INSTALLATION + SERVICE - priceindustries.com · UP/UPL: Universal plenum available for CF diffusers...
Transcript of INSTALLATION + SERVICE - priceindustries.com · UP/UPL: Universal plenum available for CF diffusers...
High Capacity Architectural Linear Diffuser Custom Flow Series
v100 – Issue Date: 01/22/18© 2018 Price Industries Limited. All rights reserved.
MANUAL – INSTALLATION + SERVICE
CUSTOM FLOWTABLE OF CONTENTS
Product Overview
Overview .......................................................................1
Before You Start ............................................................1
Getting Started ..............................................................1
Installation & Mounting Instructions
(Surface Mount Drywall Applications)
Type C Mounting
(Concealed Mounting Bracket) ......................................2
Type MP-DR Mounting
(Reversible Drywall Mounting Clip) .................................5
Type A Mounting (Countersunk Holes) ...........................7
Drywall Finishing for CMF Frame ...................................9
Installation & Mounting Instructions
(Tee Bar Lay-In Applications)
General Installation ......................................................10
Field Trimming ..............................................................12
Pattern Controller Adjustment ....................................14
Parts List .......................................................................16
1priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWPRODUCT OVERVIEW
Product OverviewCF: High capacity architectural linear slot air diffuser. Recommended for use in ceiling applications. Also available to be used in sidewall applications.
CFP: Corresponding engineered plenum for CF diffuser.
UP/UPL: Universal plenum available for CF diffusers (low profile option available)
The diffuser/plenum will have one sticker located on the outside of the frame. For ease of troubleshooting assistance, replacement parts, and general factory assistance, it is recommended that the order number and model line string be available for reference. This information can be found on the Factory Label.
Before You StartInspect all cartons and boxes for flaws and shipping damage. If anything is discovered to be damaged, contact the shipping company and file a freight claim.
Getting StartedSTEP 1: Remove CF linear diffuser from shipping carton and inspect for any damage.
STEP 2: Refer to Factory Label to determine the application of the diffuser. For surface mount applications (SM), proceed to STEP 3. For tee bar lay-in applications (LI), proceed to page 10.
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///CMF/XX///C///DPC///BFR//////B12
STEP 3: Refer to Factory Label to determine the diffuser’s mounting option. Use the following table for appropriate reference page for the particular mounting option.
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///CMF/XX///C///DPC///BFR//////B12
Mounting Type Line String Sample Page Number
Concealed Mounting Bracket C 2
Reversible Drywall Mounting Clip MP-DR 5
Countersunk Holes A 7
ORDER NUMBER
LINE STRING
2 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
This section applies to Custom Flow linear diffusers (model CF) for installation in surface mount drywall applications (SM application) in both ceilings and sidewalls.
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///CMF/XX///C///DPC///BFR//////B12
Type C Mounting (Concealed Mounting Bracket)Available frame styles: EF, CMF
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///CMF/XX///C///DPC///BFR//////B12
STEP 1: Ensure that the correct number of concealed mounting bracket kits has been shipped using the following table as reference.
STEP 2: Frame opening. Refer to chart for recommended opening width dimension. If no plenum is used, opening width may be additionally reduced by up to 1/4” (6 mm).
STEP 3: Install plenum (if required). Use price model CFP, UP, UPL, or field built plenum with hemmed edges. Secure plenum to framing or hang from structure as required by local building code. Plenum may be installed flush to framing, or located to be flush with finished drywall.
Diffuser Section Length Kit QTY.
Nom. Length ≤ 24” 2
24” < Nom. Length ≤ 48” 2
48" < Nom. Length ≤ 72" 3
72" < Nom. Length ≤ 96" 3
96” < Nom. Length ≤ 120” 4
Slot Size Slot QTY. Opening Width
1” (25 mm)1 3 3/8” (86 mm)
2 5 11/16” (144 mm)
1 1⁄2” (38 mm)1 4 3/8” (111 mm)
2 7 11/16” (195 mm)
2” (51 mm)1 5 3/8” (137 mm)
2 9 11/16” (246 mm)
2 1⁄2” (64 mm)1 6 3/8" (162 mm)
2 11 11/16” (297 mm)
3” (76 mm)1 7 3/8” (187 mm)
2 13 11/16” (348 mm)
OF REV.SHEET 1 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'C' MOUNTING (CONCEALED MOUNTING BRACKETS).
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP, UP, UPL, OR FIELD BUILD PLENUM WITH HEMMED EDGES. SECURE PLENUM TO FRAMING ORHANG FROM STRUCTURE AS REQUIRED BY LOCAL BUILDING CODE. PLENUM MAY BE INSTALLED FLUSH TO FRAMING, OR LOCATED TO BE FLUSH WITHFINISHED DRYWALL.
STEP 3:INSTALL DRYWALL. IF USING FRAME STYLE EF, FINISH DRYWALL AND PAINT. IF USING FRAME STYLE CMF, DO NOT FINISH DRYWALL UNTIL AFTERINSTALLING DIFFUSER.
IF NO PLENUM IS BEING USED, A LEDGE MAY BE ADDED FOR INSTALLING BRACKET. THIS MAY BE FORMED BY THE DRYWALL, A SHEET METAL HEM ORANGLE, OR METAL STUD FRAMING. IF NO LEDGE IS INSTALLED, BRACKET MAY ALSO BE SCREWED IN PLACE.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSHTO DRYWALL SURFACE
PLENUM EDGE FLUSHTO FRAMING
OF REV.SHEET 1 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'C' MOUNTING (CONCEALED MOUNTING BRACKETS).
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP, UP, UPL, OR FIELD BUILD PLENUM WITH HEMMED EDGES. SECURE PLENUM TO FRAMING ORHANG FROM STRUCTURE AS REQUIRED BY LOCAL BUILDING CODE. PLENUM MAY BE INSTALLED FLUSH TO FRAMING, OR LOCATED TO BE FLUSH WITHFINISHED DRYWALL.
STEP 3:INSTALL DRYWALL. IF USING FRAME STYLE EF, FINISH DRYWALL AND PAINT. IF USING FRAME STYLE CMF, DO NOT FINISH DRYWALL UNTIL AFTERINSTALLING DIFFUSER.
IF NO PLENUM IS BEING USED, A LEDGE MAY BE ADDED FOR INSTALLING BRACKET. THIS MAY BE FORMED BY THE DRYWALL, A SHEET METAL HEM ORANGLE, OR METAL STUD FRAMING. IF NO LEDGE IS INSTALLED, BRACKET MAY ALSO BE SCREWED IN PLACE.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSHTO DRYWALL SURFACE
PLENUM EDGE FLUSHTO FRAMING
OF REV.SHEET 1 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'C' MOUNTING (CONCEALED MOUNTING BRACKETS).
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP, UP, UPL, OR FIELD BUILD PLENUM WITH HEMMED EDGES. SECURE PLENUM TO FRAMING ORHANG FROM STRUCTURE AS REQUIRED BY LOCAL BUILDING CODE. PLENUM MAY BE INSTALLED FLUSH TO FRAMING, OR LOCATED TO BE FLUSH WITHFINISHED DRYWALL.
STEP 3:INSTALL DRYWALL. IF USING FRAME STYLE EF, FINISH DRYWALL AND PAINT. IF USING FRAME STYLE CMF, DO NOT FINISH DRYWALL UNTIL AFTERINSTALLING DIFFUSER.
IF NO PLENUM IS BEING USED, A LEDGE MAY BE ADDED FOR INSTALLING BRACKET. THIS MAY BE FORMED BY THE DRYWALL, A SHEET METAL HEM ORANGLE, OR METAL STUD FRAMING. IF NO LEDGE IS INSTALLED, BRACKET MAY ALSO BE SCREWED IN PLACE.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSHTO DRYWALL SURFACE
PLENUM EDGE FLUSHTO FRAMING
3priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
STEP 4: Install drywall. If using frame style EF, finish drywall and paint. If using frame style CMF, do not finish drywall until after installing diffuser.
If no plenum is being used, a ledge may be added for installing bracket. This may be formed by the drywall (A), a sheet metal hem (B) or angle (C), or metal stud framing (D). If no ledge is installed, bracket may also be screwed in place.
STEP 5: Prepare brackets by inserting one screw through each inner bracket, and pushing rubber grommet down shaft of screw.
STEP 6: Thread outer brackets about 1/4” (6 mm) onto screws.
STEP 7: Install brackets onto diffuser. Deflect side frames and snap brackets under diffuser frame. Brackets are required approximately every 36” (914 mm) to 48” (1219 mm), with one on each end. Ensure that pattern controllers are positioned to the side so that screw may be accessed through diffuser slot.
OF REV.SHEET 1 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'C' MOUNTING (CONCEALED MOUNTING BRACKETS).
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP, UP, UPL, OR FIELD BUILD PLENUM WITH HEMMED EDGES. SECURE PLENUM TO FRAMING ORHANG FROM STRUCTURE AS REQUIRED BY LOCAL BUILDING CODE. PLENUM MAY BE INSTALLED FLUSH TO FRAMING, OR LOCATED TO BE FLUSH WITHFINISHED DRYWALL.
STEP 3:INSTALL DRYWALL. IF USING FRAME STYLE EF, FINISH DRYWALL AND PAINT. IF USING FRAME STYLE CMF, DO NOT FINISH DRYWALL UNTIL AFTERINSTALLING DIFFUSER.
IF NO PLENUM IS BEING USED, A LEDGE MAY BE ADDED FOR INSTALLING BRACKET. THIS MAY BE FORMED BY THE DRYWALL, A SHEET METAL HEM ORANGLE, OR METAL STUD FRAMING. IF NO LEDGE IS INSTALLED, BRACKET MAY ALSO BE SCREWED IN PLACE.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSHTO DRYWALL SURFACE
PLENUM EDGE FLUSHTO FRAMING
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
(A) (B) (C) (D)
1 SLOT 2 SLOT
4 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
STEP 8: Position diffuser in opening. Using a screwdriver, push upward on screw until bracket snaps into place. If diffuser is multiple sections in length, align sections using Y-end splice plates. Tighten screws until frame is flush with drywall.
STEP 9: If using frame style CMF, finish drywall as per page 9.
STEP 10: Adjust pattern controllers for desired air pattern as per page 14 & 15.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
ALIGN DIFFUSER WITH OPENING PUSH UPWARD UNTIL BRACKET SNAPS INTO PLACE
TIGHTEN UNTIL FRAME IS FLUSH WITH DRYWALL
5priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
Type MP-DR Mounting (Reversible Drywall Mounting Clip)Available frame styles: EF, CMF
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///CMF/XX///MP-DR///DPC///BFR//////B12
STEP 1: Ensure that the correct number of reversible drywall mounting clips has been shipped using the following table as reference.
STEP 2: Frame opening. Refer to chart for recommended opening width dimension. If no plenum is used, opening width may be additionally reduced by up to 1/4” (6 mm).
STEP 3: Install plenum (if required). Use Price model CFP, UP, UPL, or field built plenum. Secure plenum to framing or hang from structure as required by local building code. Plenum must be installed flush to framing.
Diffuser Section Length Clip QTY.
Nom. Length ≤ 24” 4
24” < Nom. Length ≤ 48” 6
48" < Nom. Length ≤ 72" 8
72" < Nom. Length ≤ 96" 10
96” < Nom. Length ≤ 120” 12
Slot Size Slot QTY. Opening Width
1” (25 mm)1 3 3/8” (86 mm)
2 5 11/16” (144 mm)
1 1⁄2” (38 mm)1 4 3/8” (111 mm)
2 7 11/16” (195 mm)
2” (51 mm)1 5 3/8” (137 mm)
2 9 11/16” (246 mm)
2 1⁄2” (64 mm)1 6 3/8" (162 mm)
2 11 11/16” (297 mm)
3” (76 mm)1 7 3/8” (187 mm)
2 13 11/16” (348 mm)
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE MP-DR MOUNTING
II00061
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOWTYPE MP-DR MOUNTING
2018/01/03
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP,UP, UPL, OR FIELD BUILD PLENUM. SECURE PLENUM TOFRAMING OR HANG FROM STRUCTURE AS REQUIRED BYLOCAL BUILDING CODE. PLENUM MUST BE INSTALLEDFLUSH TO FRAMING.
STEP 4:IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSH TO FRAMING(PLENUM EDGE MAY BE HEMMED OR FLAT)
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'MP-DR' MOUNTING (REVERSIBLE DRYWALL MOUNTING CLIP). DIFFUSER INSTALLATION IS TO BE DONE PRIOR TO DRYWALLINSTALLATION.
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
STEP 3:SCREW DRYWALL MOUNTING CLIPS TO FRAMING. MOUNTING CLIPS SHOULD BELOCATED AT LEAST EVERY 24" (610). CLIPS MAY BE REVERSED TO ALLOW FOREITHER 5/8" (16) OR 1/2" (13) DRYWALL.
2X Y-ENDSPLICE PLATE
USE THIS ORIENTATIONFOR 5/8" DRYWALL
USE THIS ORIENTATIONFOR 1/2" DRYWALL
OF REV.SHEET 1 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'C' MOUNTING (CONCEALED MOUNTING BRACKETS).
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP, UP, UPL, OR FIELD BUILD PLENUM WITH HEMMED EDGES. SECURE PLENUM TO FRAMING ORHANG FROM STRUCTURE AS REQUIRED BY LOCAL BUILDING CODE. PLENUM MAY BE INSTALLED FLUSH TO FRAMING, OR LOCATED TO BE FLUSH WITHFINISHED DRYWALL.
STEP 3:INSTALL DRYWALL. IF USING FRAME STYLE EF, FINISH DRYWALL AND PAINT. IF USING FRAME STYLE CMF, DO NOT FINISH DRYWALL UNTIL AFTERINSTALLING DIFFUSER.
IF NO PLENUM IS BEING USED, A LEDGE MAY BE ADDED FOR INSTALLING BRACKET. THIS MAY BE FORMED BY THE DRYWALL, A SHEET METAL HEM ORANGLE, OR METAL STUD FRAMING. IF NO LEDGE IS INSTALLED, BRACKET MAY ALSO BE SCREWED IN PLACE.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSHTO DRYWALL SURFACE
PLENUM EDGE FLUSHTO FRAMING
6 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
STEP 4: Screw drywall mounting clips to framing. Mounting clips should be located at least every 24” (610 mm). Clips may be reversed to allow for either 5/8” (16 mm) or 1/2” (13 mm) drywall.
STEP 5: If diffuser is multiple sections in length, continue installing sections while aligning sections using Y-end splice plates.
STEP 6: Install drywall by sliding behind diffuser face and fastening to framing. For easiest installation, slide tapered edge of sheet behind diffuser face.
STEP 7: Finish and paint drywall. If using frame style CMF, finish drywall as per page 9.
STEP 8: Adjust pattern controllers for desired air pattern as per page 14 & 15.
OF REV.SHEET 2 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE MP-DR MOUNTING
II00061
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOWTYPE MP-DR MOUNTING
2018/01/03
STEP 5:INSTALL DRYWALL BY SLIDING BEHIND DIFFUSER FACE AND FASTENING TO CEILING FRAMING. FOR EASIEST INSTALLATION, SLIDE TAPERED EDGE OFSHEET BEHIND DIFFUSER FACE.
PARTS LIST:
DESCRIPTION PART NUMBER
Y-END SPLICE PLATE 255152-001
REVERSIBLE DRYWALL MOUNTING CLIP
255149-001
STEP 6:FINISH AND PAINT DRYWALL. IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTION II00030.
STEP 7:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATION INSTRUCTION II00040.
DIFFUSER SECTION LENGTH CLIP QTY.≤ 24" 4
24" ≤ 48" 648" ≤ 72" 872" ≤ 96" 10
96" ≤ 120" 12
REVERSIBLE DRYWALL MOUNTING CLIP QUANTITY:
OF REV.SHEET 2 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE MP-DR MOUNTING
II00061
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOWTYPE MP-DR MOUNTING
2018/01/03
STEP 5:INSTALL DRYWALL BY SLIDING BEHIND DIFFUSER FACE AND FASTENING TO CEILING FRAMING. FOR EASIEST INSTALLATION, SLIDE TAPERED EDGE OFSHEET BEHIND DIFFUSER FACE.
PARTS LIST:
DESCRIPTION PART NUMBER
Y-END SPLICE PLATE 255152-001
REVERSIBLE DRYWALL MOUNTING CLIP
255149-001
STEP 6:FINISH AND PAINT DRYWALL. IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTION II00030.
STEP 7:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATION INSTRUCTION II00040.
DIFFUSER SECTION LENGTH CLIP QTY.≤ 24" 4
24" ≤ 48" 648" ≤ 72" 872" ≤ 96" 10
96" ≤ 120" 12
REVERSIBLE DRYWALL MOUNTING CLIP QUANTITY:
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE MP-DR MOUNTING
II00061
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOWTYPE MP-DR MOUNTING
2018/01/03
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP,UP, UPL, OR FIELD BUILD PLENUM. SECURE PLENUM TOFRAMING OR HANG FROM STRUCTURE AS REQUIRED BYLOCAL BUILDING CODE. PLENUM MUST BE INSTALLEDFLUSH TO FRAMING.
STEP 4:IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSH TO FRAMING(PLENUM EDGE MAY BE HEMMED OR FLAT)
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'MP-DR' MOUNTING (REVERSIBLE DRYWALL MOUNTING CLIP). DIFFUSER INSTALLATION IS TO BE DONE PRIOR TO DRYWALLINSTALLATION.
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
STEP 3:SCREW DRYWALL MOUNTING CLIPS TO FRAMING. MOUNTING CLIPS SHOULD BELOCATED AT LEAST EVERY 24" (610). CLIPS MAY BE REVERSED TO ALLOW FOREITHER 5/8" (16) OR 1/2" (13) DRYWALL.
2X Y-ENDSPLICE PLATE
USE THIS ORIENTATIONFOR 5/8" DRYWALL
USE THIS ORIENTATIONFOR 1/2" DRYWALL
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE MP-DR MOUNTING
II00061
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOWTYPE MP-DR MOUNTING
2018/01/03
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP,UP, UPL, OR FIELD BUILD PLENUM. SECURE PLENUM TOFRAMING OR HANG FROM STRUCTURE AS REQUIRED BYLOCAL BUILDING CODE. PLENUM MUST BE INSTALLEDFLUSH TO FRAMING.
STEP 4:IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSH TO FRAMING(PLENUM EDGE MAY BE HEMMED OR FLAT)
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'MP-DR' MOUNTING (REVERSIBLE DRYWALL MOUNTING CLIP). DIFFUSER INSTALLATION IS TO BE DONE PRIOR TO DRYWALLINSTALLATION.
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
STEP 3:SCREW DRYWALL MOUNTING CLIPS TO FRAMING. MOUNTING CLIPS SHOULD BELOCATED AT LEAST EVERY 24" (610). CLIPS MAY BE REVERSED TO ALLOW FOREITHER 5/8" (16) OR 1/2" (13) DRYWALL.
2X Y-ENDSPLICE PLATE
USE THIS ORIENTATIONFOR 5/8" DRYWALL
USE THIS ORIENTATIONFOR 1/2" DRYWALL
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
OF REV.SHEET 1 1 0
MPCFIELD INSTALLATION
INSTRUCTIONSIIxxxxx
© Copyright PRICE INDUSTRIES 2011
Installation InstructionsTITLE
2009/mm/dd
OF REV.SHEET 1 1 0
MPCFIELD INSTALLATION
INSTRUCTIONSIIxxxxx
© Copyright PRICE INDUSTRIES 2011
Installation InstructionsTITLE
2009/mm/dd
USE THIS ORIENTATION FOR 5/8” DRYWALL
USE THIS ORIENTATION FOR 1/2” DRYWALL
7priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
Type A Mouting (Countersunk Holes)Available frame styles: CMF
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///CMF/XX///A///DPC///BFR//////B12
STEP 1: Frame ceiling opening. Refer to chart for recommended opening width dimension. If no plenum is used, opening width may be additionally reduced by up to 1/4” (6 mm).
STEP 2: Install plenum (if required). Use price model CFP, UP, UPL, or field built plenum. Secure plenum to framing or hang from structure as required by local building code. Plenum may be installed flush to framing, or located to be flush with finished drywall.
STEP 3: Install drywall. For best finish, use tapered edges of drywall around opening. Do not finish drywall until after installing diffuser.
STEP 4: Install diffuser into opening using drywall screws.
Slot Size Slot QTY. Opening Width
1” (25 mm)1 3 3/8” (86 mm)
2 5 11/16” (144 mm)
1 1⁄2” (38 mm)1 4 3/8” (111 mm)
2 7 11/16” (195 mm)
2” (51 mm)1 5 3/8” (137 mm)
2 9 11/16” (246 mm)
2 1⁄2” (64 mm)1 6 3/8" (162 mm)
2 11 11/16” (297 mm)
3” (76 mm)1 7 3/8” (187 mm)
2 13 11/16” (348 mm)
OF REV.SHEET 1 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'C' MOUNTING (CONCEALED MOUNTING BRACKETS).
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP, UP, UPL, OR FIELD BUILD PLENUM WITH HEMMED EDGES. SECURE PLENUM TO FRAMING ORHANG FROM STRUCTURE AS REQUIRED BY LOCAL BUILDING CODE. PLENUM MAY BE INSTALLED FLUSH TO FRAMING, OR LOCATED TO BE FLUSH WITHFINISHED DRYWALL.
STEP 3:INSTALL DRYWALL. IF USING FRAME STYLE EF, FINISH DRYWALL AND PAINT. IF USING FRAME STYLE CMF, DO NOT FINISH DRYWALL UNTIL AFTERINSTALLING DIFFUSER.
IF NO PLENUM IS BEING USED, A LEDGE MAY BE ADDED FOR INSTALLING BRACKET. THIS MAY BE FORMED BY THE DRYWALL, A SHEET METAL HEM ORANGLE, OR METAL STUD FRAMING. IF NO LEDGE IS INSTALLED, BRACKET MAY ALSO BE SCREWED IN PLACE.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSHTO DRYWALL SURFACE
PLENUM EDGE FLUSHTO FRAMING
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE MP-DR MOUNTING
II00061
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOWTYPE MP-DR MOUNTING
2018/01/03
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP,UP, UPL, OR FIELD BUILD PLENUM. SECURE PLENUM TOFRAMING OR HANG FROM STRUCTURE AS REQUIRED BYLOCAL BUILDING CODE. PLENUM MUST BE INSTALLEDFLUSH TO FRAMING.
STEP 4:IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSH TO FRAMING(PLENUM EDGE MAY BE HEMMED OR FLAT)
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) AND CMF (CONCEALED MUDFRAME), AND WITH TYPE 'MP-DR' MOUNTING (REVERSIBLE DRYWALL MOUNTING CLIP). DIFFUSER INSTALLATION IS TO BE DONE PRIOR TO DRYWALLINSTALLATION.
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING FOR FRAME STYLE CMF, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
STEP 3:SCREW DRYWALL MOUNTING CLIPS TO FRAMING. MOUNTING CLIPS SHOULD BELOCATED AT LEAST EVERY 24" (610). CLIPS MAY BE REVERSED TO ALLOW FOREITHER 5/8" (16) OR 1/2" (13) DRYWALL.
2X Y-ENDSPLICE PLATE
USE THIS ORIENTATIONFOR 5/8" DRYWALL
USE THIS ORIENTATIONFOR 1/2" DRYWALL
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE A MOUNTING
II00062
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE A MOUNTING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES CMF (CONCEALED MUD FRAME), AND WITH TYPE 'A'MOUNTING (COUNTERSUNK SCREW HOLES).
FOR INSTRUCTIONS ON COMPLETING DRYWALL TAPING AFTER INSTALLING DIFFUSER, SEE INSTALLATION INSTRUCTION II00030.
STEP 1:FRAME CEILING OPENING. REFER TO CHART FOR RECOMMENDED OPENING WIDTH DIMENSION.
SLOT SIZE SLOT QTY.1212121212
7 3⁄8" (187)13 11⁄16" (348)
3" (76)
OPENING WIDTH
1" (25)
1 1⁄2" (38)
2" (51)
2 1⁄2" (64)
3 3⁄8" (86)5 11⁄16" (144)4 3⁄8" (111)
7 11⁄16" (195)5 3⁄8" (137)
9 11⁄16" (246)6 3⁄8" (162)
11 11⁄16" (297)
STEP 2:INSTALL PLENUM (IF REQUIRED). USE PRICE MODEL CFP, UP, UPL, OR FIELD BUILD PLENUM. SECURE PLENUM TO FRAMING OR HANG FROM STRUCTUREAS REQUIRED BY LOCAL BUILDING CODE. PLENUM MAY BE INSTALLED FLUSH TO FRAMING, OR LOCATED TO BE FLUSH WITH FINISHED DRYWALL.
STEP 3:INSTALL DRYWALL. FOR BEST FINISH, USE TAPERED EDGES OF DRYWALL AROUND OPENING. DO NOT FINISH DRYWALL UNTIL AFTER INSTALLINGDIFFUSER.
OPENING LENGTH = NOMINAL SIZE
OPENINGWIDTH
PLENUM EDGE FLUSH TO DRYWALL SURFACE(PLENUM EDGE MAY BE HEMMED OR FLAT)
PLENUM EDGE FLUSH TO FRAMING(PLENUM EDGE MAY BE HEMMED OR FLAT)
OF REV.SHEET 2 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE A MOUNTING
II00062
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE A MOUNTING
2018/01/03
STEP 4:INSTALL DIFFUSER INTO CEILING USING DRYWALL SCREWS.
STEP 5:IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
2X Y-ENDSPLICE PLATE
STEP 6:FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTION II00030.
STEP7:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATION INSTRUCTION II00040.
PARTS LIST:
DESCRIPTION PART NUMBERY-END SPLICE PLATE 255152-001
OF REV.SHEET 2 2 0
CFINSTALLATION
INSTRUCTIONS
TYPE A MOUNTING
II00062
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE A MOUNTING
2018/01/03
STEP 4:INSTALL DIFFUSER INTO CEILING USING DRYWALL SCREWS.
STEP 5:IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
2X Y-ENDSPLICE PLATE
STEP 6:FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTION II00030.
STEP7:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATION INSTRUCTION II00040.
PARTS LIST:
DESCRIPTION PART NUMBERY-END SPLICE PLATE 255152-001
8 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
STEP 5: If diffuser is multiple sections in length, continue installing sections while aligning sections using Y-end splice plates.
STEP 6: Finish drywall as per page 9.
STEP 7: Adjust pattern controllers for desired air pattern as per page 14 & 15.
OF REV.SHEET 2 3 0
CFINSTALLATION
INSTRUCTIONS
TYPE C MOUNTING
II00060
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
TYPE C MOUNTING
2018/01/03
STEP 4:PREPARE BRACKETS BY INSERTING ONE SCREW THROUGH EACHINNER BRACKET, AND PUSHING RUBBER GROMMET DOWN SHAFT OFSCREW. OUTER BRACKET
STEP 5:THREAD OUTER BRACKETS ABOUT 1/4" (6) ONTO SCREWS.
INNER BRACKET
STEP 6:INSTALL BRACKETS ONTO DIFFUSER. DEFLECT SIDE FRAMES AND SNAP BRACKETS UNDER DIFFUSER FRAME. BRACKETS ARE REQUIREDAPPROXIMATELY EVERY 36" (914) TO 48" (1219), WITH ONE ON EACH END. ENSURE THAT PATTERN CONTROLLERS ARE POSITIONED TO THE SIDESO THAT SCREW MAY BE ACCESSED THROUGH DIFFUSER SLOT.
STEP 7:POSITION DIFFUSER IN CEILING. USING A SCREWDRIVER, PUSH UPWARD ON SCREW UNTIL BRACKET SNAPS INTO PLACE. IF DIFFUSER IS MULTIPLESECTIONS IN LENGTH, ALIGN SECTIONS USING Y-END SPLICE PLATES. TIGHTEN SCREWS UNTIL FRAME IS FLUSH WITH THE CEILING.
1 SLOT 2 SLOT
2X Y-ENDSPLICE PLATE
STEP 8:IF USING FRAME STYLE CMF, FINISH DRYWALL CEILING AS PER INSTALLATION INSTRUCTIONII00065.
STEP 9:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATIONINSTRUCTION II00064.
9priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (SURFACE MOUNT DRYWALL APPLICATIONS)
Drywall Finishing for CMF FrameAvailable frame styles: CMF
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///CMF/XX///C///DPC///BFR//////B12
NOTE: Before finishing drywall, install CF diffuser. For installation of CF diffusers:
· See page 2 (C mounting)
· See page 5 (MP-DR mounting)
· See page 7 (A mounting)
STEP 1: Thoroughly clean diffuser flanges to remove any oils or residue from surface.
STEP 2: Apply one coat of bonding agent over entire surface of flange, and allow to dry as per manufacturer’s instructions.
STEP 3: Apply one coat of drywall compound on diffuser flanges and approximately 3” (76 mm) onto drywall beyond flange.
STEP 4: Apply a 4” (102 mm) wide mesh or paper tape to joint compound. Be sure to smooth out and remove air pockets. Mesh or tape should cover diffuser flange, but not extend onto inside vertical edge of diffuser frame. Apply second coat of drywall compound over tape and smooth. Allow to dry.
STEP 5: Apply at least two coats of finishing compound. Allow to dry. Afterwards, sand smooth, prime, and paint surface.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
MUD-IN FRAME
II00065
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
MUD-IN FRAME
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO FINISHING DRYWALL AFTER INSTALLING CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) WITH FRAME STYLE CMF(CONCEALED MUD FRAME).
BEFORE FINISHING DRYWALL, INSTALL CF DIFFUSER. FOR INSTALLATION OF CF DIFFUSERS:• SEE INSTALLATION INSTRUCTION II00060 (C MOUNTING)• SEE INSTALLATION INSTRUCTION II00061 (MP-DR MOUNTING)• SEE INSTALLATION INSTRUCTION II00062 (A MOUNTING)
STEP 1:THOROUGHLY CLEAN DIFFUSER FLANGES TO REMOVE ANY OILS OR RESIDUE FROM SURFACE.
STEP 2:APPLY ONE COAT OF BONDING AGENT OVER ENTIRE SURFACE OF FLANGE, AND ALLOW TO DRY AS PER MANUFACTURER'S INSTRUCTIONS.
STEP 3:APPLY ONE COAT OF DRYWALL COMPOUND ON DIFFUSER FLANGES AND APPROXIMATELY 3" (76) ONTO DRYWALL BEYOND FLANGE.
STEP 4:APPLY A 4" (102) WIDE MESH OR PAPER TAPE TO JOINT COMPOUND. BE SURE TO SMOOTH OUT AND REMOVE AIR POCKETS. MESH OR TAPE SHOULDCOVER DIFFUSER FLANGE, BUT NOT EXTEND ONTO INSIDE VERTICAL EDGE OF DIFFUSER FRAME. APPLY SECOND COAT OF DRYWALL COMPOUND OVERTAPE AND SMOOTH. ALLOW TO DRY.
STEP 5:APPLY AT LEAST TWO COATS OF FINISHING COMPOUND. ALLOW TO DRY. AFTERWARDS, SAND SMOOTH, PRIME, AND PAINT SURFACE.
BONDING AGENT
ONE COATDRYWALL COMPOUND
MESH OR DRYWALL TAPE
TOP COAT LAYERSDRYWALL COMPOUND
FRAME CONCEALED BYDRYWALL COMPOUND
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
MUD-IN FRAME
II00065
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
MUD-IN FRAME
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO FINISHING DRYWALL AFTER INSTALLING CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) WITH FRAME STYLE CMF(CONCEALED MUD FRAME).
BEFORE FINISHING DRYWALL, INSTALL CF DIFFUSER. FOR INSTALLATION OF CF DIFFUSERS:• SEE INSTALLATION INSTRUCTION II00060 (C MOUNTING)• SEE INSTALLATION INSTRUCTION II00061 (MP-DR MOUNTING)• SEE INSTALLATION INSTRUCTION II00062 (A MOUNTING)
STEP 1:THOROUGHLY CLEAN DIFFUSER FLANGES TO REMOVE ANY OILS OR RESIDUE FROM SURFACE.
STEP 2:APPLY ONE COAT OF BONDING AGENT OVER ENTIRE SURFACE OF FLANGE, AND ALLOW TO DRY AS PER MANUFACTURER'S INSTRUCTIONS.
STEP 3:APPLY ONE COAT OF DRYWALL COMPOUND ON DIFFUSER FLANGES AND APPROXIMATELY 3" (76) ONTO DRYWALL BEYOND FLANGE.
STEP 4:APPLY A 4" (102) WIDE MESH OR PAPER TAPE TO JOINT COMPOUND. BE SURE TO SMOOTH OUT AND REMOVE AIR POCKETS. MESH OR TAPE SHOULDCOVER DIFFUSER FLANGE, BUT NOT EXTEND ONTO INSIDE VERTICAL EDGE OF DIFFUSER FRAME. APPLY SECOND COAT OF DRYWALL COMPOUND OVERTAPE AND SMOOTH. ALLOW TO DRY.
STEP 5:APPLY AT LEAST TWO COATS OF FINISHING COMPOUND. ALLOW TO DRY. AFTERWARDS, SAND SMOOTH, PRIME, AND PAINT SURFACE.
BONDING AGENT
ONE COATDRYWALL COMPOUND
MESH OR DRYWALL TAPE
TOP COAT LAYERSDRYWALL COMPOUND
FRAME CONCEALED BYDRYWALL COMPOUND
10 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (TEE BAR LAY-IN APPLICATIONS)
This section applies to Custom Flow linear diffusers (model CF) for installation in continuous runs in suspended tee bar ceiling applications (LI application).
Sample line string: CF//I/IN//AS/1/48.000/1/SS//LI///EF/XX///HB///DPC///BFR//////B12
General InstallationSTEP 1: Refer to Factory Label to determine the diffuser has been ordered with the hanger bracket option.
Sample line string: CF//I/IN//AS/1/48.000/1/SS//LI///EF/XX///HB///DPC///BFR//////B12
If hanger bracket option has been ordered, ensure that the correct number of hanger has been shipped using the following table as reference.
STEP 2: Install perimeter wall angle for ceiling system. Main and cross tee installation may also proceed, except for any cross tees that will rest on the back of diffuser face.
STEP 3: Install plenum (if required) to diffuser using sheet metal screws as shown. Space sheet metal screws approximately every 12” (305 mm). This step may be skipped, but is recommended to be completed first.
STEP 4: Determine preferred type of installation. Diffuser may be installed by suspending from ceiling structure using hanger wire or by resting on top of T-bar. For suspended ceiling installation, proceed to STEP 5A. For resting on top of T-bar, proceed to STEP 5B.
Diffuser Section Length Kit QTY.
Nom. Length ≤ 24” 2
24” < Nom. Length ≤ 48” 2
48" < Nom. Length ≤ 72" 3
72" < Nom. Length ≤ 96" 3
96” < Nom. Length ≤ 120” 4
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
LI APPLICATION
II00063
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
LI APPLICATION
2018/01/03
STEP 2:INSTALL PLENUM (IF REQUIRED) TO DIFFUSER USING SHEET METAL SCREWS AS SHOWN. SPACE SHEET METAL SCREWS APPROXIMATELY EVERY 12" (305).
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) FOR INSTALLATION INCONTINUOUS RUNS IN SUSPENDED T-BAR CEILING APPLICATIONS (LI APPLICATION).
STEP 1:INSTALL PERIMETER WALL ANGLE FOR CEILING SYSTEM. MAIN AND CROSS TEE INSTALLATION MAY ALSO PROCEED, EXCEPT FOR ANY CROSS TEES THATWILL REST ON THE BACK OF DIFFUSER FACE.
STEP 3A:SUSPEND DIFFUSER/PLENUM SECTIONS USING HANGER WIRE THROUGH HANGER BRACKETS OR THROUGH HANGER HOLES ON TOP OF PLENUM. HANGARBRACKETS SHOULD BE LOCATED AT LEAST EVERY 24" (610).IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
ENSURE TO ADJUST HANGER WIRES TO MAKE DIFFUSERS HANG LEVEL.
2X Y-ENDSPLICE PLATE
2X Y-ENDSPLICE PLATE
PERIMETERWALL ANGLE
HANGER WIRE
HANGER BRACKETS
11priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWINSTALLATION & MOUNTING INSTRUCTIONS (TEE BAR LAY-IN APPLICATIONS)
STEP 5A: Suspend diffuser/plenum sections using hanger wire through hanger brackets or through hanger holes on top of plenum. Alternatively, if no hanger brackets have been ordered, sheet metal screws may be drilled into diffuser side frame. Hanger brackets/screws should be located at least every 24” (610 mm). Screw hanger brackets in place using sheet metal screws in order to prevent shifting. If diffuser is multiple sections in length, continue installing sections while aligning sections using Y-end splice plates. Ensure to adjust hanger wires to make diffusers hang level.
STEP 5B: Install two main tees to run along either side of diffuser and drop diffuser in place.
STEP 6: Attach plenum to diffuser if not already done so. Hang or secure plenum to structure as required by local building codes.
STEP 7: Complete T-bar installation. Cross tees may rest on diffuser flange, or cut flush and attached using sheet metal angles, as shown.
STEP 8: Install ceiling tiles.
STEP 9: Adjust pattern controllers for desired air pattern as per page 14 & 15.
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
LI APPLICATION
II00063
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
LI APPLICATION
2018/01/03
STEP 2:INSTALL PLENUM (IF REQUIRED) TO DIFFUSER USING SHEET METAL SCREWS AS SHOWN. SPACE SHEET METAL SCREWS APPROXIMATELY EVERY 12" (305).
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) FOR INSTALLATION INCONTINUOUS RUNS IN SUSPENDED T-BAR CEILING APPLICATIONS (LI APPLICATION).
STEP 1:INSTALL PERIMETER WALL ANGLE FOR CEILING SYSTEM. MAIN AND CROSS TEE INSTALLATION MAY ALSO PROCEED, EXCEPT FOR ANY CROSS TEES THATWILL REST ON THE BACK OF DIFFUSER FACE.
STEP 3A:SUSPEND DIFFUSER/PLENUM SECTIONS USING HANGER WIRE THROUGH HANGER BRACKETS OR THROUGH HANGER HOLES ON TOP OF PLENUM. HANGARBRACKETS SHOULD BE LOCATED AT LEAST EVERY 24" (610).IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
ENSURE TO ADJUST HANGER WIRES TO MAKE DIFFUSERS HANG LEVEL.
2X Y-ENDSPLICE PLATE
2X Y-ENDSPLICE PLATE
PERIMETERWALL ANGLE
HANGER WIRE
HANGER BRACKETS
OF REV.SHEET 1 2 0
CFINSTALLATION
INSTRUCTIONS
LI APPLICATION
II00063
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
LI APPLICATION
2018/01/03
STEP 2:INSTALL PLENUM (IF REQUIRED) TO DIFFUSER USING SHEET METAL SCREWS AS SHOWN. SPACE SHEET METAL SCREWS APPROXIMATELY EVERY 12" (305).
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF), WITH FRAME STYLES EF (EXPOSED FRAME) FOR INSTALLATION INCONTINUOUS RUNS IN SUSPENDED T-BAR CEILING APPLICATIONS (LI APPLICATION).
STEP 1:INSTALL PERIMETER WALL ANGLE FOR CEILING SYSTEM. MAIN AND CROSS TEE INSTALLATION MAY ALSO PROCEED, EXCEPT FOR ANY CROSS TEES THATWILL REST ON THE BACK OF DIFFUSER FACE.
STEP 3A:SUSPEND DIFFUSER/PLENUM SECTIONS USING HANGER WIRE THROUGH HANGER BRACKETS OR THROUGH HANGER HOLES ON TOP OF PLENUM. HANGARBRACKETS SHOULD BE LOCATED AT LEAST EVERY 24" (610).IF DIFFUSER IS MULTIPLE SECTIONS IN LENGTH, CONTINUE INSTALLING SECTIONS WHILE ALIGNING SECTIONS USING Y-END SPLICE PLATES.
ENSURE TO ADJUST HANGER WIRES TO MAKE DIFFUSERS HANG LEVEL.
2X Y-ENDSPLICE PLATE
2X Y-ENDSPLICE PLATE
PERIMETERWALL ANGLE
HANGER WIRE
HANGER BRACKETS
OF REV.SHEET 2 2 0
CFINSTALLATION
INSTRUCTIONS
LI APPLICATION
II00063
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
LI APPLICATION
2018/01/03
PARTS LIST:
DESCRIPTION PART NUMBERHANGER BRACKET 269639-001
Y-END SPLICE PLATE 255152-001
DIFFUSER SECTION LENGTH BRACKET QTY.≤ 24" 4
24" ≤ 48" 648" ≤ 72" 872" ≤ 96" 10
96" ≤ 120" 12
HANGER BRACKET QUANTITY:
STEP 3B:DIFFUSER CAN ALSO BE INSTALLED BY RESTING IT ON TWO TEES RUNNING ON EITHER SIDE OF DIFFUSER.
STEP 4:ATTACH PLENUM TO DIFFUSER IF NOT ALREADY DONE SO. HANG OR SECURE PLENUM TO STRUCTURE AS REQUIRED BY LOCAL BUILDING CODES.
STEP 5:COMPLETE T-BAR INSTALLATION. CROSS TEES MAY REST ON DIFFUSER FLANGE, OR CUT FLUSH AND ATTACHED USING SHEET METAL ANGLES, ASSHOWN.
STEP 6:INSTALL CIELING TILES.
STEP 7:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATION INSTRUCTION II00040.
TEE RESTING ONDIFFUSER FLANGE
TEE FLUSH TODIFFUSER FACE
MOUNTING ANGLES (BY OTHERS)FOR FLUSH TEE
TEE RESTING ONDIFFUSER FLANGE
OF REV.SHEET 2 2 0
CFINSTALLATION
INSTRUCTIONS
LI APPLICATION
II00063
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
LI APPLICATION
2018/01/03
PARTS LIST:
DESCRIPTION PART NUMBERHANGER BRACKET 269639-001
Y-END SPLICE PLATE 255152-001
DIFFUSER SECTION LENGTH BRACKET QTY.≤ 24" 4
24" ≤ 48" 648" ≤ 72" 872" ≤ 96" 10
96" ≤ 120" 12
HANGER BRACKET QUANTITY:
STEP 3B:DIFFUSER CAN ALSO BE INSTALLED BY RESTING IT ON TWO TEES RUNNING ON EITHER SIDE OF DIFFUSER.
STEP 4:ATTACH PLENUM TO DIFFUSER IF NOT ALREADY DONE SO. HANG OR SECURE PLENUM TO STRUCTURE AS REQUIRED BY LOCAL BUILDING CODES.
STEP 5:COMPLETE T-BAR INSTALLATION. CROSS TEES MAY REST ON DIFFUSER FLANGE, OR CUT FLUSH AND ATTACHED USING SHEET METAL ANGLES, ASSHOWN.
STEP 6:INSTALL CIELING TILES.
STEP 7:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATION INSTRUCTION II00040.
TEE RESTING ONDIFFUSER FLANGE
TEE FLUSH TODIFFUSER FACE
MOUNTING ANGLES (BY OTHERS)FOR FLUSH TEE
TEE RESTING ONDIFFUSER FLANGE
OF REV.SHEET 2 2 0
CFINSTALLATION
INSTRUCTIONS
LI APPLICATION
II00063
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
LI APPLICATION
2018/01/03
PARTS LIST:
DESCRIPTION PART NUMBERHANGER BRACKET 269639-001
Y-END SPLICE PLATE 255152-001
DIFFUSER SECTION LENGTH BRACKET QTY.≤ 24" 4
24" ≤ 48" 648" ≤ 72" 872" ≤ 96" 10
96" ≤ 120" 12
HANGER BRACKET QUANTITY:
STEP 3B:DIFFUSER CAN ALSO BE INSTALLED BY RESTING IT ON TWO TEES RUNNING ON EITHER SIDE OF DIFFUSER.
STEP 4:ATTACH PLENUM TO DIFFUSER IF NOT ALREADY DONE SO. HANG OR SECURE PLENUM TO STRUCTURE AS REQUIRED BY LOCAL BUILDING CODES.
STEP 5:COMPLETE T-BAR INSTALLATION. CROSS TEES MAY REST ON DIFFUSER FLANGE, OR CUT FLUSH AND ATTACHED USING SHEET METAL ANGLES, ASSHOWN.
STEP 6:INSTALL CIELING TILES.
STEP 7:ADJUST PATTERN CONTROLLERS FOR DESIRED AIR PATTERN AS PER INSTALLATION INSTRUCTION II00040.
TEE RESTING ONDIFFUSER FLANGE
TEE FLUSH TODIFFUSER FACE
MOUNTING ANGLES (BY OTHERS)FOR FLUSH TEE
TEE RESTING ONDIFFUSER FLANGE
TEE FLUSH TO DIFFUSER FACE
TEE RESTING ON DIFFUSER FLANGE
12 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWFIELD TRIMMING
Available end conditions: W, Y, Z
Sample line string: CF//I/IN//AS/1/48.000/1/SS//SM///EF/WW///HB///DPC///BFR//////B12
NOTE: Trimming of XX (mitered) end conditions is not recommended. Field trimming on multiple section units with mitered ends may be accomplished by trimming open end.
STEP 1: Remove endcap, if installed.
STEP 2: Pull out locking pins from slots of lower spacer bar. Slide out upper spacer bar.
STEP 3: Remove pattern controllers and lower spacer bar.
STEP 4: Cut frames to length, making sure cut is clean and square. Care should be taken not to chip paint when cutting. Spacer bars may be reinstalled to support frames while cutting.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
FIELD TRIMMING
II00059
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
FIELD TRIMMING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF). FIELD TRIMMING OF X-X (MITRED) END CONDITIONS IS NOT RECOMMENDED.FIELD TRIMMING ON MULTIPLE SECTION UNITS WITH MITRED ENDS MAY BE ACCOMPLISHED BY TRIMMING OPEN END.
STEP 4:CUT FRAMES TO LENGTH, MAKING SURE CUT IS CLEAN ANDSQUARE. CARE SHOULD BE TAKEN NOT TO CHIP PAINT WHENCUTTING. SPACER BARS MAY BE REINSTALLED TO SUPPORTFRAMES WHILE CUTTING.
STEP 5:CAREFULLY TRIM PATTERN CONTROL BLADES TO LENGTH USINGTIN SNIPS, AND NOTCH FLANGES 11/16" (17), AS SHOWN.
STEP 6:REPLACE LOWER SPACER BAR AND PATTERN CONTROLLERS.SLIDE UPPER SPACER BAR ON TOP OF PATTERN CONTROLLERSAND RE-INSERT LOCKING PINS INTO SLOTS OF LOWER SPACERBAR.
STEP 7:REINSTALL ENDCAPS, IF NECESSARY, AND CONTINUEINSTALLATION OF DIFFUSER AS REQUIRED. ADJUST BLADES FORDESIRED AIR DISCHARGE PATTERN, AS PER INSTALLATIONINSTRUCTION II00040.
UPPER SPACER BAR
LOWER SPACER BAR
LOCKING PINS
CUT FRAMES TO LENGTH
TRIM PATTERN CONTROLLERS
NOTCH
STEP 1:REMOVE ENDCAP, IF INSTALLED.
STEP 2:PULL OUT LOCKING PINS FROM SLOTS OF LOWER SPACER BAR.SLIDE OUT UPPER SPACER BAR.
STEP 3:REMOVE PATTERN CONTROLLERS AND LOWER SPACER BAR.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
FIELD TRIMMING
II00059
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
FIELD TRIMMING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF). FIELD TRIMMING OF X-X (MITRED) END CONDITIONS IS NOT RECOMMENDED.FIELD TRIMMING ON MULTIPLE SECTION UNITS WITH MITRED ENDS MAY BE ACCOMPLISHED BY TRIMMING OPEN END.
STEP 4:CUT FRAMES TO LENGTH, MAKING SURE CUT IS CLEAN ANDSQUARE. CARE SHOULD BE TAKEN NOT TO CHIP PAINT WHENCUTTING. SPACER BARS MAY BE REINSTALLED TO SUPPORTFRAMES WHILE CUTTING.
STEP 5:CAREFULLY TRIM PATTERN CONTROL BLADES TO LENGTH USINGTIN SNIPS, AND NOTCH FLANGES 11/16" (17), AS SHOWN.
STEP 6:REPLACE LOWER SPACER BAR AND PATTERN CONTROLLERS.SLIDE UPPER SPACER BAR ON TOP OF PATTERN CONTROLLERSAND RE-INSERT LOCKING PINS INTO SLOTS OF LOWER SPACERBAR.
STEP 7:REINSTALL ENDCAPS, IF NECESSARY, AND CONTINUEINSTALLATION OF DIFFUSER AS REQUIRED. ADJUST BLADES FORDESIRED AIR DISCHARGE PATTERN, AS PER INSTALLATIONINSTRUCTION II00040.
UPPER SPACER BAR
LOWER SPACER BAR
LOCKING PINS
CUT FRAMES TO LENGTH
TRIM PATTERN CONTROLLERS
NOTCH
STEP 1:REMOVE ENDCAP, IF INSTALLED.
STEP 2:PULL OUT LOCKING PINS FROM SLOTS OF LOWER SPACER BAR.SLIDE OUT UPPER SPACER BAR.
STEP 3:REMOVE PATTERN CONTROLLERS AND LOWER SPACER BAR.
13priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWFIELD TRIMMING
STEP 5: Carefully trim pattern control blades to length using tin snips, and notch flanges 11/16” (17 mm), as shown.
STEP 6: Replace lower spacer bar and pattern controllers. Slide upper spacer bar on top of pattern controllers and re-insert locking pins into slots of lower spacer bar.
STEP 7: Reinstall endcaps, if necessary, and continue installation of diffuser as required.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
FIELD TRIMMING
II00059
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
FIELD TRIMMING
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF). FIELD TRIMMING OF X-X (MITRED) END CONDITIONS IS NOT RECOMMENDED.FIELD TRIMMING ON MULTIPLE SECTION UNITS WITH MITRED ENDS MAY BE ACCOMPLISHED BY TRIMMING OPEN END.
STEP 4:CUT FRAMES TO LENGTH, MAKING SURE CUT IS CLEAN ANDSQUARE. CARE SHOULD BE TAKEN NOT TO CHIP PAINT WHENCUTTING. SPACER BARS MAY BE REINSTALLED TO SUPPORTFRAMES WHILE CUTTING.
STEP 5:CAREFULLY TRIM PATTERN CONTROL BLADES TO LENGTH USINGTIN SNIPS, AND NOTCH FLANGES 11/16" (17), AS SHOWN.
STEP 6:REPLACE LOWER SPACER BAR AND PATTERN CONTROLLERS.SLIDE UPPER SPACER BAR ON TOP OF PATTERN CONTROLLERSAND RE-INSERT LOCKING PINS INTO SLOTS OF LOWER SPACERBAR.
STEP 7:REINSTALL ENDCAPS, IF NECESSARY, AND CONTINUEINSTALLATION OF DIFFUSER AS REQUIRED. ADJUST BLADES FORDESIRED AIR DISCHARGE PATTERN, AS PER INSTALLATIONINSTRUCTION II00040.
UPPER SPACER BAR
LOWER SPACER BAR
LOCKING PINS
CUT FRAMES TO LENGTH
TRIM PATTERN CONTROLLERS
NOTCH
STEP 1:REMOVE ENDCAP, IF INSTALLED.
STEP 2:PULL OUT LOCKING PINS FROM SLOTS OF LOWER SPACER BAR.SLIDE OUT UPPER SPACER BAR.
STEP 3:REMOVE PATTERN CONTROLLERS AND LOWER SPACER BAR.
14 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWPATTERN CONTROLLER ADJUSTMENT
In order to achieve desired pattern and volume adjustment, adjust pattern controllers accordingly.
NOTE: Pattern controllers must be dampered slightly in order to achieve horizontal pattern in 2 slot configurations.
Volume Adjustment
Fully open
Partially dampered
Shutoff
AS JS
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
15priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWPATTERN CONTROLLER ADJUSTMENT
ADJUSTA-SLOT (AS) PATTERN ADJUSTMENT
JET-SLOT (JS) PATTERN ADJUSTMENT
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULARHORIZONTALVERTICAL
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULARHORIZONTALVERTICAL
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULARHORIZONTALVERTICAL
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULARHORIZONTALVERTICAL
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULARHORIZONTALVERTICAL
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
OF REV.SHEET 1 1 0
CFINSTALLATION
INSTRUCTIONS
PATTERN CONTROLLER
ADJUSTMENT
II00064
© Copyright PRICE INDUSTRIES 2018
Installation InstructionsCF - CUSTOM FLOW
PATTERN CONTROLLER ADJUSTMENT
2018/01/03
ALWAYS READ & UNDERSTAND ALL INSTALLATION INSTRUCTIONS PRIOR TO STARTING.
THIS INSTRUCTION APPLIES TO CUSTOM FLOW LINEAR DIFFUSERS (MODEL CF) FOR BOTH AS (ADJUSTA-SLOT) AND JS (JET-SLOT) SERIES OF PATTERNCONTROLLERS. IN ORDER TO ACHIEVE DESIRED PATTERN AND VOLUME ADJUSTMENT, ADJUST PATTERN CONTROLLERS ACCORDINGLY.
VOLUME ADJUSTMENTS:
• FULLY OPEN:
• PARTIALLY DAMPERED:
• SHUTOFF:
AS JS
OPPOSED HORIZONTALHORIZONTAL & VERTICAL
HORIZONTAL & VERTICALOPPOSED HORIZONTAL
ANGULAR
HORIZONTAL
AS PATTERN ADJUSTMENTS:
JS PATTERN ADJUSTMENTS:
VERTICAL ANGULAR
NOTE:
PATTERN CONTROLLERS MUST BE DAMPERED SLIGHTLY IN ORDER TO ACHIEVE HORIZONTALPATTERN IN 2 SLOT CONFIGURATIONS.
HORIZONTALVERTICAL
HORIZONTAL
VERTICAL
VERTICAL
HORIZONTAL
ANGULAR
ANGULAR
OPPOSED HORIZONTAL
OPPOSED HORIZONTAL
HORIZONTAL & VERTICAL
HORIZONTAL & VERTICAL
16 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWPARTS LIST
Type C Mounting
Each type C mounting bracket kit includes:
Description Slot QTY. Slot Width Part Number
Type C mounting bracket kit
1
1.0” 505737-001
1.5” 505737-002
2.0” 505737-0032.5” 505737-0043.0” 505737-005
2
1.0” 505737-1011.5” 505737-1022.0” 505737-1032.5” 505737-1043.0” 505737-105
Inner bracket ALL
1.0” 267950-0011.5” 267950-0022.0” 267950-0032.5” 267950-0043.0” 267950-005
Outer bracket
1
1.0” 267951-0011.5” 267951-0022.0” 267951-0032.5” 267951-0043.0” 267951-005
2
1.0” 269174-0011.5” 269174-0022.0” 269174-0032.5” 269174-0043.0” 269174-005
Rubber grommet ALL ALL 033363-001#8 x 3” sheet metal screw ALL ALL 031724-001
Slot Size Slot QTY. Slot Width
Inner bracket1 1
2 2
Outer bracket 1 or 2 1
Rubber grommet1 12 2
#8 x 3” sheet metal screw1 12 2
17priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWPARTS LIST
Type MP-DR Mounting
Accessories
Field Cut Kit
Description Part Number
Reversible drywall mounting clip
255149-001
Description Part Number
Y-end splice plate 255152-001
Description Frame Style Slot QTY. End Condition Slot Width Part Number
CF field cut kit EF
1
Y
1.0” 505776-001
1.5” 505776-002
2.0” 505776-0032.5” 505776-0043.0” 505776-005
W
1.0” 505776-0061.5” 505776-0072.0” 505776-0082.5” 505776-0093.0” 505776-010
Z
1.0” 505776-0111.5” 505776-0122.0” 505776-0132.5” 505776-0143.0” 505776-015
2
Y
1.0” 505776-0161.5” 505776-0172.0” 505776-0182.5” 505776-0193.0” 505776-020
W
1.0” 505776-0211.5” 505776-0222.0” 505776-0232.5” 505776-0243.0” 505776-025
Z
1.0” 505776-0261.5” 505776-0272.0” 505776-0282.5” 505776-0293.0” 505776-030
18 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWPARTS LIST
Description Frame Style Slot QTY. End Condition Slot Width Part Number
CF field cut kit CMF
1
Y
1.0” 505776-031
1.5” 505776-032
2.0” 505776-0332.5” 505776-0343.0” 505776-035
W
1.0” 505776-0361.5” 505776-0372.0” 505776-0382.5” 505776-0393.0” 505776-040
Z
1.0” 505776-0411.5” 505776-0422.0” 505776-0432.5” 505776-0443.0” 505776-045
2
Y
1.0” 505776-0461.5” 505776-0472.0” 505776-0482.5” 505776-0493.0” 505776-050
W
1.0” 505776-0511.5” 505776-0522.0” 505776-0532.5” 505776-0543.0” 505776-055
Z
1.0” 505776-0561.5” 505776-0572.0” 505776-0582.5” 505776-0593.0” 505776-060
19priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWNOTES
20 CUSTOM FLOW - Manual | priceindustries.com
CUSTOM FLOWNOTES
21priceindustries.com | CUSTOM FLOW - Manual
CUSTOM FLOWNOTES
This document contains the most current product information as of this printing. For the most up-to-date product information, please go to priceindustries.com
© 2018 Price Industries Limited. All rights reserved.