Installation Manual ClimaCLEARSingle Track Sliding Frameless System
Level at least 6'0"
516 "
8Drill
1 14 "32
Core Drill Bitfor Pivot Point
Crowbar Soft Face Hammer
1"25
Core Drill Bitfor Eccentric Floor Socket
2,5mm allen wrench
3mm allen wrench
4mm allen wrench
5mm allen wrench
6mm allen wrench
Metric Tape Measure
2mm allen wrench
Sheet
Required Tools1. Rough Opening and Unit Dimensions2. Head Track in "kd" (knocked down) Condition3. Head Track and Sill Connectors for Side Jambs plus Weep Slot Pattern for Bottom Track4. Assembly of Head Track 5. Head Track Shimming6. Installation Sequence of Panels7. Panel Alignment and Height Adjustment8. Single Action Offset End Panel Adjustment9. Drilling Weep Holes and Cutting to Size Inserts Between Adjustable Floor Sockets10. Offset Pivot Point and Top Door Closer for Single Action Offset End Panel11. Field Applying Vertical H- and h-gaskets12. Installation of Mortise Cylinder13.
REQUIRED TOOLSTable of ContentsRev. May 3 2017
NanaWall Product Drawing
Wrench22mm
Wrench19mm
Wrench17mm
Wrench11mm
Wrench10mm
Metric Tools Supplied in Accessory Box
Installation ManualSHEET 1 OF 13ClimaCLEAR
#1 #2 #3
34 "19
12 "13
34 "19
12 "13
shim space
14 "7
Brush
Sill
Panel
FF
Rough Opening Dimensions- after applying all deadloads max. deflection of header the lesser of L/720 or 1/4"- the weight of a panel with 1/2" glass is 8 lbs/sqft
Unit Dimensions- leave enough shim space to surrounding condition
SHEET 2 OF 13Installation ManualClimaCLEAR
12 "13
38 "9
AD
AE
9 1316 "250
9 1316 "250
9 1316 "250
ER
12 "13
38 "9
optional byNanaWall
[2"]50
[2"]50
9 1316 "250
9 1316 "250
9 1316 "250
Top Track Comes Pre-Drilled
Head Track in "kd" (knocked down) Condition
NanaWall does not provide nor take responsibility for sizes, location or frequency of perimeter fasteners.
SHEET 3 OF 13Installation ManualClimaCLEAR
JA
JB
Top Connector Piece (Side Jambs and Head Track)
Bottom Connector Piece (Side Jambs and Low Profile Saddle Sill)
2.25 3.75
3
INTERIOR EXTERIOR1/4" x 1" WEEP SLOTS ATABOUT THE CENTER OF EACHPANEL ACROSS THE LENGTHOF THE SILL
INSTALLER NOTE:L.P.S.S IS NOT CENTERED
ON THE UNIT
1/4" x 1" WEEP SLOTS ABOUT 10" FROM EACH ENDAND ABOUT EVERYWEEPING POINT OF PANELSACROSS THE LENGTH OF THE SILL. MOVE SLOT LOCATIONSAS NEEDED SO THEY ARESTAGGERED AT LEAST 8"AWAY FROM THE WEEP SLOTSIN THE INNER CHANNEL
FFHFFH
1/4" x 1" WEEP SLOTS INTHE INNER CHANNEL ATABOUT THE CENTER OF EACHPANEL ACROSS THE LENGTHOF THE SILL
FFHFFH
1/4" x 1" WEEP SLOTS INTHE INNER CHANNEL ATABOUT THE CENTER OF EACHPANEL ACROSS THE LENGTHOF THE SILL
INSTALLER NOTE:L.P.S.S IS NOT CENTERED
ON THE UNIT
1/4" x 1" WEEP SLOTS ABOUT 10" FROM EACH ENDAND ABOUT EVERYWEEPING POINT OF PANELSACROSS THE LENGTH OF THE SILL. MOVE SLOT LOCATIONSAS NEEDED SO THEY ARESTAGGERED AT LEAST 8"AWAY FROM THE WEEP SLOTSIN THE INNER CHANNEL
1/4" x 1" WEEP SLOTS ATABOUT THE CENTER OF EACHPANEL ACROSS THE LENGTHOF THE SILL
EXTERIORINTERIOR
Head Track and Sill Connectors for Side Jambs plus Weep Slot Pattern for Bottom Track
SHEET 4 OF 13Installation ManualClimaCLEAR
B
B
A
B
B
B
B A
B A
A
B
B
B
B
B
RHTRemovableHeadTrack
M
P
P
R
2x
2x
AF
FG
2x
2x
DETAIL HTSCALE 1 : 4
Stopper
JA
JB
HY
Assembly of Head Track
SupportStructure by others
Suggested Side Jamb Fastening Points:A - about 4" from interior edgeB - single action offset end panel side; approx. distance every 16" from the bottom using one extra screw at the bottom
SHEET 5 OF 13Installation ManualClimaCLEAR
W
AA
AC
Finished Floor to Bottom of Head-Track Height
FFL
Head Track Shimming
SHEET 6 OF 13Installation ManualClimaCLEAR
Panel #1 Panel #2 Step 2 Step 1
Installation Sequence of Panels
RHT(Sheet 4)
Panel#2
Panel#2
SCALE 1 : 16
Panel#1
Shown on Top of the Elevation of Product Drawing
RHT(Sheet 4)
Step 0 Step 1 Step 2 Step 3 Panel Installation Sequence SHEET 7 OF 13
Installation ManualClimaCLEAR
BF
Set screw to secureaxle from turning
532 "4
532 "4
BG
CL
#1 #2
14 "7
HT
HWHW
SECTION HW-HWSCALE 1 : 24
Panel Alignment and Height Adjustment
Don't Drill Holes for Sockets, yet !
FFL
SHEET 8 OF 13Installation ManualClimaCLEAR
#1 #2 #3 must fit
HTHT
SECTION HT-HTSCALE 1 : 16
Single Action Offset End Panel Adjustment
SHEET 9 OF 13Installation ManualClimaCLEAR
DETAIL HWSCALE 1 : 1
Cutting to Size Inserts Between Adjustable Floor Sockets
Drilling Weep Holes and Cutting to Size Inserts Between Adjustable Floor Sockets
SHEET 10 OF 13Installation ManualClimaCLEAR
#3
HH
2 58 "66
3 116 "79
1 116 "28
HU
HV
HWHW
HT
Panel Heightadjustment
Set screw to secureaxle from turning
1'2 18 "358
4 18 "105
2"51
2 58 "66
Wall
1'1 716 "341
2 18 "54
3 116 "78
2 38 "60
Offset Pivot Point and Top Door Closer for Single Action Offset End Panel
SHEET 11 OF 13Installation ManualClimaCLEAR
Please cut to size the vertical clear gaskets in the field;top and bottom should exceed the top and bottom edge of the end cover by approximately 1/8"
H-gasket (between sliding panels) and
h-gasket (on the side of the sliding panel meeting the single action end panel with offset hinge)
Step 1
Field Applying Vertical H- and h-gaskets
SHEET 12 OF 13Installation ManualClimaCLEAR