Interaction Region Issues and Beam Delivery R&D Issues & IR Design Status R&D Plans T. Markiewicz...
-
Upload
douglas-owens -
Category
Documents
-
view
226 -
download
8
Transcript of Interaction Region Issues and Beam Delivery R&D Issues & IR Design Status R&D Plans T. Markiewicz...
Interaction Region Issues and Beam Delivery R&D
• Issues & IR Design Status• R&D Plans
T. Markiewicz
Klaisner Review
4/15/1999
Interaction Region Issues
Final Quadrupole Support & IR Layout
Effect of 10 mrad crossing angle and Detector Solenoid
Stabilizing the final quads against jitter @ the 1-5 nm level
Detector Backgrounds
IP Backgrounds
Machine Backgrounds
Topic SubTopic Speaker
CollimationMuon Spoiler System Lew Keller
IR TransportOverview & Energy Expandibility Peter TenenbaumTolerances & Tuning Peter Tenenbaum
Interaction Region
Crossing Angle and Solenoid Effects Peter TenenbaumBackground Calculations Takashi MaruyamaDetector Model Knut SkarpaasREC as Final Doublet IR Magnets Andy Ringwall
Extraction LinesExtraction Line Optics Yuri NosochkovExtraction Line Diagnostics Mike Woods
CollimationWakefield Tests Peter TenenbaumNovel Collimator Designs Joe FrischMaterial Survival Tests Joe Frisch
Small Spot Size IssuesVibration Stability Mike WoodsOther ideas for FD stability Joe Frisch
Design Issues
R&D
MagnetsBeam Line Magnets Andy RingwallMovers & Supports Andy RingwallIR Magnets Andy RingwallPower Supplies Andy RingwallCables Andy Ringwall
VacuumVacuum System Leif Eriksson
CollimatorsCollimators & Stoppers Eric Doyle
Beam Dump Dieter Walz
InstrumentationBeam Line Instrumentation Eric Doyle
RFCrab Cavity RF System Joe Frisch
Facility RequirementsBeam lines Knut SkarpaasIR Halls Knut Skarpaas
Engineering Status & Costs Sessions
Detailed Talks Pre-Prepared for this Committee
-0.4
-0.3
-0.2
-0.1
0
0.1
0.2
0.3
0.4
0 2 4 6 8 10 12
LCD Small Detector with L* =2m CD1 Optics
Plan View
M1
M2Q1 Q1-SC Q2
Q1-EXT
10 mrad
Support Tube
Lum
RF Shield-10 mrad
Tunnel Wall
Beam Pipe
0
1
2
3
4
5
6
0 0.5 1 1.5 2 2.5 3 3.5 4
Bz versus z, NLC IR Solenoid 1
Bz,
T
z, m
Bz, T
L*
Uniform Current Density Coil
Crossing Angle and Solenoid Field Issues
Crab Cavity (~6m from IP):– Relative phase stability 1/20 degree S-BAND required– Not a problem
Before the collision:– Beam deflected: 1.7 m , 34.4 rad – Dispersion: 3.1 m added to vertical spot size– Solutions:
• Clever optics:– Tune upstream FF and SCS skew-quad systems– Move Q1 2.6 m CCY sextupoles 1.4 m
• Flux excluder around Q1 NOT needed• ~800 G-m Dipole steering magnet between Q1 and the IP NOT needed
After the collision:– Steering: position (m) & angle (~rad) different from B=0 case– Solution:
• Only run with solenoid ON• Realign extraction line when necessary
Engineering
Final Doublet Magnet Technology Choice
Q1: Rare Earth Cobalt (REC: Sm2Co17 or Sm1Co5)•smaller mass works better with active vibration stabilization•no fluids•can it survive B|| (reduces max. pole tip field) and B (demagnetizes over time)?
•For small detector Bz(2m) < 3 T and Br(2m) < 500 G
Q1 SC for tune-ability: can we engineer this away?Q2A & Q2B iron (if it will fit)
Support details•Accommodation for
•piezo actuators•sensor systems
•lines of sight for interferometric sensors•space for inertial sensors
•fast feedback electrodes and kickers•beam monitoring and physics detectors
•Detector access•Vacuum flanges•Mask supports
Luminosity Monitor Detail
Background Simulation Status
“Engineered” LCD Small Detector in 6 Tesla w/ appropriate masks in GEANT3
Correct non-cylindrically symmetric geometry
Non-uniform magnetic field
Giant Dipole resonance and eN high energy neutron production
Extraction Line and Dump modeled as well
Machine Backgrounds
Synchrotron RadiationMuons ProductionDirect Beam Loss*
•Beam-Gas•Collimator edge re-scattering
Neutron back-shine from DumpExtraction Line Losses
IP Backgrounds
Disrupted primary beamBeamstrahlung photons
e+,e- pairs from beams. interactionsHadrons from beams. interactions
Radiative Bhabhas
Backgrounds
Machine Backgrounds
Synchrotron Radiation: 1996 results need updating
•Less serious than pair background
•Need to investigate SR from disrupted beam
Muons: 1996 result needs updating
•Four 9m long tunnel filling dipole steel dipole magnets per transport line
•100% beam can be dumped on a collimator and get < 1 muon in detector
Dump Neutrons: active effort; NOT dominant neutron source because of
•Concrete shielding around dump
•Concrete end-plug between detector door and pit wall
Beam Loss: need to begin this work
•1996 estimates showed zero re-scattered beam made it to Q1
>10 500 GeV hits on Q1 up-beam face needed before source became a detector problem
Extraction Line Beam Loss: active effort
•Recent redesign limits power lost to < 4 kW (x10 improvement)
•Need to add detectors
IP Backgrounds
Degraded e-,e+:
Energy acceptance of extraction line
Beamstrahlung photons: 1.5E10 per bunch @ <E>=30.3 GeV (0.83 Mw)
Use e+e- dump
Angular distribution set beam line length and minimum magnet apertures
e+e- pairs: 88000 per bunch @ <E>=10.5 GeV (1.7 W)
Dead cone and mask geometry
Direct hits in VXD: ~10% of secondary production
Secondary production of e+, e-, , neutrons:
VXD and tracking chamber backgrounds
VXD radiation damage lifetime
Hadrons with large pT (mini-jets)
Detector issue, will ignore here
e- e+
e- e+
e+
e-
Extraction Line Diagnostics
Standard Diagnostics: Facilitate transport to dump with minimal loss– BPMs, toroids, ion chambers
Detailed simulations needed to design Lum and Physics detectors
Luminosity Monitors:– Deflection scan BPMs
– Pair monitors
– Radiative Bhabha monitors
Physics Detectors: – Compton polarimeter
– Energy spectrometer
– Wire scanner (E)
– Colinearity detectors
– Small angle electron taggers
– Instrumented masks
– Beamstrahlung monitors
RF– Low and High power tests of crab cavity phase stability
Magnets – RECs
• Effects of external fields on various REC choice of materials• Prototypes, aging, thermal, and radiation effects
– SC Q1:• Design and testing
– Kickers and Septa: always a challengeVacuum: Cu is current choice (Al(out-gas rate) and Stainless(high R))
– Verify outgassing rates– Investigate transition materials and joining techniques for Cu and Al– Develop flanges– Prototype section of beamline
Beam Dumps:– Materials and cooling of window– Water flow patterns
Instrumentation:– Not enough thought here to begin to plan an R&D program
Engineering R&D
Collimator R&D•Accelerator Physics Design Investigations: to begin post - CD1
•Collimator wakefields experiments: work in progress
•Materials Damage
•Calculations
•Analytic: Preliminary calculations done
•ANSYS, EGS
•Beam Experiments
•Single Bunch @FFTB: Initial expt. done; beam size marginal; no damage observed on Cu
•Multi Bunch @ ESA: needs optics to make small spots
•Laser Experiments: understand single shot damage vs. many shot damage
•Collimator Design
•Rotating Solid design
•Cooling & Position accuracy in a high radiation UHV environment
•Bearings, motor, vacuum feedthroughs
•Rotating Solidifying Liquid Metal design
•Surface finish, Adherence, and Corrosion PLUS the above
Small Spot Size and Vibration Control
Achieve 1nm stability via• Site requirements: < 10 nm rms for > 1 Hz and < 200 m
• Compact detector ( to satisfy vibration req. passively)
• Allow for closed loop active feedback with piezo movers on quads (interferometer or inertial sensors)
• Fast intra-train feedback
Snowmass detector with optical anchor
• Interferometric Sensors: Optical anchor – 1 m interferometer + piezo system yields 1nm fringe stability– 10 m interferometer in place but unused– 100 kg quad simulator setup exists
• with piezo movers, capacitive displacement sensors and geophone sensors • Piezos position control with 1 nm resolution demonstrated• Stability measurements with feedback still to come
– Goal: IR mock-up once we know what to mock up
R&D Status on Small Spot Size and Vibration Control
•Inertial Sensors
•Initial discussions have re-opened
question of optimal strategy
•Conceptual designs for sensors presented
• Very fast IP feedback:– Use beam-beam deflection of head of bunch (or pilot bunch) to correct tail
• Goal: ~50 latency ns to correct following bunches of 263 ns long train– Currently only conceptual
• tools in hand to begin design• effort needed
• Tunnel support testing– Jitter requirements are also quite tight– Full prototype test required
R&D Status on Small Spot Size and Vibration Control