Integrated Storm Water Management (ISWM) Project in Cebu, Philippines By: Late Rene Burt Llanto, Edilberto L. Paradela and Juan Edgar C. Osorio 1 1Presented during the Regional Workshop on the Eco-Efficient Water Infrastructure towards Sustainable Urban Development and Green Economy in Asia and the Pacific” on Dec. 12-13, 2013 at the Millennium Hilton Hotel, Bangkok, Thailand. R. B. Llanto is formerly the Regional Director of DOST VII and the Project Manager of the UNESCAP ISWM Project in the Philippines. E. L. Paradela is currently the Officer-in-Charge, Office of the Regional Director. J.E. C. Osorio is the Project Engineer of the ISWM project as well as the head of the Fabrication Unit of DOST VII.

Transcript of Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water...

Page 1: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Integrated Storm Water Management (ISWM) Project in Cebu, Philippines

By: Late Rene Burt Llanto, Edilberto L. Paradela and Juan Edgar C. Osorio 1

1Presented during the Regional Workshop on the Eco-Efficient Water Infrastructure towards Sustainable Urban Development and Green Economy in Asia and the Pacific” on Dec. 12-13, 2013 at the Millennium Hilton Hotel, Bangkok, Thailand. R. B. Llanto is formerly the Regional Director of DOST VII and the Project Manager of the UNESCAP ISWM Project in the Philippines. E. L. Paradela is currently the Officer-in-Charge, Office of the Regional Director. J.E. C. Osorio is the Project Engineer of the ISWM project as well as the head of the Fabrication Unit of DOST VII.

Page 2: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

- Cooperation between Water Security Section of ESCAP and the Department of Science and Technology Region VII (DOST VII) to promote awareness and advocacy on eco-efficient water infrastructure development. The key other partners are KICT and EREDE.CO.,Ltd..

PHASE 1:

“INTEGRATED STORM WATER MANAGEMENT IN THE PHILIPPINES: DOST VII SYSTEM”

Objective of the Project

Strengthen the capacity of government officials in Region VII, Philippines to promote eco-efficiency of water infrastructure

Page 3: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Key Outputs of Project

• Establishment of a model on integrated storm water management system in DOST VII.

• Development of a replication strategy

• Improved capacity building through trainings and a workshop

Page 4: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Flowchart of the ISWM System in DOST VII, Cebu Philippines

Page 5: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Application of Integrated Rainwater, Stormwater & Wastewater Management System at the Green Schools for Climate Change in the Philippines

Korea Institute of Construction Technology

EREDE CO., LTD.

DOSTPHASE 2:

Page 6: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

- Cooperation between Environment and Development Division of ESCAP and the Department of Science and Technology Region VII (DOST VII) to promote awareness and advocacy on eco-efficient water infrastructure development. The key other partners are KICT and EREDE.CO.,Ltd..

The Project:

Page 7: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

•Develop a concept and a set of architectural designs for Green School development;•Pilot application of concept into selected two schools as pilot projects;•Strengthen planning and designing capacity of government officials in Region 7 of the Philippines on Green School;•Educate young generations for concept of Green Growth through implementation process of the project.

Objectives of the project:

Page 8: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

•Development of a conceptual architectural designs on Green School;•Construction of systems in two selected schools in Cebu;•Development of Policy Guidelines for development of Green School;•Enhanced capacity building including education of young generation.

Key Outputs:

Page 9: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Implementation

The project started in 2011 to December 2013.

Two project sites are selected: the Philippine Science High School – Argao Campus in Argao, Cebu (80 km south of Cebu City), and the Zapatera Elementary School in Cebu City. These were recently tested and commissioned

Development of designs for Philippine adapted green schools are prepared to convince education decision-makers to Introduce green growth in basic education. Archt. Cyril Abu completed the Green School concepts, designs and plans.

Policy guidelines were already prepared for submission. C/o EREDE Co. Ltd.

Several forums and symposia are conducted on ISWM.

Page 10: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

• Philippine Science High School in Argao, Cebu, Philippines

Project Site 1

Page 11: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Philippine Science High School – Argao Campus, Argao Cebu

Academic BuildingDormitory Building

Page 12: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Philippine Science High School – Argao Campus, Argao Cebu

Rainwater storage tank (left) and wastewater treatment tank (right).

Page 13: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Philippine Science High School – Argao Campus, Argao Cebu

Micro filtration System installed at the Machine Room

Page 14: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Diagram of ISWM at the Philippine Science High School – Argao Campus,

WATERING PLANTS

RING BLOWER

AIR

- WASH WATER

- LAVATORY

75TON R/W STORAGE TANK27TON R/W TREATED TANK

5T 5T

MICRO FILTRATIONSYSTEM, 20Tons/day capacity

SUCTION PUMP

OVERHEAD TANKS

SUCTION PUMP

MEMBRANE AERATION TANK

LEACHING WELLAERATION WELL

MEMBRANE UNIT

TO BUILDING TOILET

RAINWATER ( ROOF )

FIRST FLUSHING TREATMENT DEVICE( GREEN FILTER )

GREY WATER

Page 15: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Zapatera Elementary School Building currently under renovation to highlight a sample of green school and water museum.

Project Site 2

Page 16: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

• Rainwater Storage tank (below) in Zapatera Elementary School

Page 17: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

• Machine Room in Zapatera Elementary School

Page 18: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Diagram of ISWM at the Zapatera Elementary School – Cebu City

RAINWATER ( ROOF )

FIRST FLUSHING TREATMENT DEVICE( GREEN FILTER )

50 T R/W STORAGE TANK

10T R/W TREATED TANK

MICRO FILTRATIONSYSTEM, 10T/day

SUCTION PUMP

ROOF TOP

TREATED TANK

SUCTION PUMP

TO BUILDING TOILET

Page 19: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Major Components of the ISWM Facility

Rainwater Collection. Rainwater from roof and storm water from porous surface of roads.

Primary Rainwater Treatment (Green Filter). First flushing; initially removes contaminants/pollutants.

Micro-membrane Filtration System (MF System).Micro-membranes to reduce microbial and particulate pollutants.

Reuse Water Treatment System. Uses advance biological

treatment processes that eliminate organic and nitrogen compounds.

Page 20: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Rainwater Collection at Phil. Science High School

Rainwater from the roof of the two (2) dormitories - Total catchment area of 1,200 sq. meter (approx.)

Page 21: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Rainwater Collection at Zapatera Elem. School

Rainwater from the roof of the school building. - Total catchment area of 500 sq. meter (approx.)

Page 22: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Primary Filtration System (Green Filter)

Page 23: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

The Micro Filtration System

Page 24: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Wastewater treatment system

Page 25: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Advocacy Workshop held in DOST 7, Cebu City Sept. 27, 2013

Page 26: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Challenges

• Issues that affect the project implementation

- Procurement of the ISWM system components – Bidding process under Phil. Procurement Process is strictly followed.

- Importation led time – machine/equipment

- Working with partners and their counterpart as recipient of the project

- Dealing with local officials ( in the case of Zapatera Elem. School)

• Retrofitting concerns

- Existing buildings have single pipeline for potable water only.

• CO2 Emissions/Carbon Footprints

- Use of electric motors for pumping water

• Prone to disaster

- Earthquakes, strong typhoons, landslides, flooding, etc.

Page 27: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management
Page 28: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Follow Up actions

- Local Manufacturing of imported component parts or Local Raw Materials Substitute of imported component parts

- Avoid collaborations with political affiliations - Adherence to Phil. Building Code on 2 pipeline

system (potable and non-potable)- Possibilities of using renewable energy- Designs for disaster resilient buildings

Page 29: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Other Follow up Actions

> There is a need to develop a training manual on how to establish ISWM systems.

> More comprehensive benefit and cost analysis need to be conducted considering the economic aspect and the environmental effects, including carbon credits.

> Efforts should be exerted to encouraqe decision-makers to include ISWM in the construction of government infrastructure and in the building code.

> Incentives must be provided by government to those who use ISWM or similar technologies.

> Benchmarking with other countries is needed.

Page 30: Integrated Storm Water Management (ISWM) Project in … DOST_Paradela.pdf · Integrated Storm Water Management (ISWM) ... • Establishment of a model on integrated storm water management

Thank You

DOST VII Contact info:

Edilberto L. Paradela, OIC – Office of the Regional Director: ([email protected])Address: The Lahug S&T Complex, Sudlon, Lahug, Cebu City, Phils,Website: www.ro7.dost.gov.phTel./Fax No.: (63-32) 254-8269 or 418-9032 or +639198585050) 232-8632