Integrated Energy Policy Report 2008

download Integrated Energy Policy Report 2008

of 146

Transcript of Integrated Energy Policy Report 2008

  • 8/14/2019 Integrated Energy Policy Report 2008

    1/146

    2008 Integrated Energy Policy report UPDATE

    Arnold Schwarzenegger, Governor

  • 8/14/2019 Integrated Energy Policy Report 2008

    2/146

  • 8/14/2019 Integrated Energy Policy Report 2008

    3/146

    2008 IEPR UPDATE

    Caliornia Energy Commission

    Chairman

    Jackalyne Pannenstiel

    Vice Chair

    James D. Boyd

    Commissioners:

    Arthur H. Roseneld

    Jerey Byron

    Karen Douglas

    Executive Director

    Melissa Jones

    Principal Authors

    Jim Bartridge

    Gerry BraunPamela Doughman

    Judy Grau

    Michael Jaske

    Chris Kavalec

    Kae Lewis

    Rachel MacDonald

    Jamie Patterson

    Mike Ringer

    David Vidaver

    Jennier Williams

    Project Manager

    Suzanne Korosec

  • 8/14/2019 Integrated Energy Policy Report 2008

    4/146

    2008 IEPR UPDATE

    Please cite this report as:

    Caliornia Energy Commission 2008, 2008 Integrated Energy Policy Report Update, CEC-100-2008-008-CMF.

  • 8/14/2019 Integrated Energy Policy Report 2008

    5/146

    2008 IEPR UPDATE

    This report is dedicated to the memory o

    JANE HUGHES TURNBULLJune 13, 1932 October 18, 2008

    With gratitude or her tireless devotion and invaluable contribu-

    tions to the development o Caliornias energy policies on behal

    o the League o Women Voters and all the residents o Caliornia

  • 8/14/2019 Integrated Energy Policy Report 2008

    6/146

  • 8/14/2019 Integrated Energy Policy Report 2008

    7/146

    2008 IEPR UPDATE

    AbstractThe 2008 Integrated Energy Policy Report Updateaddresses the ollowing ve topics related to Caliornias energy

    systems:

    What physical, operational, and market changes will be needed or Caliornias electric system to1.

    support a minimum o 33 percent renewables by 2020.

    How the states energy eciency goals and programs interact with the Energy Commissions electricity2.

    and natural gas demand orecasting methods.

    Recommended changes to electricity procurement practices to standardize assumptions, extend the3.

    period o analysis, and more adequately incorporate risk in the portolio o projected resources.

    Potential vulnerability o Diablo Canyon Power Plant and San Onore Nuclear Generating Station nuclear4.

    power plants to a major disruption rom a major seismic event or plant aging, as required by Assembly

    Bill 1632.

    Evaluation o the Caliornia Public Utilities Commissions Sel-Generation Incentive Program to5.

    determine the costs and benets o providing ratepayers subsidies or renewable and ossil uel

    ultraclean and low-emission distributed generation as required by Assembly Bill 2778.

    Status report on recommendations made in past Integrated Energy Policy Reports.6.

    Key WordsRenewables Portolio Standard, Renewable Energy Transmission Initiative, renewable energy, energy eciency,

    demand orecast, electricity procurement, portolio planning, social discount rate, nuclear power plants, aging

    power plants, once-through cooling, Sel-Generation Incentive Program, distributed generation, combined

    heat and power.

  • 8/14/2019 Integrated Energy Policy Report 2008

    8/146

  • 8/14/2019 Integrated Energy Policy Report 2008

    9/146

    2008 IEPR UPDATE

    Executive Summar 1

    Caliornias Renewable Future 2

    Energy Eciency and Demand Forecasting 3

    Electricity Procurement Practices and Resource Planning Activities 4

    Assessment o Caliornias Operating Nuclear Plants 6

    Evaluation o the Sel-Generation Incentive Program 7

    State Progress on Key Integrated Energy Policy Report Recommendations 8

    Chapter 1: Caliornias Renewable Energ Future 9

    Introduction 9

    Barriers to Renewable Development 10

    Addressing Transmission Barriers

    Addressing Integration Barriers

    Addressing Contracting Issues

    Addressing Price Impacts

    Addressing Environmental Issues

    Recommendations 27

    Endnotes 31

    Chapter 2: Energ Efcienc and Demand Forecasting 37

    Introduction 37

    Measurement and Attribution Challenges 38

    Incorporating Eciency in the Demand Forecast 40

    Rening and Improving Eciency Measurement and Attribution in the Demand Forecast 44

    Utility Progress Under Assembly Bill 2021 47

    Conclusions 49

    Recommendations 49

    Endnotes 51

    Table o Contents

  • 8/14/2019 Integrated Energy Policy Report 2008

    10/146

    2008 IEPR UPDATE

    Chapter 3: Electricit Procurement Practices and Resource Planning Activities 53

    Introduction 53

    Long-Term Procurement Plans 54

    Aging Plants and Transitioning From Once-Through Cooling 58

    Procurement and the Siting Process 59

    Recommendations 59

    Endnotes 63

    Chapter 4: Assessment o Caliornias Operating Nuclear Plants 65

    Introduction 65

    Seismic Vulnerability Assessment 66

    Aging Plant Issues

    Impacts o Major Disruption 71

    Economic, Environmental, and Policy Issues 74

    Nuclear Waste Disposal and Storage Issues 74

    Power Generation Options 76

    License Renewal Issues 77

    Recommendations 78

    Endnotes 83

    Chapter 5: Evaluation o the Sel-Generation Incentive Program 85

    Introduction 85

    Analysis Approach and Method

    Results 90

    Recommendations 94

    Endnotes 97

  • 8/14/2019 Integrated Energy Policy Report 2008

    11/146

    2008 IEPR UPDATE

    Chapter 6: State Progress on Ke Integrated Energ Polic Report Recommendations 99

    Electricity and Procurement 99

    Energy Eciency 101

    Demand Response 102

    Renewable Energy 103

    Electric Distribution System andCombined Heat and Power 106

    Nuclear Power 108

    Transmission 109

    Natural Gas 112

    Transportation Energy 113

    Petroleum Inrastructure 116

    Land Use 117

    Water and Energy Use

    Endnotes 121

    Glossar o Acronms 123

    Appendix A: Aging and Once-through Cooling Power Plants, November 2008 125

  • 8/14/2019 Integrated Energy Policy Report 2008

    12/146

  • 8/14/2019 Integrated Energy Policy Report 2008

    13/146

    1

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    Senate Bill 1389 (Bowen, Chapter 568, Statutes o 2002) requires the Caliornia Energy Commission (EnergyCommission) to conduct assessments and orecasts o all aspects o energy industry supply, production, trans-

    portation, delivery and distribution, demand, and prices. The Energy Commission uses these assessments and

    orecasts to develop energy policies that conserve resources, protect the environment, ensure energy reliability,

    enhance the states economy, and protect public health and saety. The Energy Commission prepares these

    assessments and associated policy recommendations every two years in the Integrated Energy Policy Report,

    with updates in alternate years.

    The 2008 Integrated Energy Policy Report Updateassesses progress on the energy programs and policy recom-

    mendations that are critical to meeting Caliornias energy and related environmental goals. The Energy Com-

    missions Integrated Energy Policy Report Committee identied critical topics or the 2008 Integrated Energy

    Policy Report Updateat a public scoping hearing on April 28, 2008. Ater considering stakeholder eedback, the

    Committee ocused on the ollowing ve areas:

    Executive Summary

    Physical, operational, and market changes1.

    necessary or Caliornias electric system to

    support a minimum o 33 percent renewables

    by 2020.

    Evaluation o the interaction between the2.

    states energy eciency goals and programs

    with the Energy Commissions demand ore-

    casting methods.

    Status o recommended changes to electricity3.

    procurement practices to standardize assump-

    tions, extend the period o analysis, and more

    adequately incorporate risk in the portolio o

    projected resources.

    Assessment o the Diablo Canyon Power4.

    Plant and San Onore Nuclear Generating

    Station nuclear power plants, as required by

    Assembly Bill 1632 (Blakeslee, Chapter 722,

    Statutes o 2006), to determine potential vul-

    nerabilities to a major disruption rom a major

    seismic event or plant aging.

    Evaluation o the Caliornia Public Utilities5.

    Commissions Sel-Generation Incentive Pro-gram to determine the costs and benets o

    providing ratepayer subsidies or renewable

    and ossil uel ultraclean and low-emission

    distributed generation as required by

    Assembly Bill 2778 (Lieber, Statutes o 2006,

    Chapter 617).

    The 2008 Integrated Energy Policy Report Updatealso reports on the states progress in implementing policy

    recommendations rom past Integrated Energy Policy Reports. This review is intended to ensure that Caliornia

    is on track in meeting the states energy policy goals while meeting Caliornias need or aordable, sae, and

    environmentally acceptable energy choices.

  • 8/14/2019 Integrated Energy Policy Report 2008

    14/146

    2

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    Caliornias Renewable FutureSince 2002, Caliornia has had a mandate to increase

    the use o renewable generation to 20 percent o re-

    tail electricity sales by 2010. On November 17, 2008,

    Governor Schwarzenegger signed Executive Order

    S-14-08, which raises Caliornias renewable energy

    goals to 33 percent by 2020.1 This enhanced targetwill help Caliornia meet the aggressive greenhouse

    gas emission reduction target o 1990 levels by 2020.

    The Energy Commission believes the state can reach

    the 33 percent renewables target by 2020. There

    are, however, major barriers to achieving this goal,

    including: the need or transmission additions and

    upgrades to access renewable resource areas; the

    challenges associated with integrating large amounts

    o renewable resources into the states electricity

    system; the impacts o renewable contract delays or

    cancellations; potential cost and rate impacts o add-

    ing renewables to the system; and permitting issues

    or renewable generation acilities in environmentally

    sensitive areas.

    The Renewable Energy Transmission Initiative was

    established to help address transmission barriers by

    identiying and ranking renewable resource zones

    and broadly identiying the transmission needed to

    access those zones. Because environmental and land

    use issues can delay the development o transmis-

    sion projects, the Energy Commission will continueto work closely with stakeholders in the Renewable

    Energy Transmission Initiative process to ensure

    that these issues are evaluated and considered. The

    Energy Commission also recognizes the importance

    and benets o joint transmission projects between

    investor-owned and publicly owned utilities and will

    use the 2009 Integrated Energy Policy Reportorum to

    identiy strategies to reduce barriers to these joint

    projects. In addition, the Energy Commission believes

    that transmission-related research, development, and

    demonstration eorts and unding should be signi-

    cantly increased to identiy technologies and strate-gies that can help integrate renewable resources.

    Integrating large amounts o variable and intermit-

    tent resources like wind into Caliornias electricity

    system is challenging. The state should ocus on

    identiying energy storage technologies with the

    most promise o providing grid stability and im-

    proved operations, reducing the costs o those tech-

    nologies, and accelerating their commercialization.

    Improved orecasting techniques are also needed to

    give grid operators inormation to make real-time

    decisions about electricity scheduling and dispatch.The state also needs to expand eorts to include

    renewable generation at the distribution level, such

    as community-scale photovoltaics or small wind, to

    reduce electricity loads and the need or upgrades

    to the transmission system. Similarly, increased use

    o renewable technologies or heating and cooling,

    like solar thermal water heating and geothermal

    ground-source heat pumps, could reduce electricity

    loads while also decreasing the use o ossil uels and

    emissions o greenhouse gases.

    Contract delays or cancellations or renewable proj-

    ects continue to be a barrier to meeting Caliornias

    renewable goals. Thirty ve percent o the contracts

    signed under the Renewables Portolio Standard

    have been either delayed (25 percent) or cancelled

    (10 percent). There also continues to be a need or

    greater transparency in the evaluation and selection

    o electricity providers. Independent parties, such as

    the Caliornia Public Utilities Commission or inde-

    pendent evaluators and not utilities, should review,

    select, and rank renewable procurement proposals.

    The investor-owned utilities should also be required

    to provide aggregated inormation on Renewables

    Portolio Standard contract prices to assure policy

    makers that these contracts are meeting state energy

    policy goals and providing economic value to the

    state. In addition, the Caliornia Public Utilities Com-

    mission should make public the aggregate amount

    o above-market unds that are being allocated to

    Renewables Portolio Standard contracts. To help

    encourage renewable development and provide

    price certainty to renewable developers, the Calior-

    nia Public Utilities Commission should immediately

    implement a program to provide standardized con-tracts and prices or renewable projects smaller than

    20 megawatts while continuing to evaluate expand-

    ing such a program to renewable projects larger than

    20 megawatts.

  • 8/14/2019 Integrated Energy Policy Report 2008

    15/146

    3

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    The Energy Commission will evaluate impacts o a

    33 percent renewable target on natural gas demand

    and prices, as well as the impacts o regional changes

    in natural gas supply and demand on Caliornias

    natural gas market, to better understand the cost

    and price impacts o higher renewable targets. The

    Energy Commission will also continue to work on theCost o Generation Model to regularly update chang-

    ing technology costs over time. Finally, the Energy

    Commission will work with the Caliornia Public Utili-

    ties Commission to estimate potential price impacts

    o the 33 percent renewable target.

    The number and size o proposed large-scale renew-

    able power plants makes environmental permitting

    an increasing concern. Many o these new acilities

    are proposed in ecologically sensitive areas that could

    require habitat mitigation and restoration, which

    must be actored into the costs o the projects. En-

    vironmental mitigation issues can also aect project

    development schedules and project success. To help

    address these issues, Governor Schwarzeneggers

    Executive Order S-14-08 establishes the Renewable

    Energy Action Team to create a one-stop process

    or permitting renewable energy acilities. Also, the

    Energy Commission will continue participating in e-

    orts with the Department o Energy and the Bureau

    o Land Management to evaluate environmental

    impacts associated with permitting solar thermal a-

    cilities in Caliornia. In addition, the Caliornia Public

    Utilities Commission should direct investor-owned

    utilities to consider the eect o the environmental

    permitting process on project schedules, milestones,

    and costs.

    Energy Efciency andDemand ForecastingIn the 2007 Integrated Energy Policy Report, the

    Energy Commission identied the need to clariy

    and rene its Caliornia Energy Demand orecast.

    Accordingly, the 2008 Integrated Energy Policy ReportUpdatediscusses the challenges involved in measur-

    ing and attributing electricity savings rom energy

    eciency programs and other market impacts, such

    as prices, within the Energy Commissions Caliornia

    Energy Demand Forecast process. It also provides

    The Energy Commission sta has begun a pro-

    cess to make eciency attribution and measure-

    ment more transparent to users o the demand

    orecast, rene and improve modeling methods,

    and develop eciency measurement capabili-

    ties beyond what is part o the current orecast-ing process. During the 2009 Integrated Energy

    Policy Report cycle, sta will:

    Develop standard denitions o terms

    encompassing all major concepts applying

    to eciency potential studies and energy

    demand orecasts (September - November

    2008).

    Organize and participate in a stakeholder

    working group designed to address technical

    eciency issues and to develop consistent

    metrics or eciency analysis across utilities

    and various agencies (Organized September

    2008).

    Review and compare the modeling methods,

    inputs, and data sources used in Energy Com-

    mission orecasts o eciency savings with

    the Itron Asset Model, and compare interim

    savings estimates rom the Energy Commis-

    sions demand orecast and the Itron Asset

    Model or selected programs given commonsets o input and modeling assumptions (Sep-

    tember - November 2008).

    Rene and improve the Energy Commissions

    orecasting models to allow more detailed

    and complete output o committed eciency

    savings (December - June, 2009).

    Investigate alternative orecasting methods

    (Ongoing).

    Develop the capability to make projections

    o uncommitted energy eciency (June-July,

    2009).

  • 8/14/2019 Integrated Energy Policy Report 2008

    16/146

    4

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    Electricity Procurement Practicesand Resource Planning ActivitiesThe 2007 Integrated Energy Policy Reportraised con-

    cerns about electricity procurement in Caliornia and

    made recommendations to address those concerns.

    The 2008 Integrated Energy Policy Report Updatediscusses progress made in implementing those

    recommendations. The report also outlines reliability

    and resource adequacy issues associated with moving

    away rom the use o once-through cooling in power

    plants, as well as the relationship between electricity

    procurement and the Energy Commissions power

    plant siting process.

    Every two years, the major investor-owned utilities

    must submit 10-year plans to the Caliornia Public

    Utilities Commission or procuring electricity. Various

    parties criticized the plans submitted in December

    2006 or 2007 through 2016 because they did not

    allow or comparison across utilities, nor did they

    adequately evaluate high natural gas prices and

    greenhouse gas regulation that represent signicant

    ratepayer risk. The Caliornia Public Utilities Com-

    mission acknowledged the shortcomings in the

    procurement planning process and in the 2008 long-

    term procurement plan proceeding is directing the

    investor-owned utilities to provide a set o plans in

    2010 that can be compared and aggregated and that

    also consider ratepayer risks. The Caliornia Public

    Utilities Commission has developed a set o principles

    that refect their desire to evaluate utility portolios

    using a standardized, transparent methodology that

    refects uncertainties like uture natural gas prices

    and carbon costs.

    The Energy Commission sta should continue to col-

    laborate in the Caliornia Public Utilities Commissions

    long-term procurement plan proceeding. In addition,

    the 2009 Integrated Energy Policy Reportshould assess

    longer-run (20-year) uncertainties related to electric-

    ity demand and natural gas prices and supply. As theCaliornia Public Utilities Commissions 2008 procure-

    ment proceeding moves orward, other issues related

    to resource planning beyond 2020 may also need

    an overview o methods currently used by Energy

    Commission sta to incorporate energy eciency

    programs into the orecast. The chapter then identi-

    es the approach sta will use to clariy the eciency

    assumptions in the demand orecast within the 2009

    Integrated Energy Policy Reportcycle and beyond asrecommended in the 2007 Integrated Energy Policy

    Report. Finally, the chapter reports on progress

    made by Caliornia utilities in ullling the eciency

    requirements o Assembly Bill 2021 (Levine, Chapter

    734, Statutes o 2006), which set a statewide goal o

    reducing total orecasted electricity consumption by

    10 percent over the next 10 years.

    To improve the Energy Commissions demand ore-

    cast in the uture, the 2009 Integrated Energy Policy

    Reportshould compare how end-use impacts are

    characterized in the Energy Commissions demand

    orecast and in eciency program planning. Ignoring

    potential overlap will result in misleading estimates o

    how much can be achieved through uture eciency

    strategies. In addition, investor-owned utilities and

    publicly owned utilities, regulatory agencies, and

    other interested stakeholders should participate in

    the working group established in September 2008

    that is ocusing on technical issues and eectively

    communicating results to all interested stakeholders.

    Further, independent eorts to investigate and evalu-

    ate alternate orecasting methods should be contin-

    ued in the 2009 Integrated Energy Policy Reportand

    ocus on matching methods to the various purposes

    to which the demand orecast is applied.

    The Energy Commission sta should continue to

    work with publicly owned utilities to understand the

    processes used by individual utilities to estimate their

    remaining economic energy eciency potential and

    set eciency targets. The Energy Commission sta

    should also continue to assist the publicly owned

    utilities in achieving their eciency goals through

    workshops and collaborative eorts, while also en-couraging them to identiy all unding sources avail-

    able to meet those goals to refect the states policy

    o energy eciency as the top resource or meeting

    the states energy needs.

  • 8/14/2019 Integrated Energy Policy Report 2008

    17/146

    5

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    to be included in the 2009 Integrated Energy Policy

    Report, such as how to overcome utility constraints to

    reducing their portolios carbon ootprint over the

    long run.

    A second issue related to procurement that was iden-

    tied in the 2007 Integrated Energy Policy Reportwashow the discount rate used to estimate uture natural

    gas uel costs makes these costs appear unrealistically

    inexpensive. This could lead to increased depen-

    dence on natural gas-based generation because

    alternatives such as renewables and eciency would

    be undervalued. The 2007 Integrated Energy Policy

    Reportrecommended applying a 3 percent social

    discount rate (lower than the current discount rate

    which is based on a utilitys cost o capital) to uture

    natural gas costs to more accurately refect the risks

    o cost volatility o natural gas-based generation. For

    the 2008 Integrated Energy Policy Report Update, the

    Integrated Energy Policy Report Committee directed

    sta to explore the consequences o using a social

    discount rate.

    There is general agreement about the importance

    o incorporating uncertainty and risk, including

    uel price uncertainty, into the overall planning and

    decision-making process. The Energy Commission

    anticipates that the Caliornia Public Utilities Com-

    mission will require the next round o long-term

    procurement plans to incorporate risk-based portolio

    analysis by refecting a wide range o uture natural

    gas prices and associated gas price risk. The Energy

    Commission sta will continue to collaborate with

    Caliornia Public Utilities Commission sta to ensure

    that uel price risk is properly considered in con-

    structing utility portolios. The Energy Commission

    believes that the planning process is a more direct

    and transparent method to account or potential gas

    price risk than the adjustment o discount rates, and

    recommends that social discount rates should not be

    used to incorporate natural gas price risks. However,

    the Caliornia Public Utilities Commission should con-sider using risk-adjusted discount rates to compare

    projects selected in utility solicitations when they

    rene the bid evaluation process in the long-term

    procurement proceeding.

    A third major issue related to electricity procurement

    is the potential eect on electricity reliability o retire-

    ment or repowering o aging power plants combined

    with restrictions on the use o once-through cooling

    in existing and new power plants. In March 2008,

    the State Water Resources Control Board issued a

    drat proposal calling or the phased elimination oonce-through cooling between 2015 and 2021. A

    nal proposal is expected in January 2009. Accom-

    plishing this could require the retting, repowering,

    replacement, or retirement o 19 power plants rep-

    resenting nearly 40 percent o the states electricity

    generating capacity.

    Aging plant retirement, or repowering and trans-

    mission line upgrades, are subjects o an ongoing

    Caliornia Independent System Operator study to

    be completed in early 2009. Additional analysis is

    needed on the implications o replacing much o

    the once-through cooling capacity with preerred

    resources, like renewables, and natural gas-red gen-

    eration that can be dispatched on demand to meet

    local capacity and grid stability needs. The 2009 Inte-

    grated Energy Policy Reportmay need to evaluate how

    repowering, replacement or retirement o aging and

    once-through cooling plants interacts with the de-

    velopment o preerred resources like renewables, as

    well as the consequences o relying on once-through

    cooling and aging plants or energy and local capac-

    ity needs, particularly in the Los Angeles basin.

    The nal procurement issue relates to how utilities

    consider progress in the permitting process when

    evaluating what projects to select or procurement.

    In the past, investor-owned utilities selected some

    projects to receive contracts that later aced signi-

    cant siting and environmental issues that threatened

    project viability, timely construction, or cost. Projects

    competing in a solicitation should understand the

    siting-related criteria that will be used to judge them.

    In addition, projects should have a high probability

    o being permitted in the required time rame with-out major environmentally-related modications or

    cost increases.

  • 8/14/2019 Integrated Energy Policy Report 2008

    18/146

    6

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    The Caliornia Public Utilities Commission should

    develop and implement a ully transparent method

    o ranking projects in the bid evaluation phase o

    solicitations that is air, objective, and transparent;

    considers environmental impacts, the likelihood o

    obtaining permits, and prior success o bidders in

    ullling contract oerings; encourages competitiveoerings, is open to all bidders, and prevents cir-

    cumvention; avoids unnecessary administrative and

    transaction costs; expressly identies how project

    permitting is considered; and protects commercially

    competitive inormation.

    Assessment o CaliorniasOperating Nuclear PlantsAssembly Bill 1632 directed the Energy Commis-

    sion to assess the potential vulnerability o large

    baseload generation acilities o 1,700 megawatts or

    greater to a major disruption due to a seismic event

    or plant age-related issues. The Energy Commission

    was directed to adopt this assessment on or beore

    November 1, 2008, and include it in the 2008 Inte-

    grated Energy Policy Report Update.

    The Energy Commissions Electricity and Natural Gas

    Committee developed the AB 1632 Assessment o

    Caliornias Operating Nuclear Plants: AB 1632 Report

    based on a consultant report prepared by MRW &

    Associates that evaluated seismic and age-related is-sues along with other issues like reliability, economic

    impacts, and waste storage and disposal. The 2008

    Integrated Energy Policy Report Updateincludes a sum-

    mary o the ndings and recommendations rom the

    AB 1632 Report.

    Caliornias two operating nuclear acilities, the Dia-

    blo Canyon Power Plant and the San Onore Nuclear

    Generating Station, all under the Assembly Bill 1632

    requirement. Although two natural-gas red acilities

    in Caliornia Alamitos and Moss Landing have

    a nameplate capacity greater than 1,700 megawatts,these acilities operate below a 60 percent capacity

    actor and are not considered baseload acilities.

    Diablo Canyon and San Onore represent 12 percent o

    Caliornias overall electricity supply. A major disrup-

    tion because o an earthquake or plant aging could

    shut down one or both plants anywhere rom several

    months up to a year or even cause the retirement o a

    plants reactor.

    Each plant aces seismic hazards, which can include

    uncertainties about the type o ault zone near the

    plant, potential impacts rom earthquakes directly

    below the plants, or ground motion resulting rom

    an earthquake rupture. Non-saety related systems

    and structures, such as electrical switchyards, are the

    most vulnerable to damage rom earthquake and

    could result in plant outages lasting weeks or months.

    A seismic event also poses a risk to spent uel storage

    acilities at the plants.

    Because o the importance o these acilities to the

    states electricity supply, the Energy Commission be-

    lieves Pacic Gas and Electric Company and Southern

    Caliornia Edison should report in the 2009 Integrated

    Energy Policy Reporton their seismic research eorts. In

    particular, Southern Caliornia Edison should develop

    an active seismic hazards research program similar to

    Pacic Gas and Electrics Long Term Seismic Program.

    Age-related degradation is also a concern because

    these plants are approaching their ourth decade o

    operation. Eective maintenance programs and regu-

    latory oversight are essential in identiying aging plant

    equipment and components since ailure to do so

    could have serious long-term implications. The Energy

    Commission recommends that eective saety culture

    and plant maintenance programs be maintained at

    the nuclear plants along with enhanced oversight

    mechanisms by the Energy Commission, the Nuclear

    Regulatory Commission, and the Institute or Nuclear

    Power Operations.

    An earthquake, age-related plant or equipment ailure,

    or other event could lead to one or both o Caliorniasnuclear plants going o-line or extended periods,

    requiring replacement power rom other sources. The

    reliability, cost, and environmental implications o

  • 8/14/2019 Integrated Energy Policy Report 2008

    19/146

    7

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    Evaluation o the Sel-GenerationIncentive ProgramAssembly Bill 2778 requires the Energy Commission

    to include an evaluation in the Integrated Energy

    Policy Report o the Caliornia Public Utilities Com-

    missions Sel-Generation Incentive Program and the

    costs and benets o expanding eligibility or theprogram to renewable and ossil uel distributed gen-

    eration. The evaluation is to be done in consultation

    with the Caliornia Public Utilities Commission and

    the Caliornia Air Resources Board.

    The Sel-Generation Incentive Program was estab-

    lished in 2001 and is one o the largest distributed

    generation incentive programs in the United States,

    with approximately 1,200 projects totaling 300

    megawatts on-line at the end o 2007. The program

    originally included microturbines, small gas turbines,

    wind turbines, solar photovoltaics, uel cells, and

    internal combustion engines; however, as o January

    2008, only uel cells and wind energy technologies

    are eligible or the program.

    The Energy Commission selected TIAX, LLC to

    conduct the evaluation, which is presented in the

    consultant report Cost Beneft Analysis o the Sel-

    Generation Incentive Program. Based on ndings and

    inormation rom that report, the Energy Commission

    recommends that eligibility or the Sel-Generation

    Incentive Program should be based on the overall

    eciency and perormance o systems regardless o

    uel type. In addition, the Caliornia Public Utilities

    Commission should consider re-instituting ormerly

    eligible technologies that operate on landll gas,

    digester gas rom dairy waste or waste-water treat-

    ment processes, or biodiesel. TIAXs review o other

    technologies and uel types also suggests that the

    Caliornia Public Utilities Commission should consider

    providing sel-generation incentives or energy stor-

    age technologies, since these technologies provide

    capacity benets.

    Distributed generation can have location-specic grid

    benets when sized correctly. The transmission and

    distribution costs avoided by installing such systems

    can be quantied with highly accurate customer and

    utility data. There should be urther study in this area

    to better quantiy the locational benets o distrib-

    using replacement power will depend on the time o

    the outage and type o replacement power available.

    The Energy Commission, the Caliornia Public Utilities

    Commission, and the Caliornia Independent System

    Operator should evaluate the uncertainties o losing

    the electricity supplied by the states nuclear plants

    and modiy the long-term planning and procure-ment processes to ensure that replacement resources

    are acquired in a timely way.

    Diablo Canyon and San Onore have been operating

    or roughly hal o their 40-year initial license periods,

    and Pacic Gas and Electric and Southern Caliornia

    Edison are exploring the easibility o seeking 20-year

    license renewals rom the Nuclear Regulatory Com-

    mission. Diablo Canyon Unit 1s operating license ex-

    pires in 2024 and Unit 2s expires in 2025, while San

    Onore Nuclear Generating Station Units 2 and 3s

    operating licenses expire in 2022. I license renewals

    are granted, these acilities could continue to operate

    until the early to mid 2040s.

    These plants produce signicant quantities o radio-

    active waste in the orm o spent uel and other ra-

    dioactively contaminated materials. The plants must

    careully handle, store, transport, and dispose o the

    waste to protect humans and the environment rom

    exposure to radioactive materials. As part o license

    renewal easibility studies, Pacic Gas and Electric and

    Southern Caliornia Edison should evaluate the costs

    o disposing o low-level nuclear waste generated

    during a 20-year license extension and provide inor-

    mation on plans or storage and disposal o low-level

    waste and spent uel through plant decommissioning.

    In addition, the Energy Commission should work

    with the Caliornia Public Utilities Commission, as

    part o that agencys authority to und and oversee

    plant relicensing easibility studies, to develop a list

    o issues the utilities should address in those studies,

    including plant maintenance programs, saety cul-

    tures, waste storage, transport, and disposal; seismichazards; lie cycle comparison to alternative generat-

    ing and transmission resources; contingency plans

    or prolonged outages; grid reliability; and overall

    economic and environmental costs and benets o

    license extension. The utilities should report on the

    status and results o the easibility studies in uture

    Integrated Energy Policy Reports, beginning in 2009.

  • 8/14/2019 Integrated Energy Policy Report 2008

    20/146

    8

    2008 IEPR UPDATEExEcUTIvE SUmmARy

    uted generation, but in the meantime the Caliornia

    Public Utilities Commission should require investor-

    owned utilities to meet a portion o their distribution

    system upgrades by procuring distributed generation

    or combined heat and power in areas that provide

    these benets to the distribution system.

    State Progress on KeyIntegrated Energy Policy ReportRecommendationsThe 2008 Integrated Energy Policy Report Updateis a

    real-time, public orum or continuing dialog about

    Caliornias energy policies. This update examines

    the progress the state has made in addressing 45 key

    recommendations made in past Integrated Energy

    Policy Reports on electricity and procurement issues,

    energy eciency requirements, demand response,load management standards, renewable energy

    issues and goals, distribution system and combined

    heat and power, nuclear power, transmission, natural

    gas, transportation, petroleum inrastructure, land

    use, and water/energy. The 2008 Integrated Energy

    Policy Report Updateranks the progress o each rec-

    ommendation as substantial, on track, or needs

    improvement, and describes progress to date on

    each recommendation.

  • 8/14/2019 Integrated Energy Policy Report 2008

    21/146

    9

    IntroductionCaliornia has made electricity generation rom

    renewable resources a priority since the 1970s and

    leads the nation in biomass, geothermal, and solar

    capacity and generation. In addition to the environ-

    mental benets rom reducing the burning o ossil

    uels, using renewable resources reduces the risks

    and costs associated with high and volatile natural

    gas prices while also decreasing the states reliance

    on imported natural gas as a uel or electricity

    generation. Renewable resources also provide other

    benets such as economic development and new

    employment opportunities.

    Renewable energy is an essential component o the

    states loading order or meeting growing energy

    needs: rst, with energy eciency and demand re-

    sponse; second, with renewable energy and distrib-

    uted generation; and third, with clean ossil-ueled

    sources and inrastructure improvements. Caliornia

    has had a Renewables Portolio Standard (RPS) since

    2002 that requires electric utilities to increase the

    use o renewable generation to 20 percent o retail

    electricity sales by 2010. On November 17, 2008,

    Governor Schwarzenegger signed Executive Order

    S-14-08 that raises Caliornias renewable energy

    goals to 33 percent by 2020.2 This higher target has

    capter 1Caliornias RenewableEnergy Future

  • 8/14/2019 Integrated Energy Policy Report 2008

    22/146

    10

    2008 IEPR UPDATEchAPTER 1

    Barriers to Renewable DevelopmentThe primary barrier to increased development o

    renewable resources continues to be lack o transmis-

    sion to access these resources, particularly in remote

    areas o the state. The Renewable Energy Transmis-

    sion Initiative (RETI), discussed later in the chapter,

    was put in place to address this barrier by acilitatingand coordinating the planning and permitting o

    transmission and generating projects that are needed

    to urther the states renewable policy goals.

    There are also emerging technologies that can be

    used to improve the operation o the existing trans-

    mission system by increasing the carrying capacity o

    existing lines or by providing real-time inormation

    to grid operators about system outages or potential

    areas o congestion to allow better management

    o the grid. In addition, using a smart grid can

    improve eciency, reliability, and cost-eectiveness

    o the transmission and distribution system by us-

    ing advanced sensing, communication, and control

    technologies.

    Another major barrier to meeting the 33 percent

    goal is how to integrate large amounts o vari-

    able and intermittent renewable resources, such as

    wind and solar, into Caliornias electricity system.

    These technologies pose challenges to traditional

    reliability planning and resource adequacy require-

    ments because they cannot be relied on to meet

    rapid changes in load and supply during peak hours

    and generally must be backed up with dispatchable

    resources. Also, wind resources can produce large

    amounts o energy during low demand times, which,

    when combined with generation rom existing con-

    ventional baseload plants with must-run contracts

    and baseload nuclear power plants, can lead to an

    overgeneration problem. Energy storage technolo-

    gies can help rm up variable technologies, while

    data management and display systems can give grid

    operators real-time inormation to allow them to re-

    spond to the unpredicted changes in output that arecharacteristic o some renewable technologies.

    There is also the potential or wide-scale use o

    renewable generation at the distribution level, such

    as community-scale photovoltaics or small wind.

    been identied by the Caliornia Air Resources Board

    (ARB) as a key strategy or meeting the states aggres-

    sive greenhouse gas (GHG) emission reduction target

    o 1990 levels by 2020.3 To help meet the Governors

    goal to reduce GHG emissions to 80 percent below

    1990 levels by 2050,4 Caliornia may need to achieve

    even higher renewable targets depending on theelectricity sectors ultimate share o GHG reductions.

    The 2007 Integrated Energy Policy Report(2007IEPR)

    ound that the 33 percent goal by 2020 is easible,

    but only i the state commits to signicant invest-

    ments in transmission inrastructure and makes some

    key changes in policy. The priority now is to identiy

    the obstacles to reaching that goal and determine

    how to overcome those obstacles. The state needs

    to develop an appropriate package o policy reorms

    that will help get it on track or meeting the 33 per-

    cent RPS target while continuing to deliver reliable

    and aordable power to Caliornians.

    In the 2008 Integrated Energy Policy Report Update

    (2008 IEPR Update), the Energy Commission concen-

    trated on what useul inormation can be gleaned

    rom prior or ongoing studies on this topic, what

    analysis is needed to better understand how the

    2020 system should be structured to accommo-

    date higher levels o renewables, identiying major

    barriers to renewable development, what research

    and development eorts will be needed to support

    higher renewable targets, and how the states energy

    agencies can coordinate eorts to develop strategies

    to overcome barriers.

    In addition to the investor-owned utilities (IOUs) role

    in meeting the states renewable energy goals, the

    role o publicly owned utilities is also extremely sig-

    nicant. These entities provide 2530 percent o the

    retail electricity sold in Caliornia, making their par-

    ticipation essential to meeting statewide renewable

    and GHG reduction goals. There is, thereore, a need

    to work with the publicly owned utilities to under-stand their plans or helping the state to meet the 33

    percent goal by 2020, and their views on challenges,

    opportunities, and changes needed to achieve even

    higher levels o renewables.

  • 8/14/2019 Integrated Energy Policy Report 2008

    23/146

    11

    2008 IEPR UPDATEchAPTER 1

    to reduce the potential impacts o these projects will

    be a challenge depending on the species impacted,

    while uncertainty about how to account or the costs

    o mitigation measures is a major concern or renew-

    able project developers.

    In addition, with recent increased interest rom inves-tors in renewable energy as a result o climate change

    concerns and high ossil uel prices, new and less-

    experienced developers may be entering the market

    who are unamiliar with the Caliornia Environmental

    Quality Act, plant development issues, and the process

    or siting generating acilities in Caliornia. The CPUC

    has identied this risk in its quarterly reports to the

    Legislature on the RPS, and its April 2008 report noted

    that, Many new, inexperienced developers have

    diculty understanding and navigating the complex

    project development process and many approved

    contracts have been resubmitted with price reopeners

    possibly because the original bid had simply under-

    estimated project development realities.7

    Addressing Transmission BarriersEvery two years, the Energy Commission adopts a

    strategic plan or the states electric transmission grid

    that identies and recommends actions required to

    implement investments to ensure reliability, relieve

    congestion, and meet uture growth in load and

    generation, including renewable resources.

    8

    The 2007Strategic Transmission Investment Plan (2007 Strategic

    Plan) recommended 10 specic near-term transmis-

    sion projects that improve system reliability, reduce

    congestion, or interconnect renewable resources.

    Eight o those projects have the ability to interconnect

    renewables or provide operational fexibility to allow

    the transmission system to better integrate intermit-

    tent generation rom renewables.9

    The 2007 Strategic Plan also identies the need to

    remove transmission barriers to renewables. The plan

    recommended active Energy Commission participa-tion in RETI, a three-phase process which was initi-

    ated in September 2007 with the goal o identiying

    preerred renewable resource zones or generating

    projects and the transmission inrastructure needed

    to access those zones.10

    Behind-the-meter generation has the same eect as

    energy eciency in reducing load and can help avoid

    or deer the need or transmission system upgrades.

    Similarly, using renewable technologies or heating

    and cooling, like solar thermal water heating and

    geothermal ground source heat pumps, can reduce

    electricity loads while also reducing the use o ossiluels and their associated greenhouse gas emissions.

    The risk o renewable contract delays or cancellations

    represents another barrier to renewable develop-

    ment. As o September 2008, the Caliornia Public

    Utilities Commission (CPUC) had approved 90 con-

    tracts or 6,800 megawatts (MW) o new, repow-

    ered, and re-started renewable generating capacity

    signed since 2002. However, only about 570 MW

    o that contracted capacity is operational. Approxi-

    mately 35 percent o these contracts are not online

    because o delays (25 percent) or cancellations (10

    percent), making it extremely unlikely that the state

    will meet the 2010 goals.5

    A urther barrier to renewable development is the

    concern that higher levels o renewables will result

    in higher costs to ratepayers. However, the issue

    here is how to compare the incremental costs o a

    33 percent uture with potential cost increases that

    may occur even without added renewables, depend-

    ing on uture natural gas prices, potential costs o

    carbon regulation, generation costs in general, and

    needed upgrades to the transmission and distribu-

    tion system.

    Environmental permitting issues related to large-scale

    renewable development remain a major concern.

    Many energy projects are being proposed on

    public lands overseen by the ederal Bureau o Land

    Management (BLM). As o July 2008, the BLM had

    received 75 solar applications and 94 wind applica-

    tions totaling about 1.3 million acres o land.6 For

    comparison, 1,441 acres have been impacted by

    power plants (primarily natural-gas red) currentlyoperating or under construction that have been

    permitted by the Energy Commission since 1996.

    Given the sensitive nature o some o these lands,

    there may be signicant habitat impacts requiring

    mitigation measures. Identiying enough habitat land

  • 8/14/2019 Integrated Energy Policy Report 2008

    24/146

    12

    2008 IEPR UPDATEchAPTER 1

    transmission projects between publicly owned utili-

    ties and IOUs. Second, with regard to transmission

    siting, the state must continue to actively address

    environmental, land use, and local public opposition

    issues by working closely with stakeholders.

    Stakeholders agreed that RETI is a valuable orumor reaching consensus on the high-priority renew-

    able energy zones and the necessary transmission to

    reach them. Stakeholders also noted the potential or

    overlap between RETI and other orums and the lim-

    ited amount o resources available to devote to the

    many orums, and encouraged coordination between

    eorts to avoid duplication. The Energy Commission

    agrees that RETI should be coordinated with all appli-

    cable transmission planning eorts, both in Caliornia

    and throughout the Western Electricity Coordinating

    Councils service territory.

    Joint Transission ProjetsCaliornias publicly owned utilities have raised

    concerns about obstacles to joint transmission de-

    velopment in the West between the states publicly

    owned utilities and IOUs subject to the Caliornia

    Independent System Operators (Caliornia ISO) tar-

    is. According to the publicly owned utilities, unless

    these concerns are resolved, they will not be able to

    develop joint transmission projects that could help

    achieve the states renewable and GHG reduction

    policy goals. Parties discussed this issue at the July

    23, 2008, IEPR sta workshop on transmission issues,

    and there was general consensus among multiple

    parties that this is an institutional barrier that needs

    to be addressed and resolved to achieve state policy

    objectives.12

    Following the workshop, the Caliornia Municipal

    Utilities Association (CMUA), the Imperial Irrigation

    District (IID), the Los Angeles Department o Water

    and Power (LADWP), and the Sacramento Municipal

    Utility District (SMUD) led joint comments describ-ing some o the legal and market obstacles to joint

    ownership. The joint commenters noted that publicly

    owned utilities typically negotiate contract-based

    transmission rates or joint projects and contend

    that the constantly changing nature o the Caliornia

    Phase 1 o RETI, to be completed in all 2008, will

    screen and rank potential renewable resource zones

    and broadly identiy transmission needed to access

    these zones. Phase 1 has been subdivided into two

    tasks: Phase 1A, to dene the resource assessment

    method, study assumptions, and resources to be

    considered in the project-level analysis; and Phase1B, to use the method developed in Phase 1A to

    group the identied resources into renewable energy

    zones. Phase 2, to be completed in spring 2009, will

    examine generation and transmission in more detail

    and will develop transmission plans in concept to ac-

    cess the top ranking zones. Phase 3, to be completed

    in 2010, will fesh out those conceptual plans and

    support transmission owners in developing detailed

    plans o service or commercially viable transmission

    projects and establish the basis or regulatory ap-

    provals o specic transmission projects.

    The Energy Commissions participation in RETI is

    crucial in ensuring that the plans resulting rom RETI

    refect environmental, siting, and permitting per-

    spectives to reduce impacts that could delay renew-

    able energy projects.

    The 2007 Strategic Plan also recommended that the

    Energy Commission encourage corridor applications

    that would provide access to renewable resource

    areas. The Energy Commission is responsible or

    designating transmission corridors on non-ederal

    lands in advance o need to help streamline uture

    permitting o transmission projects and is the lead

    agency or preparing an environmental assessment o

    proposed transmission corridors.11 In situations where

    RETI indicates the need or one or more transmission

    lines on non-ederal land, the Energy Commissions

    transmission corridor designation process may desig-

    nate one or more corridors to expedite the eventual

    permitting o such lines.

    The Energy Commission sta held a workshop on July

    23, 2008, to discuss transmission barriers or renew-ables and identiy key issues or the 2009 Strategic

    Transmission Investment Plan. Workshop participants

    identied two major transmission-related barriers to

    achieving the states renewable goals. First, there is

    a need or mechanisms to remove barriers to joint

  • 8/14/2019 Integrated Energy Policy Report 2008

    25/146

    13

    2008 IEPR UPDATEchAPTER 1

    es this mission through tari provisions that incorpo-

    rate system operations and planning goals based on

    transparent reliability and economic objectives, and

    simultaneously provide mechanisms to accommodate

    jointly owned projects governed by bilateral agree-

    ments between the Caliornia ISO or its participating

    transmission owners and other parties. It also notedthat its Location Constrained Resource Interconnec-

    tion tari provisions require it to avoid duplication o

    acilities and to coordinate with neighboring control

    areas i the new transmission acility is in a region that

    also connects to the Caliornia ISO system.14

    The Caliornia ISO also submitted written comments

    ater the workshop to emphasize its position. In those

    comments, Caliornia ISO stated that key principles in

    carrying out its day-to-day operations and transmis-

    sion responsibilities include: costs borne by Cali-

    ornia ISO ratepayers must provide commensurate

    benets; existing transmission should be ully used

    beore new transmission expands the environmen-

    tal ootprint; and continued cooperation across the

    West is critical. Caliornia ISO also stated that its tari

    specically provides or bilateral agreements between

    owners o transmission under the Caliornia ISOs

    control and other parties, including publicly owned

    utilities.

    The Energy Commission recognizes the importance

    and benets o joint projects, especially to access

    renewable resources. In the 2007 Strategic Transmis-

    sion Investment Plan, the Energy Commissionnoted

    its concern that SCEs Tehachapi Renewable Trans-

    mission Plan and LADWPs Tehachapi Project could

    be duplicative unless the plans are coordinated and

    encouraged the two utilities to work together to

    avoid any overlap. Because there are both legal and

    market obstacles that hinder the development o

    joint projects, the Energy Commission believes that

    the state should play a role in resolving these issues.

    Enironental and Land Use IssuesAt the July 23, 2008, IEPR sta workshop, the Cali-

    ornia ISO presented the results o its conceptual

    transmission planning study or connecting renew-

    able generation to meet a 33 percent goal or the

    ISO tari does not provide the same degree o cost

    certainty, rate predictability, and asset optimization

    as bilateral contract agreements. The joint com-

    menters also noted that the Caliornia ISO is moving

    toward locational marginal pricing that uses nancial

    rights, such as congestion revenue rights13 that can

    be risky and speculative, rather than rm physicalrights to a specied amount o transmission line

    capacity. Furthermore, publicly owned utilities are

    concerned about the Caliornia ISOs insistence on

    having ull control o joint-ownership lines, as well as

    its requirement that all individual owner capacity and

    associated use must be subject to the Caliornia ISO

    tari. The CMUA believes that this provision is being

    interpreted to bar joint ownership unless the line

    is within the electric ootprint o the Caliornia ISO

    balancing authority.

    The IID, LADWP, SMUD, Turlock Irrigation District

    (TID), and the Western Area Power Administration in-

    cluded their July 2008 white paper titled Experiences

    with Joint Transmission-Project Development in the West

    in their joint comments. The paper describes recent

    joint development challenges aced by the Green

    Path Southwest and Green Path North projects and

    proposes a hybrid model or bridging the dierences

    between the Caliornia ISO tari and a contract-

    based arrangement.

    The joint parties comments and white paper were

    the ocus o a roundtable discussion at the August 21,

    2008, joint IEPR and Renewables Committee work-

    shop on achieving higher levels o renewables in Cali-

    ornias electricity system. Roundtable participants

    included SMUD, LADWP, IID, TID, and Caliornia ISO

    representatives. The publicly owned utility panel

    participants described the diculties with the Green

    Path Southwest and Green Path North projects and

    identied the Caliornia ISO tari requirements as

    one reason or the ailure o these projects to go

    orward as joint projects.

    The Caliornia ISO noted that its mission is to ensure

    the ull and ecient use o transmission assets and

    promote inrastructure expansion and development

    to achieve the greatest benets or Caliornia and Cal-

    iornia ISO ratepayers. The Caliornia ISO accomplish-

  • 8/14/2019 Integrated Energy Policy Report 2008

    26/146

    14

    2008 IEPR UPDATEchAPTER 1

    local agencies, stakeholders, and the public in the

    planning process, well beore a route is proposed. In

    addition, local agency participants in the 2007 IEPR

    emphasized their lack o expertise and experience

    with renewable energy development.18 The League o

    Women Voters oered that its 70 local leagues could

    assist local governments in developing energy ele-ments or their general plans.19

    A coordinated and proactive eort to acilitate local

    land use planning or renewable energy-related

    transmission inrastructure would help reduce

    permitting diculties and ensure that local plan-

    ning eorts are inormed by RETI and infuenced by

    the states renewable and greenhouse gas reduction

    strategies, goals, and requirements. For example,

    general plans containing energy and transmission

    elements could establish transmission corridors and

    energy zones that could acilitate the development o

    renewable energy at the local level, particularly in ar-

    eas with the greatest potential or renewable energy.

    Inormed local planning decisions regarding renew-

    able energy development would be coordinated

    with the Energy Commissions Transmission Corridor

    Designation Program in order to preserve transmis-

    sion corridors as necessary.

    However, local agencies generally lack the unds,

    stang, and expertise to carry out coordinated re-

    newable energy, electric transmission, and local level

    land use planning. Thereore, technical and nancial

    assistance to local governments would be required,

    particularly or local governments containing areas

    targeted or renewable development and related

    transmission corridors.

    A priority should be placed on reactivating the

    Energy Commissions Local Agency Siting and Permit

    Assistance Program by re-establishing the Energy

    Resources Programs Account unding pursuant to

    Public Resources Code section 25616.20 This program

    should be employed to assist local governmentswith the development o general plan transmission

    and energy elements that are consistent with RETI,

    recognize the importance o statewide renewable

    and greenhouse gas reduction requirements and

    goals, and are coordinated with the Transmission

    states three IOUs.15 The study identied the need or

    six new 500 kV transmission lines to meet the 33 per-

    cent goal through 2028 to 2030 at an estimated cost

    o about $6.5 billion.16 Although these projects are

    conceptual only and will be rened as the RETI Phase

    1B Drat Resource Reportand Phase 2 results become

    available, they provide stakeholders with a sense othe scope, location, length, size, cost, and timing o

    possible transmission additions needed to meet the

    IOUs portion o a statewide 33 percent renewables

    goal in 12 years.

    However, many o the stakeholders at the workshop

    agreed that environmental and land use barriers are

    generally the biggest obstacles to the timely devel-

    opment o transmission projects. One stakeholder

    characterized the importance o understanding land

    use issues and environmental concerns during the

    transmission planning process this way: [W]e can

    all look at perorming power fows till our aces are

    blue. But the real issue is going to be siting o that

    transmission acility.17

    As noted earlier, in the 2007 Strategic Plan the Energy

    Commission recommended that sta participate

    actively in RETI to ensure the resulting plan or

    preerred renewable resource zones or genera-

    tion and electric transmission inrastructure refects

    environmental, siting, and permitting perspectives.

    The Energy Commission will need to work closely

    with stakeholders during the RETI Phase 2 conceptual

    transmission planning process to ensure that they

    evaluate and consider land use issues and environ-

    mental concerns when planning conceptual projects

    to access renewable resource areas.

    Other stakeholders at the workshop noted that local

    opposition at both individual and institutional levels

    can make it dicult, i not impossible, to permit

    transmission projects that would be necessary to

    meet statewide policy goals. Parties stressed the

    need to educate the public and local governmentson the importance o achieving the states renew-

    able and GHG reduction goals and the dicult

    choices that must be made to accomplish those

    goals. Regarding transmission projects, parties noted

    the need to communicate and work with aected

  • 8/14/2019 Integrated Energy Policy Report 2008

    27/146

    15

    2008 IEPR UPDATEchAPTER 1

    losses. Using renewable resources to meet heating

    and cooling needs can also reduce electricity and

    natural gas loads while also reducing associated

    GHG emissions.

    There are also a number o emerging technologies

    that can help integrate renewables into the electric-ity system, including energy storage technologies,

    better orecasting o variable resources, and tech-

    nologies to improve the operation o the existing

    transmission system.

    In the 2009 IEPR, the Energy Commission intends

    to coordinate its analyses o integration issues with

    other eorts such as the Caliornias ISOs study o

    the operational impacts o integrating 33 percent

    renewables and SCEs Renewable Integration and Ad-

    vancement Project. The Energy Commission will also

    consider the costs o changes needed to integrate

    higher levels o renewables.

    Results ro Prior Integration StudiesAt the IEPR workshops on achieving higher levels

    o renewables, Energy Commission sta summa-

    rized the ndings rom two recent studies on grid

    integration issues: the Energy Commissions 2007

    Intermittency Analysis Project21 and the Consortium

    or Electric Reliability Technology Solutions/Electric

    Power Groups (CERTS/EPG) Renewable Resource In-

    tegration Project Scoping Study o Strategic Transmis-

    sion, Operations, and Reliability Issues.22 The Caliornia

    ISO also discussed its November 2007 study on the

    transmission and operational requirements to meet

    the 20 percent by 2010 renewable goal and plans or

    a study on the requirements to meet a 33 percent

    renewable scenario.

    The Energy Commissions Intermittency Analysis

    Project Final Reportevaluated what is needed or the

    transmission system to accommodate generation

    rom 33 percent renewables by 2020. The Intermit-tency Analysis Project (IAP) evaluated reliability, load

    ollowing capability, voltage support, and regulation,

    among other characteristics, or an assumed resource

    mix o 12,700 MW o wind, 5,100 MW o geother-

    mal, 3,100 MW o concentrating solar power, 2,900

    Corridor Designation Program. It should target local

    governments having the greatest renewable energy

    development potential and the corridors most likely

    to support transmission inrastructure or intercon-

    necting renewable energy development to the states

    electric grid. Funding or this type o land use plan-

    ning would allow local agencies to secure technicalconsultant support with Energy Commission over-

    sight. Reactivation o the Siting and Permit Assistance

    Program should require ull coordination with the

    existing Transmission Corridor Designation Program

    to help acilitate preservation o renewable energy-

    related transmission corridors. It should also require

    ull consideration o RETI results and state renewable

    and greenhouse gas reduction strategy, goals, and

    requirements.

    Addressing Integration BarriersAnother major barrier to increasing the amount o

    renewables in Caliornia is how to integrate large

    amounts o variable resources, like wind and solar,

    into the system while maintaining grid stability, op-

    eration, and reliability. Unexpected drops in energy

    production require quick-start units to cover the

    shortall, while unexpected increases require the abil-

    ity to absorb the unscheduled generation. Procuring

    additional resources to support intermittent renew-

    able resources will be needed, as will better orecast-

    ing techniques or wind and solar generation.

    It is important to remember that not all renewable

    resources are intermittent. Geothermal and biomass

    power plants provide reliable, baseload power and

    can be integrated into the system without any addi-

    tional backup. However, adding large amounts o any

    type o renewables to the system can still be prob-

    lematic because Caliornias local reliability require-

    ments call or load to be met primarily with local

    resources, and many renewable resources are located

    outside the states 10 load centers.

    One way to reduce the impacts o integrating renew-

    ables into the electricity system is through the use

    o distributed resources, which can reduce overall

    load, avoid or deer the need or transmission system

    upgrades, and reduce transmission and distribution

  • 8/14/2019 Integrated Energy Policy Report 2008

    28/146

    16

    2008 IEPR UPDATEchAPTER 1

    the gateways, urther increases in gateway capacity

    would be required.

    The CERTS/EPG study made the ollowing recom-

    mendations:

    Further studies should expand the ocus rom

    evaluating just the interconnection o remote

    renewable resources to the grid to deliver-

    ing that renewable energy all the way to the

    respective load centers.

    Policy makers need to provide guidance on

    resource type and location to allow timely

    integration o renewables and support

    early planning and upgrades o transmission

    gateway capacity and deliverability to load

    centers, aided by the RETI eort currently

    underway.

    Transmission owners and the Caliornia ISO

    need to move the planning horizon out to

    15 to 20 years to dene long-term gateway

    requirements, long-term transmission require-

    ments rom gateways into load centers, and

    interregional transmission requirements.

    Transmission owners and the Caliornia ISO

    need to initiate studies to expand transmis-

    sion gateways and beyond into the load

    centers.

    Policy makers need inormation associated

    with the complete transmission integration

    requirement and cost implications or deliver-

    ing all remote resources (both renewable and

    non-renewable) to the local load centers.

    The Caliornia ISO needs to provide utilities

    and the CPUC with guidance on the resource

    attributes needed or reliable operability o

    the grid.

    The state should evaluate the transmission

    requirements or transer o renewable energy

    rom the L.A. Basin area to San Diego and

    Northern Caliornia.

    MW o solar PV, and 2,000 MW o biomass.23 The

    study ound that with signicant expansion o trans-

    mission by 2020, it is easible to operate the electric-

    ity system with 33 percent renewables. However,

    the study suggests that strategies will be needed to

    address periods o high and low load and ound that

    there may be small additional costs associated withregulation and load ollowing.

    At the July 23, 2008, IEPR sta workshop on trans-

    mission issues, CERTS/EPG presented the results o its

    study to identiy transmission and operating issues

    associated with integrating renewables. CERTS/EPG

    calculated that Caliornia must integrate 20,000 MW

    o renewable capacity additions (relative to a 2006

    base) to meet a statewide goal o 33 percent renew-

    ables by 2020. The study also suggested that 23,000

    MW would be needed to continue to meet the 33

    percent target in 2030 due to increased demand

    between 2020 and 2030. Furthermore, it ound that

    a target o 50 percent renewables by 2030 would

    require 40,000 MW o renewable capacity additions.

    Based on these ndings, the study ocused on a mid-

    range value o 30,000 MW o additional renewables

    by 2030 as a reasonable starting point or examining

    system upgrades that would be necessary under that

    scenario.

    CERTS/EPG observed that more than two-thirds o

    the 30,000 MW o additions would likely require

    delivery to transmission gateways surrounding

    the Los Angeles Basin Area.24 The study concluded

    that gateway capacity would need to be tripled to

    integrate these renewable capacity additions, and

    other transmission links between regions would need

    to be expanded. From an operational perspective,

    local network reinorcements would also be required,

    including line upgrades, ault current limiters, break-

    ers, and remedial action schemes.25 The system

    would also need additional regulation and ramping

    ability, which could be addressed by energy stor-

    age, demand-side management, and automatic loadcontrol. Local voltage support could be enhanced

    by adding capacitors and dynamic voltage control

    devices. In addition, i plants in the Los Angeles Basin

    retire because o air or water restrictions, or i new

    non-renewable generation acilities are built outside

  • 8/14/2019 Integrated Energy Policy Report 2008

    29/146

    17

    2008 IEPR UPDATEchAPTER 1

    generation sources (such as wind and solar) in the

    western interconnection and acilitate the develop-

    ment and implementation o solutions that add

    value to the WECC members. The subcommittee

    will ocus on the regional reliability and market chal-

    lenges o renewable energy integration and other

    emerging issues.

    In addition, the Caliornia ISO suggested that more

    can be done to link renewables with demand side

    and thermal storage strategies. For example, the

    Caliornia ISO would like to see the ability to vary

    compressor loads or chillers in large buildings to

    help address variations in expected generation rom

    wind or other variable renewable resources and sug-

    gested the state take a leadership role in retrotting

    state buildings to provide this capability. This variable

    compressor load should be designed to allow the

    Caliornia ISO to send a signal requesting a buildings

    compressor load to change in response to changes in

    expected generation.28

    Resoure Adequa RequireentsCaliornias resource adequacy requirements are

    intended to ensure uninterrupted electricity service

    to customers. There are two types o requirements,

    planning reserve margins and operating reserve mar-

    gins. Planning reserve marginsare long-term planning

    targets based on either the probability o a loss o

    load or the value o service. These targets are used to

    determine how much capacity is needed to maintain

    real-time operating reserves. Operating reserve mar-

    ginsrelate to the ability to handle system fuctuations

    and disturbances. Operating reserve margins help

    balancing authorities, like the Caliornia ISO, ensure

    that voltage levels are maintained to prevent damage

    to transmission system components and uncontrolled

    cascading outages.29

    Under the CPUC and Caliornia ISO resource ad-

    equacy requirement, each load-serving entity mustdemonstrate that it has enough generating capacity

    to cover 115 percent o expected monthly peak de-

    mand.30 Generating resources have pre-established

    capacity values based on their perormance, known

    as the net qualiying capacity, which is used by load-

    In November 2007, the Caliornia ISO conducted a

    study on operational changes needed to accommo-

    date 20 percent renewables and believes that it can

    accommodate that level.26 According to the Caliornia

    ISO, to achieve higher levels o renewable penetra-

    tion the ollowing areas need urther examination:

    Better wind and solar orecasting capability

    and better communication between orecast-

    ers and Caliornia ISO foor operators.

    Better understanding o the amount o ramp-

    ing and regulation needed.

    Further inormation on the energy storage

    technologies that will be available.

    Changes to the Caliornia ISO market structure

    and taris to incentivize short-term storage or

    regulation fexibility.

    Whether the gas storage system can accom-

    modate rapid swings in conventional genera-

    tion needed to back up renewables, and how

    to quickly communicate the need or addi-

    tional natural gas to the pipeline companies

    in response to weather-related drops in wind

    generation.

    Recent initiatives at the Caliornia ISO and regional

    levels are designed to address many o these issues.

    The Caliornia ISO has initiated its Integration o

    Renewable Resources Program27 with the goal o sup-

    porting the integration o renewable resources into

    the Caliornia power grid to ulll state policy objec-

    tives. The program seeks to leverage the expertise

    and resources o agencies and market participants,

    including the Energy Commission. The program

    will address operational, market, and transmission

    planning issues to meet 20 percent renewables and

    beyond.

    On October 21, 2008, the Joint Guidance Commit-

    tee o the Western Electricity Coordinating Council

    (WECC) established the Variable Generation Sub-

    committee. The purpose o the subcommittee is to

    identiy issues and opportunities related to variable

  • 8/14/2019 Integrated Energy Policy Report 2008

    30/146

    18

    2008 IEPR UPDATEchAPTER 1

    able resources that will need to be integrated into

    the electricity system to meet the 33 percent goal.

    Several parties at the IEPR workshops on renewables

    asserted that there is tremendous opportunity or

    renewable generation at the distribution-level, at or

    near substations and on customer sites, or behind

    the meter. However, most renewable generationrom distributed resources, with the exception o

    acilities that are utility-owned or have specic power

    purchase contracts with a utility,33 are not currently

    eligible or the states RPS, though these technologies

    do reduce retail sales and thereore the amount o

    renewable energy that must be procured to meet

    the RPS. While the CPUC has determined that 100

    percent o the renewable energy credits (RECs) asso-

    ciated with renewable behind the meter distribut-

    ed generation projects belong to the system owners,

    generation rom these systems cannot be counted

    toward RPS obligations until the CPUC authorizes the

    use o tradeable RECs or RPS compliance.

    The Caliornia ISO has noted that when looking at

    a 33 percent goal, it is important to consider the

    contribution rom behind-the-meter distributed solar

    installations that could provide enough energy to

    satisy as much as 5 to 8 percent o that goal. In ad-

    dition, GreenVolts, a developer o photovoltaic (PV)

    systems, reerred to the RETI Phase 1B Drat Resource

    Reportwhich identies the potential or 27,500 MW

    o distributed solar PV projects, assuming 20 MW

    installations could be placed close to existing substa-

    tions.34 These projects could generate nearly 60,000

    GWh annually, which is signicant given that the

    current estimate o 33 percent o retail sales in 2020

    is about 102,000 GWh.

    In written comments submitted or the IEPR sta

    workshop on July 23, 2008, the Alliance or Respon-

    sible Energy Policy also stated that Caliornias rush to

    identiy competitive renewable energy zones and to

    permit new transmission lines has ailed to adequate-

    ly consider distributed generation and demand-sidemanagement alternatives.35

    Distributed generation is a key component o the

    states loading order or meeting new resource

    needs.36 The Caliornia Solar Initiative has a target

    serving entities when shopping around or electricity

    generation to meet resource adequacy requirements.

    Load-serving entities must secure 90 percent o their

    requirements one year ahead, and then demonstrate

    they have acquired the balance o their require-

    ments one month ahead o each calendar month.

    This approach helps ensure that the Caliornia ISOhas enough resources to cover higher than expected

    loads, orced outages, and transmission outages.

    This general ramework has important implications

    or achieving high levels o renewable generation.

    Net qualiying capacity values or generating resourc-

    es like wind and central station solar are established

    using a ormula based on historic perormance rom

    hourly production data.31 For wind resources, these

    values can be low because o the poor t between

    perormance and peak loads.32 A low net qualiying

    capacity value means that load-serving entities will be

    reluctant to select these resources to meet their re-

    newable requirements unless the economic costs and

    benets are better than those o other resource types.

    Another acet o resource adequacy requirements is

    that, beginning in 2007, load-serving entities must

    meet local capacity requirements to ensure that the

    capacity needed by the Caliornia ISO is available in

    10 separate load centers or pockets throughout the

    state. As a general rule, about 75 percent o total

    resource adequacy requirements must be satised

    with resources within these load pockets. Because

    renewable resources are location-specic and oten

    remote, this requirement highlights the disadvan-

    tages o wind, central solar, geothermal, and biomass

    resources outside o these load pockets. Renewable

    developers should thereore be encouraged to locate

    projects where they can meet local capacity require-

    ments, when easible and cost-eective.

    Distributed Renewables

    Distributed renewable resources do not directlyaddress integration issues such as the need or load

    ollowing, ramping, or regulation typically associated

    with higher levels o large-scale renewables. Howev-

    er, distributed resources do reduce overall electricity

    load and thereore the amount o large-scale renew-

  • 8/14/2019 Integrated Energy Policy Report 2008

    31/146

    19

    2008 IEPR UPDATEchAPTER 1

    customer-side renewable resources has received

    much less attention than integrating large central

    station renewable resources, it will be important to

    consider how to address distribution level integration

    o signicant amounts o renewable generation. Also,

    there may be a need or day-ahead and hour-ahead

    solar and wind orecasting at the distribution leveland even the building level and or new market

    mechanisms to eectively value distributed and

    customer-side renewables.

    Renewable Energ heating and coolingLike distributed renewable resources, renewable heat-

    ing and cooling technologies can help reduce overall

    electric loads and thereore the ultimate amount o

    renewable electricity generating resources needed to

    meet Caliornias RPS targets.

    Heating and cooling demands by the industrial,

    commercial, and residential sectors account or 40

    to 50 percent o total global energy use. Around the

    world, renewable heating and cooling technologies

    that use solar, biomass, and geothermal resources are

    used to reduce GHG emissions, electric and natural

    gas use, and ossil uel dependency. Current annual

    GHG emissions in Caliornia rom space, process, and

    water heating and cooling in the commercial, resi-

    dential, and industrial sectors are about 25 percent o

    total statewide GHG emissions.41 Using these technol-

    ogies in Caliornia could thereore provide benets

    beyond reducing electricity loads.

    China accounts or 75 percent o annual solar water

    heating capacity additions, and Germany has in-

    stalled the electric equivalent o nearly 5 GW o solar

    water heaters. In Europe and North America, there

    are more than 2 million ground source heat pumps

    in use, and about 30 percent o houses in Sweden

    have geothermal heat pumps with a combined

    equivalent electric capacity o nearly 4 GW. The solar

    share o Germanys residential space heating marketis approaching 50 percent, while many countries

    and state and local jurisdictions are mandating solar

    water heating or all new residential and commercial

    buildings.

    o 3,000 MW o new solar generating systems in the

    state by 2017.37 In addition, the Governors Bioenergy

    Action Plan calls or meeting 20 percent o the overall

    RPS target with biopower; all o the current biopower

    contribution to the RPS and most o the uture con-

    tribution will come rom power plants smaller than

    50 MW. Many o these acilities, such as landll gasgenerators and digester gas generators, are located

    in load pockets and can be connected at the distribu-

    tion level. Further, the 2007 IEPR recommended that

    all new residential buildings be net-zero energy by

    2020 and all new commercial buildings be net-zero

    energy by 2030. Distributed generation resources are

    necessary to achieve this goal.

    There is also increasing policy attention to the goal o

    sustainable communities. More Caliornia communi-

    ties are considering renewable generation options as

    they explore strategies to become net-zero energy

    communities. Options include solar PV, solar thermal

    electric, biogas, and wind power plants in the 10 to

    50 MW range. Examples o net-zero communities

    using renewable energy already exist in Caliornia on

    university campuses and in the operations o regional

    water agencies. The University o Caliornia at San

    Diego generates most o its own electricity and cold

    water or space cooling o campus buildings and is

    augmenting its natural gas cogeneration combined

    heat and power capacity with solar PV and other

    renewables.38 Likewise, the Inland Empire Utilities

    Agency (IEUA), a regional water agency in San Bernar-

    dino County, recently announced the addition o 2

    MW o PV capacity to its existing 3 MW o biopower

    generated rom dairy manure and ood waste.39

    IEUA is close to serving its total electricity demand

    or pumping and purication cost-eectively rom

    renewable. Many Caliornia schools are also purchas-

    ing renewable electricity rom solar electricity systems

    installed on school roos.40

    Widescale use o renewable generation at the distri-

    bution level could also reduce some reliability andoperational concerns associated with meeting the

    33 percent by 2020 goals by reducing overall load,

    avoiding or deerring transmission system upgrades,

    and reducing transmission and distribution losses.

    However, because integrating distribution level and

  • 8/14/2019 Integrated Energy Policy Report 2008

    32/146

  • 8/14/2019 Integrated Energy Policy Report 2008

    33/146

    21

    2008 IEPR UPDATEchAPTER 1

    Increased Capabilit o Forecasting Tools

    Higher penetration o wind and solar resources re-

    quires improved orecasting tools to inorm electricity

    scheduling and dispatch decisions. Accurate orecasts

    also help address intermittence and unpredictability

    o resources and can increase the value o variable

    resources to the system. The Caliornia ISO has beenusing hour-ahead orecasting or wind resources suc-

    cessully or several years but believes that orecast-

    ing tools need to be expanded to include day-ahead

    orecasting and orecasting capability or solar re-

    sources.47 Toward this end, it is doing in-depth stud-

    ies with three companies to improve wind orecasting

    ability. Research and development in this area should

    ocus on increasing the accuracy and reliability o

    orecasts, expanding orecasting tools to encompass

    solar resources, and working with grid operators to

    understand their needs in displaying orecast results

    to allow real-time decisions to be made.

    Snchrophasor Measurement Technologies

    Phasor Measurement Units48 can collect and report

    critical electrical measurements approximately 30

    times per second, providing inormation about grid

    conditions to system operators so they can make

    time-sensitive decisions. As more renewable re-

    sources are integrated into the grid, operators need

    this kind o technology to respond to unpredicted

    changes in output that are characteristic o so