INSPECTION AND TEST PLAN
Date:
Project: Al Fattan Crystal Towers Consultant: Tabanlioglu Page No: 1 of 1
Item Activity/DescriptionParameter to be
verifiedInspection Frequency
Acceptance CriteriaControl Method /
ReferenceFormat/Records
Inspection Authority
SECL TA
A
Material Reinforcement Bar
Tensile Strength Every batch As per Structural Specification Mill Test Certificate MIR
Concrete
Compressive strengthRCPWater AbsorptionWater PermeabilityISAT
One Time during Trial Mix
As per Each Grade2000 Coul.
2.5 %0.30 Ml/M2/S
Lab Reports
Mix
Design
Approva
l
BReinforcement work
Diameters & No. of Bars
Each Section As per Structural Drawings Structural Drawings
IR
Spacing Each Section ± 25mm Structural Drawings
Lap Length / Anchorage Length
Each Section Min. 50 dia. Structural Drawings
Cover Each Section Min. 2 no. Cover blocks per m2 Structural Specification
CShuttering Material
Surface Finish Each Section -Structural
Specification-
D Shuttering Works
MEP Fixtures Each Section -Approved Shop
DrawingsIR
Dimensions Each Section ± 3mmStructural Drawings/
Specification
IRVerticality Each Section ± 3mmStructural Drawings/
Specification
Level Each Section ± 3mm Structural Drawings
Stability Each Section RigidApproved Shop
Drawings
E Surfaces Cleanliness Each Section Free from waste / foreign - -
![Page 2: Inspection and Test Plan Concrete](https://reader035.fdocuments.net/reader035/viewer/2022072108/563dbcb6550346aa9ab094d1/html5/thumbnails/2.jpg)
INSPECTION AND TEST PLAN
Date:
Project: Al Fattan Crystal Towers Consultant: Tabanlioglu Page No: 1 of 1
Item Activity/DescriptionParameter to be
verifiedInspection Frequency
Acceptance CriteriaControl Method /
ReferenceFormat/Records
Inspection Authority
SECL TA
Preparation before Concreting
materials
F Concrete
Mix Proportion (Concrete Grade)
Each truck on Arrival
As per SpecificationStructural
SpecificationDelivery
Order
Workability (Slump test)
Each truck on Arrival
As per Approved Mix DesignStructural
Specification-
TemperatureEach truck on
ArrivalMax. 32°C
Structural Specification
-
Compression Strength (Cube test at 7 & 28 days)
Each locationNot less than the specified
valuesStructural
Specification
Cube test
results
G Placing
Concrete Duration Each truckDelivery less than 2 hours from
batching timeAs per Approved
Method StatementDelivery Tickets
Compaction Each Section Usage of vibrator in all areasStructural
Specification-
Finish Level Each Section Uniform & ± 4mmStructural
Specification-
Protection from direct sunlight
Each SectionFully covered with hessian cloth
and polytheneStructural
Specification-
Curing Each SectionWatering for 7 days or use of approved curing compound
Structural Specification
-
LEGEND : LA - LOCAL AUTHORITY H - HOLD W- WITNESS INSPECTION S - SURVEILLANCE INSPECTION R - REVIEW A - PPROVAL