Integrated Master Plan Development

140
The Integrated Master Plan And Integrated Master Schedule The Integrated Master Plan and Integrated Master Schedule are one of the six elements of a Credible Performance Measurement Baseline (PMB). The PMB is the source of data for the Program Manager. Some of this data is used in the Integrated Program Measurement Report (IPMR). Some is used in the assessment of the Program’s risk. Some define the deliverables and their Technical Performance Measures. 5 V8.7

description

Building the Integrated Master Plan (and its Integrated Master Schedule) is a critical success factor in any project domain. It describes the increasing maturity of all deliverables in units of measure meaningful to the decision makers. The IMP contains the Measures of Effectiveness and Measures of Performance. The IMS contains the Technical Performance Measures (as exit criteria for the Work Packages). Risk and estimates are applied at all levels of the IMP and IMS, then definitized in the Performance Measurement Baseline on contract

Transcript of Integrated Master Plan Development

Page 1: Integrated Master Plan Development

The  Integrated  Master  Plan  And  Integrated  Master  Schedule  

The  Integrated  Master  Plan  and  Integrated  Master  Schedule  are  one  of  the  six  elements  of  a  Credible  Performance  Measurement  Baseline  (PMB).  The  PMB  is  the  source  of  data  for  the  Program  Manager.  Some  of  this  data  is  used  in  the  Integrated  Program  Measurement  Report  (IPMR).  Some  is  used  in  the  assessment  of  the  Program’s  risk.  Some  define  the  deliverables  and  their  Technical  Performance  Measures.    

5

V8.7  

Page 2: Integrated Master Plan Development

The  IMP  tells  us  where  is  the  program  going?  

The  Plan  describes  where  we  are  going,  the  various  paths  we  can  take  to  reach  our  desLnaLon,  and  the  progress  or  performance  assessment  points  along  the  way  to  assure  we  are  on  the  right  path.  These  assessment  points  measures  the  “maturity”  of  the  product  or  service  against  the  planned  maturity.  This  is  the  only  real  measure  of  progress  –  not  the  passage  of  Lme  or  consumpLon  of  money.  

The  Integrated  Master  Plan  (IMP)  Is  A  Strategy  For  The  Successful  Comple=on  Of  The  Project  

2  

5.0  Start  with  the  IMP  

Page 3: Integrated Master Plan Development

3  

5.0  Start  with  the  IMP  

Page 4: Integrated Master Plan Development

Quick  View  to  IMP/IMS  

!  VerLcal  traceability  defines  the  increasing  maturity  of  key  deliverables  

!  Horizontal  traceability  defines  the  work  acLviLes  needed  to  produce  this  increasing  maturity  

!  Both  are  needed,  but  the  verLcal  traceability  is  the  starLng  point  

!  Program  Events,  Significant  Accomplishments,  and  Accomplishment  Criteria  must  be  defined  before  the  horizontal  work  acLviLes  can  be  idenLfied  

!  For  all  IMP  elements,  Key  Risks  must  be  idenLfied  and  assigned  from  Day  One,  even  without  miLgaLons  

4  

5.0  Start  with  the  IMP  

Page 5: Integrated Master Plan Development

The  IMP/IMS  is  Needed  on    Both  Sides  of  the  Contract  

!  Ver%cal  traceability  defines  the  increasing  maturity  of  the  program’s  deliverables  measures  in  EffecLveness  (MoE)  and  Performance  (MoP)  for  the  Government.  

!  Horizontal  traceability  defines  the  progress  to  plan  for  MoE’s  and  MoP’s  with  tangible  evidence  for  both  the  Government  and  the  Contractor.  

!  Ver%cal  traceability  provides  the  Government  with  insight  into  the  progress  of  the  MoE’s  and  MoP’s  and  Technical  Performance  Measures.  

!  Horizontal  traceability  provides  insight  into  Cost  and  Schedule  performance  for  the  Contractor,  reportable  through  the  IPMR  to  the  Government.  

5  

5.0  Start  with  the  IMP  

Page 6: Integrated Master Plan Development

MisconcepLons  of    the  IMP  /  IMS  

Why  we  don’t  need/want  an  IMP/IMS    !  Only  required  for  ACAT  I  programs  !  Too  big  and  burdensome  for  our  small  dollar  value  program  !  Contractor  spends  B&P  and  program  budget  generaLng  and  

maintaining  the  IMP,  without  measurable  benefit  !  Doesn’t  apply  on  a  services  contractors  !  Management  tool,  not  a  technical  tool  !  Doesn’t  apply  to  technology  programs  !  Doesn’t  apply  to  R&D  efforts  !  Doesn’t  apply  to  the  government  !  Help  me  get  a  waiver  so  I  don’t  have  to  use  an  IMP/IMS  

6  

5.0  Start  with  the  IMP  

Page 7: Integrated Master Plan Development

Aeributes  of  the  IMP  

!  Traceability  –  Expands  and  complies  with  the  SOO,  Performance  Requirements,  CWBS,  and  CSOW  

–  Based  on  the  customers  WBS  –  Is  the  basis  of  the  IMS,  cost  reports,  and  award  fees  

!  Implements  a  measurable  and  trackable  program  –  Accomplishes  integrated  product  development  –  Integrates  the  funcLonal  acLviLes  of  the  program  –  Incorporates  funcLonal,  lower  level  and  S/C  IMPs  

!  Provides  for  evaluaLon  of  Program  Maturity  –  Provides  insight  into  the  overall  effort  –  Level  of  detail  is  consistent  with  risk  and  complexity  per  §L  –  Decomposes  events  into  a  logical  series  of  accomplishments  –  Measurable  criteria  demonstrate  compleLon  /  quality  of  accomplishments  

7  

5.0  Start  with  the  IMP  

Page 8: Integrated Master Plan Development

Aeributes  of  the  IMS  

!  Integrated,  networked,  mulL-­‐layered  schedule  of  efforts  required  to  achieve  each  IMP  accomplishment  – Detailed  tasks  and  work  to  be  completed  –  Calendar  schedule  shows  work  compleLon  dates  – Network  schedule  shows  interrelaLonships  and  criLcal  path  

–  Expanded  granularity,  frequency,  and  depth  of  risk  areas  

!  Resource  loading  !  Correlates  IMS  work  with  IMP  events  

8  

5.0  Start  with  the  IMP  

Page 9: Integrated Master Plan Development

The  Importance  of  the  IMP  

!  The  IMP/IMS  is  the  single  most  important  document  to  a  program’s  success  –  It  clearly  demonstrates  the  providers  understanding  of  the  program  requirements  and  the  soundness  of  the  approach  a  represented  by  the  plan  

!  The  program  uses  the  IMP/IMS  to  provide:  –  Up  Front  Planning  and  commitment  from  all  parLcipants  –  A  balanced  design  discipline  with  risk  miLgaLon  acLviLes  –  Integrated  requirements  including  producLon  and  support  – Management  with  an  incremental  verificaLon  for  informed  program  decisions  

9  

5.0  Start  with  the  IMP  

Page 10: Integrated Master Plan Development

Just  A  Reminder,  before  moving  on  

10  

Page  47,  Defense  AcquisiLon  Guide,  January  10,  2012  

Page  317,  Defense  AcquisiLon  Guide,  January  10,  2012  

5.0  Start  with  the  IMP  

Page 11: Integrated Master Plan Development

Our  Goal  is  simple  …    

How  can  we  recognize  the  Reality  of  the  Program’s  current  status  and  its  future  performance?  

The  top  spins  conLnuous  while  in  a  dream  –  stops  spinning  in  the  real  world  –  Cobb’s  totem,  Incep=on  

5.0  Start  with  the  IMP  

11  

Page 12: Integrated Master Plan Development

12  

5.0  Start  with  the  IMP  

Page 13: Integrated Master Plan Development

Principles  of  Building  a  Credible  Integrated  Master  Plan  

Building  the  IMP  is  a  Systems  Engineering  acLvity.  The  Integrated  Master  Plan  is  the  Program  Architecture  in  the  same  way  the  hardware  and  sooware  are  the  Product  Architecture.  Poor,  weak,  or  unstructured  ProgrammaLc  Architecture  reduces  visibility  to  the  Product  Architecture’s  performance  measures  of  cost  and  schedule  connected  with  Technical  Performance  Measures.    

6

V8.7  

Page 14: Integrated Master Plan Development

Quick  View  of  Building  the  IMP  

!  Start  with  each  Program  Event  and  define  the  Significant  Accomplishments  their  entry  and  exit  criteria  to  assess  the  needed  maturity  of  the  key  deliverables  

!  Arrange  the  Significant  Accomplishments  in  the  proper  dependency  order    

!  Segregate  these  Significant  Accomplishments  into  swim  lanes  for  IPTs  

!  Define  the  dependencies  between  each  SA  14  

6.0  Build  IMP  

Page 15: Integrated Master Plan Development

A  CriLcal  Understanding  of  the  IMP  

The  IMP  defines  the  connecLons  between  the  Product  maturity  –  VerLcal  –  and  the  implementaLon  of  this  Product  maturity  through  the  FuncLonal  acLviLes  –  the  Horizontal    

6.0  Build  IMP  

15  

Page 16: Integrated Master Plan Development

Benefits  of  this  Formality  

16  

Objec%ve   Implementa%on  Event  Driven  Plan  versus  Schedule  Driven  Plan  is  based  on  compleLon  of  tasks  not  passage  of  Lme  

Separate  the  plan  (IMP)  from  the  schedule  (IMS)  but  link  elements  with  numbering  system  

Condensed,  easy  to  read  “Plan”  showing  the  “Events”  rather  than  the  work  effort   Indentured,  outline  format  –  not  text  

Pre-­‐defined  entry  and  exit  criteria  for  major  Program  Events  

Significant  Accomplishments  for  each  key  Program  Event  

ObjecLve  measures  of  progress  and  compleLon  for  each  Accomplishment  

Pre-­‐defined  Accomplishment  Criteria  (AC)  for  each  Significant  Accomplishment  (SA)  

Stable,  contracture  plan,  flexible  enough  to  portray  program  status  

IMP  part  of  the  contract,  IMS  is  a  data  item  

Capture  essence  of  the  funcLonal  progress  without  mandaLng  a  parLcular  process  for  performing  the  work  

Split  IMP  into  Product  and  Process  

6.0  Build  IMP  

Page 17: Integrated Master Plan Development

Risk  Management  

Building  the  IMP  Starts  at  the  RFP  with  Systems  Engineering  Measures  

17  

6.0  Build  IMP  

SOO  ConOps   SOW   Techncial  and  OperaLonal  

Requirements  

CWBS  &  CWBS  DicLonary  

Integrated  Master  Plan  (IMP)  

Integrated  Master  Schedule  (IMS)    

Earned  Value  Management  System  

ObjecLve  Status  and  EssenLal  Views  to  support  the  proacLve  management  processes  needed  to  keep  the  program  GREEN  

Performance  Measurement  Baseline  

Measures  of  EffecLveness  

Measures  of  Performance  

TPMs  and  QBDs  

JROC    Key  Performance  Parameters  

Program    Specific  Key  Performance  Parameters  

Technical  Performance  Measures  

WBS  CWBS  

Page 18: Integrated Master Plan Development

IMP  captures  end  user  requirements  in  terms  MOEs,  MOPs,  KPPs,  and  TPMs  

18  

SOW  ConOps  

WBS  CWBS  

Technical  Performance  Measures    (TPM)  

Messages  of  Performance  (MOP)  

Measures  of  EffecLveness  (MOE)  

Key  Performance  Parameters  

(KPP)  

Integrated  Master  Plan  (IMP)  

Integrated  Master  Schedule  (IMS)  

Performance  Measurement  Baseline  

(PMB)  

Technical  Requirements  

Page 19: Integrated Master Plan Development

The  IMP  /  IMS  Structure  

19  

IMS

IMP Describes how program capabilities will be delivered and how these capabilities will be recognized as ready for delivery

Supplemental Schedules (CAM Notebook)

Work Packages and Tasks

Criteria

Accomplishment

Events or

Milestones

6.0  Build  IMP  

Page 20: Integrated Master Plan Development

The  IMP/IMS  provides  Horizontal  and  VerLcal  Traceability  of    progress  to  plan  

!  VerLcal  traceability  AC  "  SA  "  PE  !  Horizontal  traceability  WP  "  WP  "  AC  

20  

Program Events Define the maturity of a Capability at a point in time.

Significant Accomplishments Represent requirements that enable Capabilities.

Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements.

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  package  

6.0  Build  IMP  

Page 21: Integrated Master Plan Development

The  IMP’s  role  during  ExecuLon  

21  

Program Execution PMB for IBR Proposal Submittal DRFP & RFP

Performance Measurement Baseline

Tasks (T)

BOE

% Complete

Statement of Work

Program Deliverables

IMP

Accomplishments (A)

Criteria (C)

EVMS

Events (E)

Budget Spreads by CA & WP CAIV

Capabilities Based Requirements

X BCWS =

Probabilistic Risk Analysis

=

Time keeping and ODC =

Technical Performance Measure

BCWP

ACWP

Cost & Schedule Risk Model

BCWS

Decreasing technical and programmatic risk using Risk Management Methods

IMS

Physical % Complete

Continuity and consistency from DRFP through Program Execution

WBS

6.0  Build  IMP  

Page 22: Integrated Master Plan Development

!  IMP  phrases  in  past  tense  –  do  describe  what  DONE  looks  like  

!  IMS  phrase  in  present  tense  –  do  describe  work  needed  to  arrive  at  DONE  

22  

The  Grammar  of  the  Integrated  Master  Plan  (IMP)  

Maturity   Product  AcLon   Product  State  

AdjecLve   Noun   Verb   Verb  Demonstrates  

Maturity  Step  in  the  Process  End  Item   Final  Status  

Preliminary   Model/Sim   Design   Complete  

Preliminary  Modeling  and  Simula%on  Design  Complete  

Page 23: Integrated Master Plan Development

1st,  Principle  –    IMP  Building  is  a  Full  Contact  Sport  

23  

6.0  Build  IMP  

Page 24: Integrated Master Plan Development

Our  First  Approach  to  the  IMP  /  IMS  Paradigm  

!  The  1st  approach  defines  Program  Events  (PE),  Significant  Accomplishments  (SA),  and  Accomplishment  Criteria  (AC),  derived  from  the  Work  Breakdown  Structure  or  the  SOW  

!  This  1st  approach  can  be  done  in  6  easy  steps  

24  

6.0  Build  IMP  

1.  IdenLfy  the  Program  Events  (PE)  (as  the  ACQ  Guide  tells  us)  

2.  IdenLfy  the  Significant  Accomplishments  (SA)  from  the  WBS  deliverables    

3.  IdenLfy  the  Accomplishment  Criteria  (AC)  needed  to  produce  these  deliverables  

4.  IdenLfy  the  Work  Packages  for  each  Accomplishment  Criteria  

5.  Sequence  the  Work  Packages  6.  Assemble  the  IMP/IMS  

Page 25: Integrated Master Plan Development

This  approach  doesn’t  give  us  visibility  into  what  “done”  looks  like  

!  We  must  measure  increasing  product  maturity  in  units  meaningful  to  the  decision  makers  

!  We  must  see  the  risks  before  they  arrive  so  we  can  take  correcLve  acLon  

6.0  Build  IMP  

25  

Page 26: Integrated Master Plan Development

First  Look  at  a  Significant  Accomplishment  (SA)  

!  SAs  are  interim  and  final  steps  to  define,  design,  develop,  verify,  produce,  and  deploy  the  product  or  system.    

!  SAs  must  occur  in  a  manner  that  ensures  a  logical  path  is  maintained  throughout  the  development  effort.    

!  SAs  are  event  related  and  not  just  Lme  coincidental.    !  SAs  should  have  one  or  more  of  the  following  characterisLcs:    

–  Consists  of  a  discrete  step  in  the  process  of  planned  development  that  must  be  complete  prior  to  an  event  

–  Produces  a  desired  result  at  a  specified  event  that  indicates  a  level  of  design  maturity  (or  progress)  directly  related  to  each  product  and  process  

–  Defines  interrelaLonships,  interdependencies,  or  “hand-­‐off”  points  of  different  funcLonal  disciplines  applied  to  the  program  

26  

6.0  Build  IMP  

SAs  must  assess  compliance  with  Measures  of  EffecLveness    

Page 27: Integrated Master Plan Development

First  look  at  an  Accomplishment  Criteria  (AC)  

!  ACs  are  definiLve  measures  directly  supporLng  successful  compleLon  of  a  significant  accomplishment.    

!  ACs  show  objecLve  evidence  of  work  progress  (maturity  of  a  product);  i.e.,  be  seen,  read,  demonstrated,  or  quanLfied.  These  results  are  usually  incorporated  into  a  report  or  document  as  evidence  of  accomplishment.    

!  ACs  are  prerequisites  for  compleLon  of  an  SA  (i.e.,  exit  criteria).    !  The  quesLons  that  need  to  be  repeatedly  asked  when  developing  

ACs  are:  –  How  do  I  know  when  an  accomplishment  has  been  completed?  –  Is  the  criteria  directly  related  to  the  accomplishment?    –  Is  it  proof?    –  What  is  the  work  product?”  

27  

6.0  Build  IMP  

ACs  must  assess  compliance  with  Measures  of  Performance  

Page 28: Integrated Master Plan Development

The  IMP  speaks  to  Measures  of  EffecLveness  (MoE)  and  Measures  of  Performance  (MoP)  

28  

6.0  Build  IMP  

!  This  is  where  TPMs    are  connected  with  the  MoE’s  and  MoP’s  

!  For  each  deliverable  from  the  program,  all  the  “measures”  must  be  defined  in  units  meaningful  to  the  decision  makers.  

! Here’s  some  “real”  examples.  

1.  Provide  Precision  Approach  for  a  200  FT/0.5  NM  DH  

2.  Provide  bearing  and  range  to  AC  plasorm  

3.  Provide  AC  surveillance  to  GRND  plasorm    

Measures  of  EffecLveness  (MoE)  

1. Net  Ready  2. Guidance  Quality  3.  Land  Interoperability  4. Manpower  5. Availability  

JROC  Key  Performance  Parameters  (KPP)  

1. Net  Ready  !  IPv4/6  compliance  ! 1Gb  Ethernet  

2. Guidance  quality  ! Accuracy  threshold  p70  @  6M  

!   Integrity  threshold  4M  @  10-­‐6  /approach  

3.  Land  interoperability  ! Processing  capability  meets  LB  growth  matrix  

4. Manpower  ! MTBC  >1000  hrs  ! MCM  <  2  hrs  

5. Availability  ! Clear  threshold  >99%  !  Jam  threshold  >90%  

Measures  of  Performance  (MoP)  

1. Net  Ready  ! Standard  message  packets  

2. Guidance  Quality  ! MulLpath  allocaLon  budget  ! MulLpath  bias  protecLon  

3.  Land  Interoperability  ! MOSA  compliant  ! Civil  compliant  

4. Manpower  ! OperaLng  elapsed  Lme  meters  

! Standby  elapsed  Lme  indicators  

5. Availability  ! Phase  center  variaLons    

Technical  Performance  Measures  (TPM)  

Mission  CapabiliLes  and  OperaLonal  Need  

Technical  Insight  –  Risk  adjusted  performance  to  plan    

Page 29: Integrated Master Plan Development

The  1st  Problem  with  the  IniLal  IMP/IMS  Paradigm  

!  There  is  no  single  source  of  guidance  for  construcLng  a  credible  IMP  and  IMS  – A  DOD  Guidebook,  but  sLll  in  Version  0.9  – A  few  DOD  service  pamphlets  – A  commercial  guidebook  – Many  contractor  guidelines  

!  No  definiLve  guidance  from  DoD  on  what  makes  a  good  IMP  

!  No  definiLve  DID  requiring  an  IMP  on  specific  programs  

29  

6.0  Build  IMP  

Page 30: Integrated Master Plan Development

The  IMP  is  a  good  start,  but  we’re  really  aoer  the  IMP  NarraLves  

!  The  IMP  NarraLves  start  with  the  Statement  of  ObjecLves  (SOO)  or  Concept  of  OperaLons  (ConOps)  – These  idenLfy  the  top  level  program  objecLves  – They  define  the  big  picture  and  provide  pre-­‐award  trade  space  

– They  provide  the  framework  for  the  Contractor  to  develop  the  proposal  through  the  IMP  

! With  the  Government’s  ExecuLve  summary,  provides  the  contractor  an  understanding  of  what  is  needed  and  what  is  important  

30  

6.0  Build  IMP  

Page 31: Integrated Master Plan Development

The  IMP  Process  NarraLve  

The  IMP  Process  NarraLve  describes  how  the  technical  and  business  elements  of  the  program  will  be  conducted,  monitored,  and  controlled.    NarraLves  provide  the  customer  visibility  into  the  contractor’s  key  funcLonal  processes  and  procedures,  the  relaLonship  of  these  processes  and  procedures,  and  an  overview  of  the  effort  required  to  implement  them.  

31  

6.0  Build  IMP  

Page 32: Integrated Master Plan Development

IMP  NarraLve  for  PDR  Program  Event   Event  Descrip%on   PE  Maturity  Assessment  

shown  in  SAs  

PDR   PDR  establishes  the  “design-­‐  to”  allocated  baseline  to  the  subsystem  level,  assures  this  design  meets  the  funcLonal  baseline,  assures  system  requirements  have  been  properly  allocated  to  the  proper  subsystem.  PDR  establishes  the  feasibility  of  the  design  approach  to  meet  the  technical  requirements  and  provide  acceptable  interface  relaLonships  between  the  hardware  and  other  interfacing  items.    Any  changes  to  the  requirements  that  have  occurred  since  the  System  Requirements  Review  (SRR2)  will  be  verified  at  the  PDR.    PDR  assures  the  design  is  verifiable,  does  not  pose  major  IMS  or  Cost  risk,  and  is  mature  enough  to  advance  to  the  detailed  design  phase  –  CDR  

!  Subsystem  level  operaLonal  concepts  defined  

!  System  level  interfaces  baselined  

!  Supportability  plans  established  

!  Sooware  requirements  finalized  

!  Subsystem  requirements  finalized  &  allocated  

!  System  verificaLon,  validaLon  &  cerLficaLon  plans  updated  

!  PDR  subsystem  design  completed  

32  

6.0  Build  IMP  

Page 33: Integrated Master Plan Development

What  the  IMP  NarraLve  Tells  Us?  

!  States  the  objecLve  of  the  processes  used  to  build  the  products  describe  in  the  SOW  

!  Provides  the  governing  documents,  compliance,  and  reference  for  the  process  acLviLes  

!  Explains  the  process  approach  –  Portrays  the  key  acLviLes  of  the  approach  –  Illustrates  the  processes  tailored  for  the  specific  program  

33  

Inputs  

AcLvity  3  

AcLvity  5  

AcLvity  4  

Tools  

AcLvity  1  

AcLvity  2  

Outputs  

Metrics  

6.0  Build  IMP  

Page 34: Integrated Master Plan Development

Some  IMP  Guidance    

34  

6.0  Build  IMP  

Page 35: Integrated Master Plan Development

The  Defense  AcquisiLon  Guide  (DAG)  Tells  Us  About  the  IMP  

35  

6.0  Build  IMP  

Page 36: Integrated Master Plan Development

The  DAG  Also  Tells  Us  

36  

6.0  Build  IMP  

Page 37: Integrated Master Plan Development

5000.01  Part  2.B.3  AcquisiLon  Strategies,  Exit  Criteria,  and  Risk  Management  

“Event  driven  acquisiLon  strategies  and  program  plans  must  be  based  on  rigorous,  objecLve  assessments  of  a  program’s  status  and  the  plans  for  managing  risk  during  the  next  phase  and  the  remainder  of  the  program.    The  acquisiLon  strategy  and  associated  contracLng  acLviLes  must  explicitly  link  milestone  decision  reviews  to  events  and  demonstrated  accomplishments  in  development,  tesLng,  and  iniLal  producLon.    The  acquisiLon  strategy  must  reflect  the  interrelaLonships  and  schedule  of  acquisiLon  phases  and  events  based  on  logical  sequence  of  demonstrated  accomplishments  not  on  fiscal  or  calendar  expediency.”  

37  

6.0  Build  IMP  

Page 38: Integrated Master Plan Development

What  makes  a  good    Program  Event  (PE)?  

!  Events  are  the  conclusion  of  an  interval  of  major  program  accomplishments  (SA)  with  their  criteria  (AC)    

!  IMP  events  represent  key  decision  transiLon  points  between  major  acLviLes  distributed  over  the  contract  period  –  The  IMP  is  a  Mini  Authoriza=on’s  to  Proceed  (ATP)  to  the  next  Program  Event  (PE)  

!  Some  guidance  for  establishing  program/product  events:  –  Customer  Given  Events.    –  Key  Decisions  Needed  –  Risk  MiLgaLon  Event  –  DOD  Systems  Engineering  Technology  Review  (SETR)  Guidance  

38  

6.0  Build  IMP  

Page 39: Integrated Master Plan Development

What  makes  a  good  Significant  Accomplishment  (SA)?  

!  IPT  can  manage  it  at  a  working  level  !  Shows  compleLon  and  result  s  of  discrete  steps  in  the  

development  process  !  Indicates  maturity  of  the  product  through  MoEs  and  MoPs  !  Its  “significance”  measures  program  event  status  !  Relevant  and  logically  linked  to  the  proper  PE  

–  Just  because  the  work  occurs  during  the  Lme-­‐frame  for  PE  A  doesn’t  mean  it’s  logically  linked  to  PE  A  

!  Uses  consistent  language,  style,  format  through  verb  dicLonary,  for  example:  –  Segment  build  4  detailed  design  completed  –  Analysis  of  structural  integrity  completed  –  Structural  integrity  verified  

39  

6.0  Build  IMP  

Page 40: Integrated Master Plan Development

IMP  Significant  Accomplishments  

!  SAs  are  NOT  just  a  list  of  “things”  to  do  before  the  Program  Event  (PE)  

!  They  are  sequenced  accomplishments,  each  of  which  leads  to  the  PE,  e.g.  CriLcal  Design  Review  (CDR),  each  increasing  the  maturity  of  the  deliverables    –  SA  #  1  =  CDR  meeLng  conducted  –  SA  #  2  =  CDR  acLon  item  work-­‐off  plan  established  –  SA  #  3  =  85%  drawings  completed  –  SA  #  4  =  CDR  CDRLs  delivered  –  SA  #  5  =  Development  environment  operaLonal  –  SA  #  6  =  CriLcal  methods  analyses  completed  –  SA  #  7  =  RVTM  approved  

40  

6.0  Build  IMP  

Page 41: Integrated Master Plan Development

What  makes  a  good  Accomplishment  Criteria  (AC)?  

!  Provides  objecLve,  measureable,  and  explicit  evidence  of  compleLon  and  closure  of  the  work  acLviLes  in  Work  Packages  that  saLsfies  the  Measure  of  Performance.  

!  Defines  condiLons  for  closing  the  Significant  Accomplishment  (SA).  

!  Answers  the  quesLon  how  do  we  know  when  a  Significant  Accomplishment  has  been  completed?  

41  

6.0  Build  IMP  

Page 42: Integrated Master Plan Development

!  Not  Significant  –  Too  small  to  significantly  contribute  to  successful  event  compleLon  –  Would  lead  to  trivial  tasks  (e.g.,  1  day  duraLon)  

!  Ambiguous  –  Read  can’t  tell  what  Done  looks  like  

!  Wrong  verb  –  Uses  a  verb  that’s  not  on  the  list  (DicLonary)  –  Uses  a  listed  verb  incorrectly  –  Doesn’t  have  a  verb  at  all  

!  Not  measurable  –  Can’t  tell  when  we’re  done  

!  Too  Many  SAs  or  ACs  –  Confuses  the  reader  and  confuses  the  execuLon  process  of  the  

program  –  Dilutes  the  MoE  and  MoP  –  Reduces  visibility  into  increasing  maturity  

42  

What  makes  a  Not  So  Good    SA  or  AC?  

6.0  Build  IMP  

Page 43: Integrated Master Plan Development

!  Program  Event  (PE)  – A  PE  assess  the  readiness  or  compleLon  as  a  measure  of  progress  

–  First  Flight  Complete  !  Significant  Accomplishment  (SA)  

–  The  desired  result(s)  prior  to  or  at  compleLon  of  an  event  demonstrate  the  level  of  the  program’s  progress  

–  Flight  Test  Readiness  Review  Complete  !  Accomplishment  Criteria  (AC)  

– DefiniLve  evidence  (measures  or  indicators)  that  verify  a  specific  accomplishment  has  been  completed  

–  SEEK  EAGLE  Flight  Clearance  Obtained  43  

F-­‐22  Example  6.0  Build  IMP  

Page 44: Integrated Master Plan Development

!  PE’s  are  easy,  they  are  in  the  SETR  and  Integrated  LogisLcs  Lifecycle  Management  System  

!  The  SA’s  can  be  defined  from  the  program’s  deliverables  –  these  may  not  be  obvious  but  can  be  discovered  with  a  Product  Development  Kaizen  process  (more  later)  

!  It’s  the  AC’s  that  are  hard  part  –  the  ACs  must  represent  the  exit  criteria  for  the  series  of  Work  Packages  that  do  the  work  to  produce  the  product  

44  

Now  comes  the  Hard  Part  6.0  Build  IMP  

Page 45: Integrated Master Plan Development

6  Steps  to  IMP  Development  

Let’s  start  to  build  the  IMP.    This  step-­‐by-­‐step  process  needs  to  be  followed  carefully.  The  IMP  is  constructed  one  Program  Event  at  a  Lme  –  Leo  to  Right  in  Lme.    To  do  otherwise  allows  confusion  and  disconnecLon  between  Program  Events  to  occur  and  dilutes  our  focus  on  defining  what  Done  looks  like  for  each  Program  Event.      

7

V8.7  

Page 46: Integrated Master Plan Development

46  

7.0  6  Steps  

Page 47: Integrated Master Plan Development

Quick  View  of  Step-­‐By-­‐Step  IMP  

IdenLfy  Program  Events  IdenLfy  Significant  Accomplishments  IdenLfy  Accomplishment  Criteria  IdenLfy  Work  Packages  needed  to  complete  the  Accomplishment  Criteria  Sequence  the  Work  Packages  (WP),  Planning  Packages  (PP),  Summary  Level  Planning  Packages  (SLPP)    in  a  logical  network.  Adjust  the  sequence  of  WPs,  PPs,  &  SLPPs  to  miLgate  major  risks.  

47  

7.0  6  Steps  

1

2

3

4

5

6

Page 48: Integrated Master Plan Development

IdenLfy  the  Program  Events  

Actors   Processes   Outcomes  

Systems  Engineer  

Define  the  process  flow  for  product  producLon  from  contract  award  to  end  of  contract  

!  Confirm  Program  Events  represent  the  logical  process  flow  for  program  maturity  

Program  Manager  Confirm  customer  is  willing  to  accept  the  process  flows  developed  by  the  IMP  

!  Engage  with  contracts  and  customer  for  PE  definiLon  

Project  Engineer  IdenLfy  interdependencies  between  program  event  work  streams  

!  IdenLfy  Value  Stream  components  at  the  PE  level  before  flowing  them  down  to  the  SA  level  

IMP/IMS  Architect  Capture  Program  Event  contents  for  each  IPT  or  work  stream  

!  Establish  foundaLon  for  a  structure  to  support  the  descripLon  of  the  increasing  mature  as  well  as  the  flow  to  needed  work.  

Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   48  

1

7.0  6  Steps  

Page 49: Integrated Master Plan Development

Outcomes  of  Step  

!  Confirm  the  end  to  end  descripLon  of  the  increasing  maturity  of  the  program’s  deliverables  

!  Establish  of  RFP  or  Contract  target  dates  for  each  Event.    

!  Socialize  the  language  of  speaking  in  “Events”  rather  than  Lme  and  efforts  

49  

1

7.0  6  Steps  

Page 50: Integrated Master Plan Development

Events  Define  the  Assessment    of  the  Program’s  Maturity  

50  

! Program  Events  are  maturity  assessment  points  in  the  program  

! They  define  what  levels  of  maturity  for  the  products  and  services  are  needed  before  proceeding  to  the  next  maturity  assessment  point  

! The  entry  criteria  for  each  Event  defines  the  units  of  measure  for  the  successful  compleLon  of  the  Event  

! The  example  below  is  typical  of  the  purpose  of  a  Program  Event  

The  Cri=cal  Design  Review  (CDR)  is  a  mul=-­‐disciplined  product  and  process  assessment  to  ensure  that  the  system  under  review  can  proceed  into  system  fabrica=on,  demonstra=on,  and  test,  and  can  meet  the  stated  performance  requirements  within  cost  (program  budget),  schedule  (program  schedule),  risk,  and  other  system  constraints.    

1

7.0  6  Steps  

Page 51: Integrated Master Plan Development

IdenLfy  the  Significant  Accomplishments  (SA)  for  Each  Program  Event  (PE)  

51  

Actors   Processes   Outcomes  

System  Engineer   IdenLfy  Integrated  Product  Teams  (IPT)  responsible  for  the  SA’s    

! Define  the  boundaries  of  these  programmaLc  interfaces  

! Define  technical  and  process  risk  categories  and  their  bounds  

Technical  Lead  Confirm  the  sequence  of  SA’s  has  the  proper  dependency  relaLonships  

! Define  the  product  development  flow  process  improves  maturity  

! Define  technical  risk  drivers  

Project  Engineer   Confirm  logic  of  SA’s  for  project  sequence  integrity  

! Define  the  program  flows  improves  maturity    

Control  Account  Manager  

Validate  SA  outcomes  in  support  of  PE  entry  condiLons  

!  Confirm  budget  and  resources  adequate  for  defined  work  effort  

IMP/IMS  Architect  

Assure  the  assessment  points  provide  a  logical  flow  of  maturity  at  the  proper  intervals  for  the  program  

! Maintain  the  integrity  of  the  IMP,  WBS,  and  IMS  

2

7.0  6  Steps  

Page 52: Integrated Master Plan Development

Outcomes  of  Step  

!  The  Significant  Accomplishments  are  the  “road  map”  to  the  increasing  maturity  of  the  program  

!  The  “Value  Stream  Map”  resulLng  from  the  flow  of  SA’s  describes  how  the  products  or  services  move  through  the  maturaLon  process  while  reducing  risk  

!  The  SA  map  is  the  path  to  “done”    

52  

2

7.0  6  Steps  

Page 53: Integrated Master Plan Development

SAs  define  the  entry  criteria  for  each  Program  Event  

53  Preliminary  Design  Review  Complete  

3

7.0  6  Steps  

Page 54: Integrated Master Plan Development

IdenLfy  Accomplishment  Criteria  (AC)  for  each  Significant  Accomplishment  (SA)  

Actors   Processes   Outcomes  

CAM  

Define  and  sequence  the  contents  of  each  Work  Package  and  select  the  EV  criteria  for  each  Task  needed  to  roll  up  the  BCWP  measurement  

!  Establish  ownership  for  the  content  of  each  Work  Package  and  the  Exit  Criteria  –  the  Accomplishment  Criteria  (AC)  

Project  Engineer  

IdenLfy  the  logical  process  flow  of  the  Work  Package  to  assure  the  least  effort,  maximum  value  and  lowest  risk  path  to  the  Program  Event  

!  Establish  ownership  for  the  process  flow  of  the  product  or  service  

Technical  Lead   Assure  all  technical  processes  are  covered  in  each  Work  Package  

!  Establish  ownership  for  the  technical  outcome  of  each  Work  Package  

IMP/IMS  Architect  

Confirm  the  process  flow  of  the  ACs  can  follow  the  DID  81650  structuring  and  Risk  Assessment  processes  

! Guide  the  development  of  outcomes  for  each  Work  Package  to  assure  increasing  maturity  of  the  program   54  

3

7.0  6  Steps  

Page 55: Integrated Master Plan Development

Outcomes  of  Step  

!  The  definiLon  of  “done”  emerges  in  the  form  of  deliverables  rather  than  measures  of  cost  and  passage  of  Lme.  

!  At  each  Program  Event,  the  increasing  maturity  of  the  deliverables  is  defined  through  the  Measures  of  EffecLveness  (MoE)  and  Measures  of  Performance  (MoP)  

55  

3

7.0  6  Steps  

Page 56: Integrated Master Plan Development

ACs  are  higher  fidelity  descripLons  of  “Done”  than  SAs  

56  Cri%cal  Design  Review  Complete  

4

7.0  6  Steps  

Page 57: Integrated Master Plan Development

IdenLfy  the  Work  for  Each  Accomplishment  Criteria  in  Work  Packages  

Actors   Processes   Outcomes  

Control  Account  Manager  

IdenLfy  or  confirm  the  work  acLviLes  in  the  Work  Package  represent  the  allocated  work  

! Define  bounded  work  effort  defined  “inside”  each  Work  Package  

Technical  Lead   Confirm  this  work  covers  the  SOW  and  CDRLs  

! Define  all  work  effort  for  100%  compleLon  of  deliverable  visible  in  a  single  locaLon  –  the  Work  Package  

!  Confirm  risk  drivers  and  duraLon  variances  

IMP/IMS  Architect   Assist  in  the  sequencing  the  work  efforts  in  a  logical  manner  

! Develop  foundaLon  of  the  maturity  flow  starLng  to  emerge  from  the  contents  of  the  Work  Packages  

Earned  Value  Analyst  

Assign  iniLal  BCWS  from  BOE  to  Work  Package  

!  ConfirmaLon  of  work  effort  against  BOEs  

! Define  EVT  for  measures  progress  to  plan   57  

4

7.0  6  Steps  

Page 58: Integrated Master Plan Development

Outcomes  of  Step  

!  The  work  idenLfied  that  produces  a  measurable  outcome.  

!  This  work  defined  in  each  Work  Package  !  The  Accomplishment  Criteria  (AC)  state  explicitly  what  “done”  looks  like  for  this  effort  

! With  “done”  stated,  measures  of  Performance  and  measures  of  EffecLveness  can  be  defined  

58  

4

7.0  6  Steps  

Page 59: Integrated Master Plan Development

Work  is  done  in  “packages”  that  produce  measureable  outcomes  

59  Launch  Readiness  Review  Complete  

5

7.0  6  Steps  

Page 60: Integrated Master Plan Development

Sequence  Work  Packages  (ACs)  for  each  Significant  Accomplishment  (SA)  

60  

Actors   Processes   Outcomes  

Control  Account  Manager  

Define  the  order  of  the  Work  Packages  needed  to  meet  the  Significant  Accomplishments  for  each  Program  Event  

! Define  the  process  flow  of  work  and  the  resulLng  accomplishments.  

! Assure  value  is  being  produced  at  each  SA  and  the  AC’s  that  drive  them  

IMP/IMS  Architect  

Assure  that  the  sequence  of  Work  Packages  adheres  to  the  guidance  provided  by  DCMA  and  the  EVMS  System  descripLon  

!  Begin  the  structuring  of  the  IMS  for  compliance  and  loading  into  the  cost  system  

Program  Controls  Staff  

Baseline  the  sequence  of  Work  Packages  using  Earned  Value  Techniques  (EVT)  with  measures  of  Physical  Percent  Complete  

! Develop  insight  to  progress  to  plan  with  measures  of  physical  progress  for  each  Work  Packages  (EVT)  

5

7.0  6  Steps  

Page 61: Integrated Master Plan Development

Outcomes  of  Step  

! Work  Packages  parLLon  work  efforts  into  “bounded”  scope  

!  Interdependencies  constrained  to  Work  Package  boundaries  prevents  “spaghe{  code”  style  schedule  flow  

!  Visibility  of  the  Increasing  Flow  of  Maturity  starLng  to  emerge  from  the  flow  of  Accomplishment  Criteria  (AC)  

61  

5

7.0  6  Steps  

Page 62: Integrated Master Plan Development

Sequence  Work  Packages  (AC’s)  into  an  IMS  for  each  Program  Event  

62  

6

7.0  6  Steps  

Page 63: Integrated Master Plan Development

Assemble  Final  IMP/IMS  Actors   Processes   Outcomes  

IMP/IMS  Architect  

StarLng  with  the  AC’s  under  each  SA’s  connect  Work  Packages  in  the  proper  order  for  each  Program  Event  

!  Establish  the  Performance  Measurement  Baseline  framework.  

!  IdenLfy  MoE  and  MoP  points  in  the  IMP  

Program  Manager  Confirm  the  work  efforts  represent  the  commieed  acLviLes  for  the  contract  

!  Review  and  approval  of  the  IMS  –  ready  for  baseline.  

!  Review  and  approve  risk  drivers  and  duraLon  variance  models  

Project  Engineer   Assess  the  product  development  flow  for  opLmizaLons  

!  Review  and  approval  of  the  IMS  –  ready  for  baseline.  

!  IdenLfy  risk  drivers  and  their  miLgaLons  

Systems  Engineer  Confirm  the  work  process  flows  result  in  the  proper  products  being  built  in  the  right  order  

!  Confirm  risk  drivers  and  duraLon  variances.  

!  Review  and  approval  of  the  IMS  –  ready  for  baseline   63  

6

7.0  6  Steps  

Page 64: Integrated Master Plan Development

Outcomes  of  Step  

!  Both  the  maturity  assessment  criteria  and  the  work  needed  to  reach  that  level  of  maturity  are  described  in  a  single  locaLon  

!  Risks  are  integrated  with  the  IMP  and  IMS  at  their  appropriate  levels  –  Risks  to  EffecLveness  –  risk  to  JROC  KPPs  –  Risks  to  Performance  –  risk  to  program  KPPs  and  TPMs  

!  Leading  and  Lagging  indicator  data  provide  through  each  measure  to  forecast  future  performance  

  64  

6

7.0  6  Steps  

Page 65: Integrated Master Plan Development

The  Previous  6  Steps  Result  In  A  Credible  IMP/IMS  

65  

!  The  IMP  is  the  “Outer  Mold  Line”,  the  Framework,  the  “Going  Forward”  Strategy  for  the  Program.  

!  The  IMP  describes  the  path  to  increasing  maturity  and  the  Events  measuring  that  maturity.  

!  The  IMP  tells  us  “How”  the  program  will  flow  with  the  least  risk,  the  maximum  value,  and  the  clearest  visibility  to  progress.  

!  The  IMS  tells  us  what  work  is  needed  to  produce  the  product  or  service  at  the  Work  Package  level.  

Our  Plan  Tells  Us  “How”  We  are  Going  to  Proceed  The  Schedule  Tells  Us  

“What”  Work  is  Needed  to  Proceed  

7.0  6  Steps  

Page 66: Integrated Master Plan Development

Significant  Accomplishments  for  an  actual  Program  Event  Flight  Test  Ascent  Aerodynamics  Confirmed  

66  

7.0  6  Steps  

Page 67: Integrated Master Plan Development

Horizontal  and  VerLcal  Traceability  of  the  IMP/IMS  

Integrated  Master  Schedule  Work  sequenced  to  produce  outcomes  

for  each  WP.  

!  VerLcal  traceability  AC  "  SA  "  PE  !  Horizontal  traceability  WP  "  WP  "AC  

Program Events Define the maturity of a Capability at a point in time.

Significant Accomplishments Represent requirements that enable Capabilities.

Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements.

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  package  

Work  Package  

Work  Package  

67  

7.0  6  Steps  

Page 68: Integrated Master Plan Development

The  IMP’s  connecLon  to  the  WBS  !  Start  with  the  Significant  Accomplishments  and  sequence  

them  to  the  maturity  flow  for  each  Program  Event  !  The  WBS  connecLons  then  become  orthogonal  to  this  flow  

68  

7.0  6  Steps  

Program  Event  

SRR   SDR   PDR   CDR   TRR   ATLO  Work  Breakdown  Structure  

4.920-­‐SDAI   A01,  A02   B01   C01,  C02   D01   E01   F01  

4.200-­‐Sys  Test   A05   B03,  B04   D02,  D03   E02   F02  

4.300-­‐Radar   A03   B02   C03   E03  

4.330-­‐O&C  Sys   A06,  A07   B05   C04   D04   E04   F03,  F04  

4.400-­‐  I&T   A08   C05   E05,  E06   F05  

4.500-­‐Support   A09   D05   E07   F06,  F07  

Page 69: Integrated Master Plan Development

69  

7.0  6  Steps  

Page 70: Integrated Master Plan Development

70  

7.0  6  Steps  

Page 71: Integrated Master Plan Development

71  

7.0  6  Steps  

Page 72: Integrated Master Plan Development

72  

7.0  6  Steps  

Page 73: Integrated Master Plan Development

73  

7.0  6  Steps  

Page 74: Integrated Master Plan Development

74  

7.0  6  Steps  

Page 75: Integrated Master Plan Development

Nuances  Of  These  6  Steps  

Building  the  Program  Event,  to  Significant  Accomplishment,  to  Accomplishment  decomposiLon  is  straight  forward.  For  each  Program  Event,  simply  idenLfy  what  are  the  needed  Significant  Accomplishment  for  the  entry  and  exit  criteria,  and  the  Accomplishment  Criteria  for  the  Work  Packages  that  produce  the  AC.  

Yea  Right,  no  problem  

8

V8.7  

Page 76: Integrated Master Plan Development

76  

8.0  Nuances  

Page 77: Integrated Master Plan Development

Quick  View  of  the  Nuances  

!  Unfortunately  building  a  credible  IMP/IMS  is  a  nuanced  process,  subject  to  many  opportuniLes  for  diversions,  blind  alleys,  and  false  starts    

!  It  is  slightly  counter  intuiLve  from  the  tradiLonal  scheduling  approach  to  start  with  the  verLcal  integraLon  –  but  it  is  criLcal  to  start  verLcally  

!  Success  requires  the  full  parLcipaLon  of  Systems  Engineering,  CAMs,  and  the  Program  Manager  

!  Success  requires  everyone  to  understand  the  nuances  of  the  IMP  building  efforts  

77  

8.0  Nuances  

Page 78: Integrated Master Plan Development

The  1st  Nuance  We  need  to  change  the  Planning  Paradigm  

Beginner     Intermediate   Advanced  

! Take  the  program  events  and  use  the  WBS  to  define  the  SAs  and  ACs.  

!  IdenLfy  the  tasks  to  produce  the  ACs  and  SAs  

! Collect  them  into  Program  Events  

! Organize  the  tasks  by  Work  Package  

! Sequence  the  work  packages  (AC’s)    

! Examine  the  exit  criteria  for  the  Program  Events  –  what  does  Done  look  like?  

! Ask  what  the  entry  criteria  are  for  each  Program  Event  

! Build  the  AC’s  to  support  these  entry  criteria  

! Pull  these  together  under  each  SA  

! Determine  the  Technical  and  ProgrammaLc  maturity  for  each  Program  Event  from  the  Concept  of  OperaLons  

! Assess  the  SA’s  for  each  Integrated  Product  Team  in  terms  of  their  streams  maturity  at  that  point  in  the  program  

! Sequence  the  SA’s  for  each  PE  and  assess  the  units  of  measure  of  “maturity”  

! Build  the  AC’s  to  support  each  SA’s  level  of  maturity  

Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   78  

8.0  Nuances  

Page 79: Integrated Master Plan Development

The  2nd  Nuance  We  need  to  speak  about  Increasing  Maturity  

Beginner   Intermediate   Advanced  

! The  sequence  of  work  closely  matches  the  horizontal  schedules  of  the  past  

! Align  this  work  with  the  WBS  elements  

! Focus  on  the  WBS  DicLonary  of  the  delivered  products  or  services  

! No  explicit  TPM,  MOE,  and  MOP  elements  

 

! The  sequence  of  work  is  related  to  the  Program  Events,  but  essenLally  “hangs”  from  the  PE  to  the  SA’s  and  then  the  AC’s  

! All  deliverables  are  visible  but  their  TPMs  and  other  system  measures  are  not  stated  in  the  IMP  or  its  narraLve.  

! There  is  a  narraLve  in  the  form  of  SA’s  and  AC’s  that  describes  how  the  program  moves  from  leo  to  right  alone  its  maturity  path  

! Risk  buy  down  and  reLrement  are  visible  

!  Intermediate  Technical  Performance  Measures,  Measures  of  EffecLveness,  and  Measures  of  Performance  are  visible  in  the  IMP  

Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   79  

8.0  Nuances  

Page 80: Integrated Master Plan Development

The  3rd  Nuance  Everything  Foot  and  Ties  to  the  IMP  &  IMS  

Beginner   Intermediate   Advanced  

! The  IMS  contains  all  the  proper  fields  in  columns  and  is  horizontally  linked  

! The  WBS  elements  can  be  found  for  all  work  elements  

! CDRL’s  are  visible  and  their  mulLple  delivery  dates  connected  to  each  Program  Event  

! WBS  is  structured  in  a  product  manner  or  possibly  a  funcLonal  manner  with  some  deliverables  defined  in  the  terminal  nodes  

! The  WBS  is  properly  formed  inside  each  AC  with  incremental  deliverables  

! WBS  numbers  form  a  “well  structured”  tree,  but  sLll  is  not  “pure”  in  the  sense  of  deliverables  only,  no  funcLonal  

! Each  column  and  each  field  can  be  “pivoted”  to  form  a  proper  “tree”  of  value  flow.  

! The  WBS  is  a  “pure”  Product  Breakdown  Structure  (PBS)  and  the  services  needed  to  produce  those  products  

! The  WBS  defines  the  structure  of  the  delivered  product  or  service  

! The  VerLcal  trace  of  the  IPM  describes  the  flow  of  increasing  maturity  of  these  products  or  services  

! The  Horizontal  trace  of  the  IMP  describes  to  work  to  be  done  to  produce  this  maturity   80  

8.0  Nuances  

Page 81: Integrated Master Plan Development

The  4th  Nuance  IMP/IMS  is  ProgrammaLc  Architecture  

Beginner   Intermediate   Advanced  

! The  IMP  is  built  from  the  WBS  for  each  Program  Event.  

! The  IMP  is  seen  as  a  compliance  document  that  lists  the  Program  Events  and  a  “bunch  of  stuff”  underneath.    

! The  IMP  is  structured  around  separate  Program  Events,  but  below  the  SA’s  looks  like  a  “shop  floor”  schedule  with  liele  verLcal  connecLvity.  

! The  IMP  is  built  as  a  “value  stream”  flow  for  the  program  but  the  Systems  Engineers  

! This  programmaLc  architecture  is  built  in  the  same  way  the  technical  system  architecture  is  built  

!  It  is  derived  from  the  ConOps  and  Tier  1  System  Requirements  

! The  IMP  shows  explicitly  how  these  are  supported  in  the  flow  of  the  SA’s  

81  

8.0  Nuances  

Page 82: Integrated Master Plan Development

The  5th  Nuance  The  IMP/IMS  connects  all  the  dots  

82  

8.0  Nuances  

Measure  of  EffecLveness  

Measure  of  Performance  

Technical  Performance  Measure  

Risk  

Aleatory  Uncertainty  

Epistemic  Uncertainty  

Reference  Classes  

Past  Performance  

SME  

Past  Performance  

System  Architecture  

AHP  

Page 83: Integrated Master Plan Development

ConnecLng  The  IMP  To  Program  Performance  Measures  

Assembling  the  IMS  from  the  IMP  appears  to  be  a  straight  forward  process  –  details  the  tasks  that  support  the  Accomplishment  Criteria.  But  there  are  some  criLcal  steps  that  must  be  done  in  the  right  order  to  end  up  with  a  risk  tolerant  IMS.  

Let’s  do  this  for  Our  Program  

9

V8.7  

Page 84: Integrated Master Plan Development

The  Primary  Role  for  the  IMP  is  to  describe  what  done  looks  like  in  MoE’s  and  MoP’s  

84  19  October  1899  Robert  Goddard  decided  that  he  wanted  to  "fly  without  wings"  to  Moon.  

9.0  Framework  

Page 85: Integrated Master Plan Development

Quick  View  to  IMP/IMS  Framework  

! Measures  of  increasing  maturity  for  the  key  deliverables  is  the  foundaLon  for  increasing  the  Probability  of  Program  Success  

! Measures  of  EffecLveness  (MoE)  and  Measures  of  Performance  (MoP)  are  defined  in  the  Integrated  Master  Plan  (IMP)  NarraLve  

!  Key  Performance  Parameters  (KPP)  –  both  JROC  and  program  specific  are  needed  

!  Technical  Performance  Measures  (TPM)  are  needed  for  all  key  deliverables  

85  

9.0  Framework  

Page 86: Integrated Master Plan Development

Components  we’ll  meet  along  the  way  to  our  desLnaLon  to  the  credible  PMB  

86  86  

ObjecLve  Status  and  EssenLal  Views  to  support  the  proacLve  management  processes  needed  to  keep  the  program  GREEN  

Risk  Management  

SOW  SOO  

ConOps  WBS   Techncial  and  OperaLonal  

Requirements  

CWBS  &  CWBS  DicLonary  

Integrated  Master  Plan  (IMP)  

Integrated  Master  Schedule  (IMS)    

Measures  of  EffecLveness  

Measures  of  Performance  

Measures  of  Progress  

JROC    Key  Performance  Parameters  

Program    Specific  Key  Performance  Parameters  

Technical  Performance  Measures  

Earned  Value  Management  System  

TPMs  Live  Here  

Performance  Measurement  Baseline  

86

9.0  Framework  

Page 87: Integrated Master Plan Development

Components  of  our  Final  DesLnaLon  

87  

Sow  SOO  

ConOps  WBS   Techncial  and  OperaLonal  

Requirements  

Performance  Measurement  Baseline  

CWBS  &  CWBS  DicLonary  

Integrated  Master  Plan  (IMP)  

Integrated  Master  Schedule  (IMS)    

Earned  Value  Management  System  

Technical Performance Measurement (TPM) involves the predicting the future values of a key technical performance parameter of the higher-level end product under development, based on current assessments of products lower in the system structure. Continuous verification of actual versus anticipated achievement for selected technical parameters confirms progress and identifies variances that might jeopardize meeting a higher-level end product requirement. Assessed values falling outside established tolerances indicate the need for management attention and corrective action.

A well thought out TPM program provides early warning of technical problems, supports assessments of the extent to which operational requirements will be met, and assesses the impacts of proposed changes made to lower-level elements in the system hierarchy on system performance.

Techncial  Performance  Measurement  

heps://dap.dau.mil/acquipedia/Pages/Default.aspx   87

9.0  Framework  

Page 88: Integrated Master Plan Development

IdenLfying  the  TPMs  starts  with  good  Systems  Engineering  

88  

9.0  Framework  

Page 89: Integrated Master Plan Development

!  EIA-­‐632  –  involves  a  technique  of  predicLng  the  future  value  of  a  key  technical  performance  parameter  of  the  higher-­‐level  end  product  under  development,  based  on  current  assessments  of  products  lower  in  the  system  structure.    

!  INCOSE  Systems  Engineering  Handbook.  InternaLonal  Council  on  Systems  Engineering  

!  INCOSE  Metrics  Guidebook  for  Integrated  System  and  Product  Development  

89  

Policy  Guidance  for  TPMs  9.0  Framework  

Page 90: Integrated Master Plan Development

The  NDIA  EVM  Intent  Guide  Says  

90  

Notice the inclusion of Technical along with Cost and Schedule

That’s the next step is generating Value from Earned Value EV MUST include the Technical Performance Measures

9.0  Framework  

Page 91: Integrated Master Plan Development

Some  More  Guidance  

91  

Systems  engineering  uses  technical  performance  measurements  to  balance  cost,  schedule,  and  performance  throughout  the  life  cycle.  Technical  performance  measurements  compare  actual  versus  planned  technical  development  and  design.  They  also  report  the  degree  to  which  system  requirements  are  met  in  terms  of  performance,  cost,  schedule,  and  progress  in  implemenLng  risk  handling.  Performance  metrics  are  traceable  to  user–defined  capabiliLes.  ―  Defense  Acquisi=on  Guide  (heps://dag.dau.mil/Pages/

Default.aspx)  

In The End ― It’s All About Systems Engineering

9.0  Framework  

Page 92: Integrated Master Plan Development

More  Guidance  Can  Be  Found  in  …  

92  

9.0  Framework  

Page 93: Integrated Master Plan Development

This  Has  All  Been  Said  Before.    We  Just  Weren’t  Listening…  

93  

… the basic tenets of the process are the need for seamless management tools, that support an integrated approach … and “proactive identification and management of risk” for critical cost, schedule, and technical performance parameters. ― Secretary of Defense, Perry memo, May 1995

Why Is This Hard To Understand? ! We seem to be focused on EV reporting, not the use of

EV to manage the program. ! Getting the CPR out the door is the end of Program

Planning and Control’s efforts, not the beginning.

TPM Handbook 1984

9.0  Framework  

Page 94: Integrated Master Plan Development

A  Final  Reminder  …  

94  

TPMs are one source of Risk Management processes

Risk  Management  Guide  to  DOD  Acquisi=on,  Sixth  EdiLon  (Version  1,0),  Aug  2006  

9.0  Framework  

Page 95: Integrated Master Plan Development

StarLng  out  on  the  Right  Foot  …  

!  Most  IMP/IMS  literature  states  how  to  build  an  IMP  from  the  RFP  and  contractual  elements,  in  simple  and  maybe  simple  minded  terms  –  Decompose  the  events  into  SAs,  ACs,  and  their  Tasks  –  sounds  easy  

!  This  approach  fails  to  provide  advice  for  several  things:  –  How  to  minimize  the  topological  connecLons  between  Events  –  How  to  increase  the  concurrency  between  IPTs  –  How  to  increase  the  tolerance  of  the  IMS  to  disrupLve  events  

•  Known  and  knowable  risk  •  Unknown  and  possibly  unknowable  risk  

!  The  construcLon  of  the  IMS  needs  to  take  place  in  what  seems  to  be  a  reverse  order  –  Build  the  IMP  as  a  Value  Stream  Map  describing  the  increasing  maturity  –  and  

therefore  the  increasing  VALUE  of  the  deliverables  to  the  customer.  –  It’s  the  delivery  of  Customer  Value  that  inverts  the  management  process,  and  

focuses  on  Keeping  the  Program  GREEN  as  planned  that  maximizes  value  to  the  customer  (the  Government)    

95  

9.0  Framework  

Page 96: Integrated Master Plan Development

SETR  Program  Events  

96  heps://acc.dau.mil/docs/technicalreviews/dod_tech_reviews.htm  

9.0  Framework  

Page 97: Integrated Master Plan Development

Build  PEs  Leo  to  Right  Start  with  SRR  (or  something  on  the  leW)  and  completely  define  its  comple=on,  before  moving  to  the  next  PE  

!  Define  the  SAs  for  an  Event  and  construct  a  work  flow  of  the  acLviLes  needed  to  saLsfy  the  SA  –  These  acLviLes  are  yet  tasks,  so  don’t  commit  too  soon  to  defining  the  detailed  work  

–  Isolate  the  SAs  by  event  first  –  only  work  on  one  event  at  a  Lme  

!  IdenLfy  the  parLcipants  in  the  work  – What  IPTs  parLcipate  in  this  work?  – What  swim  lanes  are  needed  to  isolate  the  IPTs?  

!  Define  the  elements    –  AcLviLes  performed  to  saLsfy  the  SA  –  Deliverables  that  result  from  these  acLviLes  

!  There  are  sLll  not  Accomplishment  Criteria  (AC),  but  that  comes  next  

97  

9.0  Framework  

Page 98: Integrated Master Plan Development

The  Accomplishment  Criteria  (AC)  

!  A  definiLve  measure  or  indicator  that  verifies  compleLon  of  work  for  the  accomplishment  – Completed  work  effort    

•  Manufacturing  Plan  Completed  – ConfirmaLon  of  performance  compliance    

•  Flight  Test  Report  Approved  –  Incremental  verificaLon    

•  Maintenance  DemonstraLon  Completed  – Completed  criLcal  process  acLviLes  

•  Risk  Management  Plan  Approved  

98  

9.0  Framework  

Page 99: Integrated Master Plan Development

The  Accomplishment  Criteria  (AC)  

!  Defines  the  measure  by  which  an  Accomplishment  (SA)  is  considered  “done”  

!  Terms  like  complete,  delivered,  closed  have  no  “units  of  measure”  in  the  context  of  a  Significant  Accomplishment  (SA)  and  are  open  to  interpretaLon  

!  Terms  like  …  –  Measures  of  compleLon  –  80%  of  drawings  approved  for  release  –  Counts  of  available  items  –  75%  of  pin-­‐outs  assigned  voltage  –  Fidelity  of  a  design  –  outer  mold  line  defined  within  90%  of  target  

–  Error  bounds  –  spacecraW  mass  known  to  ±20%  –  Performance  parameters  –  disconnect  force  within  allowed  limits  

–  Maturity  parameters  –  flight  ar=cle  successful  in  last  3  tests  …  are  used  to  define  the  “exit  criteria”  

99  

9.0  Framework  

Page 100: Integrated Master Plan Development

2  Types  of  Accomplishment    Criteria:  Entry  and  Exit  

!  Entry  Criteria  –  SubstanLates  readiness  for  the  review  

!  Exit  Criteria  –  SubstanLates  successful  compleLon  of  the  review  

!  CriLcal  Design  Review  (CDR)  example  – Are  we  ready  for  the  Flight  Test  Readiness  Review?  

– How  do  we  know  the  FTRR  a  success?  – What  did  we  learn  from  the  FTRR  that  increases  the  maturity  of  the  program’s  deliverables.  

100  

9.0  Framework  

Page 101: Integrated Master Plan Development

The  IMP  Focuses  us  on  Measures  of  EffecLveness  and  Performance  

101  

MoE  

KPP  

MoP   TPM  Mission  Need  

Acquirer  Defines  the  Needs  and  CapabiliLes  in  terms  of  OperaLonal  Scenarios  

Supplier  Defines  Physical  SoluLons  that  meet  the  needs  of  the  Stakeholders  

Opera%onal  measures  of  success  related  to  the  achievement  of  the  mission  or  opera%onal  objec%ve  being  evaluated.  

Measures  that  characterize  physical  or  func%onal  aKributes  rela%ng  to  the  system  opera%on.  

Measures  used  to  assess  design  progress,  compliance  to  performance  requirements,  and  technical  risks.  

9.0  Framework  

Page 102: Integrated Master Plan Development

Measure  of  EffecLveness  (MoE)  

! Measures  of  EffecLveness  …  !  Are  stated  in  units  meaningful  to  the  buyer,  !  Focus  on  capabiliLes  independent  of  any  technical  implementaLon,  

!  Are  connected  to  the  mission  success.  

The  operaLonal  measures  of  success  that  are  closely  related  to  the  achievements  of  the  mission  or  operaLonal  objecLves  evaluated  in  the  operaLonal  environment,  under  a  specific  set  of  condiLons.  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

MoE’s  Belong  to  the  End  User  

102  

9.0  Framework  

Page 103: Integrated Master Plan Development

Measure  of  Performance  (MoP)  

! Measures  of  Performance  are  …  !  Aeributes  that  assure  the  system  has  the  capability  to  perform,  

!  Assessment  of  the  system  to  assure  it  meets  design  requirements  to  saLsfy  the  MoE.  

Measures  that  characterize  physical  or  funcLonal  aeributes  relaLng  to  the  system  operaLon,  measured  or  esLmated  

under  specific  condiLons.  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

MoP’s  belong  to  the  Program  –  Developed  by  the  Systems  Engineer,  Measured  By  CAMs,  and  Analyzed  by  PP&C    

103  

9.0  Framework  

Page 104: Integrated Master Plan Development

Key  Performance  Parameters  (KPP)  Both  JROC  and  Program  Specific  

!  Key  Performance  Parameters  …  !  Have  a  threshold  or  objecLve  value,  !  Characterize  the  major  drivers  of  performance,  

!  Are  considered  CriLcal  to  Customer  (CTC).  

Represent  the  capabiliLes  and  characterisLcs  so  significant  that  failure  to  meet  them  can  be  cause  for  

reevaluaLon,  reassessing,  or  terminaLon  of  the  program  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

The  acquirer  defines  the  KPPs  during  the  operaLonal  concept  development  –  KPPs  say  what  DONE  looks  like  

104  

9.0  Framework  

Page 105: Integrated Master Plan Development

 Technical  Performance  Measures  (TPM)  for  key  deliverables    

!  Technical  Performance  Measures  …  !  Assess  design  progress,  !  Define  compliance  to  performance  requirements,  

!  IdenLfy  technical  risk,  !  Are  limited  to  criLcal  thresholds,  !  Include  projected  performance.  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

Aeributes  that  determine  how  well  a  system  or  system  element  is  saLsfying  or  expected  to  saLsfy  a  technical  

requirement  or  goal  

105  

9.0  Framework  

Page 106: Integrated Master Plan Development

What  are  Technical  Performance  Measures  Really?  

!  TPMs  are  measures  of  the  system  technical  performance  that  have  been  chosen  because  they  are  indicators  of  system  success.  They  are  based  on  the  driving  requirements  or  technical  parameters  of  high  risk  or  significance  -­‐  e.g.,  mass,  power  or  data  rate.  

!  TPMs  are  analogous  to  the  programmaLc  measures  of  expected  total  cost  or  esLmated  Lme-­‐to-­‐compleLon.  There  is  a  required  performance,  a  current  best  esLmate,  and  a  trend  line.  

!  Actual  versus  planned  progress  of  TPMs  are  tracked  so  the  systems  engineer  or  project  manager  can  assess  progress  and  the  risk  associated  with  each  TPM.    

!  The  final,  delivered  system  value  can  be  esLmated  by  extending  the  TPM  trend  line  and  using  the  recommended  conLngency  values  for  each  project  phase.  

!  The  project  life  trend-­‐to-­‐date,  current  value,  and  forecast  of  all  TPMs  are  reviewed  periodically  (typically  monthly)  and  at  all  major  milestone  reviews.  

106  

9.0  Framework  

Page 107: Integrated Master Plan Development

!  Tracking  TPMs  and  comparing  them  to  the  resource  growth  provides  an  early  warning  system  to  detect  deficiencies  or  excesses  

!  Reserve  allocaLons  narrow  as  design  proceeds  !  TPMs  that  violate  reserve  allocaLons  or  have  trends  that  

do  not  meet  the  final  performance  trigger  correcLve  acLons  

107  

Tracking  the  Technical    Performance  Measures  

9.0  Framework  

Page 108: Integrated Master Plan Development

NoLonal  TPM  Design  Margin  Guidelines  

108  

9.0  Framework  

Page 109: Integrated Master Plan Development

Sample  IMP:  A  Flight  Avionics  System  (ConLnued)  

Hardware  PDR  –  Purpose    !  Ensure  system  hardware  iniLal  design  has  been  updated,  and  meets  

funcLonal  and  allocated  performance  requirements  within  program  constraints.    

!  OperaLonal  security  concept  assessed.    !  Ensure  training  requirements  have  been  analyzed  and  their  objecLves  

have  been  defined  for  training  missions.    !  ConfirmaLon  training  objecLves  and  MTC  design  and  integraLon  conform  

to  the  Air  Force  syllabus  and  Ready  Aircrew  Program  (RAP).    !  Training  plan  will  be  updated.  !  Hardware  PDR  –  ExpectaLons  !  Team  agrees  system  hardware  iniLal  design  has  been  updated  and  can  

proceed  to  the  detailed  design  phase.    !  Team  agrees  training  plans  and  objecLves  correlate  with  the  Air  Force  

syllabus,  RAP  and  training  planning,  development  can  conLnue.    !  System  SpecificaLon  and  TTL  requirements  are  traceable  to  the  allocated  

hardware  design.    109  

9.0  Framework  

Page 110: Integrated Master Plan Development

Sample  IMP:  A  Flight  Avionics  System  (ConLnued)  

!  Hardware  PDR  –  Entry  Criteria  !  FuncLonal  Baseline  AuthenLcated  (FBA)  !  IniLate  system  hardware  iniLal  design  and  allocate  funcLons  to  the  appropriate  ConfiguraLon  Items  

!  All  specificaLons  updated  and  required  documentaLon  is  made  available  including  anLcipated  lower  level  design  documentaLon  

!  All  SRR/SFR  acLon  items  closed  or  disposiLoned    

110  

9.0  Framework  

Page 111: Integrated Master Plan Development

Sample  IMP:  A  Flight  Avionics  System  (ConLnued)  

Hardware  PDR  –  Accomplishments  !  System  hardware  iniLal  design  complete.    

–  FuncLons  allocated  to  one  or  more  hardware  configuraLon  items  and  are  traceable  to  the  MTC  SSS  and  TSSC  SSS.    

–  Human,  safety,  R&M,  EMI,  operaLonal  security,  instructor  and  operator  interfaces,  etc,  design  factors  have  been  reviewed.    

!  Drao  instructor  and  operator  manuals  reviewed    !  Program  risks  updated,  assessed,  and  reviewed.    

–  MiLgaLon  plans  in  place.  !  Program  schedule  and  constraints  updated  and  reviewed.    

–  CriLcal  schedule  path  drivers  reviewed.    !  Design  criteria  for  the  simulaLon  and  database  development  

reviewed  and  updated.  !  Program  processes  and  metrics  reviewed.  !  Test  Planning  acLviLes  and  relevant  documentaLon  reviewed  by  

test  team.  111  

9.0  Framework  

Page 112: Integrated Master Plan Development

Sample  IMP:  A  Flight  Avionics  System  (Concluded)  

Hardware  PDR  –  Exit  Criteria    !  Hardware  (ownership,  visual,  IOS,  brief/debrief)  design  reviewed,  allocated  to  a  

hardware  configuraLon  item  and  updated  to  include  instructor  and  operators  interfaces,  malfuncLon  and  control  requirements,  etc.    

!  RTM  updated,  MTC  SSS,  TSSC  SSS  and  TTL  traceable  to  allocated  hardware  design  to  include  ESOH  requirements.    

!  Human,  safety,  R&M,  EMI,  operaLonal  security,  instructor  and  operator  interfaces,  etc,  design  factors  reviewed.    

!  MTC  and  TSSC  allocated  baselines  established  and  controlled  by  appropriate  level  documentaLon  for  PDR.  

!  Drao  instructor  and  operator  manuals  reviewed  with  user  concurrence  and  incorporate  saLsfactory  human  factor  design  factors  into  the  operator  interfaces.    

!  Risk  management  and  miLgaLon  plans  updated,  in  place,  addresses  ESOH  plans  and  risks,  and  within  program  constraints.    

!  Risks  assesses,  understood,  documented,  accepted  and  understood  by  team.  !  Program  schedule  reviewed    

–  CriLcal  path  drivers  idenLfied    –  IMS  Updated  and  reflects  criLcal  paths  

112  

9.0  Framework  

Page 113: Integrated Master Plan Development

One  More  IMP  Sample  

!  (SA)  System  &  Segment  Requirements  Updated  &  Allocated  –  (AC)  SRR  /  SDR  Update  Review  Conducted  

–  (AC)  Preliminary  System  SpecificaLon  Documents  (A011)  Baselined  

–  (AC)  Preliminary  Spacecrao  Segment  SpecificaLon  Baselined  

–  (AC)  Preliminary  Ground  Segment  SpecificaLon  Baselined  

–  (AC)  Preliminary  SpecificaLon  Tree  Baselined  

!  (SA)  Preliminary  ICDs  Baselined  For  Customer  Review  

–  (AC)  Preliminary  Space-­‐Ground  ICD  Baselined    

!  (SA)  PDR  System  Design  Completed  –  (AC)  Top  Level  System  Architecture  Updated  

–  (AC)  PDR  Level  System  Analyses  Completed  

–  (AC)  PDR  Level  Reliability  /  Availability  Analysis  Completed  

–  (AC)  Preliminary  System  Level  Risk  Assessment  Completed  

–  (AC)  System  Level  Plans  Updated  For  PDR  

–  (AC)  Flight  Long  Lead  Review  Conducted  

113  

Preliminary  Design  Review  

9.0  Framework  

Page 114: Integrated Master Plan Development

The  “But”  for  this  Guidance  

! With  these  samples  and  the  SETR  guidance  we’ve  just  started  

!  The  program  needs  to  define  program  specific  events  to  assure  the  actual  maturity  measures  are  captured  – The  IMP  provides  sufficient  defini=on  to  track  the  step-­‐by-­‐step  comple=on  of  the  required  accomplishments  for  each  event  and  to  demonstrate  sa=sfac=on  of  the  comple=on  criteria  for  each  accomplishment.  [AFMC  PAMPHLET  63-­‐5]  

114  

9.0  Framework  

Page 115: Integrated Master Plan Development

IMP  Verbs  for  Significant  Accomplishments  

115  

Integrated  Master  Plan  Allowable  Verbs  

Allocated:  Segment  requirement  is  flowed  down  from  the  System  SpecificaLon  

Released:  Approved  item  for  delivery  for  intended  customer  or  supplier;  all  internal  distribuLon  and  sign  offs  complete.  An  electronic  version  is  made  accessible  on  the  IDE  

Completed:  The  subject  item,  data,  document,  or  process  is  prepared  or  concluded,  and  reviewed  and  accepted  by  the  responsible  IPT.  SupporLng  documentaLon  is  available  through  IDE  

Reviewed:  The  subject  item,  data,  document,  or  process  is  prepared  or  concluded,  and  documented  for  compleLon.  SupporLng  documentaLon  is  available  through  IDE  

Conducted:  The  subject  meeLng  or  review  has  been  held  with  all  required  parLcipants.  The  charts  or  minutes  are  available  through  the  IDE  

Updated:  The  subject  process,  data,  or  document  has  been  reevaluated  using  later  informaLon,  and  adjustments  incorporated.  

Defined:  The  subject  configuraLon  items,  data,  or  document  was  submieed  to  the  customer  

Validated:  Requirements  are  validated,  received  contractor  approvals,  were  distributed,  and  are  available  through  the  IDE  

Established:  The  subject  items  is  created  and  set  in  place  in  a  manner  consistent  with  its  intended  use  aoer  review  and  accepted  by  the  IPT  

Verified:  Requirements  are  verified  or  processed  in  accordance  with  established  pracLce.  

9.0  Framework  

Page 116: Integrated Master Plan Development

The  IMP  Process  NarraLve  

!  ObjecMve:  a  brief  statement  explaining  why  this  process  set  is  applied  for  this  program  

!  Governing  DocumentaMon:  lists  of  the  guidance  or  compliance  documents;  e.g.,  specificaLons,  manuals,  and  procedures  including  company,  government,  and  industry  references  

!  Approach:  concise  descripLon  as  to  who  owns  each  process;  what  are  the  roles  and  responsibiliLes;  and  the  overall  process  including  a  process  flow  diagram.  

116  

9.0  Framework  

Page 117: Integrated Master Plan Development

Generic  IMP  EvaluaLon  Criteria  !  Do  the  Program  Events  and  Accomplishments  reflect  the  logical  evoluLon  and  progress  of  the  overall  Program?  –  Do  program  events  and  their  definiLons  clearly  demonstrate  the  maturity  of  the  program  over  its  life?  

–  Do  the  selected  Accomplishments  and  associated  Criteria  idenLfy  meaningful  and  measurable  progress  toward  the  key  goals  of  the  Program?  

!  Do  the  Accomplishments  for  each  event  demonstrate  a  meaningful  understanding  of  the  program  requirements  or  are  they  tasks  that  anyone  could  do  for  any  contract?  –  Do  they  reflect  your  SOW  requirements?    

!  Does  the  IMP  structure  readily  map  to  the  IPT  structure  such  that  each  IPT  can  easily  visualize  the  scope  of  their  responsibility?    

!  When  awarded,  could  the  contractor  use  the  Accomplishments  as  discrete  acLvity  cost  accounts  in  their  earned  value  system?  Or  are  they  level  of  effort  in  nature?    

!  Is  sufficient  visibility  provided  to  idenLfy  and  track  the  Program  Risk  Plan  and  associated  risk  miLgaLon  accomplishments  and/or  conLngencies?  

–  Does  criteria  supporLng  the  accomplishments  include  key  performance  requirements?  

!  Are  IPT  cross-­‐dependencies  and  dependencies  external  to  the  Program  appropriately  reflected  if  they  reflect  potenLal  schedule  or  performance  risks  to  the  success  of  the  Program?  

!  Is  the  submieed  "Contract  IMP"  (the  Product  IMP  that  is  to  be  included  as  part  of  the  Program  Contract)  defined  to  the  appropriate  level:  –  Do  the  Accomplishments  and  associated  Criteria  go  down  to  a  level  sufficient  to  provide  visibility  into  key  subcontractor  acLviLes  upon  which  the  success  of  the  Program  may  be  dependent?  

–  Are  the  Events  and  Accomplishments  included  in  the  IMP  at  such  a  level  as  to  make  the  maintenance  of  the  'Contractual  IMP'  pracLcal  or  does  it  include  an  unnecessary  level  of  detail?  

117  

9.0  Framework  

Page 118: Integrated Master Plan Development

Program  Management  Levels  Program Levels" IMP/IMS Elements" CWBS"

Tier 1!Program Manager!Technical Leads!IPT Manager!Technical performance goals!

Major Program Events (PE)!!!!Significant Accomplishments (SA)!

Level 1 & 2!Links to CLINs!Level 3 & 4!Control Packages!Link to PBS!Integrated EVMS!

Tier 2!Control Account Managers !Product Work Plan!Responsible organization elements!!

Accomplishment Criteria (AC)!!!!!Tasks (NA)!

Level 5!Cost Account Package!Cost Collection Level!Links to WBS by OBS!Resource summaries!Early warning EVMS analysis!

Tier 3!Work Package Manager!

Detailed plans! Work package!Earned value calculations!

118  

9.0  Framework  

Page 119: Integrated Master Plan Development

ConnecLng  the  Components    of  the  IMP/IMS  

!  The  assembled  IMP/IMS  links  all  work  acLviLes  verLcally  to  the  ACs,  SAs,  and  PEs  

119  

IMS  

Customer  Requirements   IMP  

ORG  

IPTs  

ORG  

IPTs  

Performance  

Analysis/  Management  

Review  

Events (E)  Events (E)  

Accomplishments  Process  

Narratives  Criteria  

Integrated Master  Schedule (IMS)  

Integrated Master  Schedule (IMS)  

Control Account  Control Account  

Work Package  Work Package  

Work Package Tasks  Work Package Tasks  

WBS  

Program  Performance  Management  

System  

Supplemental Schedules  

Risk and  opportunity  Risk and  

opportunity  

9.0  Framework  

Page 120: Integrated Master Plan Development

120  

9.0  Framework  

Page 121: Integrated Master Plan Development

First  Pass  At  Building  The  Integrated  Master  Plan    

Many  contractors  all  ready  have  work  processes  to  do  this.  These  steps  are  guidance  for  contractors  new  to  this  process.    With  the  RFP,  the  contract  should  be  capable  of  the  following  steps  to  create  the  Integrated  Master  Plan  and  Integrated  Master  Schedule.    We’ll  build  the  IMP/IMS  from  the  point  of  view  of  the  Government  to  compare  the  contractors  IMP  in  the  proposal  

10  

V8.7  

Page 122: Integrated Master Plan Development

Focused  with  the  Air  Vehicle  

122  

10.  1st  Pass  

Page 123: Integrated Master Plan Development

Quick  View  of  1st  Pass  for  IMP  

!  Start  with  WBS  !  Use  Preliminary  Design  Review  Program  Event  !  IdenLfy  subsystems  for  flight  vehicle  !  IdenLfy  Significant  Accomplishments  for  PDR  compleLon  

!  IdenLfy  Accomplishment  Criteria  for  each  sequence  of  Work  Packages  to  produce  the  deliverables  for  PDR  

123  

10.  1st  Pass  

Page 124: Integrated Master Plan Development

Examine  the  IMS  for  these  and  other  aeributes  

!  Deliverables  represent  the  required  mission  capabiliLes  and  its  value  as  defined  by  the  business  and  shared  by  the  contractor  team.  

!  When  all  deliverables  and  their  Work  Packages  are  complete,  they  are  not  revisited  or  reopened.  –  They  are  100%  done.  

!  The  progression  of  Work  Packages  defines  the  increasing  maturity  of  the  deliverables.  –  The  mission  value  of  the  deliverables  to  the  customer  

increases  as  Work  Packages  are  completed.  !  CompleLon  of  Work  Packages  is  represented  by  the  

Physical  Percent  Comple=on  of  the  deliverables.  –  Either  0%/100%  or  Appor=oned  Milestones  are  used  

to  state  the  compleLon  of  each  Work  Package.  124  

Mission  Requirements  

Technical  CapabiliLes  

Work  Packages  

Deliverables  

10.  1st  Pass  

Page 125: Integrated Master Plan Development

The  Cri=cal  Few  for  the  IMS  

1.  EsLmated  duraLons  developed  to  known  confidence  levels  for  work  acLviLes  

2.  Probability  DistribuLons  for  categories  of  work  –  Reference  Class  ForecasLng  

3.  Risk  parameters  for  each  category  of  work  –  Reference  Class  Risk  Assessments  

4.  Credible  sequences  of  work  dependencies  5.  AlteraLve  paths  through  the  network  to  deal  

with  uncertainLes  in  cost  and  schedule  6.  Measures  of  Performance  (MoP)  in  units  

meaningful  to  the  decision  makers  125  

10.  1st  Pass  

Page 126: Integrated Master Plan Development

Understand  the  Product  

!  IdenLfy  Customer,  the  business  processes,  poliLcal  aspects  of  the  customer  and  any  other  aeributes.  

!  Compile  customer  requirements  from  SOO,  SOW,  CDRLs  and  other  applicable  documents.  These  documents  define  the  master  schedule  and  the  deliverables  around  this  schedule.  

!  Document  the  ground  rules  and  assumpLons  that  describes  how  the  Program  Events,  Significant  Accomplishments  and  their  Accomplishment  Criteria.  

!  Clarify  the  product  requirements  by  cross  references  all  the  customer  document  through  the  Concept  of  OperaLons  (ConOps).  

126  

10.  1st  Pass  

Page 127: Integrated Master Plan Development

Develop  the  Product  Structure  

!  Create  Top  Level  CWBS  that  describes  the  product  structure  first,  then  the  IPTs  that  will  deliver  those  products.  

!  Assess  structure  for  completeness  and  workability  by  asking  “how  will  the  components  of  the  product  structure  come  together  during  the  execuLon  of  the  program?”    

!  Is  the  assembling  in  a  tree  structure  from  the  boeom  to  the  top?  Or  is  it  scaeered  all  over  the  WBS/CWBS.  If  it  is  the  laeer,  the  WBS  will  be  nothing  but  trouble  during  execuLon.  

!  Write  the  CWBS  dicLonary.  This  is  a  narraLve  staLng  what  is  being  delivered  for  each  element  of  the  CWBS.  It  is  from  these  descripLons  that  lower  level  work  efforts  will  be  defined.  

!  Define  Teams  –  in  terms  of  IPTs  –  who  will  deliver  the  products  !  Develop  the  top  level  SOW  task  statement  to  assure  the  cross  

reference  between  the  CWBS  and  SOW  127  

10.  1st  Pass  

Page 128: Integrated Master Plan Development

Form  Integrated  Product  Teams  

!  Form  teams  and  define  leaders  and  key  resources.    

!  Teams  are  accountable  for  deliverables  described  in  the  WBS/CWBS.  

!  Validate  and  extend  the  SOW,  CWBS  and  CWBS  dicLonary  across  the  IPTs  for  each  product  or  process.  

!  Develop  IMP/IMS  elements    !  Define  duraLon  and  cost  variances  and  event  based  risks  for  each  Program  Event  

128  

10.  1st  Pass  

Page 129: Integrated Master Plan Development

Create  Integrated  Master  Plan  

!  Select  Key  events  and  decision  points  using  government  provided  Events  and  program  maturity  assessment  points  that  assure  maturity  is  increasing  and  risk  and  being  reduced.  

!  Write  the  event  descripLons  describing  the  measurable  outcomes  of  each  event  in  terms  of  maturity  assessment  and  risk  reducLon.  

!  Development  the  Significant  Accomplishments  (SA)  and  Accomplishment  Criteria  (SA)  for  each  Program  Event  in  a  top  down  manner,  with  the  focus  on  describing  the  increasing  maturity  of  the  products  resulLng  from  the  work  held  in  the  ACs.  

!  Develop  the  verLcal  logic  between  the  PE/SA/AC  describing  the  logical  flow  of  increasing  maturity,  the  physical  assessment  of  the  product’s  performance  against  the  Technical  Performance  Criteria,  and  the  dependencies  between  each  Accomplishment  Criteria.  

!  Write  the  IMP  process  narraLves  in  the  form  of  a  product  specificaLon.  

!  Prepare  a  logic  flow  diagram  for  the  SAs,  showing  increasing  maturity  of  the  products  

129  

10.  1st  Pass  

Page 130: Integrated Master Plan Development

Create  Integrated  Master  Schedule  

!  Define  high  level  Work  Packages  from  the  ACs.  One  WP  /  AC  if  possible  

!  Decompose  tasks  within  the  WP  on  a  single  work  sheet  !  Define  the  logic  and  dependencies  between  the  ACs  first.  Only  then  connect  task  dependencies  

!  Apply  the  schedule  constraints  !  Establish  work  package  and  supporLng  task  duraLons  !  Add  resources  at  the  work  package  level  !  Asses  the  criLcal  paths  !  Perform  schedule  risk  assessment  

130  

10.  1st  Pass  

Page 131: Integrated Master Plan Development

Create  Basis  of  EsLmate  

!  Receive  flow  down  of  requirements  and  the  cost  esLmaLng  processes  around  them  

!  Determine  appropriate  methods  of  defining  costs  

!  EsLmate  the  hours  !  Review  and  adjust  the  costs  to  match  the  allocaLons  

131  

10.  1st  Pass  

Page 132: Integrated Master Plan Development

Develop  Risk  Register  

!  For  each  Program  Event,  Significant  Accomplishment,  and  Accomplishment  Criteria  define  the  Event  Based  Risks  that  prevent  success  

!  Focus  on  the  IMP  NarraLve  contents  as  the  source  of  these  risks  

!  Define  the  risk  in  the  Risk  Register  from  the  point  of  view  of  the  Exit  Criteria  for  the  IMP  elements  

132  

10.  1st  Pass  

Page 133: Integrated Master Plan Development

Adjust  Work  AcLviLes  for  Uncertainty  in  DuraLons  

!  Past  performance  is  a  good  indicator  of  future  performance  

!  Reference  class  forecasLng  for  categories  of  work  – Avionics  – Propulsion  

!  Define  upper  and  lower  bounds  of  duraLon  ! Most  Likely  duraLon  used  as  a  Target  value  ! Monte  Carlo  SimulaLon  shows  confidence  of  Comple=ng  On  Or  Before  the  Target  Date  

133  

10.  1st  Pass  

Page 134: Integrated Master Plan Development

Define  Risk  Drivers  

!  PotenLal  risks  !  Probability  of  occurrence  !  Consequence  when  the  risk  occurs  !  Cost  to  miLgate  !  Remaining  risk  aoer  miLgaLon  !  Remaining  consequence  aoer  miLgaLon  !  Drivers  and  their  network  connecLons  !  Integrate  this  informaLon  in  the  Risk  Register  and  the  Integrated  Master  Schedule  for  miLgaLon  acLviLes.  

134  

10.  1st  Pass  

Page 135: Integrated Master Plan Development

Use  the  DOD  SETR  Guidance  as  the  StarLng  point  

135  heps://acc.dau.mil/docs/technicalreviews/dod_tech_reviews.htm  

10.  1st  Pass  

Page 136: Integrated Master Plan Development

!  System  of  Systems  Program  Events  – Follow  the  SETR  guidelines  – First  Ler  System  SAs  – Sequence  first  Ler  SAs  – First  Tier  ProgrammaLc  and  Technical  Risks  at  the  SA  level    

!  UAV  Flight  Avionics  IMP  – SAs  and  ACs  for  the  Flight  Avionics  Subsystems  – Sequence  the  ACs  for  the  Flight  Avionics  

136  

Program  Events  10.  1st  Pass  

Page 137: Integrated Master Plan Development

!  SoS  IMP  using  SETR  and  top  level  system  SAs  – SSs  linked  to  show  path  to  the  end  with  risks  assigned  

!  UAV  with  Avionics  to  the  Mission  Management  Computer  ready  for  the  IMS  development  – ACs  linked  with  Work  Packages  

137  

Let’s  build  our  Two  IMPs  10.  1st  Pass  

Page 138: Integrated Master Plan Development

System  of  Systems  IMP  SAs  

138  

SoS  PDR   SoS  CDR   SoS  TRR  

1.  Timing  /  Entry  Criteria  2.  Program  Schedule  3.  Management  Metrics  4.  Program  Staffing  5.  Process  Review  6.  Requirements  Management  7.  Net-­‐Centric  OperaLons  And  

Warfare  Consolidated  Compliance  Checklist  

8.   System  Preliminary  Design  9.  Life  Cycle  LogisLcs  10.  Program  Risk  Assessment  11.  CompleLon  /  Exit  Criteria  12.  System  Engineering  

Processes  13. Drao  SOS  T&E    14.  Common  Support  Equip  15.  Training  Plan  Assessment    

1.  Timing  /  Entry  Criteria  2.  Planning  3.  Program  Schedule  4.  Management  Metrics  5.  Program  Staffing  6.  Process  Review  7.  Product  Review  8.  Product  Support  9.   Requirements  Management  10.  System  VerificaLon  11.  Program  Risk  Assessment  12.  CerLficaLon  And  Legal  

Requirements  13.  CompleLon  And  Exit  Criteria  

1.  Timing  /  Entry  Criteria  2.  Test  Readiness  Review  

Planning  3.  TRR  LogisLcs  4.  Test  Program  Schedule  5.  Test  Program  Staffing  6.  Test  Plan  /  Process  Review  7.  Management  Metrics  

Relevant  To  Planned  Test  8.  Test  Program  Risk  

Assessment  9.   System  Under  Test  

Requirements  10.   System  Under  Test  11.  CompleLon  And  Exit  Criteria  

Bold  items  will  flow  down  to  subsystems  to  the  Flight  Avionics  IMP  

10.  1st  Pass  

Page 139: Integrated Master Plan Development

UAV  Flight  Avionics  IMP  SAs  

139  

UAV  Avionics  PDR   UAV  Avionics  CDR   UAV  Avionics  TRR  

1.  Avionics  System  Requirements  Defined  

2.  PDR  Test  &  EvaluaLon  Planning  Complete  

3.  Avionics  System/Subsystem  Design  Development  

4.  Cost,  Schedule,  and  Technical  Performance  Reviewed  

5.  Preliminary  Safety  Assessment  Complete  

6.  Test  &  EvaluaLon  ExecuLon  7.  Reliability  Planning  8.  LogisLcs  and  Maintainability  

ExecuLon  

1.  Avionics  Suite  System  Design  Complete  

2.  Final  OperaLons  and  Support  Hazard  (O&S)  Analysis  Completed  

3.  Updated  Trade  Studies  Completed  

4.  Final  Test  Plans  Complete  5.  Preliminary  Test  Procedures  

Complete  6.  Cost,  Schedule,  and  Technical  

Performance  Reviewed  7.  System/Subsystem  Design  

Development  8.  Sooware  Development  Planning  9.  Sooware  Development  10.  Security  Program  Planning  11.  Safety  Program  ExecuLon  12.  Test  &  EvaluaLon  Planning  13.  Test  &  EvaluaLon  ExecuLon  14.  Reliability  Planning  15.  Reliability  Analysis  16.  LogisLcs  and  Maintainability  17.  CDR  CDRL's  

1.  Government  and  Contractor  QualificaLon  TesLng  "Ready  to  Proceed"  

2.  Final  Test  Procedures  Complete  3.  Avionics  Suite  System  

Development  Complete  4.  System/Subsystem  Design  

Development  5.  Sooware  Development  Planning  6.  Sooware  Development  7.  Safety  Program  ExecuLon  8.  Test  &  EvaluaLon  Planning  9.  Test  &  EvaluaLon  ExecuLon  10.  Security  Program  Planning  11.  LogisLcs  and  Maintainability  And  

Exit  Criteria  

10.  1st  Pass  

Page 140: Integrated Master Plan Development

140  

10.  1st  Pass