Estimating Future
Demand & Cash Flow
Documentation
Create & Approve
Legal Documents
Print Final Documentati
on
Raising Fund
Create first draft
proposal
Line up sources of
capital
Sign Contract
Transfer funds
WORK BREAKDOWN STRUCTURE
Activity OPTIMISTICa
MOST LIKELY
m
PESSIMISTICb
Weightage average activity
time
(b-a/6)^2
A 4 7 10 7 1B 2 4 8 4 1C 2 5 8 5 1D 16 19 28 20 4E 6 9 24 11 9F 1 7 13 7 4G 4 10 28 12 16H 2 5 14 6 4I 5 8 17 9 4J 2 5 8 5 1K 17 29 45 30 22
0 A 7
0 Draft using templates
0 7 7
0 B 4
3 ResearchClientFirm
3 4 7
7 C 12
0 Due Diligance
7 5 12
38 J 43
0 Check, approve and print
38 5 43
30 I 39
4 Line up Sources
34 9 43
32 H 38
0 Integrate Draft
32 6 38
23 F 30
2 Draft Future Plan
25 7 32
12 G 24
8 Legal Document
20 12 32
12 E 23
2 Future Demand and cash flow
14 11 25
12 D 32
0 Need Proposal
12 20 32
43 K 73
0 Sign Contract
43 30 73
0Chance of average (70) with initial plan (73)0Z = (TS – TE) / Sq. root of sum of variance
0 Critical path is A,C,D,H,J,K0Z = (70 – 73) / Sq. root of 33 = -3 / 5.7 = -0.520 The probability is 31 percent.0 This does not meet the 95% criteria
Q.1 How does this project stack up with the average projects?
0Getting to the average of 70 days and increasing the chance of making it would require compressing the project.
0Z = (TS – TE) / Sq. root of sum of variance
0 1.7 = 70-Te Sqr. Root of 33 = 60.31 days0This would require compression down to 60 days from
the current plan of 73 days. 0Compressing to 60 days will improve the chance of
meeting the 95% confidence level but probably increase the risk.
Q.2 What would the average have to be to ensure a 95 % chance of completion the project
in 70 workdays?