Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019...

17
Inspection practice for NPP in decommissioning Theo Neuffer Ministry of the Environment, Climate Protection and the Energy Sector Baden-Württemberg

Transcript of Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019...

Page 1: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Inspection practice for NPP in decommissioning

Theo Neuffer

Ministry of the Environment, Climate Protection and the Energy Sector Baden-Württemberg

Page 2: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Aspects I want to cover

• Experience with decommissioning license

• Involvement of regulatory body during decommissioning activities

• Evaluation of operator data

• Core areas of on-site inspection during decommissioning

• Upcoming challenges - 2019

Page 3: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Experience with decommissioning license

• Operation licence is still valid

• Decommissioning license equals an modification license

• It regulates certain areas e.g. emissions, overall decomm. activities, modifications (construction projects)

• License as „toolbox“, regulates mostly processes e.g. decommissioning process

• Only one license needed

• Building permit included e.g. for additional material hatch(es)

• Decommissioning with NSF inside reactor building

Page 4: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Involvement of regulatory body during decommissioning activities

Residual Systems

Decommissioning

Operation of res. systems System downgrading System termination and

separation

System decommissioning Material logistics

Decommissioning Unit

Operational Unit

(reduced) routine on-site inspections

routine modification process incl. on-site

inspections

new allowance process incl. on-site inspections

Clearance

Waste treatment

Storage for NHGW

new facility, new operator

new facility, new operator

Page 5: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

New allowance process

• Measures to separate systems from residual systems

• modification process with allowance by RB

• Assessment of dismantling activities in particular with regard to rad. protect., fire protect., labor protect., and measures to exclude interference with residual systems

System termination

and separation

Description of dismantling activities by

Operator

Report by TSOs / External

expert Opinion

Allowance by RB

Work-allowance-process by Operator

• May contain recommendations and suggestions

• Contains all recommendations and suggestions taken into account by RB

• allowance of dismantle activities

• RB performs regular on-site inspections of operator activities

Page 6: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Evaluation of operator dataStrategic decision

1,8E+18

4,0E+16

7,5E+13

2017 2018 2019

Overall Activity in Bq

• Removal of SNF

• Removal of core equipment• Removal of resins• Waste disposal emptied

494

1101

1727

2017 2018 2019

Dismantled Masses in metr. tons

~0,6% of total mass

Start of dismantling

Start of dismantling

Page 7: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Comparison of representative operator activities by man-hours1 year after start of decomm.

0 5 10 15 20 25 30 35

RADIATION PROTECTION

IN-SERVICE INSPECTIONS/ MAINTENANCE

SCAFFOLDING

CHEMISTRY

in 1000 hours

Plant in Power Operation

Plant in Decommissioning

Considerable less in-service and maintenance activities

Page 8: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Distribution of collective dose in decommissioning

Overall collective dose: ~76 mSv

collective dose from decom. activity: ~61 mSv

Decommissioning activities represent ~80% of collective dose of plant in decommissioning.

Page 9: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

0

20

40

60

80

100

120

2011 2012 2013 2014 2015 2016 2017 2018

ave

rage

ind

ivid

ual

do

se [

µSv

]

Plant in decomm.

Plant in power op.

Comparison of doses in decomm. and power operation

0

20

40

60

80

100

120

2011 2012 2013 2014 2015 2016 2017 2018

ave

rage

ind

ivid

ual

do

se [

µSv

]

Plant in decomm.

Plant in power op.

Average individual dose does not differ much between plant in power operation and decommissioningeven though the overall activity on site is strongly reduced from 1E19 Bq to 1E13 Bq

Start Decomm.End of power op.

Page 10: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

37%

27%

21%

13%

1%

0%

0% 5% 10% 15% 20% 25% 30% 35% 40% 45%

<0,001

>0,001-0,01

>0,01-0,1

>0,1-1

>1-2

>2-5

mSv

/a

2017

Decommissioning

Comparison of the dose distribution of the exposed personnel

37%

27%

21%

13%

1%

0%

42%

23%

22%

13%

0,3%

0% 5% 10% 15% 20% 25% 30% 35% 40% 45%

<0,001

>0,001-0,01

>0,01-0,1

>0,1-1

>1-2

>2-5

mSv

/a

2017

Power Operation

Decommissioning

39%

28%

19%

13%

1%

0,1%

38%

20%

24%

17%

0,1%

0% 5% 10% 15% 20% 25% 30% 35% 40% 45%

<0,001

>0,001-0,01

>0,01-0,1

>0,1-1

>1-2

>2-5

mSv

/a

2018

Power Operation

Decommissioning

Dose-ranges are comparable and do not differ much between plant in power operation and decommissioning

Page 11: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

0

5

10

15

20

25

30

JAN 17 FEB 17 MRZ 17 APR 17 MAI 17 JUN 17 JUL 17 AUG 17 SEP 17 OKT 17 NOV 17 DEZ 17

Do

se in

µSv

Decommissioning

Power Operation

Comparison of operator activity by doses

Cask handling

0

5

10

15

20

25

30

JAN 17 FEB 17 MRZ 17 APR 17 MAI 17 JUN 17 JUL 17 AUG 17 SEP 17 OKT 17 NOV 17 DEZ 17

ave

rage

ind

ivid

ual

do

se [

µSv

]

Decommissioning

Power Operation

0

5

10

15

20

25

30

JAN 17 FEB 17 MRZ 17 APR 17 MAI 17 JUN 17 JUL 17 AUG 17 SEP 17 OKT 17 NOV 17 DEZ 17

ave

rage

ind

ivid

ual

do

se [

µSv

]

Decommissioning

Power Operation

Annual Outage

Cask handling

During power operation the major activities are performed on specific occasions during the year

During decommissioning there´re continuous activities during the year

Page 12: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Operator activity oriented Inspections

0

5

10

15

20

25

30

JAN FEB MRZ APR MAI JUN JUL AUG SEP OKT NOV DEZ

Collective Dose 2017

Plant in decomm.

Plant in power op.

0

2

4

6

8

10

12

14

16

18

JAN FEB MRZ APR MAI JUN JUL AUG SEP OKT NOV DEZ

on-site inspections by RB in 2017

Plant in decomm.

Plant in power op.

During power operation• Specific knowledge at the RB

about activities• Inspections plannable

During decommissioning• General knowledge at the RB• Inspections on short notice• unscheduled inspections

become more relevant

Page 13: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

0

20

40

60

80

100

120

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

on

-sit

e in

spe

ctio

ns

of

RB

Plant in decomm.

Plant in power op.

0

20

40

60

80

100

120

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

on

-sit

e in

spe

ctio

ns

of

RB

Plant in decomm.

Plant in power op.

Level of on-site inspections in comparison

Permanent shutdown

Avg. 78 Man-days/a in Power OperationAvg. 46 Man-days/a in decommissioning

Level of on-site inspections in decommissioning comes up to 60 %compared to power operation

Start of decomm.

Support by TSO • in power Operation: ~1773 in-service

inspections per year and facility• in decommissioning: ~323 in-service

inspections per year and facility

Level of TSO technical checksdecrease to ~20%

Page 14: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

0

10

20

30

40

50

60

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

on

-sit

e in

spe

ctio

ns

of

RB

Level of on-site inspections in advanced stateof decommissioning

Supervision density in first years of decommissioning around 60%.

Drops to around 40%Permanent shutdown

Start of decomm.

NSF handling

Reasons:- Less safety relevant systems- Less in-service

inspections/maintenance- Less modifications- Less reportable events- Less events from other NPP with

relevancy

Page 15: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Core areas of on-site inspection during decommissioning

Inspection of residual systems (maintenance, in-service inspections)

Inspect measures to protect residual systems

Control if (relevant) dismantling sequences are obeyed

Check of external staff/specialized suppliers activities

Inspection of radiation protection- and fire protection measures, escape routes

walk-downs with radiation protection unit of the operator

Control of operator documentation

Control of the clearance process

Attend training sessions of the operator

Page 16: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Experience

Licensing in one step is appropriate

New process for approval of decomm. activities in license

Parallel supervision of residual systems and decomm. activities

During decommissioning there are permanent operator activities

Regular on-site-inspections are needed in order to keep an overview over the plants status

Inspections scheduled on short notice

Risk to impair safety relevant systems decreases constantly

Increase of decom. logistics

Page 17: Inspection practice for NPP in decommissioning€¦ · 1,8E+18 4,0E+16 7,5E+13 2017 2018 2019 Overall Activity in Bq • Removal of SNF • Removal of core equipment • Removal of

Challenges for Decommissioning - 2019

• Interim storage of dismantled components

• Commissioning and operation of waste treatment and storage facilities

• Adaption of infrastructure of reactor- and auxiliary building (material hatches)

• Decommissioning of primary components (SG, Pressurizer, MCP)

• Decontamination of buildings/compartments

• Establishing a process for clearance of structures/buildings

• Human resources: Change of operator staff/external suppliers

• Organizational changes after final shutdown of the last NPPs

• Handle the load of parallel authorization processes and multiple operators on site