INNOVATIVE AUTOMATION OF ELECTRICAL DESIGN OF OFF-SHORE WINDFARMS TO FIND THE LEAST COST OPTION
description
Transcript of INNOVATIVE AUTOMATION OF ELECTRICAL DESIGN OF OFF-SHORE WINDFARMS TO FIND THE LEAST COST OPTION
© 2013 Siemens Energy, Inc. All rights reserved.
Answers for energy.
INNOVATIVE AUTOMATION OF ELECTRICAL DESIGN OF OFF-SHORE WINDFARMS TO FIND THE
LEAST COST OPTION
Infrastructure & Cities Sector, Smart Grid DivisionInfrastructure & Cities Sector, Smart Grid Division Siemens Power Technologies International (PTI)Siemens Power Technologies International (PTI)Presenter:Victor SellwoodPresenter:Victor Sellwood
Dr. Dusko P. Nedic ([email protected])Dr. Dusko P. Nedic ([email protected])Victor Sellwood([email protected])Victor Sellwood([email protected])
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Presentation Overview
Introduction - why Optimise construction and operation costs?
Development and Experiences / Validation of a software tool for automating the electrical design of large off-shore wind farms.
Case Study 1 - Edge-located collector platforms vs Central-located
Case Study 2 - Comparison of CAPEX / OPEX for offshore windfarms based on publicly-available data
Conclusions
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Why Optimise Construction / Operation Costs ?
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Why Optimise Construction / Operation Costs ?
UK's Round 3 program will offer 32.2GW / 36GW and there is up-to 80GW offshore in the North Sea
2010: National Grid announced that a radial offshore transmission network is not acceptable
2011: Ofgem report shows that moving from an Independent (radial) to Integrated (mesh) transmission system could reduce Capex from £18B to £15.4B (-16%)
A study showed that for only 2 wind farms in the North Sea considering only voltage as a choice, design options would exceed 7,000
Image from “Eirgrid_Offshore_Grid_Study_FA Nov2011.pdf”
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Software Tool for automated design
Tool Features: Three analysis sub-systems
Inter-array cable system Off-shore platforms Off-shore transmission
Automated design of inter-array cable system and VUI for correcting such designs.
Catalogue of components. Creating of network models and
possibility of merging them. Cable sizing. Voltage/reactive power control. Electrical losses. Reliability. CAPEX and OPEX evaluation.
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Visualisation User Interface (for modifications of inter-array cable design)
Interactive tool for creating/editing inter-array cable system.Multiple projects.
Information on the selected project
Restructure string,change string origin, shift platform, swap strings between platforms
Find and correct cablecrossovers
Adding/editing cable knee points
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Proving the Software Tool by Practical Application
Driven by projects / clients and cooperation with the UK Universities
HornSea (over 10 different transmission options with sensitivity analyses)
Seagreen (4 different transmission options and a number of sensitivity analyses)
UoM Electrical Engineering – research project and a PhD to assess thousands of electrical designs for different offshore wind farm sizes
University of Strathclyde – Industry supervision of a 4 year PhD on transmission options in North-Sea. The research will be conducted using the tool.
Dogger Bank - Inter array cable design (over 80 layouts – capacity ranging from 7GW to 20 GW)
Availability calculations:
London Array
Greater Gabbard
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Case Study 1: Comparison of Edge- vs Central- location
Each platform 600 MW, 18 strings per platform (14 of 5WTGs strings and 4 of 4WTG strings).
Centrally Located option (CLo) Edge Mounted option (EMo)
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Case Study 1: Comparison of Edge- vs Central- location
0.0
3.0
6.0
9.0
12.0
15.0
18.0
Cab
le lo
sses
MW
1 7 22 49 82 100
Turbine MW Output as % of installed MW capacity
CLoEMo
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Case Study 2: Illustrative Comparison of Design Options Based on Publicly-Available Data
Investment Cost in £ (Millions)
Cost figures for illustrative purposes only!
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Case Study 2: Illustrative Comparison of Design Options Based on Publicly Available Data
Case 1 and Case 3 use the same electrical components -> losses are same
Case 2 has least electrical losses as no HVDC conversion equipment and good reliability because of the 3 x HVAC shore connections
Case 3 has least reliability losses due to redundant string connections
Case 4 has most electrical losses as longest string cables, but the least Investment Cost as the quantity of higher gauge cables is less
This demonstrates that the differences in Investment are swamped by the differences in Costs of Losses during operation
© 2013 Siemens I@C, Inc. All rights reserved
Siemens Power Technologies International
Conclusions
This automated approach significantly reduces the time for manual and visual inspection / verification of the proposed cabling system for the layouts
Risk of human errors is significantly reduced and re-verifications / inspections can be quick and efficient
Effortlessly and quickly design and undertake cost benefit analyses of preferred options.
Possibility to merge network models for cost benefit analyses of the off-shore grid.
Complex design solutions can easily be compared (both construction and operation) using the most significant comparator: cost