INSPECTION AND TESTING REQUIREMENTS -...

85
INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General Provisions § IT-2 Streetscape § IT-3 Reserves § IT-4 Transportation Network § IT-5 Stormwater § IT-6 Wastewater § IT-7 Water Supply § IT-8 Public Lighting § IT-9 Network Utilities

Transcript of INSPECTION AND TESTING REQUIREMENTS -...

Page 1: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTS

IN THIS SECTION

§ IT-1 General Provisions§ IT-2 Streetscape§ IT-3 Reserves§ IT-4 Transportation Network§ IT-5 Stormwater§ IT-6 Wastewater§ IT-7 Water Supply§ IT-8 Public Lighting§ IT-9 Network Utilities

Page 2: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-1 GENERAL PROVISIONS

TABLE OF CONTENTS

IT-1.1 General ................................................................................................................1

IT-1.2 Minimum Requirements .......................................................................................1

IT-1.3 Applying for Inspections/Tests..............................................................................2

IT-1.4 Asset Inspection/Testing Requirements ...............................................................3

IT-1.5 Random Inspections ............................................................................................4

IT-1.6 Final Inspection ....................................................................................................4

IT-1.7 Liability .................................................................................................................4

Page 3: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 1

IT-1.1 General

The Consent Holder's Representative or the Engineer are responsible for ensuring that theformal inspections/testing is undertaken in accordance with the IDC. Council also undertakesrandom informal inspections during the course of the works.

Council attends these inspections/tests:

a) As a co-stakeholder of infrastructure development with the emphasis on the constructionof quality assets that will be vested in Council ownership and/or private assets thatconnect to and therefore have an effect on public assets.

b) To ensure good industry practice that benefits all stakeholders, especially the generalpublic and to ensure the quality, longevity and maintenance of the assets in the future.

Development Works

Type 1 Process

a) Unless notified otherwise in the Development Works Approval, Type 1 developmentsrequire the following 2 inspections:i) A pre-backfill inspection for all services intended for Council ownership.

ii) The Final Inspection.

b) Usually, no formal testing of services is required for smaller developments where theonly assets being created are service connections or short laterals or connections toreticulation mains.

c) Testing is required where the services being constructed involve reticulation mains,ridermains, manholes or the like. In these cases testing shall be undertaken inaccordance with IT-1.4 Asset Inspection/Testing Requirements.

d) The final inspection will ensure that assets constructed meet the required standards.

Type 2 Process

a) Unless notified otherwise in the Development Works Approval, Type 2 developmentsshall undertake the inspections and testing in accordance with IT-1.4 AssetInspection/Testing Requirements and IT-1.6 Final Inspection.

Capital Works

a) Refer to the contract documents for testing requirements.

Inspections and tests organised or undertaken by the Project Engineer shall be asprovided for by this section of the IDC.

IT-1.2 Minimum Requirements

a) As a minimum, Council will undertake formal inspections/tests as referenced within thissection of the IDC.

Page 4: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 2 Updated 01/07/2014

b) In some cases additional inspections/tests may be required. These additionalinspections/tests will be outlined in the Development Works Approval or requested whenunforeseen circumstances arise or to resolve a difference of opinion. These additionalinspections/tests will be advised by Council where required.

c) Council will not attend any formal inspections/tests where the work to be inspected/testedhas not been pre-inspected/tested and confirmation provided to Council that theinspection/test is ready for formal inspection/test. Where work to be inspected/tested isnot ready for inspection/testing or the equipment required for the inspection/testing is noton site then Council staff will leave the site and only return when the work is ready forinspection/testing.

d) Where Council arrives for a formal inspection/test and that inspection/test is deemed "notready" to be undertaken, Council reserves the right to cancel the inspection/test andrequire it to be re-scheduled.

e) Council will charge associated costs to the Consent Holder for any inspection/testattended that is deemed not ready and for any re-testing/re-inspection whereinspections/tests have previously been failed.

f) The requirements for application for re-inspection/re-tests are the same as for therequirements for the initial inspection/test.

Where the Consent Holder's Representative fails to comply with these provisions, Councilmay not:

a) Accept the assets for vesting.

b) Allow the new infrastructure to be connected to the existing network.

c) Issue the s224 for the subdivision.

d) Issue building consents or code compliance certificates for any buildings proposing toconnect to the infrastructure.

IT-1.3 Applying for Inspections/Tests

a) Council shall be notified in writing (includes email) by the Consent Holder's Representativeor Engineer at least 2 full working days before the formal inspection/test is required. Therequest to undertake a formal inspection/test shall confirm that the work has beenpre-inspected/pre-tested by the Engineer and Contractor and is ready for inspection byCouncil.

b) The request for a formal inspection/test shall be made to the Development Engineer orCouncil Project Manager assigned to the project. Council will not respond to any requestfor inspection/test from any party other than the Consent Holder's Representative orEngineer or made to any other staff member other than the assigned DevelopmentEngineer or Council Project Manager.

c) If no response is received within 2 full working days, the applicant shall call Council tocheck that Council has received the request. Works may proceed 3 working days afterwritten notification has been sent to Council and no response has been received.

Page 5: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 3

d) Unless otherwise advised, all equipment required for the formal inspection/test shall beprovided by the Consent Holder's Representative on-site and ready for use in theinspection. This includes any equipment required for confined space inspections. Wherethis equipment is not available on site then the inspection/test will be re-scheduled. Anadditional fee will be charged to the Consent Holder for Council to return to the site for therescheduled inspection/test.

e) Where Council is unable to attend a formal inspection/test, it may engage a third party toattend on its behalf. Where this occurs the applicant will be notified in writing, confirmingwhat arrangements/reporting Council may require to certify that the works meet therequired inspection/testing criteria. Once the required reporting has been received by theConsent Holder's Representative, Council will again notify in writing that the works mayproceed.

f) To arrange for Council to observe a formal inspection/test, please contact the assignedDevelopment Engineer / Council Project Manager via writing (email) or phone.

Note: All telephone requests for observation require a written request as well.

IT-1.4 Asset Inspection/Testing Requirements

a) For the requirements of inspection/testing for each different asset group, refer to thefollowing:

i) IT-2 Streetscape.

ii) IT-3 Reserves.

iii) IT-4 Transportation Network.

iv) IT-5 Stormwater.

v) IT-6 Wastewater.

vi) IT-7 Water Supply.

vii) IT-8 Public Lighting.

viii) IT-9 Network Utilities.b) Unless advised by Council, all equipment required for the formal inspection/testing shall be

provided by the Contractor and/or Engineer on-site and be ready for use for theinspection/test. This includes all equipment and requirements for confined space entry.

c) Where applicable, all inspections/tests shall be reported on Council's standardinspection/testing sheets and signed by:

i) The Contractor’s Representative (as the party who constructed the works to beinspected/tested).

ii) The Engineer (as the party responsible for the certification of the works).

iii) Council’s approved representative (as the party acting as co-stakeholder fordevelopment of quality assets on Council’s behalf).

d) Where inspection/testing sheets are not provided, the results shall be formalised in writingby the Engineer and signed as per c) above.

Page 6: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 4 Updated 01/07/2014

IT-1.5 Random Inspections

Council will, during the course of construction of the development works, undertake recurrentrandom observation of the development works as well as attend formal milestone inspectionsand testing. For large scale developments random inspections will occur, on average, at leastonce per week when construction is being undertaken and once per month at other times.

IT-1.6 Final Inspection

a) A final inspection and walkover with As-Built plans shall be undertaken once all works aredeemed complete.

b) The request for final inspection shall confirm that all physical works requiring inspectionhave been pre-inspected by the Certifying Engineer or Consent Holder's Representative,that all testing has been successfully completed and the site is ready for the finalinspection by Council. This inspection is sometimes known as the pre-(s)224c inspection.

IT-1.7 Liability

Confirmation from Council that a section of development work has passed a formalinspection/test and that work may continue does not free or indemnify the Consent Holder'sRepresentative from certifying that the development works comply with the requirements ofthe IDC, any Resource Consent condition and good industry practice.

Page 7: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 5

IT-1 - Appendix AInspection and Testing Summary

Page 8: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 6 Updated 01/07/2014

IT-1 - Appendix A.1 Inspection and Testing Summary

Test SpecifiedUndertaken

by (IANZCertified)

Descriptor Unit QuantityNumber of

TestsRequired

Target Result RequirementsTCCHoldPoint

Check

1 Earthworks All Earth Filling

Earthworks Design Provided to Council at either designapproval or Development Works Approvalphase.

Y

NZ Standard Compaction Curve(NZS 4402 Test 4.1.1) Minimum of2 tests

IANZCertifiedTestingCompany

Soil type 1Soil type 2Soil type 3

N/AN/AN/A

111

Undertaken at the direction of theGeo-Professional.

N

Solids Density Determination IANZCertifiedTestingCompany

Soil type 1Soil type 2Soil type 3

N/AN/AN/A

111

Undertaken at the discretion of theGeo-Professional.

N

Page 9: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 7 Updated 01/07/2014

Compaction Testing - PrimaryNuclear Densometer Test

IANZCertifiedTestingCompany

Total volumeof fill cu m

Minimum 1per1000m3evenlydistributedoverthe areaanddepth offilling.Minimum 1per750mm liftof fillor partthereof

Refer to DS-10.10.7.Minimum dry density of not less than95% of the value of the maximum drydensity obtained from the laboratorysample.Maximum air voids o 10%.

N

One Point Proctor Compaction Test IANZCertifiedTestingCompany

To be included as part of Nuclear Densometer Test.Minimum 1 test per 1000m3 of filling evenly distributedover the extent and depth of the filling. A minimum of 1 testper 750mm lift or part there of.

Results used to determine Maximum DryDensity.

N

Compaction Testing -SupplementaryCohesive soils - Undrained ShearStrength Shear Vane.

IANZCertifiedTestingCompany

Minimum 1 test per500m3 of filling evenly distributed overthe extent and depth of the filling. A minimum of 1 test per750mm lift or part there of.

150kPa minimum average over 10 tests.Minimum single strength of 140 kPa.Maximum average of 10% air voids overany 10 tests. Maximum single test of 12%air voids.

N

Compaction Testing -SupplementaryNon-cohesive soils (sands /pumice) - Scala Penetrometer

IANZCertifiedTestingCompany

Minimum 1 test per500m3 of filling evenly distributed overthe extent and depth of the filling. A minimum of 1 test per750mm lift or part there of.

Target >5 blows per 100mm. Maximumaverage of 10% air voids over any 10 tests.Maximum single test of 12% air voids.

N

Page 10: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 8 Updated 01/07/2014

2 Streetscape

Inspection of plant/tree species Engineer 1 inspection prior to planting Y

Street tree inspection Engineer 1 inspection per tree Pass the requirements on IS-2.1 - Tree. N

Street garden planting, structuresand surfacing.

Engineer General inspection of completed gardens, structures andsurfaces.

Visually in accordance with approved plansand documents.

N

3 Reserves

Inspection of plant/tree species CHR 1 inspection prior to planting Y

Street tree inspection CHR 1 inspection per tree Pass the requirements on IS-2.1 - Tree. N

Street garden planting, structuresand surfacing.

Engineer General inspection of completed gardens, structures andsurfaces.

Visually in accordance with approved plansand documents.

N

4 Transportation

4.1 Subgrade

Subgrade design performancecriteria

Engineer Provided to Council at either designapproval or Development Works Approvalphase.

Y

Primary Test: Insitu CBR Testing.Tests performed at a minimum of15m intervals on alternate lanes

IANZCertifiedTestingCompany

Road Length Metres As shown on the plans but if not specified,in cohesive subgrades CBR>7 innon-cohesive subgrades CBR>10.

N

Alternative: Scale Penetrometer.Non-cohesive soils (sands/pumice) only.Tests performed in both wheeltracks @ 10 metre intervals.

IANZCertifiedTestingCompany

Road Length Metres Required CBR value or >6 blows per100mm.

N

Alternative: Shear Vane.Cohesive soils (ash) only.Tests performed in both wheeltracks @ 10 metre intervals.

IANZCertifiedTestingCompany

Road Length Metres >150Pa. N

Page 11: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 9 Updated 01/07/2014

Alternative: Benkelman Beam.Tests performed at a minimum of15m intervals on alternate lanes.

IANZCertifiedTestingCompany

Road Length Metres As approved and displayed on theapproved plans or if not specified thenaverage deflection <4mm.Deflections in excess of 6mm will requireremedial action determined by theEngineer.

N

Stringing at not less than 20 metreintervals

Contractor Road Length Metres Finished subgrade is uniform and smoothwith the finished level no more than 0mmabove, and 20mm below design level.

N

Geogrid Contractor As instructed by the Engineer Detailed record of geogrid type andlocations.

N

Digouts Contractor As instructed by the Engineer Detailed record of digout depth andlocations.

N

Finished subgrade inspection CHR Acceptance of the subgrade and its testresults by both CHR and Council.

Y

4.2 Subbase GAP 65

4.2.1 Materials Testing

Grading/ Sieve analysis within 2months

IANZ TestingCompany orQuarry TestData

RelevantStockpile

<400m3400-1500m31500-4000m3>4000m3

2341 per 1000

Complies with grading limits referenced inIT-4.2.2 Sub-base Testing Table 2.

N

Sand Equivalent within 2 months IANZ TestingCompany orQuarry TestData

<400m3400-1500m31500-4000m3>4000m3

2341 per 1000

Complies with grading limits referenced inIT-4.2.2 Sub-base Testing Table 2.

N

Crushing Resistance within 6months

IANZ TestingCompany orQuarry TestData

<400m3400-1500m31500-4000m3>4000m3

2341 per 1000

Complies with grading limits referenced inIT-4.2.2 Sub-base Testing Table 2.

N

Laboratory CBR within 6 months Project 1 Complies with grading limits referenced inIT-4.2.2 Sub-base Testing Table 2.

N

Laboratory Compaction curve within6 months

Project 1 N

Page 12: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 10 Updated 01/07/2014

4.2.2 Compaction Testing

Compaction Testing.Nuclear Densometer in backscattertransmission mode.Tests performed at 15m intervals onalternate lanes.

IANZ TestingCompany orQuarry TestData

Testsperformed at15m intervalson alternatelanes.

Average 95% MDD minimum 92% MDD(Refer to IT-4.2.2.1 Compaction ofSub-base).

N

Stringing not less than 20 metreintervals

Contractor/Engineer

not less than20 metreintervals

Tolerance +0 or -20mm. Sub-base surfaceis uniform and smooth.

N

Sub-base inspection Engineer Acceptance of the sub-base and its testresults by both Engineer and Council

Y

4.3 Basecourse GAP 40 or AP40 as specified in drawings

4.3.1 Materials Testing

Grading/ Sieve analysis Within 2months

IANZ TestingCompany orQuarry TestData

RelevantStockpile

>400m3400-1500m31500-4000m3>4000m3

2341 per 1000

Complies with grading limits referenced inIT-4.2.3 Basecourse Testing Table 3 andTable 4.

N

Sand Equivalent Within 2 months IANZ TestingCompany orQuarry TestData

<400m3400-1500m31500-4000m3>4000m3

2341 per 1000

Complies with grading limits referenced inIT-4.2.3 Basecourse Testing Table 3 andTable 4.

N

Crushing Resistance Within 6months

IANZ TestingCompany orQuarry TestData

<400m3400-1500m31500-4000m3>4000m3

2341 per 1000

Complies with grading limits referenced inIT-4.2.3 Basecourse Testing Table 3 andTable 4.

N

Weathering Resistance Within 6months

IANZ TestingCompany orQuarry TestData

<400m3400-1500m31500-4000m3>4000m3

2341 per 1000

Complies with grading limits referenced inIT-4.2.3 Basecourse Testing Table 3 andTable 4.

N

Page 13: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 11 Updated 01/07/2014

Laboratory CBR Within 6 months IANZ TestingCompany

1 CBR>80 N

Laboratory Compaction curve within6 months

IANZ TestingCompany

1 N

4.3.2 Compaction testing

Benkelman Beam total andD250/D0 - Testing at not less than15 metre intervals alternate lanes

IANZ TestingCompany

Road Length Metres As shown on the plans but if not specified,average deflection <3mm. And none>4.5mm. D250/D0 >0.54 for chip seal and25mm ashphalt, >0.65 for 40mm asphaltand >0.70 for >50mm asphalt.

N

Compaction Testing.Nuclear Densometer in backscattertransmission mode.Tests performed at 15m intervals onalternate lanes.

IANZ TestingCompany

Road Length Metres Average 95% MDD minimum 92% MDD(Refer to IT-4.2.3.1 Compaction ofBasecourse)

N

Stringing at not less than 20 metreintervals

Contractor/Engineer

Road Length Metres Tolerance +5mm or -5mm. Basecoursesurface is uniform and smooth.

N

Pre-seal inspection Engineer Acceptance of the basecourse and its testresults by both Engineer and Council andpass the requirements on IS-4.2 - Pre-seal.

Y

4.4 Surfacing

Pre-seal inspection Engineer Acceptance of the membrane seal and itstest results by both CHR and Council.

Y

4.5 Concrete

Footpath inspection Engineer Acceptance of the formwork and footpathsubgrade by both CHR and Council.

Y

Vehicle Crossing inspection Engineer Acceptance of the basecourse and its testresults by both CHR and Council and Passthe requirements on IS-4.1 – VehicleCrossing.

Y

Page 14: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 12 Updated 01/07/2014

5 Stormwater

Visual Inspection ("lamping") Engineer Gravitypipedreticulation<50m

Oneinspectionfor eachstormwaterline <50m.

Pipeline is straight for grade andalignment, has retained its shape (i.eroundness) and is clean.

N

Visual Inspection (walk through) Engineer Gravitypipedreticulation<1200mmÆ

Oneinspectionfor eachstormwaterline>1200mmÆ

Pipeline is straight for grade andalignment, has retained its shape (i.e.roundness), is clean, joints are uniform,pipe barrel isn't cracked and little or noinfiltration occurring.

CCTV inspections Engineer Gravity pipedreticulation>50m

Oneinspectionfor eachstormwaterline >50m

Meet the requirements of IT-1 Apx C. N

Sump inspections Engineer Sumps Oneinspectionfor eachSump

Pass the requirements on IS-5.2 Sump. N

Manhole Infiltration Test Engineer Manhole Asinstructedby Council

Pass the requirements on TS-6.4 ManholeInfiltration Test.

N

6 Wastewater

Manhole Structure Inspections Engineer Manhole Oneinspectionfor eachManhole

Pass the requirements on IS-6.1 –Manhole & Pipework <50m.

N

Page 15: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 13 Updated 01/07/2014

Visual Inspection ("lamping") Engineer Gravitypipedreticulation<50m

Oneinspectionfor eachgravityline which is<50m

Pipeline is straight for grade andalignment, has retained its shape (i.e.roundness) and is clean.

N

CCTV Inspections Engineer Gravity pipedreticulation>50m

Oneinspectionfor eachgravity line>50m

Meet the requirements of IT-1 Apx C.

Low Pressure Air test Contractor Gravity pipedreticulation ñgroundwater table

One test foreachgravity line.

Pass the requirements on TS-6.1 LowPressure Air Test.

N

High Pressure Air Test Contractor Gravity pipedreticulation ògroundwater table

One test foreachgravity line

Pass the requirements on TS-6.2 HighPressure Air Test.

N

Rising Main Pressure Test Contractor PressureRising Main

One test foreachpressurerising main

Pass the requirements on TS-6.3 PressureTest.

N

Manhole Infiltration Test Contractor Manhole Asinstructedby Council

Pass the requirements on TS-6.4 ManholeInfiltration test.

N

Pump Station Commissioning Contractor Pump Station Oneinspectiononcompletion

N

Page 16: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 14 Updated 01/07/2014

7 Water Supply

Fire Hydrant Inspections Engineer Hydrants Oneinspectionfor allhydrants

Pass the requirements on IS-7.1 Hydrants. N

Valve Inspections Engineer Valves Oneinspectionfor allvalves

Pass the requirements on IS-7.2 Valves. N

Water Meter Inspections Engineer Water Meters Oneinspectionfor allmeters

Pass the requirements on IS-7.3 WaterConnections.

N

Pressure Test Contractor Water Mains Pass the requirements on TS-7.1 PressureTest.

N

Disinfection Contractor Water Mains Pass the requirements on TS-7.2Installation Disinfection.

N

8 Public Lighting

Lighting Inspection Engineer Visual acceptance of the public lighting byboth CHR and Council

N

9 Network Utilities

Broadband ducting inspection Engineer Acceptance of the broadband ducting priorto backfill by both CHR and Council.

Y

10 S224 Final Walkover

Final Inspection Engineer Acceptance of the finished developmentworks and As-built plans by both Engineerand Council prior to application for s224.

Y

The Consent Holders Representative is required to notify Council's Development Engineer not less than 48 hours prior to each test or inspection to allow for Council attendance.

Page 17: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 15

IT-1 - Appendix BCompany Requirements for Soils, Earthworks, Materials and Pavement Testing

IT-1 - Appendix B.1 Minimum Requirements

All testing of soils, earthworks, materials and pavements to determine:

a) Soils properties and performance criteria.

b) Compliance of earthworks with Geo-Professionals earthworks design.

c) Confirmation of materials properties for pavements.

d) Pavement compliance testing.

Shall be undertaken by a company (laboratory) who is accredited with IANZ formechanical testing in compliance with NZS ISO/IEC 17025 General Requirements for theCompetence of Testing and Calibration laboratories and specific technical criteria whereappropriate.

Where the testing company (laboratory) is employed to undertake the testing associatedwith b) above, then the Geo-Professional, or their delegate, shall be the only person todirect the activities of the testing company to ensure the testing requirements for theearthfill are met. Regular frequent contact shall occur between the testing company andGeo-Professional during earthworks testing to ensure that the location and frequency ofthe earthworks testing meets the Geo-Professional's requirements.

Where the testing company is employed to undertake testing associated with either c) ord) above then the testing company shall be directed and managed solely by the Engineeror their Representative. Frequent contact shall occur between the testing company andEngineer during pavement testing to ensure that the location, frequency and results of thetesting meets the Engineer's design requirements.

Note: The testing company forms an integral part of the Geo-Professional's or Engineer'scertification of the earthworks, determining the long term viability of any new or modifiedlandform, the pavement and determining the long term serviceability of the new orre-constructed road. It can't be stressed enough that the Geo-Professional and/or Engineerbe the sole manager of the testing company's testing activities on their behalf.

Page 18: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 16 Updated 01/07/2014

IT-1 - Appendix CClosed Circuit Television (CCTV) Inspections

Page 19: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 17

IT-1 - Appendix C.1 General

Unless modified by this document CCTV inspections shall be in accordance with TheGeneral Specification of The New Zealand Pipe Inspection Manual, Third Edition,Published 2006.

Page 20: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 18 Updated 01/07/2014

IT-1 - Appendix C.2 Engaging a CCTV Provider

a) Development Works

Prior to works commencing, the Consent Holder’s Representative shall provide to Council,in writing, the names of three (3) proposed CCTV providers, including their proposedinspection rates and the length of pipelines to be inspected. (Inspection rates shall bequoted in $/ lin. m)

Council will consider the three (3) proposed providers and their respective inspection ratesand confirm in the Development Works Approval which CCTV provider Council agrees toundertaking the CCTV inspection works. Where Council considers the rates provided bythe CCTV providers are too expensive Council may require the Consent Holder to engagea CCTV provider of Council nomination.

The Consent Holder’s Representative shall then engage the services of theagreed/nominated CCTV provider to undertake the CCTV inspection for the developmentas and when required.

b) Capital Works

The Contractor shall engage the services of a CCTV provider in accordance with theconditions of contract.

Page 21: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 19

IT-1 - Appendix C.3 Responsibilities of all Parties

a) Development Works

The Consent Holder’s Representative is responsible for ensuring the required CCTVinspections for the development are completed and submitted to Council for acceptance.The Consent Holder’s Representative is also responsible for the on site coordination of theContractor and CCTV Provider. Council accepts no liability for the CCTV Provider or thecoordination and timing of inspection requirements.

b) Capital Works

The Contractor is responsible to ensure the required CCTV inspections for the contract arecompleted and submitted to Council for acceptance. The Contractor is responsible for theon site coordination and timing of the CCTV Provider and inspection requirements.

c) CCTV Provider

The CCTV Provider is the person or entity engaged by either the Consent Holder, theConsent Holder’s Representative or the Contractor to provide the services required by thisdocument. The CCTV provider shall ensure the CCTV footage of all pipelines requiringinspection is undertaken in accordance with the requirements of this document and thatthey meet any inspection timing requirements of the Consent Holder’s Representative orthe Contractor.

Page 22: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 20 Updated 01/07/2014

IT-1 - Appendix C.4 Cleaning

Prior to the CCTV inspections being undertaken pipes are to be fully cleaned to remove allforeign matter, including all roots. This may involve either several passes of jettingequipment or the use of several different cleansing techniques to ensure that all debris isremoved from the pipeline.

Page 23: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 21

IT-1 - Appendix C.5 Water Flow in Pipe

a) Stormwater

A nominal flow of water maybe permitted in the pipe invert during the CCTV inspection. i.e.the pipe is to be predominantly dry and any water present must not inhibit the CCTVequipment from completing a thorough inspection of the pipeline.

b) Wastewater

No water is permitted within the pipeline during the CCTV inspection. i.e. the pipe is to bedry.

Page 24: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 22 Updated 01/07/2014

IT-1 - Appendix C.6 Defect Codes

The following table lists Condition Scores in accordance with the New Zealand PipeInspection Manual Third Edition, May 2006.

CODE CONDITION DESCRIPTION S M LCC Structural Crack Circumferential 2 15 30

CL Structural Crack Longitudinal 3 15 30CM Structural Crack Multiple 10 20 40DF Structural Deformed Pipe N/A 25 65

DP Structural Dipped Pipe 10 15 35IP Structural Infiltration Present 2 15 30JD Structural Joint Displaced 0 15 45JF Structural Joint Faulty 1 10 25JO Structural Joint Open 0 5 25LF Structural Lateral Sealing Defective 5 10 25LP Structural Lateral Protruding 0 15 25

LX Structural Lateral Problem 5 20 30OP Structural Obstruction Permanent 10 20 35PB Structural Pipe Broken 15 30 75PF Structural Deformed Plastic Pipe 5 10 30PH Structural Pipe Holed 5 25 40PL Structural Protective Lining Defective 5 25 60PX Structural Pipe Collapsed N/A N/A 100SD Structural Surface Damage 3 20 60TM Structural Tomo N/A N/A 40DE Service Debris Silty 8 20 40DG Service Debris Greasy 8 20 40ED Service Encrustation Deposit 0 5 20OT Service Obstruction Temporary 0 5 20RI Service Root Intrusion 5 25 70

Page 25: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 23

IT-1 - Appendix C.7 Failure Triggers

A pipeline is deemed to have failed when one of the thresholds as detailed in Tables 4-5and/or 4-6 of the New Zealand Pipe Inspection Manual Third Edition are exceeded.

These failures thresholds are:

a) Structural Condition:

Peak Score of 2 and a Mean Score of 0.5.

b) Service Condition:

Peak Score of 3 and a Mean Score of 0.5.

These values equate to a grading of excellent in the New Zealand Pipe Inspection ManualThird Edition.

Page 26: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 24 Updated 01/07/2014

IT-1 - Appendix C.8 Failures

Failure of structural item requires defect(s) to be remedied and a second CCTV inspectionundertaken to show compliance.

Failure of service item requires pipe to be cleaned and a second CCTV inspectionundertaken to show compliance.

Page 27: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 25

IT-1 - Appendix C.9 Major Defects Requiring Immediate Attention

If the CCTV provider identifies any of the following defects, they are to immediately notifythe Council:

a) Pipe Broken (L severity).

b) Pipe Collapsed (L severity).

c) Deformed Pipe (L severity).

d) Tomo (L severity).

e) Any defects where it is evident that tomos are forming outside the pipe.

Page 28: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 26 Updated 01/07/2014

IT-1 - Appendix C.10 Deliverables

The CCTV provider is required to provide the following:

a) Two hard copy (A3) As-built drawings of the pipe layout and manhole positionslabelled to correspond with the information on the CCTV video.

b) Two copies on DVD+R disks of the CCTV inspections; these are to be recorded in anmpeg2 programme stream (PS) format, with a variable bit rate of 4.5 mbps or higher.

Page 29: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 27

IT-1 - Appendix C.10.1 CCTV Footage Requirements

The CCTV footage shall include the following text information:

a) Screen header information shown for a minimum of 10 seconds showing:

i) Name of main Contractor.

ii) Name of CCTV Contractor.

iii) Name of Client.

iv) Date of inspection.v) Resource Consent Number or Council Contract Number.

vi) Upstream manhole number.

vii) Setup Manhole number.

viii) Downstream manhole number.

ix) Pipe Diameter in millimetres.

x) Pipe Material e.g. UPVC.

xi) Pipe use e.g. Stormwater.

b) Continuous header information located on screen so as not to impede the view ofthe pipe showing:

i) Upstream manhole number.

ii) Downstream manhole number.

iii) Distance along pipe.

iv) Inclinometer.

Example of Continuous Header Information Position

Page 30: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Page 28 Updated 01/07/2014

IT-1 - Appendix C.10.2 Unacceptable Footage

The video will be deemed unacceptable and rejected due to any of the followingissues:

a) Camera out of focus.

b) Insufficient / excessive lighting.

c) Fog or steam in the pipe.

d) Condensation or grease on the lens.

e) Temporary discharge of water down the pipe.

f) Debris or spider webs over the lens due to insufficient cleaning.

g) Camera moving too fast or too slow through the pipe.

Page 31: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-1 GENERAL PROVISIONS

Updated 01/07/2014 Page 29

IT-1 - Appendix C.10.3 Condition Assessment Reports

CCTV inspection footage shall be submitted to Council by either the Contractor or theConsent Holder’s Representative. Once Council has received the CCTV footage, it willbe forwarded to Council’s data management contractor who will review the CCTVfootage, produce a condition assessment report and convert the footage into a formatsuitable for migration into Council's Asset Management System.

Council’s internal timeframe to complete preparation of the condition assessmentreport is 5 working days, excluding the day the CCTV footage is received by Council.The result of the Condition Assessment Report will be forwarded to the ConsentHolder's Representative on receipt.

Council will notify the Consent Holder's Representative at the time of DevelopmentWorks Approval, the current rates for production of the Condition Assessment Reportin $/ lin. m.

Page 32: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-2 STREETSCAPE

TABLE OF CONTENTS

IT-2.1 Inspection.............................................................................................................1

IT-2.2 Testing .................................................................................................................1

Page 33: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-2 STREETSCAPE

Updated 01/07/2014 Page 1

IT-2.1 Inspection

Refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-2.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) Inspection of plant/tree species prior to commencement of planting.

b) Completion of all planting, surfacing and structures. Street trees shall satisfy therequirements of inspection sheet IS-2.1 Tree.

c) Should inspection of other streetscape features be required, Council shall advise inwriting what inspections are required.

d) Final inspection as specified in IT-1 General Provisions.

IT-2.1.2 Random Inspections

Council will undertake random inspections of all site features throughout the constructionperiod to ensure good industry practices and compliance with all requirements for theinfrastructure development are being followed.

IT-2.2 Testing

a) Testing of streetscape features over and above the inspection requirements specified inIT-2.1 Inspections will not generally be required.

b) Refer to IT-8 Public Lighting for the testing requirements for public lighting.

c) Should testing of other streetscape features be required, Council shall advise in writingwhat test method/s shall be used.

Page 34: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 35: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-3 RESERVES

TABLE OF CONTENTS

IT-3.1 Inspection.............................................................................................................1

IT-3.2 Testing .................................................................................................................1

Page 36: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-3 RESERVES

Updated 01/07/2014 Page 1

IT-3.1 Inspection

Refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-3.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) Inspection of plant/tree species prior to commencement of planting.

b) Completion of all planting, surfacing and structures. Street trees shall satisfy therequirements of inspection sheet IS-2.1 Tree.

c) Should inspection of other reserve features be required, Council shall advise in writingwhat inspections are required.

Final inspection as specified in IT-1 General Provisions.

IT-3.1.3 Random Inspections

Council will undertake random inspections of all site features throughout the constructionperiod to ensure good industry practices and compliance with all requirements for theinfrastructure development are being followed.

IT-3.2 Testing

a) Testing of reserves features over and above the inspection requirements specified inIT-3.1 Inspections will not generally be required.

b) Refer to IT-8 Public Lighting for the testing requirements for lighting.

c) Should testing of other reserve features be required, Council shall advise in writing whattest method/s shall be used.

Page 37: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 38: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-4 TRANSPORTATION NETWORK

TABLE OF CONTENTS

IT-4.1 Inspection.............................................................................................................1

IT-4.2 Testing .................................................................................................................2

Page 39: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Updated 01/07/2014 Page 1

IT-4.1 Inspection

Refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-4.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) Sub-grade inspection.

Acceptance of the subgrade and its test results by both the Engineer and Council’sRepresentative shall be confirmed prior to work commencing on thesub-base/basecourse construction activities.

b) Sub-base inspection.

Acceptance of the sub-base and its test results by both the Engineer and Council'sRepresentative shall be confirmed prior to work commencing on the basecourse.

c) Pre-seal inspection (completed carriageway basecourse).

Acceptance of the basecourse and its test results by both the Engineer and Council’sRepresentative shall be confirmed prior to membrane sealing of the carriageway.

d) Pre-surfacing inspection (after completion of seal membrane).

Acceptance of the membrane seal, any relevant test results and any other inspectionand testing requirements for other assets located in the carriageway by both theEngineer and Council’s Representative shall be confirmed prior to final surfacing.

e) Pre-concrete pour inspection for footpaths.

Acceptance of the formwork and footpath sub-base by both the Engineer andCouncil’s Representative shall be confirmed prior concrete pour.

f) Other inspections may be required that are not listed above. These will be advised byCouncil where applicable.

g) A complete inspection of all assets prior to s224(c) application is required as specifiedin IT-1 General Provisions.

IT-4.1.2 Random Inspections

Council will undertake random inspections of all site features throughout the constructionperiod to ensure good industry practice and compliance with all requirements for theinfrastructure development are being followed.

Page 40: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Page 2 Updated 01/07/2014

IT-4.2 Testing

a) Council shall be advised when testing is being undertaken but may choose not to attendthe testing.

b) All compliance testing is to be carried out by an IANZ Registered testing Company IT-4 -Appendix A – Company Requirements for Pavement Testing.

c) It is expected that Contractors will carry out their own uniformity testing in addition to thecompliance testing. While not acceptable for compliance, copies of all of the Contractor’suniformity testing results will be made available to Council if requested.

IT-4.2.1 Subgrade Testing Carriageways

The tests in IT-4.2.1.1 Test Methods shall be completed and accepted before placing anypavement aggregate.

It is the Engineer’s responsibility to ensure soils and bearing testing is undertaken (as maybe required) and to identify and carry out any necessary remedial works on the subgrade(not less than 400mm depth) to achieve the required bearing capacity and, where utilised,deflections necessary at subgrade level.

Testing requirements covered in this section address only the tests required to satisfyCouncil that the finished subgrade of the pavement is competent in both bearing capacityand deflection to support the road pavement.

IT-4.2.1.1 Test Methods

The test method to be utilised to measure and prove the strength of a completedsub-grade for all soil types is the Insitu CBR test method in accordance with NZS 4402Methods of Testing Soils for Civil Engineering Purposes.

Other test methods can be utilised between Insitu CBR tests to confirm the uniformityof the completed subgrade.

The other test methods that can be used for consistency testing are for:

a) Cohesive soils: shear vane testing.

b) Non-cohesive soils: scala-penetrometer testing.

Both methods require calibration against several of the passed Insitu CBR tests.

Benkelman Beam testing is also an acceptable test utilised by the Engineer to test asubgrade for consistency and uniformity of performance. (This is a non-mandatoryrequirement.)

a) CBR Testing:

Insitu CBR tests are to be carried out on all completed subgrades. Tests shall becarried out at 15m intervals on alternate lanes. The subgrade CBR’s shallachieve:

i) CBR ≥7 for modified ash subgrades.

Page 41: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Updated 01/07/2014 Page 3

ii) CBR ≥10 for modified sand pumice subgrades.

unless the approved design CBR is different.

The CBR value used in the design shall be the 10 percentile value of the CBRtests taken on the subgrade material. A selection of tests shall be taken at150mm, 300mm and 450mm below final subgrade level.

b) Scala Penetrometer testing (non-cohesive soils only):

The Scala Penetrometer shall be calibrated by performing tests located adjacentto one or more insitu CBR test that meets the approved design CBR orperformance standards referenced in a) above.

Once calibrated the Scala Penetrometer can be used to check the uniformity ofthe subgrade.

Testing with Scala Penetrometer shall be carried out in both wheel tracks of eachlane of the pavement at 10m intervals:

i) The Scala Penetrometer shall only be employed on non-cohesivesubgrades where a significant part of the subgrade particles pass a 9.5mmsieve. The penetrometer shall be bedded into the soil with one (or more)blows. The zero point for depth and the number of blows is taken neglectingthe bedding blows.

ii) Table 1: Scala Penetrometer vs CBR Approximation sets out the firstapproximation co-relationship between the Scala Penetrometer readings innon-cohesive soils and equivalent CBR readings.

iii) Refer to IT-4.2.6 Scala Penetrometer CBR Conversion Chart for theCalifornia Bearing Ratio (CBR) vs Penetration relationship.

c) Shear Vane Testing (cohesive soils only):

The shear vane shall be calibrated by performing tests located adjacent to one ormore insitu CBR test that meets the approved design CBR or performancestandards referenced in a) above.

Once calibrated the Shear Vane can be used to check the uniformity of thesubgrade.

Testing with Shear Vane is to be carried out in both wheel tracks of each lane ofthe pavement at 10.0m intervals:

i) There is no established direct correlation between the Shear Vane and CBRas every soil type has different characteristics, however, by calibratingdirectly to insitu CBR results as in a) CBR Testing above, a localcomparison is useful for uniformity assurance. In general the local ashes forsoils close to optimum moisture content (OMC) and 100% maximum drydensity, the shear strength should be >150 kPa.

d) Benkelman Beam Testing:

Although not mandatory, Benkelman Beam tests for total deflection areencouraged to be carried out on all prepared subgrades. Tests shall be carriedout at not less than 15.0m intervals on alternate lanes. It is anticipated that in

Page 42: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Page 4 Updated 01/07/2014

general subgrade total deflections should be 4mm average and not exceed 6mm.Deflections in excess of 6mm shall require remediation of the subgrade or theEngineer will need to reassess the pavement design to ensure the maximum finalpavement deflection is not exceeded:

i) The Benkelman Beam test shall be as per NZTA Specification T/1Benkelman Beam Deflection Measurements.

Table 1: Scala Penetrometer vs CBR Approximation

CBR Maximum mm per blow Minimum blows /100mm

7 32 310 23 415 17 6

IT-4.2.1.2 Shape of Subgrade

Stringing may be carried out by the Contractor in the presence of the Engineer andshall be at no greater than 20m intervals and within a tolerance of +0mm and -20mm ofdesign subgrade level.

IT-4.2.2 Sub-base Testing

All sub-bases shall be constructed from GAP65 aggregate. The GAP65 shall bewell-graded crushed rock, free from silt or clay lumps, organic and other non-mineralmatter. Unless otherwise approved, Representative samples shall be tested forcompliance with the following:

a) Table 2: Table 2: GAP65 RequirementsGAP65 Requirements.

b) Grading Limits: When wet sieved in accordance with NZS 4402 Test No. 2.8.1. Thegrading shall lie within the envelope of values given in Table 2: GAP65 Requirements.

c) Sand Equivalent: When tested in accordance with NZS 4407 Test No. 3.6 the sandequivalent shall not be ≤ 40.

d) Crushing Resistance: When tested in accordance with NZS 4407 Test No. 3.10 thepercentage of fines produced from a 110 kN load shall be ≤10%.

e) CBR: The minimum CBR shall not be ≤ 80% when laboratory tested.

f) Stringing: Stringing, which may be carried out by the Contractor in the presence of theEngineer, shall be at no greater than 20m intervals and within the tolerance +20 or -20mm of design subgrade level.

Page 43: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Updated 01/07/2014 Page 5

Table 2: GAP65 Requirements

Test Sampling and Testing Frequency(based on TNZ M/4)

Grading limits Minimum of 2samples lessthan 2 monthsold at date ofdelivery.Actual numberdependant onvolume requiredas follows:< 400m³ - 2 tests400-1500m³ - 3tests1500-4000m³ - 4tests> 4000m³ - 1 testper 1000m³ orpart thereof

Test Sieve Aperture % Passing by mass70mm Minimum 100%19mm Minimum 40%9.5mm Maximum 70%425um Maximum 10%

Sand equivalent ≥ 40%

Crushing resistance With 110 kN load≤ 10% fines

Minimum of 2 samples less than 6 months oldat date of delivery.Actual number dependant on volume required.

Laboratory SoakedCBR > 80% 1 sample per project

IT-4.2.2.1 Compaction of Sub-Base

Nuclear Densometer: The degree of compaction shall be tested at 15m intervals onalternate sides of the pavement at the completion of primary compaction. Compactiontesting shall be undertaken by a calibrated Nuclear Densometer in BackscatterTransmission mode. Target results for density are an average of 95% of MDD and aminimum of 92% of MDD.

IT-4.2.2.2 Shape of Sub-Base

Stringing at not more than 20m intervals and within a tolerance of +0mm and -20mm ofdesign sub-base level.

IT-4.2.3 Basecourse Testing

All basecourse aggregate shall be either GAP40 or AP40 (TNZ M4) metal meeting thefollowing test requirements:

Page 44: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Page 6 Updated 01/07/2014

a) Aggregate for construction of basecourse layers shall be crushed rock, free from silt orclay lumps, weathered or disintegrated rock, organic and other non mineral matter.

b) Unless otherwise approved, the following tables shall be used:

i) Table 3: GAP40 Requirements (based on NZS 4404).

ii) Table 4: AP40 Requirements (based on TNZ M/4).

c) Grading Limits: When wet sieved in accordance with NZS 4402 Test No. 2.8.1. Thegrading shall lie within the envelope of values given in Table 3: GAP40 Requirements(based on NZS 4404) and Table 4: AP40 Requirements (based on TNZ M/4).

d) Sand Equivalent: When tested in accordance with NZS 4407 Test No. 3.6 the sandequivalent shall not be ≤ 25 for GAP40 or 40 for AP40.

e) Crushing Resistance: When tested in accordance with NZS 4407 Test No. 3.10 thepercentage of fines produced from a 110 kN load shall be ≤10%.

f) CBR: The minimum CBR shall not be less than 100% when laboratory tested.

Table 3: GAP40 Requirements (based on NZS 4404)

Test Sampling and Testing Frequency(based on TNZ M/4)

Grading limitsMinimum of 2 samples less than 2months old at date of delivery.

Actual number dependant on volumerequired as follows:< 400m³ - 2 tests400-1500m³ - 3 tests1500-4000m³ - 4 tests> 4000m³ - 1 test per 1000m³ or partthereof

Test SieveAperture

% Passing by mass

37.5mm 100%19mm 61–81%9.5mm 38–57%

4.75mm 23–43%2.36mm 14–33%

1.18mm 7–25%600um 2–19%300um 0–14%150um 0–10%75um 0–7%

Sand equivalent > 25%Crushing resistance With 110 kN load

< 10% finesMinimum of 1 sample less than 6 months old atdate of delivery.Actual number dependant on volume required.

Weatheringresistance

AA, AB, AC, BA, BB,BC, CA or CB

Minimum of 1 sample less than 6 months old atdate of delivery.Actual number dependant on volume required.

Page 45: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Updated 01/07/2014 Page 7

Table 4: AP40 Requirements (based on TNZ M/4)

Test Sampling and Testing Frequency(based on TNZ M/4)

Grading limits

Test SieveAperture % Passing by mass Minimum of 2 samples less than 2

months old at date of delivery.Actual number dependant on volumerequired as follows:< 400m³ - 2 tests400-1500m³ - 3 tests1500-4000m³ - 4 tests>4000m³ - 1 test per 1000m³ or partthereof

37.5mm 100%19mm 66–81%9.5mm 43–57%

4.75mm 28–43%2.36mm 19–33%1.18mm 12–25%600um 7–19%300um 3–14%150um 0–10%75um 0–7%

Shape Limits

19 mm - 4.75 mm 28–48%

9.5 mm - 2.36 mm 14–34%

4.75 mm - 1.18 mm 7–27%

2.36 mm - 600 um 6–22%

1.18 mm - 300 um 5–19%

600 um - 150 um 2–14%Sand equivalent >40%

Crushing resistance With 130 kN load< 10% fines

Minimum of 1 sample less than 6 monthsold at date of delivery.Actual number dependant on volumerequired.

Weatheringresistance

AA, AB, AC, BA, BB,BC, CA or CB

Minimum of 1 sample less than 6 monthsold at date of delivery.Actual number dependant on volumerequired.

IT-4.2.3.1 Compaction of Basecourse

a) Nuclear Densometer: The degree of compaction shall be tested at 15m intervalson alternate sides of the pavement at the completion of primary compaction.Compaction testing shall be undertaken by a calibrated Nuclear Densometer inBackscatter Transmission mode. Target results for density are an average of 98%of MDD and a minimum of 95% of MDD.

Page 46: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Page 8 Updated 01/07/2014

b) Tolerances shall meet the requirements of NZTA specification B/2 Construction ofUnbound Granular Pavement Layers.

c) Benkelman Beam tests for total deflection and D250/D0 are to be carried out onall prepared basecourse surfaces. Tests shall be carried out at not less than 15mintervals on alternate lanes. The basecourse total deflections shall be about 3mmaverage and not exceed 4.5mm. D250/D0 ratios are required to meet thefollowing:

i) Chip Seal and 25 mm asphalt >0.54

ii) 40 mm Asphalt >0.65

iii) >50mm Asphalt >0.70iv) The beam test shall be as per NZTA Specification T/1 Benkelman Beam

Deflection Measurements.

d) The Engineer shall provide the results from the Benkelman Beam tests (specifiedabove) to show that the pavement complies with the requirements detailed. Theorganisation carrying out the tests shall be IANZ accredited.

e) Acceptance of pavements with deflections exceeding the target figures will be atthe discretion of the Council.

IT-4.2.3.2 Shape of Basecourse

Stringing, which may be carried out by the Contractor in the presence of the Engineer,shall be at not more than 20m intervals and within a tolerance of +5mm and -5mm ofdesign basecourse level.

IT-4.2.4 Surface Texture

The method for determining surface texture shall be TNZ Specification T/3 Sand CircleSurface Texture measurements.

IT-4.2.5 Sealed Surface Roughness

This shall only apply to designated collector, arterial and strategic arterial roads.

a) The target maximum values for roughness of sealed surfaces shall be 60 for asphaltand 70 for chipseal.

b) Roughness measurements shall normally, but not exclusively, only be taken onsurfacing applied to areas on new or reworked road surface or as directed by theEngineer.

c) In addition to the shape requirements of TNZ B/2, TNZ P/9, TNZ P/9P and TNZ P/11notes, National Association of Australian State Road Authorities (NAASRA)roughness readings shall be recorded in each lane at 20m intervals.

d) A minimum of 3 runs for roughness measurements shall be taken in each direction.Roughness measurements taken through rotary intersections shall not be consideredas part of the average roughness.

Page 47: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Updated 01/07/2014 Page 9

e) The moving 100m average of those 20m readings (in each lane including tie ins) shallbe determined and none of those 100m averages shall exceed a value of 70 NAASRAcounts/km.

f) Where the finished surfacing is asphaltic concrete, the maximum 100m movingaverage lane roughness requirement is reduced to 60 NAASRA counts/km.

g) Roughness readings are not required on lengths 100m or less, as the shaperequirements of the above TNZ specifications are expected to be sufficient to controlisolated bumps over this short length.

h) The average roughness value shall be taken to be the arithmetic mean of all recordedreadings excluding readings taken through rotary intersections.

i) For the purposes of comparing with the specified Average Construction Roughness,the average roughness obtained shall be rounded to the nearest whole number.

j) The Contractor shall be responsible for all costs in arranging and carrying out thetesting and informing the Engineer of the results.

k) The Contractor shall provide the Engineer with all the Certified Test results. TheCertification shall include that the testing has been carried out in accordance with thisclause.

Page 48: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Page 10 Updated 01/07/2014

IT-4.2.6 Scala Penetrometer CBR Conversion Chart

Page 49: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-4 TRANSPORTATION NETWORK

Updated 01/07/2014 Page 11

IT-4 - Appendix ACompany Requirements for Pavement Testing

IT-4 - Appendix A.1 General

All testing of pavements shall be undertaken by a company (laboratory) who is accreditedwith IANZ for mechanical testing in compliance with NZS ISO/IEC 17025 GeneralRequirements for the Competence of Testing and Calibration Laboratories and specifictechnical criteria where appropriate.

The testing company shall be directed and managed solely by the Engineer or theirRepresentative. Frequent contact shall occur between the testing company and Engineerduring pavement testing to ensure that the location, frequency and results of the testingmeets the Engineer’s design requirements and the requirements of the IDC.

Note: The testing company forms an integral part of the Engineer’s certification of thepavement and determining the long term serviceability of the new or reconstructed road. It cannot be stressed enough that the Engineer is the sole manager of the testing company’scertification activities on their behalf.

Page 50: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 51: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 52: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-5 STORMWATER

TABLE OF CONTENTS

IT-5.1 Inspection.............................................................................................................1

IT-5.2 Testing .................................................................................................................2

Page 53: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-5 STORMWATER

Updated 01/07/2014 Page 1

IT-5.1 Inspection

Refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-5.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) Manhole structures shall be inspected to satisfy the requirements noted underinspection sheet IS-5.1 – Inspection Sheet Stormwater Manhole and Pipeline <50m.

b) Gravity piped reticulation where the distance between manholes is 50m or less, shallundergo visual inspection. Visual inspection includes "lamping" between manholesto ensure the pipeline is laid straight for grade and alignment, has retained its shape(i.e. roundness) and is clean.

c) Gravity piped reticulation, where the pipe size is >1200mmÆ, shall undergo visualinspection. Visual inspection includes a walk through the pipeline between manholesor inlet and outlet structure to ensure the pipeline is laid straight for grade andalignment, has retained its shape (i.e. roundness), is clean, joints are uniform, pipebarrel isn't cracked and little or no infiltration occurring.

d) Gravity piped reticulation where the distance between manholes is more than 50m orthe pipe size is 1200mmØ or less shall be inspected using closed circuit television(CCTV) to satisfy the same requirements as noted under b) above.

Note: If any part of the reticulation is required to be CCTV'ed then all pipes on thedevelopment shall be CCTV'ed.

e) Sumps shall be inspected to satisfy the requirements noted under inspection sheetIS-5.2 – Inspection Sheet Sump.

f) Should inspection of other stormwater features be required, Council shall advise inwriting what inspection/s are required.

g) Final inspection as specified in IT-1 General Provisions.

IT-5.1.2 Random Inspections

Council shall undertake random inspections of all site features throughout the constructionperiod to ensure good industry practice and compliance with all requirements for theinfrastructure development are being followed.

IT-5.1.3 CCTV Inspections

CCTV inspections and deliverables shall be in accordance with IT-1 Appendix C - ClosedCircuit Television (CCTV) Inspections.

All Stormwater network components shall be completed before commencement of CCTV.

Page 54: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-5 STORMWATER

Page 2 Updated 01/07/2014

IT-5.2 Testing

Testing of stormwater pipelines shall include:

a) IT-5.2.1 Testing of Butt Welds in Polyethylene Pipes

b) IT-5.2.2 Testing of Electrofusion Welds in Polyethylene Pipes

IT-5.2.1 Testing of Butt Welds in Polyethylene Pipes

Testing shall be carried out in accordance with ISO 13953:2001. The number ofspecimens per weld tested shall be in accordance with this standard.

In addition to the results provided in terms of the standard, a graph of load vs tensileextension shall be provided to assist with the interpretation of ductile and brittle failure. Theresults shall be submitted to Council. Test pieces shall be retained by the Contractor untilthe issue of the Defects Liability Certificate and shall be made available to the Engineer onrequest.

Before welding of the main pipe string commences, two proof welds shall be carried outand tested. If at any time during the welding of the pipe string either the welder or thewelding machine is changed two further proof welds shall be carried out and tested. On themain pipe string 5% of welds carried out shall be tested, with a minimum of one weld.

If a weld has failed the Contractor shall expose the immediately preceding weld whichshall be tested as described above.

IT-5.2.2 Testing of Electrofusion Welds in Polyethylene Pipes

Testing of electrofusion welds shall be carried out in accordance with ISO 13954:1997.The minimum number of specimens per weld shall be three.

Before welding of the main pipe string commences, two proof welds shall be carried outand tested. If at any time during the welding of the pipe string either the welder or thewelding machine is changed two further proof welds shall be carried out and tested. On themain pipe string 5% of welds carried out shall be tested, with a minimum of one weld.

If a weld has failed the Contractor shall expose the immediately preceding weld, whichshall be tested as described above.

Page 55: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 56: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 57: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-6 WASTEWATER

TABLE OF CONTENTS

IT-6.1 Inspection.............................................................................................................1

IT-6.2 Testing .................................................................................................................2

Page 58: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-6 WASTEWATER

Updated 01/07/2014 Page 1

IT-6.1 Inspection

Please refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-6.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) Manhole structures shall be inspected to satisfy the requirements noted underinspection sheet IS-6.1 – Wastewater Manhole and Pipeline <50m.

b) Gravity piped reticulation where the distance between manholes is 50m or less, shallundergo visual inspection. Visual inspection includes "lamping" between manholesto ensure the pipeline is laid straight for grade and alignment, has retained its shape(i.e. roundness) and is clean.

c) Gravity piped reticulation where the distance between manholes is more than 50mshall be inspected using closed circuit television (CCTV) to satisfy the samerequirements as noted under b) above.

Note: If any part of the reticulation is required to be CCTV'ed then all pipes on thedevelopment shall be CCTV'ed.

d) Wastewater pump station commissioning which includes testing the operation of thepumps, electrical and telemetry systems.

e) Should inspection of other wastewater features be required, Council shall advise inwriting what inspection/s are required.

f) Final inspection as specified in IT-1 General Provisions.

IT-6.1.2 Random Inspections

Council shall undertake random inspections of all site features throughout the constructionperiod to ensure good industry practice and compliance with all requirements for theinfrastructure development are being followed.

IT-6.1.3 CCTV Inspections

CCTV inspections and deliverables shall be in accordance with IT-1 Appendix C - ClosedCircuit Television (CCTV) Inspections.

All Wastewater network components shall be completed before commencement of CCTV.

Slope corrections shall be carried out where the pipe alignment is out of tolerance.

Page 59: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-6 WASTEWATER

Page 2 Updated 01/07/2014

IT-6.2 Testing

Please refer to IT-1 General Provisions for the procedure for initiating testing attendance byCouncil Representatives.

IT-6.2.1 Pre-Testing

All wastewater mains, branch pipelines and extended connections shall be pre-testedduring construction. The Contractor and Engineer must be satisfied that the final test willpass (by undertaking pre-testing), before initiating the final test with Council.

IT-6.2.2 Gravity Reticulation

The following applies to testing of gravity reticulation:

a) All testing shall be carried out when backfilling is complete and prior to final surfacesealing and/or pavement works being completed if within the carriageway.

b) All manholes and pipes shall be flushed before testing.

c) No infiltration of water either via a manhole or pipe is permitted.

IT-6.2.2.1 Low Pressure Air Test

TS 6.1

a) Unless pipes are installed under natural groundwater, this test shall beundertaken on all pipes unless another test method is agreed to by Council.

b) The pipeline to be tested shall be effectively plugged by fixing suitably struttedplugs at both ends and into side connections with particular care being taken to fixplugs against movement. Air shall be introduced by suitable means (such as handpumps) until either:

i) A pressure of 300mm of water is indicated by a suitable manometer (suchas a U-tube) connected to the system.

ii) As noted on test sheet TS-6.1 Low Pressure Air Test.c) After the air has attained a uniform temperature, as indicated by the pressure

becoming steady, the source of air supply shall be physically disconnected andthe pressure drop measured after a test period of 5 minutes.

d) The acceptance limit shall be a pressure drop not exceeding 50mm in 5 minutes.

e) All results and comments shall be recorded on test sheet TS-6.1 Low Pressure AirTest.

f) If the test is passed, the test sheet shall be signed by:i) The Contractor who completed the test.

ii) The Certifying Engineer or their Representative to certify that the test haspassed all requirements.

Page 60: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-6 WASTEWATER

Updated 01/07/2014 Page 3

iii) Council's Representative as a witness to ensure that the test wasundertaken correctly.

g) If the test does not pass the Engineer and Contractor shall investigate thereason/s for the test failure, fix the problem/s and rearrange a new test.

IT-6.2.3 High Pressure Air Test

TS 6.2

a) Where pipes are installed under natural groundwater, this test shall be undertaken onall pipes unless another test method is agreed to by Council.

b) The pipeline being tested shall be plugged as for the Low Pressure Air Test, carebeing taken to secure the plugs against movement and pressurised by a compressoror other appropriate means to a pressure of 25kPa.

c) A period of at least 2 minutes shall be allowed to ensure temperature stabilisation. Thesource of air supply shall be physically disconnected and the time for the test pressureto drop from 25kPa to 17kPa noted.

d) The acceptance limit shall be as follows:

Pipe diameter(mm)

Time for permissible pressure drop(minutes)

100150200230250300

3.04.06.06.57.59.0

e) If the test is passed the Test Sheet shall be signed by:

i) The Contractor who completed the test.

ii) The Certifying Engineer or their Representative to certify that the test haspassed all requirements.

iii) Council's Representative as a witness to ensure that the test was undertakencorrectly.

f) If the test does not pass the Engineer and Contractor shall investigate the reason/s forthe test failure, fix the problem/s and rearrange a new test.

IT-6.2.4 Rising Main Pressure Test

TS 6.3

a) Pressure testing shall be undertaken in accordance with the procedure on test sheetTS 6.3 - Wastewater Rising Main Pressure Test.

b) All results and comments shall be recorded on test sheet. TS 6.3 - Wastewater RisingMain Pressure Test.

c) If the test is passed the Test Sheet shall be signed by:

Page 61: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-6 WASTEWATER

Page 4 Updated 01/07/2014

i) The Contractor who completed the test.

ii) The Certifying Engineer or their Representative to certify that the test haspassed all requirements.

iii) Council's Representative as a witness to ensure that the test was undertakencorrectly.

d) If the test does not pass the Engineer and Contractor shall investigate the reason/s forthe test failure, fix the problem/s and rearrange a new test.

IT-6.2.5 Manhole Testing

Where required by Council, manholes shall be water tested. The test shall satisfy therequirements noted under testing sheet TS-6.4 Manhole Infiltration Test.

IT-6.2.6 Wastewater Pump Station Commissioning

Commissioning of pump stations shall comply with:

a) IT-6.2.6.1 Pumps

b) IT-6.2.6.2 Electronic Equipment

c) IT-6.2.6.3 Control Systems

IT-6.2.6.1 Pumps

This involves but is not limited to the following:

a) Ensuring all chambers and pumps are clear of all debris and tools.

b) Operation of each pump separately and in their possible combinations to confirmsystem and component performance.

c) Check for excess vibration and noise.

d) Check pump polarity/rotation.

e) Receipt of factory test certificate for the pumps.

f) Pumps shall be set to work in the normal automatic operation mode after the testshave been completed.

IT-6.2.6.2 Electronic Equipment

This involves but is not limited to the following:

a) All tests and checks required for provision of an electrical compliance by aregistered electrician.

b) Receipt of factory test and calibration certificates.

c) Tests as per manufacturers installation requirements.

d) Calibration check against a standard.

e) Confirmation of protection against out of specification power impulses.

Page 62: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-6 WASTEWATER

Updated 01/07/2014 Page 5

f) Ensuring that all overload systems are functioning.

g) Checking signals to and from the control system.

h) Checking signals to and from remote sensors.

i) Checking signals from all level control equipment to ensure safe operation and toensure machines will not run dry.

j) Setting to work in the normal automatic operational mode after the tests havebeen completed.

IT-6.2.6.3 Control Systems

This involves, but is not limited to, the following:

a) Ensure all mechanical, electrical and electronic systems are set to work and are“on-line” to operate.

b) Simulate all level induced control functions.

c) Operate all control modes.

d) Check all remote control and monitoring functions.

e) Where any of the above fail to satisfy the requirements of the specification or theEngineer, correct the defect/s and retest.

f) Oversee operation and carry out adjustments as necessary throughout thedefects liability period.

IT-6.2.7 Testing of Butt Welds in Polyethylene Pipes

Please refer to IT-5.2.1 Testing of Butt Welds in Polyethylene Pipes.

IT-6.2.8 Testing of Electrofusion Welds in Polyethylene Pipes

Please refer to IT-5.2.2 Testing of Electrofusion Welds in Polyethylene Pipes.

Page 63: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 64: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 65: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 66: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 67: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 68: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 69: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 70: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 71: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 72: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-7 WATER SUPPLY

TABLE OF CONTENTS

IT-7.1 Inspection.............................................................................................................1

IT-7.2 Testing .................................................................................................................1

Page 73: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-7 WATER SUPPLY

Updated 01/07/2014 Page 1

IT-7.1 Inspection

Refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-7.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) Hydrants shall be inspected to satisfy the requirements noted under inspection sheetIS 7.1 – Inspection Sheet -Hydrant.

b) Valves shall be inspected to satisfy the requirements noted under inspection sheet IS7.2 – Inspection Sheet - Valve.

c) Water meters shall be inspected to satisfy the requirements noted under inspectionsheet IS 7.3 - Inspection Sheet - Water Connection.

d) Should inspection of other water supply features be required, Council shall advise inwriting what inspection/s are required.

e) Final inspection as specified in IT-1 General Provisions.

IT-7.1.2 Random Inspections

Council shall undertake random inspections of all site features throughout the constructionperiod to ensure good industry practice and compliance with requirements forinfrastructure development.

IT-7.2 Testing

Please refer to IT-1 General Provisions for the procedure for initiating testing attendance byCouncil Representatives.

IT-7.2.1 Prior to Testing

The Contractor and Engineer shall be fully familiar with the test procedure and all testequipment shall be fully functional and compliant before initiating the final test withCouncil.

IT-7.2.2 Pressure Testing

Pressure testing shall be undertaken in accordance with Council's guideline documentTesting of Pressure Pipelines.

Page 74: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-7 WATER SUPPLY

Page 2 Updated 01/07/2014

IT-7.2.3 Water Supply Disinfection

a) Disinfection of new mains shall be undertaken in accordance with the procedure ontest sheet TS-7. 2 Installation Disinfection.

b) All results and comments shall be recorded on test sheet TS-7.2 InstallationDisinfection.

c) If the test passes, the test sheet shall be signed by:

i) The Contractor who completed the test.

ii) The Certifying Engineer or their Representative to certify that the test haspassed all requirements.

iii) Council’s Representative as a witness to ensure that the test was undertakencorrectly.

d) If the test does not pass, the Engineer and Contractor shall investigate the reason/s forthe failure, fix the problem/s and rearrange a new test.

IT-7.2.4 Testing of Butt Welds in Polyethylene Pipes

Please refer to IT-5.2.1 Testing of Butt Welds in Polyethylene Pipes.

IT-7.2.5 Testing of Electrofusion Welds in Polyethylene Pipes

Please refer to IT-5.2.2 Testing of Electrofusion Welds in Polyethylene Pipes.

Page 75: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 76: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 77: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 78: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

Please contact Council for Test Sheets.

Page 79: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 80: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General
Page 81: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-8 PUBLIC LIGHTING

TABLE OF CONTENTS

IT-8.1 Inspection.............................................................................................................1

IT-8.2 Testing .................................................................................................................1

Page 82: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-8 PUBLIC LIGHTING

Updated 01/07/2014 Page 1

IT-8.1 Inspection

Refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-8.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) At completion of all public lighting structures to ensure structural stability and durablepaint/coating.

b) The lighting shall be visually inspected in working condition.

c) Should inspection of other lighting features be required, Council shall advise in writingwhat inspection/s are required.

d) Final inspection as specified in IT-1 General Provisions.

IT-8.1.2 Random Inspections

Council shall undertake random inspections of all site features throughout the constructionperiod to ensure good industry practices and compliance with all requirements for theinfrastructure development are being followed.

IT-8.2 Testing

a) Testing of public lighting features over and above the requirements specified in IT-8.1Inspection will not generally be required.

b) Should testing of public lighting features be required, Council shall advise in writing whattest method/s shall be used.

Page 83: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

INSPECTION AND TESTING REQUIREMENTSIT-9 NETWORK UTILITIES

TABLE OF CONTENTS

IT-9.1 Inspection.............................................................................................................1

IT-9.2 Testing .................................................................................................................1

Page 84: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

IT-9 NETWORK UTILITIES

Updated 01/07/2014 Page 1

IT-9.1 Inspection

Refer to IT-1 General Provisions for the procedure for initiating inspection by CouncilRepresentatives.

IT-9.1.1 Formal Inspections

The following inspections shall be advised to and undertaken with Council’sRepresentatives:

a) Before any backfilling of broadband ducting.

b) Should inspection of other network utility features be required, Council shall advise inwriting what inspection/s are required.

c) Final inspection as specified in IT-1 General Provisions.

IT-9.1.2 Random Inspections

Council shall undertake random inspections of all site features throughout the constructionperiod to ensure good industry practices and compliance with all requirements for theinfrastructure development are being followed.

IT-9.1.3 Inspection by Others

Where network utilities are not to be owned by Council, the inspection requirements of thenetwork Utility Operator for each utility shall be met.

IT-9.2 Testing

a) Testing of broadband ducting and/or structures will not generally be required.

b) Should testing of broadband features be required, Council shall advise in writing what testmethod/s shall be used.

IT-9.2.1 Testing by Others

Where network utilities are not to be owned by Council, the testing requirements of thenetwork Utility Operator for each utility shall be met.

Page 85: INSPECTION AND TESTING REQUIREMENTS - Taurangaecontent.tauranga.govt.nz/data/idc/07_inspection_and_testing... · INSPECTION AND TESTING REQUIREMENTS IN THIS SECTION § IT-1 General

STANDARD DRAWINGS

IN THIS SECTION

§ SD-1 General Provisions§ T100 Perspective Drawings§ CBD Series Drawings§ T200 Streetscape§ T300 Reserves§ T400 Transportation Network§ T500 Stormwater§ T600 Wastewater§ T700 Water Supply§ T800 Public Lighting§ Quality Assurance Drawings